Health Post Building, Thalajung

Abstract of Cost
Government of Nepal
Ministry of Urban Development
Department of Urban Development & Building Construction
Division Office
Gorkha

Abstract of Cost
Name of works :- Site Development works of Health Post Building
Place :- Thalajung, Gorkha FY- 070/71

Quantity
Amount
Item No. Description of Work Unit Landscaping & Rate Rs. Remarks
Retaining Wall
(NRs.)

CIVIL WORKS
1 SITE PREPARATION & DISMANTLING WORKS
1.1 Site Clearance & layout
1.1.4
Earthwork in excavation in hard soil using machine and M3 1,065.21 1,886.00 2,008,986.06
removing out of site all complete.
2 EXCAVATION AND FILLING
2.1 Earthwork in excavation for foundation in all kind of soil M3 37.29 28.29 1,054.93
including necessary lead and lift.
3 MASONRY WORK
3.1 Soling Works
3.1.2 Providing & laying boulder stone soling in foundation & floor
including voids filling with sand all complete as per instruction M3 13.97 2,710.56 37,866.52
of the site engineer.
3.6 Providing, laying and curing stone masonry works in cement,
sand mortar (1:6) in substructure & compound wall finished in
perfect lines & level as per specification, drawings & M3 47.42 9,330.19 442,437.61
instructions of the site engineer.
4 CEMENT CONCRETE WORKS
4.1 Providing, laying, compacting and curing plain cement
concrete M10 (1:3:6) in foundation with cement, sand and
stone ballast 20mm gauge finishing to approved level, lines M3 4.31 2,710.56 11,682.51
and dimensions all complete as per drawings, specifications
and instruction of the site engineer.
4.2 Providing, laying, compacting and curing plain cement
concrete M15 (1:2:4) in Solid Floor with cement, sand and
stone ballast 20mm gauge finishing to approved level, lines M3 6.57 2,710.56 17,808.38
and dimensions using all complete as per drawings,
specifications and instruction of the site engineer.
4.3 Providing, laying, compacting and curing M20 (1:1.5:3) plain cement
concrete for column, slab, beams, tie beam Lintel Sill and all kinds of
R.C.C. works with cement sand and stone ballast 20mm down
finishing to approved level, line and dimensions using mixer machine
M3 4.88 16,711.19 81,550.61
& vibrator all complete as per specifications, drawings and
instructions of the site engineer, all complete.

5 REINFORCEMENT
5.1 Reinforcement bars (Fe 500 TMT) work including
straightening, cleaning, cutting, bending, binding with 20 SWG
annealed wire & fixing in position as per drawing, bar bending
schedule for raft foundation column, beam, wall, stair, slab in Kg 382.75 111.36 42,623.04
all R.C.C. works as per specification, drawing & instruction of
site engineer. Approved brands: Himal Iron, Panchakanya or
equivalent.

7 PLASTERING & POINTING WORKS

Prepared by- Checked by- Recommended by- Approved by-


1 of 123
Health Post Building, Thalajung
Abstract of Cost

Quantity
Amount
Item No. Description of Work Unit Landscaping & Rate Rs. Remarks
Retaining Wall
(NRs.)

7.2 Providing, laying & curing 12.5 mm thick cement sand (1:4)
Plastering on outside wall to perfect plumb, lines & level
including band (pani patti) for preventing the flow of rain
water from slab edges during rain fall all complete as per M2 7.20 321.96 2,318.11
design drawings, specifications and instruction of the site
engineer all complete:
7.4 Providing and pointing in perfect line, level and groove depth
with 1:3 cement sand mortar for joints of stone masonry
works above ground level in compound wall including raking
the joints, scafolding, curing the works all complete as per M2 163.50 218.77 35,768.90
specifications and instruction of the site engineer.

11 MISCELLANEOUS WORKS
Providing, fabricating & fixing iron gate using 40mm dia.
Medium Black pipe frame with 25mm dia. Medium black pipe
sub gate frame, 25x25x 2mm thick square pipe, 18 guage MS
sheet, 20x4.5 mm grill plate on top of gate and other
11.09 necessary hinges, tower bolt, aldrops and plates with one coat Kg 190.19 1,886.00 358,698.34
of metal primer & enamel paint as per design drawing,
specifications and instructions of site engineer all complete.

Providing and paving heavy duty concrete interlocking block


60mm thk siddhico or equivalent in walk way as per drawing,
11.10 design and instruction of site engineer all complete.. M2 198.00 1,673.32 331,317.36

Supplying & Fixing 0.075x0.125 m size, 2.10m height


concrete (1:2:4) post with reinforcement for fencing at 2.00 m
11.11
interval as per design, drawing, specifications and instructions No 126.00 825.93 104,067.18
of site engineer.
Supplying & Fixing GI Barbed wire fencing work (5 layer
11.12 horizontal & 2 layer diagonal) as per design, drawing, Rm 1,867.50 1,886.00 3,522,105.00
specifications and instructions of site engineer.
Providing and paving 50mm thk flag stone in 1:4 cement sand
mortar in perfect lines & level in walk way as per drawing,
11.16 M2 60.00 1,431.36 85,881.60
design and instruction of site engineer all complete.

Supplying and planting outdoor gardening plants (Dhupi,


11.17 Kapur etc.) and flowering plants in specified space as per Tree 20.00 553.61 11,072.20
instruction of the site engineer all complete.
Estimate Amount 7,095,238.35

Prepared by- Checked by- Recommended by- Approved by-


2 of 123
Health Post Building, Thalajung, Gorkha
BOQ

Government of Nepal
Ministry of Urban Development
Department of Urban Development & Building Construction
Division Office
Gorkha

Bill of Quantity
Name of works :- Construction of Health Post Building
Place :- Thalajung, Gorkha
A. The Rate quoted here under shall be inclusive of :
1. Supplying the materials along with accessories to the site
2. Fixing and erecting them in position as per general practices, specifications and instructions of Site Engineer
3. Tests and Maintenance up to the period, specified in the agreement
4. Necessary water for sprinkling, mixing, curing etc all complete.
B. The itemwise rate should be quoted without VAT

Total Rate (NRs.) Excluding VAT


Item No. Description of Work Unit
Quantity In Figure In Word
CIVIL WORKS
1 SITE PREPARATION & DISMANTLING WORKS
1.1 Site Clearance & layout

Clearing the site of all the vegetation, roots and other unuseful materials
including excavation of top soil to a depth of 15 cm, removing bushes, trees
and leveling the Site for stacking the useful items in specified space and
1.1.1 L.S. 1.00
disposing other item before commencing the construction work & Placing
project description sign board as per instruction of the site engineer all
complete including layout of buildings, roads and ancillary services.

Clearing the site of all the unuseful materials including removing all them from
1.1.2 site and leveling the Site after completing the works as per instruction of the L.S. 1.00
site engineer all complete.

Providing and maintaning site office (room of about 12 sq m) during the project
1.1.3 month 15.00
period including necessary furniture for the personnel of the office staff.

Earthwork in excavation in hard soil using machine and removing out of site all
1.1.4 complete. M3 1,065.21

Contracter's signature:- 3 of 123


Health Post Building, Thalajung, Gorkha
BOQ

Total Rate (NRs.) Excluding VAT


Item No. Description of Work Unit
Quantity In Figure In Word
2 EXCAVATION AND FILLING
2.1 Earthwork in excavation for foundation in all kind of soil including necessary
lead and lift. M3 374.43

2.2 Earthwork in filling in trench of foundation & floor including consolidation in


layers of 15 cm and watering as per instruction of site engineer. M3 158.77

2.3 Sand filling in floor including supply of filling materials, watering, consolidation
in layers of 15 cm and ramming as per instruction of site engineer. M3 37.42

2.4 Brick ballast filling in soak pit including supply of filling materials as per
instruction of site engineer. m3 5.65

3 MASONRY WORK
3.1 Soling Works
3.1.1 Providing & laying flat brick soling in foundation & floor including voids filling
with sand all complete as per instruction of the site engineer. m2 27.53

3.1.2 Providing & laying boulder stone soling in foundation & floor including voids
filling with sand all complete as per instruction of the site engineer. M3 96.23

3.2 Providing, laying and curing first class brick masonry works in cement, sand
mortar (1:6) in substructure, ground floor & soak pit finished in perfect lines &
level as per specification, drawings & instructions of the site engineer. M3 100.89

3.3 Providing, laying and curing first class brick masonry works in cement, sand
mortar (1:6) above ground floor finished in perfect lines & level as per M3 81.46
specification, drawings & instructions of the site engineer.
3.4 Providing, laying and curing first class brick masonry works in cement, sand
mortar (1:4) in substructure & ground floor for partation wall finished in perfect
lines & level as per specification, drawings & instructions of the site engineer. M3 27.23

3.5 Providing, laying and curing first class brick masonry works in cement, sand
mortar (1:4) above ground floor for partation wall finished in perfect lines & level
as per specification, drawings & instructions of the site engineer. M3 2.93

3.6 Providing, laying and curing stone masonry works in cement, sand mortar (1:6)
in substructure & compound wall finished in perfect lines & level as per M3 101.14
specification, drawings & instructions of the site engineer.
4 CEMENT CONCRETE WORKS
4.1 Providing, laying, compacting and curing plain cement concrete M10 (1:3:6) in
foundation with cement, sand and stone ballast 20mm gauge finishing to
approved level, lines and dimensions all complete as per drawings, M3 25.85
specifications and instruction of the site engineer.

Contracter's signature:- 4 of 123


Health Post Building, Thalajung, Gorkha
BOQ

Total Rate (NRs.) Excluding VAT


Item No. Description of Work Unit
Quantity In Figure In Word
4.2 Providing, laying, compacting and curing plain cement concrete M15 (1:2:4) in
Solid Floor with cement, sand and stone ballast 20mm gauge finishing to
approved level, lines and dimensions using all complete as per drawings, M3 29.21
specifications and instruction of the site engineer.
4.3 Providing, laying, compacting and curing M20 (1:1.5:3) plain cement concrete for
column, slab, beams, tie beam Lintel Sill and all kinds of R.C.C. works with cement sand
and stone ballast 20mm down finishing to approved level, line and dimensions using M3 209.40
mixer machine & vibrator all complete as per specifications, drawings and instructions of
the site engineer, all complete.

4.4 Providing, laying, compacting and curing M20 (1:1.5:3) plain cement concrete
with silica cement admixture @ 5% for top floor slab, beams and water tank of
R.C.C. works with cement sand and stone ballast 20mm down finishing to
approved level, line and dimensions using mixer machine & vibrator all m3 6.93
complete as per specifications, drawings and instructions of the site engineer,
all complete.

5 REINFORCEMENT
5.1 Reinforcement bars (Fe 500 TMT) work including straightening, cleaning,
cutting, bending, binding with 20 SWG annealed wire & fixing in position as per
drawing, bar bending schedule for raft foundation column, beam, wall, stair,
slab in all R.C.C. works as per specification, drawing & instruction of site Kg 29,309.04
engineer. Approved brands: Himal Iron, Panchakanya or equivalent.

6 FORMWORKS
6.1 Centering and shuttering with approved waterproof plywood for all kinds of
R.C.C. work including all necessary steel propping, scaffolding, staging,
supporting, dismantling and clearing from the site, including shuttering of M2 1,771.91
circular column up to 2 m dia etc. all complete as per design drawings,
specifications and instruction of the site engineer .
7 PLASTERING & POINTING WORKS
7.1 Providing, laying & curing 20 mm thick cement sand (1:4) Plastering on inside
wall and floor to perfect plumb, lines & level all complete as per design
drawings, specifications and instruction of the site engineer all complete: M2 1,375.76

7.2 Providing, laying & curing 12.5 mm thick cement sand (1:4) Plastering on
outside wall to perfect plumb, lines & level including band (pani patti) for
preventing the flow of rain water from slab edges during rain fall all complete as M2 1,135.80
per design drawings, specifications and instruction of the site engineer all
complete:
7.3 Providing, laying & curing 12.5 mm thick cement sand (1:3) plastering in ceiling,
beams surfaces including chipping & wetting the concrete surfaces finished in
perfect plumb, lines and level as per drawings, specifications and instructions M2 611.05
of the site engineer.

Contracter's signature:- 5 of 123


Health Post Building, Thalajung, Gorkha
BOQ

Total Rate (NRs.) Excluding VAT


Item No. Description of Work Unit
Quantity In Figure In Word
7.4 Providing and pointing in perfect line, level and groove depth with 1:3 cement
sand mortar for joints of stone masonry works above ground level in
compound wall including raking the joints, scafolding, curing the works all M2 170.47
complete as per specifications and instruction of the site engineer.
8 FLOOR FINISHING
8.1 Providing and laying 25mm thick mosaic flooring & skirting - 6mm thick white
cement and marble chips in (1:1) over 19 mm thick cement sand plaster (1:2) in
perfect line and level with finish according to drawing and specificattion and M2 432.88
instruction of site engineer as all complete
8.2 Providing, laying and curing 3mm thk. (1:1) cement sand punning on below
plinth, appron, drain & skirting of buildings on perfect line & level as per M2 330.09
design, specification and instruction of site engineer.
8.3 Providing and paving 25mm thick telia brick in 1:2 lime surki mortar and
pointing with 1:1 cement sand mortar on terrace to perfect plumb, lines & level
all complete as per design drawings, specifications and instruction of the site M2 293.86
engineer all complete.
8.4 Providing & laying porcelain non glazed floor tiles in 1:4 cement sand mortar in
perfect lines & level finishing the joint with white cement with or without
pigments where necessary all complete as per design drawings, patterns, M2 69.57
specifications and instruction of the site engineer:
8.5 Providing & laying porcelain glazed wall tiles in 1:4 cement sand mortar in
perfect lines & level finishing the joint with white cement with or without
pigments where necessary all complete as per design drawings, patterns, M2 140.05
specifications and instruction of the site engineer:
8.6 Providing, laying and curing 38mm thick PCC (1:2:4) flooring with punning on
floor on perfect line & level as per design, specification and instruction of site M2 128.12
engineer.
9 PAINTING WORKS
9.1 Providing & painting two coats of Enamel paint with one coat of primer of
approved brand and colour as per specifications and instruction of the site M2 673.72
engineer.
9.2 Providing & painting two coats of Readymade acrylic washable Distemper paint
with one coat of cement primer of approved brand and colour over plastered
surfaces of building, walls ceiling and passage area as per specifications and M2 1,597.37
instruction of the site engineer.
9.3 Supplying and applying Two coat weather proof painting (Apex or equivalent)
with one coat of cement primer of approved colour in outer side of building as M2 960.84
per specifications and instruction of the site engineer.
10 DOORS AND WINDOWS WORKS
10.01 Suppling and fixing Salwood chaukhat frame works for doors & windows as
approved by site incharge , the timber shall be matured,free from wraps. M3 5.263
Knots holes and other defects all complete.

Contracter's signature:- 6 of 123


Health Post Building, Thalajung, Gorkha
BOQ

Total Rate (NRs.) Excluding VAT


Item No. Description of Work Unit
Quantity In Figure In Word
10.02 Supplying and fixing 38 mm thick salwood panelled shutter in door including
fixing with approved size of heavy duty hinges, brass tower bolts handle,
locking set, door stopper, shock absorber as per design and instruction all M2 18.69
complete.
10.03 Supplying and fitting Ready made Teak wood Doors,special (Seasoned and
Poisoned treated ,one side teak) with heavy duty 6" hinges, 6" aluminium
tower bolts handle, 12" aldrops set, door stopper, shock absorber all M2 32.35
complete.
10.04 Supplying and fitting Ready made Teak wood Doors,special (Seasoned and
Poisoned treated ,one side teak & other side water proof ply fitting) with heavy
duty 6" hinges, 6" aluminium tower bolts handle, 12" aldrops set door stopper, M2 18.03
shock absorber all complete.
10.05 Supplying and fixing 4 mm thick glazed shutter in 38 mm thick sal wood frame
with approved size of heavy duty 4" hinges, 6" aluminium tower bolts handle as M2 65.73
per design and instruction all complete.
10.06 Supplying and fixing Mosquito proof net and expanded metal net in 38 mm
thick sal wood frame with approved size of heavy duty 4" hinges, 6" aluminium M2 69.19
tower bolts handle as per design and instruction all complete.
10.07 Providing and fixing 5 mm thick glass on fixed frame of windows & ventilation M2
12.38
with wooden listy as per design and instruction all complete.
10.08 Providing and Fitting 25mm thick well seasoned salwood eavesboard with
necessary nails, screws, metal brackets etc as per drawing and instruction all M2 6.95
complete.
10.09 Providing and fabricating MS grill with 10mmx10mm square strips of approved
pattern and manufacture finished with one coat of metal primer paint with
approved colour as per design, drawing and instruction all complete. Kg 1,413.20

10.10 Making & fixing MS door for pump house with locking arrangement of approved
pattern and manufacture finished with one coat of metal primer paint and two
coat of enamel paint with approved colour as per design, drawing and L.S. 2.00
instruction all complete.
11 MISCELLANEOUS WORKS
Providing 26 gauge (0.41mm) Colour CGI sheet for roof including fixing in
11.01 proper shape & size with all necessary rails, screws, bolts & nuts washers, J & M2 77.85
L hocks etc as per drawing & instruction all complete.
Providing and fitting 26 gauge (0.41mm) Colour G.I plane sheet for ridge in
11.02 proper shape and size with all necessary screws, bolts and nuts as per drawing Rm 8.00
and instruction all complete
Providing M.S. blackpipe Truss, Rafter, purlin, Post with I.S. or B.S. section
including jointting , fixing, erection and primer & enamel painting with all
11.03 necessary M.S. bed plates, shoe angles, anchor bolts leas sheeting or cement Kg 1,006.36
grouting as per drawing and instructions all complete .

Contracter's signature:- 7 of 123


Health Post Building, Thalajung, Gorkha
BOQ

Total Rate (NRs.) Excluding VAT


Item No. Description of Work Unit
Quantity In Figure In Word
Providing 2" dia stainless steel pipe hand rail fixing on staircase & verandah ( 3
line 1" dia pipe horizontal laying & 2" dia pipe vertical laying at 2m c/c, ht 0.9m
11.04
including painting as per design drawing and specifications and instructions of M2 86.72
site engineer.
Providing, fabricating & fixing MS angle for water tank stand of approved
pattern and manufacture finished with one coat of metal primer & enamel paint
11.05 with approved colour as per design, drawing and instruction all complete. Kg 249.04

Providing & fixing 2" dia stainless steel pipe hand rail fixing on parapet wall
11.06 including painting as per design drawing and specifications and instructions of Rm 198.16
site engineer.
Providing & fixing metal monkey ladder using rectangular hollow section of
50x25x2 mm size with 450 mm wide with one coat of metal primer & enamel
11.07 paint as per design, specification & instructions of Site Engineer all complete kg 30.10

Providing and fitting 26 gauge Colour G.I plane sheet gutter in proper shape
11.08 and size with all necessary brackets, screws, bolts and nuts as per drawing and Rm 31.50
instruction all complete.
Providing, fabricating & fixing iron gate using 40mm dia. Medium Black pipe
frame with 25mm dia. Medium black pipe sub gate frame, 25x25x 2mm thick
square pipe, 18 guage MS sheet, 20x4.5 mm grill plate on top of gate and other
11.09 necessary hinges, tower bolt, aldrops and plates with one coat of metal primer Kg 190.19
& enamel paint as per design drawing, specifications and instructions of site
engineer all complete.

