May-2016 Month Plan Boiler Unit # 8 Boiler

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 11

BHAVANI ERECTORS PVT LTD

2x660MW SURATGARH POWER PROJECT


ERECTION PLAN FOR THE MONTH OF MAY-2016 OF UNIT # 8 Date: 02/05/2016
TARGET ERECTION
SL No. Activity REMARKS
WEIGHT

1 ESP 114MT

2 BOILER STRUCTURES 260MT

3 ROTATING PARTS 95MT

4 PRESSURE PARTS 24MT

5 DUCTING 260MT

6 COAL PIPING 70MT

7 PENT HOUSE 10MT

8 INSULATION & CLADDING 70MT

9 CRITICAL PIPING 110MT

TOTAL TONNAGE :- 1013MT


BHAVANI ERECTORS PVT LTD
2x660MW SURATGARH POWER PROJECT
ERECTION PLAN FOR THE MONTH OF MAY-2016OF ESP UNIT # 8 Date02/05/2016
PGMA
SL No. Activity TARGET ERECTION WEIGHT REMARKS
DETAILS
1 COLL ELECT RAPP MECH 79925 8.00MT
2 RECTIFIER HANDL SYST 79956 2.50MT
3 GAS DIST. ASSY 79908 2.00MT
4 OUTER ROOF-EP 79942 75.00MT
5 TRANSFORMERS 26.40MT

TOTAL TONNAGE(A,B,C&D PASS) :- 113.90MT


BHAVANI ERECTORS PVT LIMITED

2x660MW SURATGARH POWER PROJECT


Erection Plan of Boiler for the Month of MAY-2016, Unit # 8 Boiler
Date02/05/2016
Target Erection
SL No. Activity PGMA Remarks
weight

1 COLUMNS NEAR AIR PRE HEATERS 36-110 30.00MT

BEAMS AND BRACINGS NEAR AIR


2 36-150 25.00MT
PREHEATER

3 MISCELLANEOUS PLATFORMS-PART II 36-392 35.00MT

4 MAIN FLOOR I MBL 2ND PASS 36-312 10.00MT

NON-MBL FLOOR BETWEEN MBL I AND


5 36-313 10.00MT
II

NON-MBL FLOOR BETWEEN MBL I AND


6 36-315 40.00MT
II

NON-MBL FLOOR BETWEEN MBL I AND


7 36-316 25.00MT
II

8 MAIN FLOOR II MBL IST PASS 36-321 5.00MT


9 MAIN FLOOR II MBL 2ND PASS 36-322 10.00MT

NON-MBL FLOOR BETWEEN MBL II AND


10 36-324 20.00MT
III

NON-MBL FLOOR BETWEEN MBL II AND


11 36-326 10.00MT
III

NON-MBL FLOOR BETWEEN MBL III


12 36-333 10.00MT
AND IV

13 HOR BEAM-SECOND PASS- TIER-1 35-451 10.00MT

14 HOR BEAM-SECOND PASS- TIER-2 35-452 10.00MT

FLOORGRILLSANDGUARDPLATE
15 36-812 10.00MT
MIDDLE

Total Tonnage :- 260.00MT


BHAVANI ERECTORS PVT LTD
2x660MW SURATGARH POWER PROJECT

ERECTION PLAN FOR THE MONTH OF MAY-2016 OF ROTATING MACHINES UNIT # 8


Date-Date Date02/05/2016
PGMA TARGET ERECTION
SL No. AREA Activity REMARKS
DETAILS WEIGHT

1 LARG AH-ROTORHOUSING 52-030 15.00MT

2 COLD END CONN PLATE 52-042 80.00MT

TOTAL TONNAGE :- 95.00MT


BHAVANI ERECTORS PVT LTD
2x660MW SURATGARH POWER PROJECT

ERECTION PLAN FOR THE MONTH OF MAY-2016 OF PRESSURE PARTS UNIT # 8


Date Date02/05/2016
PGMA TARGET ERECTION
SL No. PASS Activity REMARKS
DETAILS WEIGHT

1 SOOT BLOWER'S 20-051 20.00MT


1ST &
2ND
PASS
2 SH PLATEN LOOSE TUBES 11-078 4.00MT

TOTAL TONNAGE :- 24.00MT


BHAVANI ERECTORS PVT LTD
2x660MW SURATGARH POWER PROJECT
ERECTION PLAN FOR THE MONTH OF MAY-2016 OF DUCTING UNIT # 8 Date Date02/05/2016
PGMA
SL No. Activity TARGET ERECTION WEIGHT REMARKS
DETAILS

1 DUCT - BET F.D FAN AND AIRHEATER 48-012 20.00MT

DUCT - S PRI FAN TO AIRHEATER


2 48-112 50.00MT
PRISID
DUCT - SAIRHEATER TO
3 48-202 50.00MT
WINDBOXDUCT

4 DUCT BELOW DIVERTOR 48-386 10.00MT

DUCT - BOILER OUTLET TO ELEC


5 48-462 15.00MT
PRECP

6 BEAMS AND BRACING BEFORE ESP 39-102 50.00MT

7 GATE-ESP INLET 57-460 20.00MT

8 COLUMNS BEFORE ESP 39-101 45.00MT

TOTAL TONNAGE :- 260.00MT


BHAVANI ERECTORS PVT LTD
2x660MW
SURATGARH POWER PROJECT
ERECTION PLAN FOR THE MONTH OF MAY-2016 OF COAL PIPING UNIT # 8
Date Date02/05/2016
TARGET ERECTION
SL No. Activity REMARKS
WEIGHT

1 ST PIPES&SHOP BENDS FOR A & B MILL 20.00MT

ST PIPES&SHOP BENDS FOR C & D MILL


2 & ST PIPES & SHOP BENDS FOR E & F 50.00MT
MILL

TOTAL TONNAGE :- 70.00MT


BHAVANI ERECTORS PVT LTD
2x660MW SURATGARH POWER PROJECT

ERECTION PLAN FOR THE MONTH OF MAY-2016 OF PENT HOUSE UNIT # 8


Date Date02/05/2016
PGMA TARGET ERECTION
SL No. Activity REMARKS
DETAILS WEIGHT
MAIN BOILER ,VERTICAL ROOF
30-215 ,30-219
1 ENCLOSURE FRAMING & FIRST PASS 10.00MT
& 30-233
DECK SPRT AND SEAL

TOTAL TONNAGE :- 10.00MT


BHAVANI ERECTORS PVT LTD
2x660MW SURATGARH POWER PROJECT

ERECTION PLAN FOR THE MONTH OF MAY-2016 OF INSULATION & CLADDINGUNIT # 8


Date Date02/05/2016
PGMA TARGET ERECTION
SL No. Activity REMARKS
DETAILS WEIGHT
BOILER INSULATION & CLADDING

BLR PR PARTS MINERAL WOOL & MAIN


1 33-021 &33-230 20.00MT
BLR POURABLE INSULATION

2 POURABLE INSULATION 33-230 40.00MT

ESP INSULATION & CLADDING

1 ESP HOPPER FUNNE50 MM THICK 79967 10.00MT

TOTAL TONNAGE :- 70.00MT


BHAVANI ERECTORS PVT LTD
2x660MW SURATGARH POWER PROJECT

ERECTION PLAN FOR THE MONTH OF MAY-2016 OF CRITICAL PIPING UNIT # 8


Date Date02/05/2016
PGMA TARGET ERECTION
SL No. Activity REMARKS
DETAILS WEIGHT

1 CRH FROM TURBINE TO REHEATER 80-320 30MT

2 BFD FROM FINAL HPH TO SG TP 80-425 40MT

HRH FROM REHEATER TO


3 80-310 20MT
INTERCEPTOR

4 C-D BAY STRUCTURE 80-940 20MT

TOTAL TONNAGE :- 110.00MT