Providing and paving heavy duty concrete interlocking block 60mm thk siddhico
11.10 or equivalent in walk way as per drawing, design and instruction of site M2 198.00
engineer all complete..
Supplying & Fixing 0.075x0.125 m size, 2.10m height concrete (1:2:4) post with
11.11 reinforcement for fencing at 2.00 m interval as per design, drawing, No 126.00
specifications and instructions of site engineer.
Supplying & Fixing GI Barbed wire fencing work (5 layer horizontal & 2 layer
11.12 diagonal) as per design, drawing, specifications and instructions of site Rm 1,867.50
engineer.
Providing and laying 2 coats of water proofing materials for terrace roof
(elastocrate cementious elastrometric water proofing coating two components)
11.13 capacity per Kg 6 sq ft as per specification and direction complete works. M2 348.45

Making & fixing 3mm thick MS sheet manhole cover (.60cmx.60cm) as per
11.14 design drawing, specifications and instructions of site engineer all complete. Set 2.00

Contracter's signature:- 8 of 123


Health Post Building, Thalajung, Gorkha
BOQ

Total Rate (NRs.) Excluding VAT


Item No. Description of Work Unit
Quantity In Figure In Word
Providing and fitting chimney of 100 nominal dia heavy gauge structural steel
pipe with 6mm thick ms flue cap plate on top welded with 4 nos 38x6 ms slits
11.15
on bottom surface of cap plate fix with mesh around cap to prevent ash as per KG 21.44
drawing and instruction all complete.
Providing and paving 50mm thk flag stone in 1:4 cement sand mortar in perfect
11.16 lines & level in walk way as per drawing, design and instruction of site engineer M2 60.00
all complete.
Supplying and planting outdoor gardening plants (Dhupi, Kapur etc.) and
11.17 flowering plants in specified space as per instruction of the site engineer all Tree 20.00
complete.
12 ELECTRICAL WORKS
12.1 LUMINAIRES ( FIXTURES)
Accessories:screws, gripes, pvc tape, choke, starter, Tube, bulbs, holder,
12.1.0
flexible wire,GI pipe/ chain etc all complete.
12.1.1 Ceiling ligh/Dome light 8" heavy carrier with CFL etc all complete. Set 66.00

12.1.2 Wall lamp with CFL lamp decorative etc all complete. Set 8.00

12.1.3 Wall lamp with GLS lamp decorative etc all complete. Set 9.00

12.1.4 Down light (concealed ) with CFL etc all complete. Set 6.00

12.1.5 Hanging light with CFL lamp decorative etc all complete. Set 1.00

12.1.6 1X40watt Tube light box type Wipro /Ge or eqvt. etc all complete. Set 24.00

12.1.7 2x40 watt tube light box type Wipro/Ge or eqvt.etc all complete. Set 4.00

12.1.8 2x40 watt tube light box mirror optic Wipro/Ge or eqvt.etc all complete. Set 4.00

12.1.9 Mirror light with CFL lamp decorativeor eqvt etc all complete. Set 9.00

12.1.10 Electrical bell musical type. Set 2.00


12.2 FAN / EXHAUST FAN
Accssories:as per sn A +nut, bolt, hook,clamp, regulator, flexible wire etc all
12.2.0
complete.
12.2.1 42'' ceiling fan Almonard/Bajaj or eqvt.etc all complete. Set 16.00

12.2.2 9"exhaust fan Almonard /Bajaj or eqvt.etc all complete. Set 10.00

Contracter's signature:- 9 of 123


Health Post Building, Thalajung, Gorkha
BOQ

Total Rate (NRs.) Excluding VAT


Item No. Description of Work Unit
Quantity In Figure In Word

12.2.3 16'' wall fan Almonard/Bajaj or eqvt.etc all complete. Set 1.00
12.3 SOCKET,SWITCH ,JUNCTION BOX (Flush type)
12.3.0 Accessories: metal box ,screws ,gripes, flexible wire etc all complete.
12.3.1 Dimmer switch for ceiling fan etc all complete. Set 16.00

12.3.2 Bell push switch Anchor or eqvt etc all complete. Set 2.00

16/6 Amps combined S/socket flush type with child lock Anchor or eqvt.etc all
12.3.3 Set 65.00
complete.
12.3.4 1 gang 1,2 way switch Anchor or eqvt.etc all complete. Set 22.00

12.3.5 2gang one way switch Anchor or eqvt.etc all complete. Set 18.00

12.3.6 3 gang one way switch Anchor or eqvt.etc all complete. Set 12.00

12.3.7 4 gang one way switch Anchor or eqvt.etc all complete. Set 14.00

12.3.8 6 gang one way switch Anchoror eqvt. etc all complete. Set 2.00

12.3.9 Junction box made of metal with cover size 6"X4" etc. all complete. Set 20.00
12.4 MAIN SWITCH / DISTRIBUTION BOARD
Accessories ;screws, gripes, nut bolt,cu bus bar,earth bus bar, neutral bus
12.4.0 bar,fuse, porcelin base ,cu. Strip for connection, cable shoe ,phase bar,pvc
tape etc all complete.
60 Amps Panel board made of mild steel sheet with cu. busbar double cover
12.4.1 floor mount suitable size & color push type lock for housing the following Set 1.00
items all complete.(space for 4 no. MCCB).

12.4.1.1 40- 50 Amps TP MCCB Siemens ,Ge or eqvt. for incoming. No 1.00

12.4.1.2 20-30 Amps TP MCCB Siemens, Geor eqvt. for outgoing. No 3.00

12.4.1.3 10 Amps DP MCB Siemens Ge,Merlin gerain or eqvt. for main . No 2.00

12.4.1.4 Ammeter 0-500A No 1.00

12.4.1.5 Voltmeter 0-500 v No 1.00

12.4.1.6 Selector switch No 2.00

Contracter's signature:- 10 of 123


Health Post Building, Thalajung, Gorkha
BOQ

Total Rate (NRs.) Excluding VAT


Item No. Description of Work Unit
Quantity In Figure In Word

12.4.1.7 CT coil of suitable ratio for panel board. No 3.00

12.4.1.8 Indicator with fuse No 3.00

Distribution board 6 way TPN made of mild steel sheet double cover lockable
12.4.2 Set 3.00
Geco,Standard,Nepal made flush type etc all complete.
12.4.2.1 25-32 Amps TP MCB Siemens Ge,Merlin gerain or eqvt. for main.(1x3=3) No 3.00
6,16,25 Amps. SP MCB Siemens,Ge,Merlin gerain or eqvt. for light & power
12.4.2.2 No 54.00
circuit.(18x3=54)
Distribution board 12 way SPN made of mild steel sheet double cover lockable
12.4.3 Set 2.00
Geco,Standard, Nepal made flush type etc all complete.
12.4.3.1 20 Amps DP MCB Siemens Ge,Merlin gerain or eqvt. for main .(1x2=2) No 2.00
6,16,25 Amps. SP MCB Siemens,Ge,Merlin gerain or eqvt. for light , power &
12.4.3.2 No 24.00
A/C circuit.(2x12=24)
Distribution board 6 way SPN made of mild steel sheet double cover lockable
12.4.4 Set 1.00
Geco,Standard, Nepal made flush type etc all complete.
12.4.4.1 10 Amps DP MCB Siemens Ge,Merlin gerain or eqvt. for main . No 1.00
6 Amps. SP MCB Siemens,Ge,Merlin gerain or eqvt. for light , power & A/C
12.4.4.2 No 2.00
circuit.
12.5 POINT WIRING / WIRES/CABLES (concealed wiring )
Accessories:HDPE polythene pipe,screws,pvc tape, grips, circular box etc all
12.5.0
complete.
2x2.50 sq mm multi strand flexible cu .wire for light & fan point in 1/2"HDPE
12.5.1 Point 166.00
polythene pipe etc all complete.
2x4.0+1x1.50 sq.mm multi strand flexible cu wire for power point in 3/4" HDPE
12.5.2 Point 65.00
polythene pipe etc all complete.
10 sq.mm 4 core unarmoured copper cable for main panel board to DB,
12.5.3 Rm 65.00
through polythene pipe etc all complete.
2x6.0+1.50 sq.mm copper cable from panel board to( toilet block) DB-3, DB-4
12.5.4 Rm 60.00
to DB-5,DB -6 through 1" HDPE polythene pipe etc all complete.
8 swg copper wire for earth continuity from panel board to DB,main switch &
12.5.5 Rm 75.00
earthing site in 1/2"HDPE polythene pipe etc all complete.
12.6 EARTHING
12.6.0 Accessories :salt, coal, cu plate, HDPE polythene pipe., etc all complete.
Earthing with cu plate size 65 cmx65cmx3.15mm with 8 swg copper wire for
earth continuity from panel board to earthing site including excavation of 6 ft
12.6.1 Set 1.00
deep trench in moist area and refilling the tranch with cubical salt and charcoal
in alternet layer with watering arrangement etc all complete.

Contracter's signature:- 11 of 123


Health Post Building, Thalajung, Gorkha
BOQ

Total Rate (NRs.) Excluding VAT


Item No. Description of Work Unit
Quantity In Figure In Word
13 SANITARY WORKS
Supplying and Fixing White glazed earthenware Indian pattern Orissa Pan with
low level Pvc flushing cistern ,trap,pipe connector with complete accessories
13.01
including bracket, flushing pipe,pipe connector etc. all complete set. (Hindware,
Parryware, Classi
Indian pattern W C 530mm Orissa Pan with PVC low level flushing cistern all
13.1.1 set 8.00
complete set.
Supplying and Fixing Porcelain clay Indian Pattern Comode P or S trap, Pvc
13.02 Cistern and Plastic seat cover with pipe connector all complete set (Hindware,
Parryware, Classica, bolan or equivalent.)
Indian pattern Comode with PVC low level flushing cistern and seat cover all
13.2.1 set 2.00
complete set.
Supplying and fixing White glaze Indian Pattern Porcelain clay wash basin/Oval
with brackets 32mm dia. Pvc bottle trap, 32mm CP waste coupling ,
13.3
15mmx450mm long c.p. pipe connector etc all complete.Sanitaryware:-.
( Parryware,Hindware, or equivalent
Indian pattern Porcelain clay white glaze 55X40 cm Wash Basin with pedestal
13.3.1 set 6.00
and swan type piller cock complete set.
Porcelain clay white glaze Indian Pattern 55X40 cm size , wash basin with
13.3.2 Set 3.00
pedestal and central hole Aerator type basin mixer etc all complete.
Indian pattern Porcelain clay white glaze Oval Wash Basin 50x40cm with
13.3.3 inbuilt hole/over counter/under counter and swan type piller cock complete set 4.00
set.
Indian pattern White glazed porceline clay Urinal 46.5X31.5X26.5cm with
13.3.4 Set 2.00
necessary accessories all complete set .
Porcelain clay white glaze Indian Pattern 68X30cm size Urinal partation all
13.3.5 Set 1.00
complete set .
Kitchen sink stainless steel 900x450x200mm depth with drain board 1mm
13.3.6 Set 2.00
thickness with Aerator/swan type sink cock.
Kitchen sink stainless steel 900x450x200mm depth with drain board 1mm
13.3.7 one 5.00
thickness with Aerator/swan type sink Mixer all complete set..
Supplying and Fixing ( Fabricated Scrub sink) The spalsh made of 304 qwality
prime grade of Stainless steel 16 swg thickness,Floor mounted with
13.4
leg(stand),kantipur kitchen equipment, Qwality kitchen or equivalent.Sample to be
approved by project engineer

13.4.1 Stainless steel Scrub sink 1.5mt length,deep 500mm+150mm splash set 1.00
Supplying and Fixing Indian pattern C.P. valves with wall flange Including c.p.
13.5
nipple all complete set.

13.5.1 15mm C.P. concealed stop cock with sliding flange Nos 9.00

13.5.2 Chrome plate shower rose 7.5 cm dia.with wall flange all complete set. nos 3.00

Contracter's signature:- 12 of 123


Health Post Building, Thalajung, Gorkha
BOQ

Total Rate (NRs.) Excluding VAT


Item No. Description of Work Unit
Quantity In Figure In Word

13.5.3 15mm dia C.P. bath spout with wall flange. Nos 3.00

13.5.4 C.P. Bibcock 15mm dia long neck type with wall flange nos 8.00

13.5.5 15mm dia Angle valve with wall flange. nos 34.00

13.5.6 15mm dia two way angle valve nos 5.00

13.5.7 15 mm CP water spray with 1.2mt. Long flexiable pipe. set 2.00

13.5.8 15mm dia. Urinal Auto Closing Valve with built in Control Cock nos 2.00
13.6 Supplying and Fixing Indian pattern bathroom accessories all complete set.

13.6.1 Chrome plated toilet paper holder flap type(cover type). nos 2.00

13.6.2 Chrome plated soap tray(heavy). nos 18.00

13.6.3 C p 15mm dia x450mm long towel rod. nos 15.00

13.6.4 Looking Mirror Modi guard 450x600mm (18"x 24") nos 8.00

13.6.5 European pattern Stainless steel 45cm long with bend type Grab Bar . Set 2.00
Indian pattern Electric water heater (Geyser) with built up check valve, pressure
13.7
relief valve all complete set.(Crompton,bajaj,Jaquar or equivalent.)

13.7.1 25 lit electric water heater (Geyser) nos 2.00

Supplying and Fixing Pvc roof water tank With screw type cover including drain
13.8
hole ,inlet outlet, over flow etc.all complete set .Hill take, Roof top or equivalent

13.8.1 1000 lit capacity PVC water tank. nos 3.00


Supplying and Fixing Electric moter Pump single or three phase phase with base,
13.9
nut and bolts all complete set (Kirloskar, Compton or equiv),

13.9.1 1HP Electric motor Pump monoblock. nos 1.00

13.9.2 0.5HP Electric motor Pump monoblock type. nos 1.00

13.9.3 Pressure sensor switch for pump auto switch off all complete set. Set 2.00

Contracter's signature:- 13 of 123


Health Post Building, Thalajung, Gorkha
BOQ

Total Rate (NRs.) Excluding VAT


Item No. Description of Work Unit
Quantity In Figure In Word
Supplying and fixing PPR pipe (hot and cold). or equivalent with PPR fittings/
13.10 specials (Tees, elbows, Unions etc) clamps(m.s plate with nut and bolt with
hexagonal screws for clamp in ceiling,wall), nails, including
20 mm PPR pipe, PN-10 \SDR 11, Pachanya, Napatop or eqv, includes
13.10.1 Rm 24.00
fixing/laying with necessary fittings all complete.
25 mm PPR pipe, PN-10 \SDR 11, Pachanya, Napatop or eqv, includes
13.10.2 Rm 174.00
fixing/laying with necessary fittings all complete.
32 mm PPR pipe, PN-10 \SDR 11, Pachanya, Napatop or eqv, includes
13.10.3 Rm 127.00
fixing/laying with necessary fittings all complete.
40 mm PPR pipe, PN-10 \SDR 11, Pachanya, Napatop or eqv, includes
13.10.4 Rm 42.00
fixing/laying with necessary fittings all complete.
Supplying and fixing PPR valve including jointing materials. all complete
13.11
set as per specification and instruction.
13.11.1 20 mm dia PPR Brass Gate Valve all complete. Nos 2.00

13.11.2 25 mm dia PPR Brass Gate Valve all complete. Nos 10.00

13.11.3 32 mm dia PPR Brass Gate Valve all complete. Nos 7.00

13.11.4 40 mm dia PPR Brass Gate Valve all complete. Nos 2.00
Supplying and Fixing Gun metal gate valve/check valve full way medium all
13.12
complete set as per specification and instruction.

13.12.1 (G.M.) check valve 25mm dia nos 2.00

THERMAL INSULATION TUBES:-Providing and fixing in position 6mm thick wall


13.13 thickness thermal insulation tubes for Insulation to hot water line pipes as per
need joining and covering .

13.13.1 15mm dia.6mm wall thickness insulation for hot water pipe all complete. Rm 6.00

13.13.2 20mm dia,6mm thick wall thickness insulation for hot water pipe Rm 42.00

Supplying and Fixing solar water heater with 3.0 k.w. electric booster with
thermostat all complete set. Technical spe.:-Inside boiler M.S sheet 4.0 mm thick
13.14
with Expansion joint(over lap joint) in cover and bottom with 25x25x3 mm angle
welded,4.0 kg/sq

13.14.1 300 lit. 3 panel solar heater fixing with electric booster all complete. Set 1.00
Supplying and Fixing uPVC pipe 6kg/sqcm all complete set as per specification
13.15
and instruction. (Dwv,Panchakanya,SN-4, Prince,Supreme )

13.15.1 50mm PVC pipe of 6 kg/cm2 Rm 42.00

Contracter's signature:- 14 of 123


Health Post Building, Thalajung, Gorkha
BOQ

Total Rate (NRs.) Excluding VAT


Item No. Description of Work Unit
Quantity In Figure In Word

13.15.2 75mm PVC pipe of 6 kg/cm2 Rm 92.00

13.15.3 110mm PVC pipe of 6 kg/cm2 Rm 193.00

Supplying and Fixing UPVC specials with O ring rubber washer,Pvc


13.16 liquid(Solvent cement), Pvc cream,Pvc pipe clips with screw,Vent cowl all
complete set as per specification and instruction. (Panchakanya,Prince,Supreme )

13.16.1 50 mm dia UPVC 90 degree bend nos 63.00

13.16.2 50 mm dia UPVC 45 degree bend. nos 21.00

13.16.3 50 mm dia UPVC plain Y-Tee. nos 3.00

13.16.4 75 mm dia UPVC vent cowl nos 5.00

13.16.5 75 mm dia UPVC plain. nos 5.00

13.16.6 75 mm dia UPVC door tee. nos 8.00

13.16.7 75 mm dia UPVC 90 degree bend. nos 18.00

13.16.8 75 mm dia UPVC door bend. nos 8.00

13.16.9 75 mm dia UPVC 45 degree bend. nos 12.00

13.16.10 75 mm dia UPVC Y branch. nos 3.00

13.16.11 75 mm dia UPVC pipe clip. nos 14.00

13.16.12 110 mm dia UPVC vent cowl. nos 3.00

13.16.13 110 mm dia UPVC plain . nos 2.00

Contracter's signature:- 15 of 123


Health Post Building, Thalajung, Gorkha
BOQ

Total Rate (NRs.) Excluding VAT


Item No. Description of Work Unit
Quantity In Figure In Word

13.16.14 110 mm dia UPVC Door Tee nos 4.00

13.16.15 110 mm dia UPVC 90 degree bend. nos 33.00

13.16.16 110 mm dia UPVC Door bend. nos 6.00

13.16.17 110 mm dia UPVC 45 degree bend nos 25.00

13.16.18 110 mm dia UPVC Y branch nos 6.00

13.16.19 110 mm dia UPVC pipe clip nos 40.00

13.16.20 75x75mm dia.Pvc p-trap Nos 10.00

13.16.21 110x110mm dia.Pvc p-trap Nos 10.00

13.16.22 110x75 red. Socket Nos 10.00

13.16.23 5 kg fire extinguiser with pressure guage type all complete set. set 6.00

13.16.24 CI cover 45x45 cm size (medium).Round type set. nos 18.00

13.16.25 C I Cover round type 60x60cm, with locking arrangement (16kg) complete set. Set 1.00

Supplying and Fixing HDP Pipe 4 kg/sq.cm all complete set as per specification
13.17
and instruction. (Panchakanya or equivalent(N.S. )

13.17.1 4 kg/cm2 (110 mm) HDP pipe. Rm 42.00

13.17.2 10 kg/cm2 (20 mm) HDP pipe including fittings & layings Rm 200.00

Providing and laying non-pressure NP2 class (light duty) RCC pipes with collars
13.18 jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2
find sand) including testing of joints etc. complete.

13.18.1 150 mm dia NP2 RCC Hume pipe including collar with all complete. Rm 39.00

Contracter's signature:- 16 of 123


Health Post Building, Thalajung, Gorkha
BOQ

Total Rate (NRs.) Excluding VAT


Item No. Description of Work Unit
Quantity In Figure In Word
Supplying good condition 4WD vehicle (5 door Jeep or 4 door Pick up
Toyota, Nissan, Ford or eqivalent with full option latest by 2000 Model)
14 with driver including 300 Ltr. diesel per month with necessary other month 2.00
lubricants like mobil, brake oil etc. to the project staff as instructed by
office.
Provisional cost for the expenses such as performance bond
commission, insurances (project period+ maintenance period+1 months),
consultancy fees, cost of preparation of as built drawings, cost of quality
15 assurance tests, registration tax for town development committee before job 1.00 409,888.46 not to be filled by contractors
execution of work etc as per written instruction of the engineer. (The
payment of this item will be done according to submitted original copy of
related invoices.)

Contractor's firm : Total Amount NRs.

Seal : Total Amount In Words

Propriter's Name : 13% VAT :

Address : Grand Total :

Telephone : Mobile :

Signature : E-mail :

Date :

Contracter's signature:- 17 of 123


Health Post Building, Thalajung, Gorkha
BOQ

Government of Nepal
Ministry of Urban Development
ban Development & Building Construction
Division Office
Gorkha

ll of Quantity

FY- 070/71

Total Amount
(NRs.)

Contracter's signature:- 18 of 123


Health Post Building, Thalajung, Gorkha
BOQ

Total Amount
(NRs.)

Contracter's signature:- 19 of 123


Health Post Building, Thalajung, Gorkha
BOQ

Total Amount
(NRs.)

Contracter's signature:- 20 of 123


Health Post Building, Thalajung, Gorkha
BOQ

Total Amount
(NRs.)

Contracter's signature:- 21 of 123


Health Post Building, Thalajung, Gorkha
BOQ

Total Amount
(NRs.)

Contracter's signature:- 22 of 123


Health Post Building, Thalajung, Gorkha
BOQ

Total Amount
(NRs.)

Contracter's signature:- 23 of 123


Health Post Building, Thalajung, Gorkha
BOQ

Total Amount
(NRs.)

Contracter's signature:- 24 of 123


Health Post Building, Thalajung, Gorkha
BOQ

Total Amount
(NRs.)

Contracter's signature:- 25 of 123


Health Post Building, Thalajung, Gorkha
BOQ

Total Amount
(NRs.)

Contracter's signature:- 26 of 123


Health Post Building, Thalajung, Gorkha
BOQ

Total Amount
(NRs.)

Contracter's signature:- 27 of 123


Health Post Building, Thalajung, Gorkha
BOQ

Total Amount
(NRs.)

Contracter's signature:- 28 of 123


Health Post Building, Thalajung, Gorkha
BOQ

Total Amount
(NRs.)

Contracter's signature:- 29 of 123


Health Post Building, Thalajung, Gorkha
BOQ

Total Amount
(NRs.)

Contracter's signature:- 30 of 123


Health Post Building, Thalajung, Gorkha
BOQ

Total Amount
(NRs.)

Contracter's signature:- 31 of 123


Health Post Building, Thalajung, Gorkha
BOQ

Total Amount
(NRs.)

Total Amount In Words

Contracter's signature:- 32 of 123


Government of Nepal
Ministry of Urban Development
Department of Urban Development & Building Construction
Division Office
Gorkha

Summary of Cost Estimate

Project Name:- Construction of Thalajung Health Post Building.


Location:- Thalajung, Gorkha FY: 070/71

S No Description of work Amount Remarks


A Building & Other Supporting 39,390,520.34
B Site Development (Landscaping) 7,095,238.35 6.22%
C Sanitary Installation 1,210,731.65
D Electrical Installation 928,170.66
E Provisional (Insurance and etc..) 409,888.46
F Sum without Vat and contingencies 49,034,549.46
G Contingencies @ 5% of F 2,451,727.47
H Sum with contingencies (F+G) 51,486,276.93
I VAT @ 13% of H 6,693,216.00
J Sum with Vat (H+I) 58,179,492.93
For Budget Provision
K Physical Contingency @10% of H 5,148,627.69
L Price Adjustment Contingencies @10% of H 5,148,627.69
Grand Total Cost (J+K+L) 68,476,748.31

Prepared by- Checked by- Recommended by- Approved by-


33 of 123
Health Post Building, Thalajung
Abstract of Cost
Government of Nepal
Ministry of Urban Development
Department of Urban Development & Building Construction
Division Office
Gorkha

Abstract of Cost
Name of works :- Construction of Health Post Building
Place :- Thalajung, Gorkha FY- 070/71

Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity
Landscaping Inspection Pump Total Amount
Item No. Description of Work Unit Main Septic Soakpit Water Placenta Waste Rate Rs. Remarks
Toilet & Retaining Tank 19 House 2 Quantity (NRs.)
Building Wall Tank 2 Nos Tank Pit Burner
Nos Nos
CIVIL WORKS
1 SITE PREPARATION & DISMANTLING WORKS
1.1 Site Clearance & layout
Clearing the site of all the vegetation, roots and other unuseful
materials including excavation of top soil to a depth of 15 cm,
removing bushes, trees and leveling the Site for stacking the
useful items in specified space and disposing other item
1.1.1 L.S. 1.00 - - - - - - - - - 1.00 10,000.00 10,000.00
before commencing the construction work & Placing project
description sign board as per instruction of the site engineer
all complete including layout of buildings, roads and ancillary
services.

Clearing the site of all the unuseful materials including


removing all them from site and leveling the Site after
1.1.2 L.S. 1.00 - - - - - - - - - 1.00 5,000.00 5,000.00
completing the works as per instruction of the site engineer all
complete.
Providing and maintaning site office (room of about 12 sq m)
1.1.3 during the project period including necessary furniture for the month 15.00 - - - - - - - - - 15.00 1,500.00 22,500.00
personnel of the office staff.

1.1.4
Earthwork in excavation in hard soil using machine and M3 - - 1,065.21 - - - - - - - 1,065.21 1,886.00 2,008,986.06
removing out of site all complete.
2 EXCAVATION AND FILLING
2.1 Earthwork in excavation for foundation in all kind of soil M3 232.00 30.39 37.29 17.19 13.63 11.54 0.55 25.47 6.11 0.26 374.43 28.29 10,592.62
including necessary lead and lift.
2.2 Earthwork in filling in trench of foundation & floor including
consolidation in layers of 15 cm and watering as per M3 143.33 15.44 - - - - - - - - 158.77 237.47 37,703.11
instruction of site engineer.
2.3 Sand filling in floor including supply of filling materials,
watering, consolidation in layers of 15 cm and ramming as per M3 32.66 4.76 - - - - - - - - 37.42 5,584.40 208,968.25
instruction of site engineer.
2.4 Brick ballast filling in soak pit including supply of filling m3 - - - - 5.65 - - - - - 5.65 3,422.40 19,336.56
materials as per instruction of site engineer.

Prepared by- Checked by- Recommended by- Approved by-


34 of 123
Health Post Building, Thalajung
Abstract of Cost
Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity
Landscaping Inspection Pump Total Amount
Item No. Description of Work Unit Main Septic Soakpit Water Placenta Waste Rate Rs. Remarks
Toilet & Retaining Tank 19 House 2 Quantity (NRs.)
Building Wall Tank 2 Nos Tank Pit Burner
Nos Nos
3 MASONRY WORK
3.1 Soling Works
3.1.1 Providing & laying flat brick soling in foundation & floor
including voids filling with sand all complete as per instruction m2 - - - 7.81 4.33 15.39 - - - - 27.53 1,225.85 33,747.65
of the site engineer.
3.1.2 Providing & laying boulder stone soling in foundation & floor
including voids filling with sand all complete as per instruction M3 70.89 9.02 13.97 - - - 0.33 1.50 0.32 0.20 96.23 2,710.56 260,837.19
of the site engineer.
3.2 Providing, laying and curing first class brick masonry works in
cement, sand mortar (1:6) in substructure, ground floor & soak
pit finished in perfect lines & level as per specification, M3 76.22 18.47 - - 6.20 - - - - - 100.89 15,684.05 1,582,363.80
drawings & instructions of the site engineer.

3.3 Providing, laying and curing first class brick masonry works in
cement, sand mortar (1:6) above ground floor finished in
perfect lines & level as per specification, drawings & M3 81.46 - - - - - - - - - 81.46 15,926.87 1,297,402.83
instructions of the site engineer.
3.4 Providing, laying and curing first class brick masonry works in
cement, sand mortar (1:4) in substructure & ground floor for
partation wall finished in perfect lines & level as per M3 3.13 4.44 - 5.06 - 5.31 1.12 3.34 4.10 0.73 27.23 16,133.87 439,325.28
specification, drawings & instructions of the site engineer.

3.5 Providing, laying and curing first class brick masonry works in
cement, sand mortar (1:4) above ground floor for partation
wall finished in perfect lines & level as per specification, M3 2.93 - - - - - - - - - 2.93 16,376.70 47,983.73
drawings & instructions of the site engineer.
3.6 Providing, laying and curing stone masonry works in cement,
sand mortar (1:6) in substructure & compound wall finished in
perfect lines & level as per specification, drawings & M3 46.69 7.03 47.42 - - - - - - - 101.14 9,330.19 943,655.42
instructions of the site engineer.
4 CEMENT CONCRETE WORKS
4.1 Providing, laying, compacting and curing plain cement
concrete M10 (1:3:6) in foundation with cement, sand and
stone ballast 20mm gauge finishing to approved level, lines M3 19.24 1.80 4.31 - - - - 0.50 - - 25.85 2,710.56 70,067.98
and dimensions all complete as per drawings, specifications
and instruction of the site engineer.
4.2 Providing, laying, compacting and curing plain cement
concrete M15 (1:2:4) in Solid Floor with cement, sand and
stone ballast 20mm gauge finishing to approved level, lines M3 17.06 2.99 6.57 0.78 - 1.54 0.25 - - 0.02 29.21 2,710.56 79,175.46
and dimensions using all complete as per drawings,
specifications and instruction of the site engineer.
4.3 Providing, laying, compacting and curing M20 (1:1.5:3) plain cement
concrete for column, slab, beams, tie beam Lintel Sill and all kinds of
R.C.C. works with cement sand and stone ballast 20mm down
finishing to approved level, line and dimensions using mixer machine
M3 181.90 20.20 4.88 0.66 0.43 - 0.36 - 0.59 0.38 209.40 16,711.19 3,499,323.19
& vibrator all complete as per specifications, drawings and
instructions of the site engineer, all complete.

Prepared by- Checked by- Recommended by- Approved by-


35 of 123
Health Post Building, Thalajung
Abstract of Cost
Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity
Landscaping Inspection Pump Total Amount
Item No. Description of Work Unit Main Septic Soakpit Water Placenta Waste Rate Rs. Remarks
Toilet & Retaining Tank 19 House 2 Quantity (NRs.)
Building Wall Tank 2 Nos Tank Pit Burner
Nos Nos
4.4 Providing, laying, compacting and curing M20 (1:1.5:3) plain
cement concrete with silica cement admixture @ 5% for top
floor slab, beams and water tank of R.C.C. works with cement
sand and stone ballast 20mm down finishing to approved
level, line and dimensions using mixer machine & vibrator all m3 - - - - - - - 6.93 - - 6.93 25,129.71 174,148.89
complete as per specifications, drawings and instructions of
the site engineer, all complete.

5 REINFORCEMENT
5.1 Reinforcement bars (Fe 500 TMT) work including
straightening, cleaning, cutting, bending, binding with 20 SWG
annealed wire & fixing in position as per drawing, bar bending
schedule for raft foundation column, beam, wall, stair, slab in Kg 24,988.51 2,774.98 382.75 66.40 44.00 - 27.34 914.02 58.81 52.23 29,309.04 111.36 3,263,854.69
all R.C.C. works as per specification, drawing & instruction of
site engineer. Approved brands: Himal Iron, Panchakanya or
equivalent.

6 FORMWORKS
6.1 Centering and shuttering with approved waterproof plywood
for all kinds of R.C.C. work including all necessary steel
propping, scaffolding, staging, supporting, dismantling and
clearing from the site, including shuttering of circular column M2 1,556.04 165.83 - 6.59 3.30 - 3.54 29.00 4.72 2.89 1,771.91 111.36 197,319.90
up to 2 m dia etc. all complete as per design drawings,
specifications and instruction of the site engineer .

7 PLASTERING & POINTING WORKS


7.1 Providing, laying & curing 20 mm thick cement sand (1:4)
Plastering on inside wall and floor to perfect plumb, lines &
level all complete as per design drawings, specifications and M2 1,181.81 193.95 - - - - - - - - 1,375.76 432.77 595,387.66
instruction of the site engineer all complete:
7.2 Providing, laying & curing 12.5 mm thick cement sand (1:4)
Plastering on outside wall to perfect plumb, lines & level
including band (pani patti) for preventing the flow of rain
water from slab edges during rain fall all complete as per M2 911.98 151.12 7.20 27.38 - 19.24 12.06 - 6.82 - 1,135.80 321.96 365,682.17
design drawings, specifications and instruction of the site
engineer all complete:
7.3 Providing, laying & curing 12.5 mm thick cement sand (1:3)
plastering in ceiling, beams surfaces including chipping &
wetting the concrete surfaces finished in perfect plumb, lines M2 562.63 48.42 - - - - - - - - 611.05 368.57 225,214.70
and level as per drawings, specifications and instructions of
the site engineer.
7.4 Providing and pointing in perfect line, level and groove depth
with 1:3 cement sand mortar for joints of stone masonry
works above ground level in compound wall including raking
the joints, scafolding, curing the works all complete as per M2 - - 163.50 - - - - - - 6.97 170.47 218.77 37,293.72
specifications and instruction of the site engineer.

Prepared by- Checked by- Recommended by- Approved by-


36 of 123
Health Post Building, Thalajung
Abstract of Cost
Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity
Landscaping Inspection Pump Total Amount
Item No. Description of Work Unit Main Septic Soakpit Water Placenta Waste Rate Rs. Remarks
Toilet & Retaining Tank 19 House 2 Quantity (NRs.)
Building Wall Tank 2 Nos Tank Pit Burner
Nos Nos
8 FLOOR FINISHING
8.1 Providing and laying 25mm thick mosaic flooring & skirting -
6mm thick white cement and marble chips in (1:1) over 19 mm
thick cement sand plaster (1:2) in perfect line and level with M2 432.88 - - - - - - - - - 432.88 2,532.56 1,096,294.57
finish according to drawing and specificattion and instruction
of site engineer as all complete
8.2 Providing, laying and curing 3mm thk. (1:1) cement sand
punning on below plinth, appron, drain & skirting of buildings
on perfect line & level as per design, specification and M2 227.80 24.67 - 27.38 - 19.24 - 31.00 - - 330.09 210.64 69,530.16
instruction of site engineer.
8.3 Providing and paving 25mm thick telia brick in 1:2 lime surki
mortar and pointing with 1:1 cement sand mortar on terrace
to perfect plumb, lines & level all complete as per design M2 293.86 - - - - - - - - - 293.86 1,591.35 467,634.11
drawings, specifications and instruction of the site engineer all
complete.
8.4 Providing & laying porcelain non glazed floor tiles in 1:4
cement sand mortar in perfect lines & level finishing the joint
with white cement with or without pigments where necessary M2 41.06 28.51 - - - - - - - - 69.57 2,547.92 177,258.79
all complete as per design drawings, patterns, specifications
and instruction of the site engineer:
8.5 Providing & laying porcelain glazed wall tiles in 1:4 cement
sand mortar in perfect lines & level finishing the joint with
white cement with or without pigments where necessary all M2 54.18 85.87 - - - - - - - - 140.05 2,854.18 399,727.91
complete as per design drawings, patterns, specifications and
instruction of the site engineer:
8.6 Providing, laying and curing 38mm thick PCC (1:2:4) flooring
with punning on floor on perfect line & level as per design, M2 61.29 66.83 - - - - - - - - 128.12 119,479.82 15,307,754.54
specification and instruction of site engineer.
9 PAINTING WORKS
9.1 Providing & painting two coats of Enamel paint with one coat
of primer of approved brand and colour as per specifications M2 627.50 46.22 - - - - - - - - 673.72 228.24 153,769.85
and instruction of the site engineer.
9.2 Providing & painting two coats of Readymade acrylic
washable Distemper paint with one coat of cement primer of
approved brand and colour over plastered surfaces of M2 1,489.29 108.08 - - - - - - - - 1,597.37 117.44 187,595.13
building, walls ceiling and passage area as per specifications
and instruction of the site engineer.
9.3 Supplying and applying Two coat weather proof painting
(Apex or equivalent) with one coat of cement primer of
approved colour in outer side of building as per specifications M2 834.39 126.45 - - - - - - - - 960.84 221.37 212,701.15
and instruction of the site engineer.
10 DOORS AND WINDOWS WORKS
10.01 Suppling and fixing Salwood chaukhat frame works for doors
& windows as approved by site incharge , the timber shall be
matured,free from wraps. Knots holes and other defects all M3 4.692 0.571 - - - - - - - - 5.263 190,525.44 1,002,735.39
complete.

Prepared by- Checked by- Recommended by- Approved by-


37 of 123
Health Post Building, Thalajung
Abstract of Cost
Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity
Landscaping Inspection Pump Total Amount
Item No. Description of Work Unit Main Septic Soakpit Water Placenta Waste Rate Rs. Remarks
Toilet & Retaining Tank 19 House 2 Quantity (NRs.)
Building Wall Tank 2 Nos Tank Pit Burner
Nos Nos
10.02 Supplying and fixing 38 mm thick salwood panelled shutter in
door including fixing with approved size of heavy duty hinges,
brass tower bolts handle, locking set, door stopper, shock M2 18.69 - - - - - - - - - 18.69 9,693.99 181,180.67
absorber as per design and instruction all complete.

10.03 Supplying and fitting Ready made Teak wood Doors,special


(Seasoned and Poisoned treated ,one side teak) with heavy
duty 6" hinges, 6" aluminium tower bolts handle, 12" aldrops M2 32.35 - - - - - - - - - 32.35 1,886.00 61,012.10
set, door stopper, shock absorber all complete.

10.04 Supplying and fitting Ready made Teak wood Doors,special


(Seasoned and Poisoned treated ,one side teak & other side
water proof ply fitting) with heavy duty 6" hinges, 6" M2 6.31 11.72 - - - - - - - - 18.03 5,110.49 92,142.13
aluminium tower bolts handle, 12" aldrops set door stopper,
shock absorber all complete.
10.05 Supplying and fixing 4 mm thick glazed shutter in 38 mm thick
sal wood frame with approved size of heavy duty 4" hinges, 6"
aluminium tower bolts handle as per design and instruction all M2 62.07 3.66 - - - - - - - - 65.73 6,731.50 442,461.50
complete.
10.06 Supplying and fixing Mosquito proof net and expanded metal
net in 38 mm thick sal wood frame with approved size of
heavy duty 4" hinges, 6" aluminium tower bolts handle as per M2 65.53 3.66 - - - - - - - - 69.19 4,060.35 280,935.62
design and instruction all complete.
10.07 Providing and fixing 5 mm thick glass on fixed frame of
windows & ventilation with wooden listy as per design and M2 11.39 0.99 - - - - - - - - 12.38 850.89 10,534.02
instruction all complete.
10.08 Providing and Fitting 25mm thick well seasoned salwood
eavesboard with necessary nails, screws, metal brackets etc M2 6.95 - - - - - - - - - 6.95 4,184.06 29,079.22
as per drawing and instruction all complete.
10.09 Providing and fabricating MS grill with 10mmx10mm square
strips of approved pattern and manufacture finished with one
coat of metal primer paint with approved colour as per design, Kg 1,334.51 78.69 - - - - - - - - 1,413.20 1,886.00 2,665,295.20
drawing and instruction all complete.
10.10 Making & fixing MS door for pump house with locking
arrangement of approved pattern and manufacture finished
with one coat of metal primer paint and two coat of enamel L.S. - - - - - - 2.00 - - - 2.00 2,000.00 4,000.00
paint with approved colour as per design, drawing and
instruction all complete.
11 MISCELLANEOUS WORKS
Providing 26 gauge (0.41mm) Colour CGI sheet for roof
including fixing in proper shape & size with all necessary rails,
11.01 screws, bolts & nuts washers, J & L hocks etc as per drawing M2 77.85 - - - - - - - - - 77.85 1,090.30 84,879.86
& instruction all complete.
Providing and fitting 26 gauge (0.41mm) Colour G.I plane
sheet for ridge in proper shape and size with all necessary
11.02
screws, bolts and nuts as per drawing and instruction all Rm 8.00 - - - - - - - - - 8.00 642.85 5,142.80
complete

Prepared by- Checked by- Recommended by- Approved by-


38 of 123
Health Post Building, Thalajung
Abstract of Cost
Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity
Landscaping Inspection Pump Total Amount
Item No. Description of Work Unit Main Septic Soakpit Water Placenta Waste Rate Rs. Remarks
Toilet & Retaining Tank 19 House 2 Quantity (NRs.)
Building Wall Tank 2 Nos Tank Pit Burner
Nos Nos
Providing M.S. blackpipe Rafter, purlin, Post with I.S. or B.S.
section including jointting , fixing, erection and primer &
11.03 enamel painting with all necessary M.S. bed plates, shoe Kg 1,006.36 - - - - - - - - - 1,006.36 1,886.00 1,897,994.96
angles, anchor bolts leas sheeting or cement grouting as per
drawing and instructions all complete .
Providing 2" dia stainless steel pipe hand rail fixing on
staircase & verandah ( 3 line 1" dia pipe horizontal laying & 2"
11.04 dia pipe vertical laying at 2m c/c, ht 0.9m including painting as M2 86.72 - - - - - - - - - 86.72 2,767.22 239,973.32
per design drawing and specifications and instructions of site
engineer.
Providing, fabricating & fixing MS angle for water tank stand of
approved pattern and manufacture finished with one coat of
11.05 metal primer & enamel paint with approved colour as per Kg 249.04 - - - - - - - - - 249.04 1,886.00 469,689.44
design, drawing and instruction all complete.
Providing & fixing 2" dia stainless steel pipe hand rail fixing on
parapet wall including painting as per design drawing and
11.06 specifications and instructions of site engineer. Rm 198.16 - - - - - - - - - 198.16 460.00 91,153.60

Providing & fixing metal monkey ladder using rectangular


hollow section of 50x25x2 mm size with 450 mm wide with
11.07 one coat of metal primer & enamel paint as per design, kg 30.10 - - - - - - - - - 30.10 1,886.00 56,768.60
specification & instructions of Site Engineer all complete

Providing and fitting 26 gauge Colour G.I plane sheet gutter in


proper shape and size with all necessary brackets, screws,
11.08 bolts and nuts as per drawing and instruction all complete. Rm 31.50 - - - - - - - - - 31.50 986.64 31,079.16

Providing, fabricating & fixing iron gate using 40mm dia.


Medium Black pipe frame with 25mm dia. Medium black pipe
sub gate frame, 25x25x 2mm thick square pipe, 18 guage MS
sheet, 20x4.5 mm grill plate on top of gate and other
11.09 necessary hinges, tower bolt, aldrops and plates with one coat Kg - - 190.19 - - - - - - - 190.19 1,886.00 358,698.34
of metal primer & enamel paint as per design drawing,
specifications and instructions of site engineer all complete.

Providing and paving heavy duty concrete interlocking block


60mm thk siddhico or equivalent in walk way as per drawing,
11.10 design and instruction of site engineer all complete.. M2 - - 198.00 - - - - - - - 198.00 1,673.32 331,317.36

Supplying & Fixing 0.075x0.125 m size, 2.10m height


concrete (1:2:4) post with reinforcement for fencing at 2.00 m
11.11
interval as per design, drawing, specifications and instructions No - - 126.00 - - - - - - - 126.00 825.93 104,067.18
of site engineer.
Supplying & Fixing GI Barbed wire fencing work (5 layer
11.12 horizontal & 2 layer diagonal) as per design, drawing, Rm - - 1,867.50 - - - - - - - 1,867.50 1,886.00 3,522,105.00
specifications and instructions of site engineer.

Prepared by- Checked by- Recommended by- Approved by-


39 of 123
Health Post Building, Thalajung
Abstract of Cost
Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity
Landscaping Inspection Pump Total Amount
Item No. Description of Work Unit Main Septic Soakpit Water Placenta Waste Rate Rs. Remarks
Toilet & Retaining Tank 19 House 2 Quantity (NRs.)
Building Wall Tank 2 Nos Tank Pit Burner
Nos Nos
Providing and laying 2 coats of water proofing materials for
terrace roof (elastocrate cementious elastrometric water
11.13 proofing coating two components) capacity per Kg 6 sq ft as M2 292.86 55.59 - - - - - - - - 348.45 1,886.00 657,176.70
per specification and direction complete works.
Making & fixing 3mm thick MS sheet manhole cover
11.14 (.60cmx.60cm) as per design drawing, specifications and Set - - - - - - - 1.00 1.00 - 2.00 2,185.00 4,370.00
instructions of site engineer all complete.
Providing and fitting chimney of 100 nominal dia heavy gauge
structural steel pipe with 6mm thick ms flue cap plate on top
11.15 welded with 4 nos 38x6 ms slits on bottom surface of cap KG - - - - - - - - - 21.44 21.44 108.34 2,322.84
plate fix with mesh around cap to prevent ash as per drawing
and instruction all complete.
Providing and paving 50mm thk flag stone in 1:4 cement sand
mortar in perfect lines & level in walk way as per drawing,
11.16 M2 - - 60.00 - - - - - - - 60.00 1,431.36 85,881.60
design and instruction of site engineer all complete.

Supplying and planting outdoor gardening plants (Dhupi,


11.17 Kapur etc.) and flowering plants in specified space as per Tree - - 20.00 - - - - - - - 20.00 553.61 11,072.20
instruction of the site engineer all complete.
12 ELECTRICAL WORKS
12.1 LUMINAIRES ( FIXTURES)
Accessories:screws, gripes, pvc tape, choke, starter, Tube,
12.1.0
bulbs, holder, flexible wire,GI pipe/ chain etc all complete.

Ceiling ligh/Dome light 8" heavy carrier with CFL etc all
12.1.1 Set 66.00 66.00 4,511.45 297,755.70
complete.
12.1.2 Wall lamp with CFL lamp decorative etc all complete. Set 8.00 8.00 612.37 4,898.96
12.1.3 Wall lamp with GLS lamp decorative etc all complete. Set 9.00 9.00 353.62 3,182.58
12.1.4 Down light (concealed ) with CFL etc all complete. Set 6.00 6.00 1,175.87 7,055.22
12.1.5 Hanging light with CFL lamp decorative etc all complete. Set 1.00 1.00 2,134.40 2,134.40
1X40watt Tube light box type Wipro /Ge or eqvt. etc all
12.1.6 Set 24.00 24.00 1,564.57 37,549.68
complete.
2x40 watt tube light box type Wipro/Ge or eqvt.etc all
12.1.7 Set 4.00 4.00 2,336.22 9,344.88
complete.
2x40 watt tube light box mirror optic Wipro/Ge or eqvt.etc all
12.1.8 Set 4.00 4.00 5,269.30 21,077.20
complete.
12.1.9 Mirror light with CFL lamp decorativeor eqvt etc all complete. Set 9.00 9.00 612.37 5,511.33

12.1.10 Electrical bell musical type. Set 2.00 2.00 34.50 69.00
12.2 FAN / EXHAUST FAN
Accssories:as per sn A +nut, bolt, hook,clamp, regulator,
12.2.0
flexible wire etc all complete.
12.2.1 42'' ceiling fan Almonard/Bajaj or eqvt.etc all complete. Set 16.00 16.00 3,305.10 52,881.60
12.2.2 9"exhaust fan Almonard /Bajaj or eqvt.etc all complete. Set 10.00 10.00 3,390.20 33,902.00
12.2.3 16'' wall fan Almonard/Bajaj or eqvt.etc all complete. Set 1.00 1.00 3,473.57 3,473.57

Prepared by- Checked by- Recommended by- Approved by-


40 of 123
Health Post Building, Thalajung
Abstract of Cost
Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity
Landscaping Inspection Pump Total Amount
Item No. Description of Work Unit Main Septic Soakpit Water Placenta Waste Rate Rs. Remarks
Toilet & Retaining Tank 19 House 2 Quantity (NRs.)
Building Wall Tank 2 Nos Tank Pit Burner
Nos Nos
12.3 SOCKET,SWITCH ,JUNCTION BOX (Flush type)
Accessories: metal box ,screws ,gripes, flexible wire etc all
12.3.0
complete.
12.3.1 Dimmer switch for ceiling fan etc all complete. Set 16.00 16.00 34.50 552.00
12.3.2 Bell push switch Anchor or eqvt etc all complete. Set 2.00 2.00 34.50 69.00
16/6 Amps combined S/socket flush type with child lock
12.3.3 Set 65.00 65.00 34.50 2,242.50
Anchor or eqvt.etc all complete.
12.3.4 1 gang 1,2 way switch Anchor or eqvt.etc all complete. Set 22.00 22.00 34.50 759.00
12.3.5 2gang one way switch Anchor or eqvt.etc all complete. Set 18.00 18.00 34.50 621.00
12.3.6 3 gang one way switch Anchor or eqvt.etc all complete. Set 12.00 12.00 34.50 414.00
12.3.7 4 gang one way switch Anchor or eqvt.etc all complete. Set 14.00 14.00 34.50 483.00
12.3.8 6 gang one way switch Anchoror eqvt. etc all complete. Set 2.00 2.00 34.50 69.00
Junction box made of metal with cover size 6"X4" etc. all
12.3.9 Set 20.00 20.00 2,535.75 50,715.00
complete.
12.4 MAIN SWITCH / DISTRIBUTION BOARD

Accessories ;screws, gripes, nut bolt,cu bus bar,earth bus


12.4.0 bar, neutral bus bar,fuse, porcelin base ,cu. Strip for
connection, cable shoe ,phase bar,pvc tape etc all complete.

60 Amps Panel board made of mild steel sheet with cu.


busbar double cover floor mount suitable size & color push
12.4.1 Set 1.00 1.00 8,400.75 8,400.75
type lock for housing the following items all complete.(space
for 4 no. MCCB).

12.4.1.1 40- 50 Amps TP MCCB Siemens ,Ge or eqvt. for incoming. No 1.00 1.00 5,270.45 5,270.45

12.4.1.2 20-30 Amps TP MCCB Siemens, Geor eqvt. for outgoing. No 3.00 3.00 5,270.45 15,811.35
10 Amps DP MCB Siemens Ge,Merlin gerain or eqvt. for
12.4.1.3 No 2.00 2.00 1,530.65 3,061.30
main .
12.4.1.4 Ammeter 0-500A No 1.00 1.00 1,092.50 1,092.50
12.4.1.5 Voltmeter 0-500 v No 1.00 1.00 1,141.95 1,141.95
12.4.1.6 Selector switch No 2.00 2.00 793.50 1,587.00
12.4.1.7 CT coil of suitable ratio for panel board. No 3.00 3.00 1,598.50 4,795.50
12.4.1.8 Indicator with fuse No 3.00 3.00 264.50 793.50
Distribution board 6 way TPN made of mild steel sheet
12.4.2 double cover lockable Geco,Standard,Nepal made flush type Set 3.00 3.00 4,096.87 12,290.61
etc all complete.
25-32 Amps TP MCB Siemens Ge,Merlin gerain or eqvt. for
12.4.2.1 No 3.00 3.00 1,808.95 5,426.85
main.(1x3=3)
6,16,25 Amps. SP MCB Siemens,Ge,Merlin gerain or eqvt.
12.4.2.2 No 54.00 54.00 333.50 18,009.00
for light & power circuit.(18x3=54)
Distribution board 12 way SPN made of mild steel sheet
12.4.3 double cover lockable Geco,Standard, Nepal made flush type Set 2.00 2.00 2,624.87 5,249.74
etc all complete.
20 Amps DP MCB Siemens Ge,Merlin gerain or eqvt. for
12.4.3.1 No 2.00 2.00 1,530.65 3,061.30
main .(1x2=2)
6,16,25 Amps. SP MCB Siemens,Ge,Merlin gerain or eqvt.
12.4.3.2 No 24.00 24.00 333.50 8,004.00
for light , power & A/C circuit.(2x12=24)

Prepared by- Checked by- Recommended by- Approved by-


41 of 123
Health Post Building, Thalajung
Abstract of Cost
Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity
Landscaping Inspection Pump Total Amount
Item No. Description of Work Unit Main Septic Soakpit Water Placenta Waste Rate Rs. Remarks
Toilet & Retaining Tank 19 House 2 Quantity (NRs.)
Building Wall Tank 2 Nos Tank Pit Burner
Nos Nos
Distribution board 6 way SPN made of mild steel sheet
12.4.4 double cover lockable Geco,Standard, Nepal made flush type Set 1.00 1.00 2,017.67 2,017.67
etc all complete.
10 Amps DP MCB Siemens Ge,Merlin gerain or eqvt. for
12.4.4.1 No 1.00 1.00 1,530.65 1,530.65
main .
6 Amps. SP MCB Siemens,Ge,Merlin gerain or eqvt. for light
12.4.4.2 No 2.00 2.00 333.50 667.00
, power & A/C circuit.
12.5 POINT WIRING / WIRES/CABLES (concealed wiring )
Accessories:HDPE polythene pipe,screws,pvc tape, grips,
12.5.0
circular box etc all complete.
2x2.50 sq mm multi strand flexible cu .wire for light & fan Rate as
12.5.1 Point 166.00 166.00 893.10 148,254.60 provided by
point in 1/2"HDPE polythene pipe etc all complete. dudbc

2x4.0+1x1.50 sq.mm multi strand flexible cu wire for power Rate as


12.5.2 Point 65.00 65.00 1,489.50 96,817.50 provided by
point in 3/4" HDPE polythene pipe etc all complete. dudbc

10 sq.mm 4 core unarmoured copper cable for main panel


12.5.3 Rm 65.00 65.00 64.40 4,186.00
board to DB, through polythene pipe etc all complete.

2x6.0+1.50 sq.mm copper cable from panel board to( toilet


Rate as
12.5.4 block) DB-3, DB-4 to DB-5,DB -6 through 1" HDPE polythene Rm 60.00 60.00 269.40 16,164.00 provided by
pipe etc all complete. dudbc
8 swg copper wire for earth continuity from panel board to
12.5.5 DB,main switch & earthing site in 1/2"HDPE polythene pipe Rm 75.00 75.00 184.40 13,830.00
etc all complete.
12.6 EARTHING
Accessories :salt, coal, cu plate, HDPE polythene pipe., etc
12.6.0
all complete.

Earthing with cu plate size 65 cmx65cmx3.15mm with 8 swg


copper wire for earth continuity from panel board to earthing
12.6.1 site including excavation of 6 ft deep trench in moist area and Set 1.00 1.00 15,946.82 15,946.82
refilling the tranch with cubical salt and charcoal in alternet
layer with watering arrangement etc all complete.

13 SANITARY WORKS
Supplying and Fixing White glazed earthenware Indian pattern
Orissa Pan with low level Pvc flushing cistern ,trap,pipe
13.01 connector with complete accessories including bracket, flushing
pipe,pipe connector etc. all complete set. (Hindware, Parryware,
Classi
Indian pattern W C 530mm Orissa Pan with PVC low level
13.1.1 set 8.00 8.00 8,843.50 70,748.00
flushing cistern all complete set.
Supplying and Fixing Porcelain clay Indian Pattern Comode P or
S trap, Pvc Cistern and Plastic seat cover with pipe connector
13.02
all complete set (Hindware, Parryware, Classica, bolan or
equivalent.)
Indian pattern Comode with PVC low level flushing cistern
13.2.1 set 2.00 2.00 8,547.95 17,095.90
and seat cover all complete set.

Prepared by- Checked by- Recommended by- Approved by-


42 of 123
Health Post Building, Thalajung
Abstract of Cost
Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity
Landscaping Inspection Pump Total Amount
Item No. Description of Work Unit Main Septic Soakpit Water Placenta Waste Rate Rs. Remarks
Toilet & Retaining Tank 19 House 2 Quantity (NRs.)
Building Wall Tank 2 Nos Tank Pit Burner
Nos Nos
Supplying and fixing White glaze Indian Pattern Porcelain clay
wash basin/Oval with brackets 32mm dia. Pvc bottle trap,
13.3 32mm CP waste coupling , 15mmx450mm long c.p. pipe
connector etc all complete.Sanitaryware:-.
( Parryware,Hindware, or equivalent

Indian pattern Porcelain clay white glaze 55X40 cm Wash


13.3.1 set 6.00 6.00 7,073.65 42,441.90
Basin with pedestal and swan type piller cock complete set.

Porcelain clay white glaze Indian Pattern 55X40 cm size ,


13.3.2 wash basin with pedestal and central hole Aerator type basin Set 3.00 3.00 9,953.25 29,859.75
mixer etc all complete.
Indian pattern Porcelain clay white glaze Oval Wash Basin
13.3.3 50x40cm with inbuilt hole/over counter/under counter and set 4.00 4.00 5,377.40 21,509.60
swan type piller cock complete set.
Indian pattern White glazed porceline clay Urinal
13.3.4 46.5X31.5X26.5cm with necessary accessories all complete Set 2.00 2.00 3,151.00 6,302.00
set .
Porcelain clay white glaze Indian Pattern 68X30cm size Urinal
13.3.5 Set 1.00 1.00 2,443.75 2,443.75
partation all complete set .

Kitchen sink stainless steel 900x450x200mm depth with drain


13.3.6 Set 2.00 2.00 6,387.10 12,774.20
board 1mm thickness with Aerator/swan type sink cock.

Kitchen sink stainless steel 900x450x200mm depth with drain


13.3.7 board 1mm thickness with Aerator/swan type sink Mixer all one 5.00 5.00 8,788.30 43,941.50
complete set..
Supplying and Fixing ( Fabricated Scrub sink) The spalsh made
of 304 qwality prime grade of Stainless steel 16 swg
13.4 thickness,Floor mounted with leg(stand),kantipur kitchen
equipment, Qwality kitchen or equivalent.Sample to be approved
by project engineer

Stainless steel Scrub sink 1.5mt length,deep 500mm+150mm Rate as


13.4.1 set 1.00 1.00 74,071.50 74,071.50 provided by
splash dudbc
Supplying and Fixing Indian pattern C.P. valves with wall flange
13.5
Including c.p. nipple all complete set.
Rate as
13.5.1 15mm C.P. concealed stop cock with sliding flange Nos 9.00 9.00 1,910.15 17,191.35 provided by
dudbc
Chrome plate shower rose 7.5 cm dia.with wall flange all
13.5.2 nos 3.00 3.00 1,147.70 3,443.10
complete set.
13.5.3 15mm dia C.P. bath spout with wall flange. Nos 3.00 3.00 1,041.90 3,125.70
13.5.4 C.P. Bibcock 15mm dia long neck type with wall flange nos 8.00 8.00 1,041.90 8,335.20
13.5.5 15mm dia Angle valve with wall flange. nos 34.00 34.00 1,016.60 34,564.40
13.5.6 15mm dia two way angle valve nos 5.00 5.00 1,455.90 7,279.50
13.5.7 15 mm CP water spray with 1.2mt. Long flexiable pipe. set 2.00 2.00 2,035.15 4,070.30
15mm dia. Urinal Auto Closing Valve with built in Control
13.5.8 nos 2.00 2.00 2,810.60 5,621.20
Cock
Supplying and Fixing Indian pattern bathroom accessories all
13.6
complete set.

Prepared by- Checked by- Recommended by- Approved by-


43 of 123
Health Post Building, Thalajung
Abstract of Cost
Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity
Landscaping Inspection Pump Total Amount
Item No. Description of Work Unit Main Septic Soakpit Water Placenta Waste Rate Rs. Remarks
Toilet & Retaining Tank 19 House 2 Quantity (NRs.)
Building Wall Tank 2 Nos Tank Pit Burner
Nos Nos
13.6.1 Chrome plated toilet paper holder flap type(cover type). nos 2.00 2.00 639.40 1,278.80
13.6.2 Chrome plated soap tray(heavy). nos 18.00 18.00 639.40 11,509.20
13.6.3 C p 15mm dia x450mm long towel rod. nos 15.00 15.00 715.30 10,729.50
13.6.4 Looking Mirror Modi guard 450x600mm (18"x 24") nos 8.00 8.00 1,796.30 14,370.40
European pattern Stainless steel 45cm long with bend type
13.6.5 Set 2.00 2.00 5,192.25 10,384.50
Grab Bar .
Indian pattern Electric water heater (Geyser) with built up check
13.7 valve, pressure relief valve all complete set.
(Crompton,bajaj,Jaquar or equivalent.)
13.7.1 25 lit electric water heater (Geyser) nos 2.00 2.00 21,125.50 42,251.00
Supplying and Fixing Pvc roof water tank With screw type cover
13.8 including drain hole ,inlet outlet, over flow etc.all complete
set .Hill take, Roof top or equivalent
13.8.1 1000 lit capacity PVC water tank. nos 3.00 3.00 15,327.20 45,981.60
Supplying and Fixing Electric moter Pump single or three phase
13.9 phase with base, nut and bolts all complete set (Kirloskar,
Compton or equiv),
13.9.1 1HP Electric motor Pump monoblock. nos 1.00 1.00 13,813.80 13,813.80
13.9.2 0.5HP Electric motor Pump monoblock type. nos 1.00 1.00 10,402.90 10,402.90
Pressure sensor switch for pump auto switch off all complete
13.9.3 Set 2.00 2.00 4,478.90 8,957.80
set.
Supplying and fixing PPR pipe (hot and cold). or equivalent
with PPR fittings/ specials (Tees, elbows, Unions etc)
13.10
clamps(m.s plate with nut and bolt with hexagonal screws for
clamp in ceiling,wall), nails, including

20 mm PPR pipe, PN-10 \SDR 11, Pachanya, Napatop or eqv,


13.10.1 Rm 24.00 24.00 116.32 2,791.68
includes fixing/laying with necessary fittings all complete.

25 mm PPR pipe, PN-10 \SDR 11, Pachanya, Napatop or eqv,


13.10.2 Rm 174.00 174.00 161.16 28,041.84
includes fixing/laying with necessary fittings all complete.

32 mm PPR pipe, PN-10 \SDR 11, Pachanya, Napatop or eqv,


13.10.3 Rm 127.00 127.00 230.67 29,295.09
includes fixing/laying with necessary fittings all complete.

40 mm PPR pipe, PN-10 \SDR 11, Pachanya, Napatop or eqv,


13.10.4 Rm 42.00 42.00 366.28 15,383.76
includes fixing/laying with necessary fittings all complete.

Supplying and fixing PPR valve including jointing


13.11 materials. all complete set as per specification and
instruction.
13.11.1 20 mm dia PPR Brass Gate Valve all complete. Nos 2.00 2.00 513.50 1,027.00
13.11.2 25 mm dia PPR Brass Gate Valve all complete. Nos 10.00 10.00 686.51 6,865.10
13.11.3 32 mm dia PPR Brass Gate Valve all complete. Nos 7.00 7.00 1,101.74 7,712.18
13.11.4 40 mm dia PPR Brass Gate Valve all complete. Nos 2.00 2.00 1,775.46 3,550.92

Supplying and Fixing Gun metal gate valve/check valve full way
13.12
medium all complete set as per specification and instruction.

13.12.1 (G.M.) check valve 25mm dia nos 2.00 2.00 1,942.35 3,884.70

Prepared by- Checked by- Recommended by- Approved by-


44 of 123
Health Post Building, Thalajung
Abstract of Cost
Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity
Landscaping Inspection Pump Total Amount
Item No. Description of Work Unit Main Septic Soakpit Water Placenta Waste Rate Rs. Remarks
Toilet & Retaining Tank 19 House 2 Quantity (NRs.)
Building Wall Tank 2 Nos Tank Pit Burner
Nos Nos
THERMAL INSULATION TUBES:-Providing and fixing in position
6mm thick wall thickness thermal insulation tubes for
13.13
Insulation to hot water line pipes as per need joining and
covering .
15mm dia.6mm wall thickness insulation for hot water pipe all
13.13.1 Rm 6.00 6.00 173.65 1,041.90
complete.
20mm dia,6mm thick wall thickness insulation for hot water
13.13.2 Rm 42.00 42.00 220.80 9,273.60
pipe
Supplying and Fixing solar water heater with 3.0 k.w. electric
booster with thermostat all complete set. Technical spe.:-Inside
13.14 boiler M.S sheet 4.0 mm thick with Expansion joint(over lap
joint) in cover and bottom with 25x25x3 mm angle welded,4.0
kg/sq
300 lit. 3 panel solar heater fixing with electric booster all
13.14.1 Set 1.00 1.00 60,312.90 60,312.90
complete.
Supplying and Fixing uPVC pipe 6kg/sqcm all complete set as
13.15 per specification and instruction. (Dwv,Panchakanya,SN-4,
Prince,Supreme )
13.15.1 50mm PVC pipe of 6 kg/cm2 Rm 42.00 42.00 242.90 10,201.80
13.15.2 75mm PVC pipe of 6 kg/cm2 Rm 92.00 92.00 439.73 40,455.16
13.15.3 110mm PVC pipe of 6 kg/cm2 Rm 193.00 193.00 834.90 161,135.70

Supplying and Fixing UPVC specials with O ring rubber


washer,Pvc liquid(Solvent cement), Pvc cream,Pvc pipe clips
13.16
with screw,Vent cowl all complete set as per specification and
instruction. (Panchakanya,Prince,Supreme )

13.16.1 50 mm dia UPVC 90 degree bend nos 63.00 - 63.00 164.45 10,360.35
13.16.2 50 mm dia UPVC 45 degree bend. nos 21.00 21.00 163.30 3,429.30
13.16.3 50 mm dia UPVC plain Y-Tee. nos 3.00 3.00 189.75 569.25
13.16.4 75 mm dia UPVC vent cowl nos 5.00 5.00 194.35 971.75
13.16.5 75 mm dia UPVC plain. nos 5.00 5.00 304.75 1,523.75
13.16.6 75 mm dia UPVC door tee. nos 8.00 8.00 339.25 2,714.00
13.16.7 75 mm dia UPVC 90 degree bend. nos 18.00 18.00 263.35 4,740.30
13.16.8 75 mm dia UPVC door bend. nos 8.00 8.00 301.30 2,410.40
13.16.9 75 mm dia UPVC 45 degree bend. nos 12.00 12.00 235.75 2,829.00
13.16.10 75 mm dia UPVC Y branch. nos 3.00 3.00 324.30 972.90
13.16.11 75 mm dia UPVC pipe clip. nos 14.00 14.00 33.35 466.90
13.16.12 110 mm dia UPVC vent cowl. nos 3.00 3.00 319.70 959.10
13.16.13 110 mm dia UPVC plain . nos 2.00 2.00 520.95 1,041.90
13.16.14 110 mm dia UPVC Door Tee nos 4.00 4.00 572.70 2,290.80
13.16.15 110 mm dia UPVC 90 degree bend. nos 33.00 33.00 435.85 14,383.05
13.16.16 110 mm dia UPVC Door bend. nos 6.00 6.00 485.30 2,911.80
13.16.17 110 mm dia UPVC 45 degree bend nos 25.00 25.00 396.75 9,918.75
13.16.18 110 mm dia UPVC Y branch nos 6.00 6.00 592.25 3,553.50
13.16.19 110 mm dia UPVC pipe clip nos 40.00 40.00 44.85 1,794.00
Rate as
13.16.20 75x75mm dia.Pvc p-trap Nos 10.00 10.00 317.40 3,174.00 provided by
dudbc
13.16.21 110x110mm dia.Pvc p-trap Nos 10.00 10.00 526.70 5,267.00

Prepared by- Checked by- Recommended by- Approved by-


45 of 123
Health Post Building, Thalajung
Abstract of Cost
Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity
Landscaping Inspection Pump Total Amount
Item No. Description of Work Unit Main Septic Soakpit Water Placenta Waste Rate Rs. Remarks
Toilet & Retaining Tank 19 House 2 Quantity (NRs.)
Building Wall Tank 2 Nos Tank Pit Burner
Nos Nos
Rate as
13.16.22 110x75 red. Socket Nos 10.00 10.00 263.35 2,633.50 provided by
dudbc

13.16.23 5 kg fire extinguiser with pressure guage type all complete set. set 6.00 6.00 8,889.50 53,337.00

13.16.24 CI cover 45x45 cm size (medium).Round type set. nos 18.00 18.00 2,846.25 51,232.50
C I Cover round type 60x60cm, with locking arrangement Rate as
13.16.25 Set 1.00 1.00 2,750.11 2,750.11 provided by
(16kg) complete set. dudbc
Supplying and Fixing HDP Pipe 4 kg/sq.cm all complete set as
13.17 per specification and instruction. (Panchakanya or
equivalent(N.S. )
13.17.1 4 kg/cm2 (110 mm) HDP pipe. Rm 42.00 42.00 646.38 27,147.96
13.17.2 10 kg/cm2 (20 mm) HDP pipe including fittings & layings Rm 200.00 200.00 36.19 7,237.30
Providing and laying non-pressure NP2 class (light duty) RCC
pipes with collars jointed with stiff mixture of cement mortar in
13.18
the proportion of 1:2 (1 cement : 2 find sand) including testing of
joints etc. complete.
150 mm dia NP2 RCC Hume pipe including collar with all
13.18.1 Rm 39.00 39.00 888.20 34,639.80
complete.
Hiring & maintain 4WD vehicle to the project staff as
14 specified in special specification with 300lt. diesel Per month 2.00 2.00 127,276.40 254,552.81
month
Provisional cost for the expenses such as performance
bond commission, insurances (project period+
maintenance period+1 months), consultancy fees, cost of
preparation of as built drawings, cost of quality not to be
15
assurance tests, registration tax for town development job 1.00 1.00 409,888.46 409,888.46
filled by
committee before execution of work etc as per written contractor
instruction of the engineer. (The payment of this item will s
be done according to submitted original copy of related
invoices.)

Estimate Amount 49,034,549.46


Contingency (5%) 2,451,727.47
Sub Total 51,486,276.93
VAT (13%) 6,693,216.00
Total 58,179,492.93
For Budget Management
Price Adjustment Contingencies (10%) 5,148,627.69
Physical Contingency (10%) 5,148,627.69
Grand Total 68,476,748.31
IN FIG : Six Crore Eighty Four Lacs Seventy Six Thousand Seven Hundred Forty Eight and Paisa Thirty One Only

Prepared by- Checked by- Recommended by- Approved by-


46 of 123
Government of Nepal
Ministry of Urban Development
Department of Urban Development & Building Construction
Division Office
Gorkha

Provisional Sum
Project Name:- Construction of Thalajung Health Post Building.
Location:- Thalajung, Gorkha FY: 070/71

S.N. Description of Work Quantity Unit Rate Amount


A Insurance Provision
Insurance premium for the work, plant and
materials damage for contract work for all risk
1 including Riot, Strike, Damage, Malicious damage 1.00 Job 219,788.46 219788.46
and Terrorism for contract work of 4 crores for 2
years + 1 year Maintenance period.

Insurance premium for the insurance of owner and


consultant staff (named) Rs. 10,00,000.00 per
2 person for 20 persons with unlimited number of 1.00 Job 60,010.00 60010.00
occurances for two years.
Insurance Premium for construction equipments
3 and machines with value of Rs.20,00,000.00 for 2 1.00 Job 7,045.00 7045.00
years.
Insurance Premium for third party liability personal
4 only per person Rs.2,00,000.00 for 10 persons for 2 1.00 Job 9,045.00 9045.00
years with unlimited number of occurance.
B Laboratory Test Provision
Carrying out diferrent laboratory tests of
construction material like cement, rod, bricks, sand,
1 aggregate, filling materials, concrete cubes etc. 1.00 Job 44000.00 44000.00
during construction work as per specification and
direction.

C As Built Drawing Provision


Preparation of as built Architetectural, Sanitary &
1 Electrical drawing as per instruction all complete. 1.00 Job 50000.00 50000.00

Connection of Electric supply line from main


distribution pole to panel board and instalation of
D NEA electric meter with switable size MCB as per 1.00 Job 10000.00 10000.00
instruction of site engineer all complete.
Connection of Water supply line from main
distribution system to storage tank and instalation
E of water meter as per instruction of site engineer all 1.00 Job 10000.00 10000.00
complete.

Prepared By:- Checked By:- Recommended By:- Approved By:-


Sub Total 409888.46

Prepared By:- Checked By:- Recommended By:- Approved By:-


FY: 070/71

Remark

Prepared By:- Checked By:- Recommended By:- Approved By:-


Prepared By:- Checked By:- Recommended By:- Approved By:-
Government of Nepal
Ministry of Urban Development
Department of Urban Development & Building Construction
Division Office
Gorkha

Insurance Provision
Project Name:- Construction of Thalajung Health Post Building.
Location:- Thalajung, Gorkha FY: 070/71

1 Insurance premium for the work, plant and materials damage for contract work for all risk including
Riot,Strike, Damage,Malicious damage and Terrorism for contract work of 4 crores for 2 years + 1 year
Maintenance period.
Insurance with value 2,42,80,346.37 Rs. 3.03 per thousand Rs 147,332.72
do for Terrorism Rs. 1.49 per thousand Rs 72,450.74
Premium Rs 219,783.46
for stamp duty Rs 5.00
Premium with stamp duty Rs 219,788.46
VAT 13.00% of premium with stamp duty Rs 28,572.50
Total Amount with VAT Rs 248,360.96

2 Insurance premium for the insurance of owner and consultant staff (named) Rs. 10,00,000.00 per person
for 10 persons with unlimited number of occurances per annum
Personnel accident of 10,00,000.00 for 10 Rs.2.00 per thousand Rs 20,000.00
Do for Terrorism Rs.0.50 per thousand Rs 10,000.00
Premium Rs 30,000.00
For stamp duty Rs 5.00
Premium with stamp duty Rs 30,005.00
VAT 13.00% of premium with stamp duty Rs 3,900.65
Total Amount with VAT Rs 33,905.65 Per Annum

3 Insurance Premium for construction equipments and machines with value of Rs.20,00,000.00 for 2 years
Insurance premium of Rs. 20,00,000.00 Rs.2.03 per thousand Rs 4060.00
Do for Terrorism Rs.1.49 per thousand Rs 2980.00
Premium Rs 7040.00
For stamp duty Rs 5.00
Premium with stamp duty Rs 7045.00
VAT 13.00% of premium with stamp duty Rs 915.85
Total Amount with VAT Rs 7960.85

4 Insurance Premium for third party liability personal only per person Rs.2,00,000.00 for 10 persons for 2
years
P.A. of third party 10 per.=20,00,000.00 Rs. 3.03 per thousand Rs 6060.00
Do for Terrorism Rs. 1.49 per thousand Rs 2980.00
Premium Rs 9040.00
For stamp duty Rs 5.00
Premium with stamp duty Rs 9045.00
VAT 13.00% of premium with stamp duty Rs 1175.85

Prepared By:- Checked By:- Recommended By:- Approved By:-


Total Amount with VAT Rs 10220.85

Prepared By:- Checked By:- Recommended By:- Approved By:-


Government of Nepal
Ministry of Urban Development
Department of Urban Development & Building Construction
Division Office
Gorkha

Material Testing & 4WD Vehicle Hiring Cost

Project Name:- Construction of Health Post Building


Location:- Thalajung, Gorkha FY: 070/71

S No Description of work Quantity Unit Rate Amount Remarks


1 Concrete Test
a cubes or cylinder crushing 84.00 Nos 150.00 12,600.00
2 Brick Test
a Brick Crossing Test 6.00 Nos 100.00 600.00
b Water Absortion Test 6.00 Nos 100.00 600.00
c Brick Test 6.00 Nos 1400.00 8,400.00
3 Aggregate Test
a Aggregate Crushing Value Test 1.00 Nos 489.00 489.00
b Aggregate Impact Value 1.00 Nos 350.00 350.00
4 Sieve Analysis
a Sieve Analysis (Wet) 2.00 Nos 844.00 1,688.00
b Sieve Analysis (Dry) 2.00 Nos 450.00 900.00
5 U.T.M. Tensile Strength Test Nos
a 8mm Ø 2.00 Nos 1200.00 2,400.00
b 10mm Ø 2.00 Nos 1200.00 2,400.00
c 12mm Ø 2.00 Nos 1200.00 2,400.00
d 16mm Ø 2.00 Nos 1200.00 2,400.00
e 20mm Ø 2.00 Nos 1500.00 3,000.00
f 25mm Ø 2.00 Nos 1500.00 3,000.00
6 Cement Test
Cement mortar cube Crushing 3
a 3.00 Nos 450.00 1,350.00
Nos.
b Intial setting & Final Setting 3.00 Nos 500.00 1,500.00
Total 44,077.00
Say 44,000.00

Monthly Rate for Hiring 4WD Vehicle


S No Description Quantity Unit Rate Amount Remarks
1 Vehicle 1 month 70,000.00 70,000.00
2 Driver 1 person 13,330.00 13,330.00 per month
3 Fuel 300 litre 91.15 27,345.13 per month
Total 110,675.13
Overhead 15 % 16,601.27
Grand Total 127,276.40

Prepared by- Checked by- Recommended by- Approved by-


53 of 123
Construction of Health Post Building
Thalajung, Gorkha

Government of Nepal
Ministry of Urban Development
Department of Urban Development & Building Construction
Division Office
Gorkha
Detailed Estimate

Name of works :- Construction of Health Post Building


Place :- Thalajung, Gorkha Fiscal Year :- 070/71

Item Total
S.N. Description No Length Breadth Height Quantity
No Length
CIVIL WORKS

Clearing the site of all the vegetation,


roots and other unuseful materials
including excavation of top soil to a
depth of 15 cm, removing bushes,
trees and leveling the Site for stacking
1 1.1.1 the useful items in specified space and 1 – – – – 1.00
disposing other item before
commencing the construction work as
per instruction of the site engineer all
complete including layout of buildings,
roads and ancillary services.

Clearing the site of all the unuseful


materials including removing all them
2 1.1.2 from site and leveling the Site after 1 – – – – 1.00
completing the works as per instruction
of the site engineer all complete.

3 E/W in excavation in foundation -


column foundation - F1 8 1.50 12.00 1.50 1.725 31.05
F2 9 1.70 15.30 1.70 1.725 44.87
F3 3 1.90 5.70 1.90 1.725 18.68
F4 4 2.00 8.00 2.00 1.725 27.60
F5 2 2.30 4.60 2.30 1.725 18.25
wall foundation -
Grid A-A 1 6.10 6.10
Grid B-B, C-C 2 5.30 10.59
Grid D-D 1 4.80 4.80
Grid E-E 1 4.90 4.90
Grid F-F 1 4.90 4.90
Grid G-G 1 5.10 5.10
Grid 1-1 1 8.20 8.20
Grid 2-2 1 10.80 10.80
Grid 3-3 1 9.40 9.40
Grid 4-4 1 11.50 11.50
partation 5 3.36 16.80
2 3.96 7.92
1 1.50 1.50
102.51 0.60 0.825 50.74
veranda 1 17.60 17.60 0.35 0.675 4.16
Ramp side wall 1 5.40 5.40 0.35 0.675 1.28

Prepared by- Checked by- Recommended by- Approved by-


54 of 123
Construction of Health Post Building
Thalajung, Gorkha

Item Total
S.N. Description No Length Breadth Height Quantity
No Length
steps 1 2.75 2.75 0.90 0.675 1.67
1 2.45 2.45 0.90 0.675 1.49
1 1.00 1.00 0.90 0.675 0.61
1 1.00 1.00 1.50 0.675 1.01
Appron 1 67.25 67.25 0.505 0.175 5.94
drain 1 72.50 72.50 0.80 0.425 24.65
2.1 Total E/W = 232.00

Earth filling on floor with necessary L B Area


4
compaction
Dressing 1 3.36 3.96 13.31
EPI/MCH 1 3.36 3.96 13.31
Examination 1 3.36 3.96 13.31
Blood store 1 3.36 1.98 6.65
lobby 1 3.36 1.74 5.85
DOTS clinic 1 3.36 2.155 7.24
Dispensary 1 3.36 2.155 7.24
Administration/Registration 1 3.36 3.96 13.31
Waiting 1 3.36 3.96 13.31
1 3.36 2.155 7.24
store/lobby 1 3.36 3.96 13.31
lobby 1 3.36 1.50 5.04
stair case area 1 3.36 4.62 15.52
pre/post delivary+sluice 2 3.36 3.96 26.61
auto clave/ lobby 1 3.36 3.96 13.31
delivery 1 3.36 3.96 13.31
Verendaha 1 10.75 1.98 21.29
1 4.32 1.98 8.55
217.71 0.300 65.31
ramp 1 5.40 1.80 9.72 0.150 1.46
Back filling in foundation 33% of total excavation – 76.56
2.2 Total Earth filling 143.33

5 2.3 Sand filling with necessary compaction areas of floor = 217.71 0.150 32.66

6 Stone soling in foundation & floor-


column foundation - F1 8 1.50 12.00 1.50 0.150 2.70
F2 9 1.70 15.30 1.70 0.150 3.90
F3 3 1.90 5.70 1.90 0.150 1.62
F4 4 2.00 8.00 2.00 0.150 2.40
F5 2 2.30 4.60 2.30 0.150 1.59
Below beam
Grid A-A, B-B, C-C, D-D, E-E 5 9.75 48.73
Grid F-F, G-G 2 7.70 15.40
Grid 1-1 1 13.00 13.00
Grid 2-2, 3-3, 4-4 3 19.50 58.50
partation 5 3.36 16.80
2 3.96 7.92
1 1.50 1.50
161.85 0.35 0.15 8.50
veranda wall 1 17.60 17.60 0.35 0.15 0.92
Ramp side wall 1 5.40 5.40 0.35 0.15 0.28
steps 1 2.75 2.75 0.90 0.15 0.37
1 2.45 2.45 0.90 0.15 0.33
1 1.00 1.00 0.90 0.15 0.14

Prepared by- Checked by- Recommended by- Approved by-


55 of 123
Construction of Health Post Building
Thalajung, Gorkha

Item Total
S.N. Description No Length Breadth Height Quantity
No Length
1 1.00 1.00 1.50 0.15 0.23
Appron 1 67.25 67.25 0.505 0.15 5.09
drain 1 72.50 72.50 0.800 0.15 8.70
Floor area – areas of floor = 217.71 0.15 32.66
ramp 1 5.40 5.40 1.80 0.15 1.46
3.1.2 Total stone soling = 70.89

7 Masonary works : -
7.1 Stone masonry in 1:6 c/s mortar in sub structure
Foundation
Toe wall 1 161.85 161.85 0.35 0.60 33.99
veranda 1 17.60 17.60 0.35 0.975 6.01
Ramp side wall 1 5.40 5.40 0.35 0.675 1.28
steps 1 6.20 6.20 0.90 0.600 3.35
1 6.20 6.20 0.60 0.15 0.56
1 6.20 6.20 0.30 0.15 0.28
1 1.00 1.00 1.50 0.600 0.90
1 1.00 1.00 1.20 0.15 0.18
1 1.00 1.00 0.90 0.15 0.14
3.6 Total = 46.69

7.2 1st class B/W in 1:6 c/s mortar in ground floor


super structure
Grid wall 19 3.25 61.75 0.23 2.845 40.41
12 3.85 46.20 0.23 2.845 30.23
5 2.05 10.25 0.23 2.845 6.71
staircase wall 1 3.36 3.36 0.23 2.845 2.20
blood store wall 1 2.165 2.17 0.23 2.845 1.42
blood store wall 1 3.36 3.36 0.23 3.075 2.38
store/scrub partation 1 2.085 2.09 0.23 3.075 1.48
store/lobby partation 1 3.96 3.96 0.23 3.075 2.80
administration partation 1 2.56 2.56 0.23 1.800 1.06
135.70
drain 2 72.50 145.00 0.23 0.23 7.67
96.36
Deduction :-
GF DW1 1 1.80 1.80 0.23 2.60 -1.08
1 1.15 1.150 0.23 1.45 -0.38
D1 1 1.20 1.20 0.23 2.60 -0.72
D1A 2 1.20 2.40 0.23 2.60 -1.44
D1B 1 1.20 1.20 0.23 2.60 -0.72
D2 4 1.00 4.00 0.23 2.60 -2.39
D2A 2 1.00 2.00 0.23 2.60 -1.20
D2B 1 1.00 1.00 0.23 2.60 -0.60
D2C 1 1.00 1.00 0.23 2.60 -0.60
D3 3 0.90 2.70 0.23 2.60 -1.61
W1 8 1.80 14.40 0.23 1.40 -4.64
W1B 1 1.80 1.80 0.23 1.20 -0.50
W2 2 1.20 2.40 0.23 1.40 -0.77
W2A 2 1.20 2.40 0.23 1.40 -0.77
V2 8 1.20 9.60 0.23 0.60 -1.32
V2A 3 1.20 3.60 0.23 0.60 -0.50
V3 1 0.60 0.60 0.23 0.80 -0.11
opening 1 1.20 1.20 0.23 2.85 -0.79
3.2 Net B/W in Ground Floor = 76.22

Prepared by- Checked by- Recommended by- Approved by-


56 of 123
Construction of Health Post Building
Thalajung, Gorkha

Item Total
S.N. Description No Length Breadth Height Quantity
No Length

7.3 1st class B/W in 1:6 c/s mortar above ground floor -
Grid wall 11 3.25 35.75 0.23 2.85 23.39
11 3.85 42.35 0.23 2.85 27.71
2 2.05 4.10 0.23 2.85 2.68
1 1.925 1.93 0.23 2.85 1.26
living / kitchen partation 3 3.36 10.08 0.23 3.075 7.13
multipurpose hall wall 1 6.96 6.96 0.23 3.075 4.92
Top floor 2 3.25 6.50 0.23 2.85 4.25
2 3.85 7.70 0.23 2.85 5.04
2 2.05 4.10 0.23 2.85 2.68
119.47
Deduction : -
D1A 2 1.20 2.40 0.23 2.60 -1.44
D2A 2 1.00 2.00 0.23 2.60 -1.20
D3 4 0.90 3.60 0.23 2.60 -2.15
D3A 1 0.90 0.90 0.23 2.10 -0.43
D4A 3 0.75 2.25 0.23 2.60 -1.35
W1A 8 1.80 14.40 0.23 1.70 -5.63
W1B 1 1.80 1.80 0.23 1.20 -0.50
W2B 3 1.20 3.60 0.23 1.70 -1.41
W3 3 0.60 1.80 0.23 1.40 -0.58
V1 2 1.80 3.60 0.23 0.60 -0.50
DW 1 0.975 0.975 0.23 2.60 -0.58
1 1.225 1.225 0.23 1.70 -0.48
DW1 1 0.975 0.975 0.23 2.60 -0.58
1 1.225 1.225 0.23 1.70 -0.48
1st floor parapet wall at veranda 1 20.23 20.23 0.23 0.80 3.72
brick pillar on terrace 15 0.35 5.25 0.35 1.10 2.02
parapet wall at terrace 1 53.20 53.20 0.23 0.80 9.79
brick pillar on top terrace 6 0.35 2.10 0.35 1.10 0.81
parapet wall at top terrace 1 18.30 18.30 0.23 0.80 3.37
3.3 Net B/W in 1st and second floor = 81.46
7.4 1st class B/W in 1:4 c/s mortar in ground floor
super structure
auto clave partation 1 3.36 3.36 0.115 3.075 1.19
sluice partation 1 3.96 3.96 0.115 3.075 1.40
toilet 1 3.00 3.00 0.115 3.075 1.06
Deduction :-
D2B 1 1.00 1.00 0.115 2.60 -0.30
D4A 1 0.75 0.75 0.115 2.60 -0.22
3.4 Net B/W = 3.13

7.5 1st class B/W in 1:4 c/s mortar above ground floor -
toilet/kitchen partation 3 2.76 8.28 0.115 3.075 2.93
3.5 Net B/W = 2.93

8 1:3:6 P.C.C. in foundation -


Column foundation - F1 8 1.50 12.00 1.50 0.075 1.35
F2 9 1.70 15.30 1.70 0.075 1.95
F3 3 1.90 5.70 1.90 0.075 0.81
F4 4 2.00 8.00 2.00 0.075 1.20
F5 2 2.30 4.60 2.30 0.075 0.79
wall foundation - 1 161.85 161.85 0.35 0.075 4.25
veranda wall 1 17.60 17.60 0.35 0.075 0.46

Prepared by- Checked by- Recommended by- Approved by-


57 of 123
Construction of Health Post Building
Thalajung, Gorkha

Item Total
S.N. Description No Length Breadth Height Quantity
No Length
Ramp side wall 1 5.40 5.40 0.35 0.075 0.14
steps 1 2.75 2.75 0.90 0.075 0.19
1 2.45 2.45 0.90 0.075 0.17
1 1.00 1.00 0.90 0.075 0.07
1 1.00 1.00 1.50 0.075 0.11
Appron 1 67.25 67.25 0.505 0.10 3.40
Drain 1 72.50 72.50 0.800 0.075 4.35
4.1 Total p.c.c. 1:3:6 = 19.24

9 1:2:4 P.C.C. on floor


Floor area – areas of floor = 217.71 0.075 16.33
ramp 1 5.40 1.80 9.72 0.075 0.73
4.2 Total P.C.C. 1:2:4 = 17.06

10 1:1.5:3 P.C.C. for R.C.C. work -


Column base -
F1 8 1.50 12.00 1.50 0.15 2.70
F2 9 1.70 15.30 1.70 0.15 3.90
F3 3 1.90 5.70 1.90 0.15 1.62
F4 4 2.00 8.00 2.00 0.175 1.00
F5 2 2.30 4.60 2.30 0.175 2.83
Trapezoidal F1 h/3*(l^2+l'^2+l*l') 1.80
F2 h/3*(l^2+l'^2+l*l') 2.48
F3 h/3*(l^2+l'^2+l*l') 1.12
F4 h/3*(l^2+l'^2+l*l') 1.44
F5 h/3*(l^2+l'^2+l*l') 1.03
Column upto plinth
F1 & F2 column 17 0.35 5.95 0.35 1.75 3.64
F3 & F4 column 7 0.35 2.45 0.35 1.725 1.48
F5 column 2 0.35 0.70 0.35 1.70 0.42
Foundation beam 1 161.85 161.85 0.23 0.30 11.17
Tie beam 1 161.85 161.85 0.23 0.30 11.17
column
Ground floor C 26 0.35 9.10 0.35 3.075 9.79
First floor C 26 0.35 9.10 0.35 3.075 9.79
Top floor column 6 0.35 0.15 0.35 3.075 0.16
Floor beam :- GF 1 135.63 135.63 0.23 0.230 7.17
F floor - 1 135.63 135.63 0.23 0.230 7.17
top Floor 1 18.30 18.30 0.23 0.230 0.97
Slab :- Ground floor - 1 23.75 23.75 12.945 0.125 38.43
Deduction L corner 1 7.20 7.20 2.395 0.125 -2.16
Deduction of staircase opening 1 2.10 2.10 4.620 0.125 -1.21
Slab :- First floor - 1 23.75 23.75 12.945 0.125 38.43
Deduction L corner 1 7.20 7.20 2.395 0.125 -2.16
Deduction of staircase opening 1 3.360 3.360 4.620 0.125 -1.94
stair cover slab 1 5.75 5.75 8.745 0.125 6.29
steps 0.5*42 21 1.20 25.20 0.30 0.150 1.13
landing 7 1.20 8.40 1.20 0.125 1.26
inclined slab 2 2.40 4.80 1.20 0.125 0.72
2 2.00 4.00 1.20 0.125 0.60
4 1.35 5.40 1.20 0.125 0.81
Slab for sink
sink slab of Dressing, auto clave, Delivery 3 3.36 10.08 0.60 0.075 0.45
Sluice 1 3.00 3.00 0.60 0.075 0.14
counter slab in registration 1 2.00 2.00 0.60 0.075 0.09

Prepared by- Checked by- Recommended by- Approved by-


58 of 123
Construction of Health Post Building
Thalajung, Gorkha

Item Total
S.N. Description No Length Breadth Height Quantity
No Length
in dispensary 1 2.25 2.25 0.60 0.075 0.10
waiting 1 4.50 4.50 0.60 0.075 0.20
FF Kitchen sink slab area 2 4.32 8.64 0.60 0.075 0.39
FF pantry sink slab area 1 4.32 4.32 0.60 0.075 0.19
GF Sill band (wall length-opening) 1 118.40 118.40 0.325 0.075 2.89
FF Sill band 1 108.32 108.32 0.325 0.075 2.64
GF lintel band (wall length) 1 135.70 135.70 0.23 0.150 4.68
FF Lintel band (wall length) 1 119.47 119.47 0.23 0.150 4.12
Copping of parapet wall at top terrace
1 20.40 20.40 0.40 0.075 0.61
Copping of parapet wall at lower
terrace 1 78.68 78.68 0.40 0.075 2.36
4.3 Net R.C.C. Work = 181.90

Steel reinforcement for R.C.C. work


12 5.1 1.75% of Total R.C.C. = 24988.51
-
24.99

13 Form work -
Column -
F1 8 6.00 48.00 – 0.15 7.20
F2 9 6.80 61.20 – 0.15 9.18
F3 3 7.60 22.80 – 0.15 3.42
F4 4 8.00 32.00 – 0.175 5.60
F5 2 9.20 18.40 – 0.175 3.22

Column upto plinth


F1 & F2 column 17 1.40 23.80 – 1.75 41.65
F3 & F4 column 7 1.40 9.80 – 1.725 16.90
F5 column 2 1.40 2.80 – 1.70 4.76

Foundation beam 2 161.85 323.70 – 0.30 97.11


Tie beam 2 161.85 323.70 – 0.30 97.11
column
Ground floor C 26 1.40 36.40 – 3.075 111.93
First floor C 26 1.40 36.40 – 3.075 111.93
Top floor column 6 1.40 8.40 – 3.075 25.83
Floor beam :- G floor - 2 135.63 271.26 – 0.230 62.39
F floor - 2 135.63 271.26 – 0.230 62.39
top Floor 2 18.30 36.60 – 0.230 8.42
Slab :- Ground floor - 1 23.75 23.75 12.945 – 307.44
Slab side bar 1 73.39 73.39 – 0.125 9.17
Deduction L corner 1 7.20 7.20 2.395 – -17.24
Deduction of staircase opening 1 2.10 2.100 4.620 – -9.70
Slab :- First floor - 1 23.750 23.750 12.945 – 307.44
Slab side bar 1 73.39 73.39 – 0.125 9.17
Deduction L corner 1 7.20 7.20 2.395 – -17.24
Deduction of staircase opening 1 3.36 3.360 4.620 – -15.52
stair cover slab 1 5.75 5.75 8.745 – 50.28
Slab side bar 1 28.99 28.99 – 0.125 3.62
steps 42 1.200 50.40 – 0.150 7.56
landing 7 1.200 8.40 1.20 – 10.08
inclined slab 2 2.400 4.80 1.20 – 5.76
2 2.000 4.00 1.20 – 4.80

Prepared by- Checked by- Recommended by- Approved by-


59 of 123
Construction of Health Post Building
Thalajung, Gorkha

Item Total
S.N. Description No Length Breadth Height Quantity
No Length
4 1.350 5.40 1.20 – 6.48
Steps side 0.5x42 21 0.300 6.30 – 0.150 0.95
Slab for sink
sink slab of Dressing, auto clave, Delivery 3 3.36 10.08 0.675 – 6.80
Sluice 1 3.00 3.00 0.675 – 2.03
counter slab in registration 1 2.00 2.00 0.675 – 1.35
in dispensary 1 2.25 2.25 0.675 – 1.52
waiting 1 4.50 4.50 0.675 – 3.04
FF Kitchen sink slab area 2 4.32 8.64 0.675 – 5.83

Prepared by- Checked by- Recommended by- Approved by-


60 of 123
Construction of Health Post Building
Thalajung, Gorkha

Item Total
S.N. Description No Length Breadth Height Quantity
No Length
FF pantry sink slab area 1 4.32 4.32 0.675 – 2.92
GF Sill band (wall length-opening) 2 118.400 236.80 – 0.075 17.76
1 118.400 118.40 0.095 – 11.25
FF Sill band 2 108.320 216.64 – 0.075 16.25
1 108.320 108.32 0.095 – 10.29
GF lintel band (wall length) 2 135.700 271.40 – 0.150 40.71
FF Lintel band (wall length-partation) 2 119.470 238.94 – 0.150 35.84
parapet wall copping side bar 2 20.40 40.80 – 0.150 6.12
2 78.68 157.36 – 0.150 23.60
top floor column 17 1.40 23.80 – 1.200 28.56
6 1.40 8.40 – 1.200 10.08
6.1 Total Formwork = 1556.04

14 Plaster work :-
a 20 mm thick c/s plaster (1:4)
Inside
Ground floor
Dressing (3.36+3.96)*2 1 14.64 14.64 – 3.075 45.02
EPI/MCH (3.36+3.96)*2 1 14.64 14.64 – 3.075 45.02
Examination (3.36+2.76)*2 1 12.24 12.24 – 3.075 37.64
lobby (3.60+1.74)*2-1.74 1 8.94 8.94 – 3.075 27.49
Blood store (3.36+1.98)*2 1 10.68 10.68 – 3.075 32.84
DOTS clinic (3.36+2.155)*2 1 11.03 11.03 – 3.075 33.92
Dispensary (3.36+2.155)*2 1 11.03 11.03 – 3.075 33.92
Administration (3.36+3.96)*2 1 14.64 14.64 – 3.075 45.02
Registration partation 2 2.56 5.12 – 1.800 9.22
Waiting 1 16.19 16.19 – 3.075 49.78
lobby (1.82+5.695)*2-1.44 1 13.59 13.59 – 3.075 41.79
store (1.86+3.12)*2 1 9.96 9.96 – 3.075 30.63
scrub + lobby area (5.155+2.351)*2 1 15.01 15.01 – 3.075 46.16
stair case area (3.36+4.62)*2 1 15.96 15.96 – 3.075 49.08
pre/post delivery (5.345+3.96)*2 1 18.61 18.61 – 3.075 57.23
staff utility area (3.36+2.59)*2 1 11.90 11.90 – 3.075 36.59
delivery (3.36+3.96)*2 1 14.64 14.64 – 3.075 45.02
sluice (1.495+3.96)*2 1 10.91 10.91 – 3.075 33.55
beam 2*2 4 3.36 13.44 – 0.230 3.09
1*2 2 1.685 3.37 – 0.230 0.78
1*2 2 1.44 2.88 – 0.230 0.66
1*2 2 1.20 2.40 – 0.230 0.55
1*2 2 3.85 7.70 – 0.230 1.77
First floor
living cum dining (3.36+5.16)*2 2 17.04 34.08 – 3.075 104.80
kitchen (2.16+2.76)*2 2 9.84 19.68 – 3.075 60.52
toilet (1.08+2.76)*2 2 7.68 15.36 – 3.075 47.23
Bed room (3.36+3.96)*2 2 14.64 29.28 – 3.075 90.04
pantry (2.08+2.555)*2 1 9.27 9.27 – 3.075 28.51
toilet (1.08+2.555)*2 1 7.27 7.27 – 3.075 22.36
Open area (3.36+3.076)*2-1.2 1 11.67 11.67 – 3.075 35.89
stair case area 1 15.96 15.96 – 3.075 49.08
multi purpose hall (6.96+5.94)*2 1 25.80 25.80 – 3.075 79.34
beam 5*2 10 3.36 33.60 – 0.230 7.73
1*2 2 3.85 7.70 – 0.230 1.77
1*2 2 1.685 3.37 – 0.230 0.78
Top floor
stair case area 1 19.54 19.54 – 3.075 60.09

Prepared by- Checked by- Recommended by- Approved by-


61 of 123
Construction of Health Post Building
Thalajung, Gorkha

Item Total
S.N. Description No Length Breadth Height Quantity
No Length
Total inside plaster = 1294.91

Prepared by- Checked by- Recommended by- Approved by-


62 of 123
Construction of Health Post Building
Thalajung, Gorkha

Item Total
S.N. Description No Length Breadth Height Quantity
No Length
Deduction
GF DW1 0.5 1.80 0.90 – 2.60 -2.34
0.5 1.15 0.58 – 1.45 -0.83
D1 1 1.20 1.20 – 2.60 -3.12
D1A 3 1.20 3.60 – 2.60 -9.36
D1B 1 1.20 1.20 – 2.60 -3.12
D2 3.5 1.00 3.50 – 2.60 -9.10
D2A 3.5 1.00 3.50 – 2.60 -9.10
D2B 2 1.00 2.00 – 2.60 -5.20
D2C 1 1.00 1.00 – 2.60 -2.60
D2D 0 1.00 0.00 – 2.60 0.00
D3 6 0.90 5.40 – 2.60 -14.04
D3A 0.5 0.90 0.45 – 2.10 -0.95
D4 0 0.75 0.00 – 1.80 0.00
D4A 4 0.75 3.00 – 2.60 -7.80
W1 4 1.80 7.20 – 1.40 -10.08
W1A 4 1.80 7.20 – 1.70 -12.24
W1B 1 1.80 1.80 – 1.20 -2.16
W2 1.5 1.20 1.80 – 1.40 -2.52
W2A 1.5 1.20 1.80 – 1.40 -2.52
W2B 1.5 1.20 1.80 – 1.70 -3.06
W3 1.5 0.60 0.90 – 1.40 -1.26
V1 1 1.80 1.80 – 0.60 -1.08
V2 5 1.20 6.00 – 0.60 -3.60
V2A 3 1.20 3.60 – 0.60 -2.16
V3 0.5 0.60 0.30 – 0.80 -0.24
DW 0.5 0.975 0.488 – 2.60 -1.27
0.5 1.225 0.613 – 1.70 -1.04
DW1 0.5 0.975 0.488 – 2.60 -1.27
0.5 1.225 0.613 – 1.70 -1.04
Total Deduction -113.10
7.1 Total 20mm wall plaster = 1181.81

b 12.5mm Cement plaster (1:4) on outside wall -


Outside - G.F. front back 2 21.95 43.90 – 3.20 140.48
side 2 11.145 22.29 – 3.20 71.33
F.F. front back 2 21.95 43.90 – 3.20 140.48
side 2 11.145 22.29 – 3.20 71.33
pillar 5 1.40 7.00 – 3.075 21.53
T.F. 1 21.79 21.79 – 3.20 69.73
wall at veranda 2 16.80 33.60 – 1.000 33.60
4 2.045 8.18 – 1.000 8.18
brick pillar on terrace 15 1.400 21.00 – 1.200 25.20
parapet wall at terrace 2 53.20 106.40 – 1.00 106.40
Copping of parapet wall FF+SF 1 78.68 78.68 0.400 – 31.47
brick pillar on top terrace 6 1.40 8.40 – 1.20 10.08
parapet wall at top terrace 2 18.30 36.60 1.00 36.60
Copping of parapet wall TF 1 20.40 20.40 0.40 – 8.16
below plinth 2 24.225 48.45 – 0.60 29.07
2 13.42 26.84 – 0.60 16.10
outside steps floor 1 6.20 6.20 0.90 – 5.58
1 1.00 1.00 1.50 – 1.50
appron+drain 1 72.50 72.50 1.70 – 123.25
Deduction
GF DW1 0.5 1.80 0.90 – 2.60 -2.34

Prepared by- Checked by- Recommended by- Approved by-


63 of 123
Construction of Health Post Building
Thalajung, Gorkha

Item Total
S.N. Description No Length Breadth Height Quantity
No Length
0.5 1.15 0.58 – 1.45 -0.83
D1A 1 1.20 1.20 – 2.60 -3.12
D2 0.5 1.00 0.50 – 2.60 -1.30
D2A 0.5 1.00 0.50 – 2.60 -1.30
D3 1 0.90 0.90 – 2.60 -2.34
D3A 0.5 0.90 0.45 – 2.10 -0.95
W1 4 1.80 7.20 – 1.40 -10.08
W1A 4 1.80 7.20 – 1.70 -12.24
W1B 1 1.80 1.80 – 1.20 -2.16
W2 0.5 1.20 0.60 – 1.40 -0.84
W2A 0.5 1.20 0.60 – 1.40 -0.84
W2B 1.5 1.20 1.80 – 1.70 -3.06
W3 1.5 0.60 0.90 – 1.40 -1.26
V1 1 1.80 1.80 – 0.60 -1.08
V2 3 1.20 3.60 – 0.60 -2.16
V3 0.5 0.60 0.30 – 0.80 -0.24
DW 0.5 0.975 0.488 – 2.60 -1.27
0.5 1.225 0.613 – 1.70 -1.04
DW1 0.5 0.975 0.488 – 2.60 -1.27
0.5 1.225 0.613 – 1.70 -1.04
Total outside plaster = 899.31
FF wall skirting 1 63.36 63.36 – 0.20 12.67
7.2 Total 12.5mm plaster = 911.98

c 12.5 mm thick 1:3 cement plaster on ceiling


Inside ceiling
Ground floor
Dressing 1 3.36 3.36 3.96 – 13.31
EPI/MCH 1 3.36 3.36 3.96 – 13.31
Examination 1 3.36 3.36 2.76 – 9.27
lobby 1 3.60 3.60 1.74 – 6.26
Blood store 1 3.36 3.36 1.98 6.65
DOTS clinic 1 3.36 3.36 2.155 – 7.24
Dispensary 1 3.36 3.36 2.155 – 7.24
Administration and registration 1 3.36 3.36 3.96 – 13.31
Waiting 1 3.36 3.36 6.38 – 21.44
lobby 1 1.58 1.58 5.695 – 9.00
store 1 1.86 1.86 3.120 – 5.80
scrub 1 1.555 1.56 2.351 – 3.67
lobby 1 3.600 3.60 1.255 – 4.52
stair case area 1 3.36 3.36 4.62 – 15.52
pre/post delivery 1 5.345 5.35 3.96 – 21.19
staff utility area 1 3.36 3.36 2.59 – 8.70
delivery 1 3.36 3.36 3.96 – 13.31
sluice 1 1.495 1.50 3.96 – 5.94
First floor
living cum dining 2 3.36 6.72 5.16 – 34.68
kitchen 2 2.16 4.32 2.76 – 11.92
toilet 2 1.08 2.16 2.76 – 5.96
Bed room 2 3.36 6.72 3.96 – 26.61
pantry 1 2.08 2.08 2.555 – 5.31
toilet 1 1.08 1.08 2.555 – 2.76
Open area 1 3.36 3.36 3.076 – 10.34
staircase 1 3.36 3.36 4.62 – 15.52
multi purpose hall 1 6.96 6.96 5.94 – 41.34

Prepared by- Checked by- Recommended by- Approved by-


64 of 123
Construction of Health Post Building
Thalajung, Gorkha

Item Total
S.N. Description No Length Breadth Height Quantity
No Length
stair cover slab 1 3.36 3.36 6.41 – 21.54
Total inside ceiling 361.66
Outside ceiling
GF & FF slab projection 2 69.79 139.58 0.90 – 125.62
FF veranda ceiling 1 10.855 10.86 2.45 – 26.61
1 7.255 7.26 2.275 – 16.52
TF slab projection 1 25.12 25.12 0.900 – 22.61
beam 5*2 10 3.36 33.60 – 0.230 7.73
2*2 4 2.045 8.18 – 0.230 1.88
Total outside ceiling 200.97
7.3 Total ceiling plaster = 562.63

15 25mm thick mosaic flooring


Ground Floor area areas of floor = 217.71 – 217.71
deduction delivery toilet floor 1 1.20 1.20 1.68 – -2.02
wall skirting GF 1 229.73 229.73 – 0.20 45.95
opening deduction 1 18.45 18.45 – 0.20 -3.69
First Floor Room
Open area 1 3.36 3.36 3.076 – 10.34
multi purpose hall 1 6.96 6.96 5.94 – 41.34
FF veranda 1 10.855 10.86 2.45 – 26.61
1 7.255 7.26 2.275 – 16.52
wall skirting FF 1 37.47 37.47 – 0.20 7.49
opening deduction 1 5.10 5.10 – 0.20 -1.02
staircase area 2 3.36 6.72 4.62 – 31.05
steps 42 1.20 50.40 0.15 7.56
Top floor staircase area 1 3.36 3.36 1.74 – 5.85
sink slab of Dressing, auto clave, Delivery 3 3.36 10.08 0.675 – 6.80
Sluice 1 3.00 3.00 0.675 – 2.03
counter slab in registration 1 2.00 2.00 0.675 – 1.35
in dispensary 1 2.25 2.25 0.675 – 1.52
waiting 1 4.50 4.50 0.675 – 3.04
sink slab of Dressing, auto clave, Delivery 3 4.56 13.68
Sluice 1 3.60 3.60
scrub sink area 1 3.355 3.36
20.64 – 0.70 14.45
8.1 Total = 432.88

16 3mm cement punning in (1:1) Same as below plinth & step plaster 175.50
FF wall skirting 1 63.36 63.36 – 0.20 12.67
Copping of parapet wall FF+SF 1 78.68 78.68 0.400 – 31.47
Copping of parapet wall TF 1 20.40 20.40 0.40 – 8.16
8.2 Total punning = 227.80

17 25mm thick telia brick in 1:2 lime surki mortar


Terrace 1 15.30 15.30 12.355 189.03
1 7.86 7.86 9.960 78.29
deduction stair room 1 3.84 3.84 6.65 -25.54
top staircase terrace 1 5.16 5.16 8.21 42.36
ramp 1 5.40 5.40 1.80 – 9.72
8.3 Total = 293.86

18 a) Floor tiles work in c/s mortar (1:4) -


kitchen 2 2.16 4.32 2.76 – 11.92
pantry 1 2.08 2.08 2.555 – 5.31

Prepared by- Checked by- Recommended by- Approved by-


65 of 123
Construction of Health Post Building
Thalajung, Gorkha

Item Total
S.N. Description No Length Breadth Height Quantity
No Length
kitchen skirting 2 9.84 19.68 – 0.150 2.95
pantry skirting 1 9.27 9.27 – 0.150 1.39
FF Kitchen sink slab area 2 4.32 8.64 0.675 – 5.83
FF pantry sink slab area 1 4.32 4.32 0.675 – 2.92
GF toilet 1 1.20 1.20 1.68 – 2.02
FF toilet 2 1.080 2.160 2.76 – 5.96
1 1.080 1.080 2.555 – 2.76
8.4 Total floor tile = 41.06

b) Glazed wall tiles work in c/s mortar (1:4)


GF toilet 1 5.76 5.76
FF toilet 2 7.68 15.36
1 7.27 7.27
28.39 – 1.50 42.59
FF Kitchen sink slab area 2 5.52 11.04 – 0.700 7.73
FF pantry sink slab area 1 5.52 5.52 – 0.700 3.86
8.5 Total wall tile = 54.18

19 38mm thick P.C.C(1:2:4) punning


First floor floor area l b a
living cum dining 2 3.36 5.16 34.68 – 34.68
Bed room 2 3.36 3.96 26.61 – 26.61
8.6 Total = 61.29

20 Painting work
a 2 coats readymade enamel paints over one coats primer factor
Door GF DW1 1 1.80 1.80 2.25 2.60 10.53
DW1 1 0.975 0.98 2.25 2.60 5.70
DW 1 0.975 0.98 2.25 2.60 5.70
D1 1 1.20 1.20 2.25 2.60 7.02
D1A 4 1.20 4.80 2.25 2.60 28.08
D1B 1 1.20 1.20 2.25 2.60 7.02
D2 4 1.00 4.00 2.25 2.60 23.40
D2A 4 1.00 4.00 2.25 2.60 23.40
D2B 2 1.00 2.00 2.25 2.60 11.70
D2C 1 1.00 1.00 2.25 2.60 5.85
D3 7 0.90 6.30 2.25 2.60 36.86
D3A 1 0.90 0.90 2.25 2.10 4.25
D4A 4 0.75 3.00 2.25 2.60 17.55
W1 8 1.80 14.40 1.125 1.40 22.68
W1A 8 1.80 14.40 1.125 1.70 27.54
W1B 2 1.80 3.60 1.125 1.20 4.86
W2 2 1.20 2.40 1.125 1.40 3.78
W2A 2 1.20 2.40 1.125 1.40 3.78
W2B 3 1.20 3.60 1.125 1.70 6.89
W3 3 0.60 1.80 1.125 1.40 2.84
V1 2 1.80 3.60 1.125 0.60 2.43
V2 8 1.20 9.60 1.125 0.60 6.48
V2A 3 1.20 0.60 1.125 0.60 0.41
V3 1 0.60 0.60 1.125 0.80 0.54
Window GF DW1 1 1.15 1.15 1.125 1.45 1.88
DW1 1 1.225 1.225 1.125 1.70 2.34
DW 1 1.225 1.23 1.125 1.70 2.34
on eaves board both side 2 area 6.95 13.90
same as area of grill 62.07 62.07

Prepared by- Checked by- Recommended by- Approved by-


66 of 123
Construction of Health Post Building
Thalajung, Gorkha

Item Total
S.N. Description No Length Breadth Height Quantity
No Length
GF inside wall upto 1.2 m ht. 1 229.73 229.73 1.20 275.68
9.1 Total enamel paint = 627.50

b Two coat Distemper paint In inner ceiling & inner walls 1656.57
Deduction opening -113.10
deduction wall tile area -54.18
9.2 Total distemper paint 1489.29

c Two coats weather proof paint (apex) for outside


area- same as outer plaster+outside ceiling and below plinth 1112.95
Deduction opening -50.76
deduction punning area -227.80
9.3 Total = 834.39
21 Doors & windows Works
a Salwood Doors chaukhat
Door GF DW1 1 8.80 8.80
DW1 1 7.15 7.15
DW 1 7.15 7.15
D1 1 7.60 7.60
D1A 4 7.60 30.40
D1B 1 7.60 7.60
D2 4 7.20 28.80
D2A 4 7.20 28.80
D2B 2 7.20 14.40
D2C 1 7.20 7.20
D3 7 7.00 49.00
D3A 1 5.10 5.10
D4A 4 5.95 23.80
W1 8 7.80 62.40
W1A 8 10.50 84.00
W1B 2 7.20 14.40
W2 2 5.20 10.40
W2A 2 6.40 12.80
W2B 3 7.00 21.00
W3 3 4.00 12.00
V1 2 5.40 10.80
V2 8 3.60 28.80
V2A 3 3.60 0.60
V3 1 2.80 0.60
Window GF DW1 1 5.20 5.20
DW1 1 5.85 5.85
DW 1 5.85 5.85
500.50 0.125 0.075 4.692
10.01 Total 4.692

b 38mm thick wooden panel shutter


Door GF DW1 1 1.675 1.675 2.04 3.41
D1A 3 1.075 3.225 2.04 6.57
D2 1 0.875 0.875 2.04 1.78
D2A 1 0.875 0.875 2.04 1.78
D2B 2 0.875 1.750 2.04 3.57
D3 1 0.775 0.775 2.04 1.58
10.02 Total 18.69

c 38mm thick Ready made Teak wood shutter

Prepared by- Checked by- Recommended by- Approved by-


67 of 123
Construction of Health Post Building
Thalajung, Gorkha

Item Total
S.N. Description No Length Breadth Height Quantity
No Length
D1 1 1.075 1.075 2.04 2.19
D1A 1 1.075 1.075 2.04 2.19
D1B 1 1.075 1.075 2.04 2.19
D2 3 0.875 2.625 2.04 5.35
D2A 3 0.875 2.625 2.04 5.35
D2C 1 0.875 0.875 2.04 1.78
D3 5 0.775 3.875 2.04 7.90
D3A 1 0.775 0.775 2.04 1.58
D4A 3 0.625 1.875 2.04 3.82
10.03 Total 32.35

d 38mm thick Ready made water proof Teak wood shutter


Door DW 1 0.850 0.850 2.04 1.73
Door DW1 1 0.850 0.850 2.04 1.73
D3 1 0.775 0.775 2.04 1.58
D4A 1 0.625 0.625 2.04 1.27
10.04 Total 6.31

e Glazed shutter
W1 8 1.625 13.000 1.275 16.58
W1A 8 1.625 13.000 1.275 16.58
W1B 2 1.625 3.250 1.275 4.14
W2B 3 1.075 3.225 1.525 4.92
W2 2 1.075 2.150 1.275 2.74
W3 3 0.475 1.425 1.275 1.82
W2A 2 1.075 2.150 1.275 2.74
V1 2 1.625 3.250 0.475 1.54
V2 8 1.075 8.600 0.475 4.09
V2A 3 1.075 3.225 0.475 1.53
V3 1 0.475 0.600 0.675 0.41
Window GF DW1 1 1.100 1.100 1.275 1.40
DW1 1 1.175 1.175 1.525 1.79
DW 1 1.175 1.175 1.525 1.79
10.05 Total 62.07

f Mosquito proof shutter


Same as glazed shutter area 62.07
FF door shutter 2 0.850 1.700 2.04 3.46
10.06 Total 65.53

g 5mm thick fixed glass


D1 10 1.075 10.750 0.375 4.03
D1A 1 1.075 1.075 0.375 0.40
D1B 1 1.075 1.075 0.375 0.40
D2 3 0.875 2.625 0.375 0.98
D2A 3 0.875 2.625 0.375 0.98
D2C 1 0.875 0.875 0.375 0.33
D3 6 0.775 4.650 0.375 1.74
D3A 1 0.775 0.775 0.375 0.29
D4A 4 0.625 2.500 0.375 0.94
Door DW 1 1.738 1.738 0.375 0.65
Door DW1 1 1.738 1.738 0.375 0.65
10.07 Total 11.39

22 25mm thick eaves board fixing works

Prepared by- Checked by- Recommended by- Approved by-


68 of 123
Construction of Health Post Building
Thalajung, Gorkha

Item Total
S.N. Description No Length Breadth Height Quantity
No Length
GF veranda 1 20.30 20.30 – 0.20 4.06
1 6.02 6.02 – 0.20 1.20
1 5.58 5.58 – 0.20 1.12
1 2.83 2.83 – 0.20 0.57
10.08 Total 6.95

23 10mmx10mm square m.s steel grill work


Same as glazed shutter area 62.07
Total 62.07
area kg/m2
10.09 62.07 21.50 Total 1334.51

Prepared by- Checked by- Recommended by- Approved by-


69 of 123
Construction of Health Post Building
Thalajung, Gorkha

Item Total
S.N. Description No Length Breadth Height Quantity
No Length
24 26 Guage (0.41 mm ) Colour C.G.I. sheet roofing work.
1 20.30 20.30 3.00 – 60.90
1 3.22 3.22 3.00 – 9.66
1 2.43 2.43 3.00 – 7.29
11.01 Total = 77.85

25 26 Guage (0.41 mm ) Colour Plain sheet roofing works for ridge.


2 4.00 8.00 – 8.00
11.02 Total = 8.00

26 Black pipe iron work of medium class for rafter, purlin, post
80 mm dia. Post 11 3.90 42.90 8.48 kg/m 363.79
50 mm dia. Rafter 9 2.90 26.10 5.10 kg/m 133.11
2 4.00 8.00 5.10 kg/m 40.80
40 mm dia. Purlin 4 17.50 70.00 3.61 kg/m 252.70
4 4.62 18.48 3.61 kg/m 66.71
4 4.00 16.00 3.61 kg/m 57.76
nutbolt, plate @ 10% = 91.49
11.03 Total = 1006.36

Providing 2" dia stainless steel pipe


hand rail fixing on staircase &
verandah ( 3 line 1" dia pipe
horizontal laying & 2" dia pipe
27 vertical laying at 2m c/c, ht 0.9m
including painting as per design
drawing and specifications and
instructions of site engineer

Stair case 1 20.40 20.40 0.90 18.36


Ramp 1 20.85 20.85 0.90 18.77
veranda railing 1 55.11 55.11 0.90 49.60
11.04 Total = 86.72

28 MS angle Water tank stand


50 x50 x 5 mm 6 2.45 14.70
14.70 3.80 kg/m 55.86
40 x40 x 5 mm 4 3.50 14.00
9 3.00 27.00
4 1.50 6.00
4 2.40 9.60
56.60 3.00 kg/m 169.80
25 x 25 x 4 mm 1 2.45 2.45
2 3.00 6.00
2 1.50 3.00
9 0.30 2.70
8.45 1.40 kg/m 11.83
20 x 4.5 mm grill plate 11 1.500 16.50 0.70 kg/m 11.55
11.05 Total = 249.04

Providing & fixing 1.5" dia stainless


steel pipe hand rail fixing on parapet
wall including painting as per
29 design drawing and specifications
and instructions of site engineer

on Parapet wall 2 99.08 198.16 198.16

Prepared by- Checked by- Recommended by- Approved by-


70 of 123
Construction of Health Post Building
Thalajung, Gorkha

Item Total
S.N. Description No Length Breadth Height Quantity
No Length
11.06 Total = 198.16

Providing & fixing metal monkey


ladder using rectangular hollow
section of 50x25x2 mm size with 450
30 mm wide as per design,
specification & instructions of Site
Engineer all complete

Rectangular ms pipe 50x25x2mm 2 3.90 7.80


12 0.45 5.40
13.20 2.28 kg/m 30.10
11.07 Total = 30.10

31 11.08 Plain sheet gutter 1 31.50 31.50

32 Providing and laying 2 coats of


water proofing materials for terrace
roof (elastocrate cementious
elastrometric water proofing coating
two components) capacity per Kg 6
sq ft as per specification and
direction complete works.

Terrace 1 15.30 15.30 12.355 189.03


1 7.86 7.86 9.960 78.29
deduction stair room 1 3.84 3.84 6.65 -25.54
top staircase terrace 1 5.16 5.16 8.21 42.36
FF toilet 2 1.080 2.160 2.76 5.96
1 1.080 1.080 2.555 2.76
11.13 Total = 292.86

14 Hiring and maintaining 4 wheel drive


33 for office personnel during the 2 2.00
project period

34 15 Provisional cost 1 1.00

Providing and maintaining site


office (room of about 12 sqm)
35 during the project period including 15 15.00
necessary furniture for the
personnel of the office staff
1.1.3

Prepared by- Checked by- Recommended by- Approved by-


71 of 123
Construction of Health Post Building
Thalajung, Gorkha

Government of Nepal
Ministry of Urban Development
Urban Development & Building Construction
Division Office
Gorkha
Detailed Estimate

Fiscal Year :- 070/71

Remarks

L.S.

L.S.

M3
,,
,,
,,
,,

M3
,,
,,

Prepared by- Checked by- Recommended by- Approved by-


72 of 123
Construction of Health Post Building
Thalajung, Gorkha

Remarks

,,
,,
,,
,,
,,
,,
M3

M3

M3

M3
,,
,,
,,
,,

M3
,,
,,
,,
,,
,,

Prepared by- Checked by- Recommended by- Approved by-


73 of 123
Construction of Health Post Building
Thalajung, Gorkha

Remarks

,,
,,
,,
,,
,,
M3

M3
,,
,,
,,
,,
,,
,,
,,
,,
M3

M3
,,
,,
,,
,,
,,
,,
,,
,,

M3
M3

M3
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
M3

Prepared by- Checked by- Recommended by- Approved by-


74 of 123
Construction of Health Post Building
Thalajung, Gorkha

Remarks

M3
,,
,,
,,
,,
,,
,,
,,
,,

M3
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
M3

M3
,,
,,

M3
,,
M3

M3
M3

M3
,,
,,
,,
,,
,,
,,

Prepared by- Checked by- Recommended by- Approved by-


75 of 123
Construction of Health Post Building
Thalajung, Gorkha

Remarks

,,
,,
,,
,,
,,
,,
,,
M3

M3
,,
M3

M3
,,
,,
,,
,,
,,
,,
,,
,,
,,

M3
,,
,,
,,
,,

M3
,,
,,
,,
,,

,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,

M3
,,
,,

Prepared by- Checked by- Recommended by- Approved by-


76 of 123
Construction of Health Post Building
Thalajung, Gorkha

Remarks

,,
,,
,,
,,
,,
,,
,,
,,

,,

,,
M3

Kg

Mt

M2
,,
,,
,,
,,

M2
,,
,,

M2
,,

M2
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,

Prepared by- Checked by- Recommended by- Approved by-


77 of 123
Construction of Health Post Building
Thalajung, Gorkha

Remarks

,,
,,

M2
,,
,,
,,
,,
,,

Prepared by- Checked by- Recommended by- Approved by-


78 of 123
Construction of Health Post Building
Thalajung, Gorkha

Remarks

,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
M2

M2
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,

M2
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,

M2

Prepared by- Checked by- Recommended by- Approved by-


79 of 123
Construction of Health Post Building
Thalajung, Gorkha

Remarks

M2

Prepared by- Checked by- Recommended by- Approved by-


80 of 123
Construction of Health Post Building
Thalajung, Gorkha

Remarks

M2
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
M2
M2

M2
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,

M2

Prepared by- Checked by- Recommended by- Approved by-


81 of 123
Construction of Health Post Building
Thalajung, Gorkha

Remarks

,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
M2

M2

M2
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,

M2
,,
,,
,,
,,
,,
,,
,,
,,

Prepared by- Checked by- Recommended by- Approved by-


82 of 123
Construction of Health Post Building
Thalajung, Gorkha

Remarks

,,
M2

M2
,,
,,
,,
,,
,,
M2
M2

M2
,,
,,
,,

,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,

M2
M2

M2
,,
,,
,,
M2

,,
,,
,,
,,
,,
M2

M2
,,

Prepared by- Checked by- Recommended by- Approved by-


83 of 123
Construction of Health Post Building
Thalajung, Gorkha

Remarks

,,
,,
,,
,,
,,
,,
,,
M2

M2
,,
,,
M2

M2
,,
M2

M2
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,

Prepared by- Checked by- Recommended by- Approved by-


84 of 123
Construction of Health Post Building
Thalajung, Gorkha

Remarks

,,
M2

M2
,,
,,
M2

M2
,,
,,
M2

M3
M3

M2
,,
,,
,,
,,
,,
M2

Prepared by- Checked by- Recommended by- Approved by-


85 of 123
Construction of Health Post Building
Thalajung, Gorkha

Remarks

M2
,,
,,
,,
,,
,,
,,
,,
,,
M2

M2
,,
,,
,,
M2

M2
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
M2

M2
,,
M2

M2
,,
,,
,,
,,
,,
,,
,,
,,
,,
,,
M2

Prepared by- Checked by- Recommended by- Approved by-


86 of 123
Construction of Health Post Building
Thalajung, Gorkha

Remarks

M2
,,
,,
,,
M2

M2

Kg

Prepared by- Checked by- Recommended by- Approved by-


87 of 123
Construction of Health Post Building
Thalajung, Gorkha

Remarks

M2
,,
,,
M2

Rm
Rm

Kg
,,
,,
,,
,,
,,
,,
Kg

M2

M2

Kg

Kg

Kg
Kg
Kg

Prepared by- Checked by- Recommended by- Approved by-


88 of 123
Construction of Health Post Building
Thalajung, Gorkha

Remarks

Rm

kg

Rm

M2
,,
,,
,,
,,
,,
M2

month

job

month

Prepared by- Checked by- Recommended by- Approved by-


89 of 123
Construction of Toilet Block
Thalajung, Gorkha

Government of Nepal
Ministry of Urban Development
Department of Urban Development & Building Construction
Division Office
Gorkha
Detailed Estimate

Name of works :- Construction of Toilet block


Place :- Thalajung, Gorkha Fiscal Year :- 070/71

Item Total
S.N. Description No Length Breadth Height Quantity Remarks
No Length
1 E/W in excavation in foundation -
column foundation - F1 6 1.30 7.80 1.30 1.725 17.49 M3
wall foundation -
Grid A-A, B-B, C-C 3 3.32 9.96
Grid 1-1, 2-2 2 4.86 9.72
19.68 0.60 0.825 9.74 M3
Ramp side wall 2 5.40 10.80 0.35 0.675 2.55 ,,
steps 1 1.50 1.50 0.60 0.675 0.61 ,,
2.1 Total E/W = 30.39 M3

Earth filling on floor with necessary L B Area


2
compaction
Room 1 3.07 4.49 13.78
1 4.00 4.49 17.96
31.74 0.150 4.76 M3
ramp 1 5.40 0.80 4.32 0.150 0.65 ,,
Back filling in foundation 33% of total excavation – 10.03 ,,
2.2 Total Earth filling 15.44 M3

3 2.3 Sand filling with necessary compaction areas of floor = 31.74 0.150 4.76 M3

4 Stone soling
column foundation - F1 6 1.30 7.80 1.30 0.150 1.52 M3
Below beam
Grid A-A, B-B, C-C 3 4.27 12.81
Grid 1-1, 2-2 2 6.76 13.52
26.33 0.35 0.150 1.38 M3
Ramp side wall 2 5.40 10.80 0.35 0.150 0.57 ,,
steps 1 1.50 1.50 0.60 0.150 0.14 ,,
Floor area area = 31.74 0.150 4.76 ,,
ramp 1 5.40 5.40 0.80 0.150 0.65 ,,
3.1.2 Total soling = 9.02 M3

5 Masonary works : -
5.1 Stone masonry in 1:6 c/s mortar in sub structure
Foundation wall 1 26.33 26.33 0.35 0.45 4.15 M3
Ramp side wall 2 5.40 10.80 0.35 0.600 2.27 ,,
steps 1 1.50 1.50 0.60 0.600 0.54 ,,
1 1.50 1.50 0.30 0.150 0.07 ,,
3.6 Total = 7.03 M3

5.2 Brick Masonry work in 1:6


super structure

Prepared by- Checked by- Recommended by- Approved by-


90 of 123
Construction of Toilet Block
Thalajung, Gorkha

Item Total
S.N. Description No Length Breadth Height Quantity Remarks
No Length
wall 3 4.27 12.81 0.23 2.845 8.38 M3
2 2.91 5.82 0.23 2.845 3.81 ,,
2 3.85 7.70 0.23 2.845 5.04 ,,
Deduction for opening
D2A 2 1.00 2.00 0.23 2.60 -1.20 M3
D2D 1 1.00 1.00 0.23 2.60 -0.60 ,,
W2 2 1.20 2.40 0.23 1.40 -0.77 ,,
V2 1 1.20 1.20 0.23 0.60 -0.17 ,,
V3 5 0.60 3.00 0.23 0.80 -0.55 ,,
parapet wall at terrace 1 24.60 24.60 0.23 0.80 4.53 ,,
3.2 Total brick masonry 1:6 = 18.47 M3

5.3 Brick Masonry work in 1:4


male toilet partation wall 1 4.48 4.48 0.115 3.075 1.58 M3
2 1.65 3.30 0.115 3.075 1.17 ,,
1 2.70 2.70 0.115 3.075 0.95 ,,
female toilet partation wall 1 3.07 3.07 0.115 1.800 0.64 ,,
2 1.50 3.00 0.115 1.800 0.62 ,,
urinal partation wall 2 0.75 1.50 0.115 1.500 0.26 ,,
Deduction for opening
D4 5 0.75 3.75 0.115 1.80 -0.78 M3
3.4 Total brick masonry 1:4 = 4.44 M3

6 1:3:6 P.C.C. in foundation -


column foundation - F1 6 1.30 7.80 1.30 0.075 0.76 M3
Below beam
Grid A-A, B-B, C-C 3 4.27 12.81
Grid 1-1, 2-2 2 6.76 13.52
26.33 0.35 0.075 0.69 M3
Ramp side wall 2 5.40 10.80 0.35 0.075 0.28 ,,
steps 1 1.50 1.50 0.60 0.075 0.07
4.1 Total p.c.c. 1:3:6 = 1.80 M3

7 1:2:4 P.C.C. on floor


Floor area – areas of floor = 31.74 0.075 2.38 M3
ramp 1 5.40 5.40 1.50 0.075 0.61 ,,
4.2 Total P.C.C. 1:2:4 = 2.99 M3

8 1:1.5:3 P.C.C. for R.C.C. work -


Column base -
F1 6 1.30 7.80 1.30 0.15 1.52 M3
Trapezoidal F1 h/3*(l^2+l'^2+l*l') 1.04 ,,
Column upto plinth
F1 column 6 0.35 2.10 0.35 1.60 1.18 M3
Foundation beam 1 26.33 26.33 0.23 0.30 1.82 ,,
Tie beam 1 26.33 26.33 0.23 0.30 1.82 ,,
Ground floor Column 6 0.35 2.10 0.35 3.075 2.26 ,,
Floor beam :- GF 1 26.33 26.33 0.23 0.230 1.39 ,,
Slab :- Ground floor - 1 9.01 9.01 6.17 0.125 6.95 ,,
Sill band 1 23.33 23.33 0.325 0.075 0.57 ,,
Lintel band 1 26.33 26.33 0.23 0.15 0.91 ,,
Copping of parapet wall 1 24.60 24.60 0.40 0.075 0.74 ,,
4.3 Net R.C.C. Work = 20.20 M3

Prepared by- Checked by- Recommended by- Approved by-


91 of 123
Construction of Toilet Block
Thalajung, Gorkha

Item Total
S.N. Description No Length Breadth Height Quantity Remarks
No Length

9 5.1 Steel reinforcement for R.C.C. work - 1.75% of Total R.C.C. = 2774.98 Kg

2.77 Mt
10 Form work -
Column base - F1 6 5.20 31.20 0.15 4.68 M2
Column upto plinth F1 column 6 1.40 8.40 1.60 13.44 ,,
Foundation beam 2 26.33 52.66 0.30 15.80 ,,
Tie beam 2 26.33 52.66 0.30 15.80 ,,
Ground floor Column 6 1.40 8.40 3.075 25.83 ,,
Floor beam :- GF 2 26.33 52.66 0.230 12.11 ,,
Slab :- Ground floor - 1 9.01 9.01 6.170 – 55.59 ,,
Slab side bar 1 30.36 30.36 – 0.125 3.80 ,,
Sill band 2 23.33 46.66 0.075 3.50 ,,
Lintel band 2 26.33 52.66 0.150 7.90 ,,
parapet wall copping side bar 2 24.60 49.20 0.150 7.38 ,,
6.1 Total Formwork = 165.83 M2

11 Plaster work :-
a 20 mm thick c/s plaster (1:4)
Inside female toilet 1 15.12 15.12 – 3.075 46.49 M2
2 3.07 6.14 – 1.800 11.05 ,,
4 1.50 6.00 – 1.800 10.80 ,,
Inside male toilet 1 11.20 11.20 – 3.075 34.44 ,,
1 7.54 7.54 – 3.075 23.19 ,,
1 1.65 1.65 – 1.800 2.97 ,,
disabled toilet 1 7.78 7.78 – 3.075 23.92 ,,
urinal partation 4 0.75 3.00 – 1.500 4.50 ,,
outside corridor 1 6.76 6.76 – 3.075 20.79 ,,
beam 1*2 2 1.20 2.40 – 0.230 0.55 ,,
Deduction
D2A 2 1.00 2.00 – 2.60 -5.20 M2
D2D 0.5 1.00 0.50 – 2.60 -1.30 ,,
D4 5 0.75 3.75 – 1.80 -6.75 ,,
W2 1 1.20 1.20 – 1.40 -1.68 ,,
V2 0.5 1.20 0.60 – 0.60 -0.36 ,,
V3 2.5 0.60 1.50 – 0.80 -1.20 ,,
Floor area – areas of floor = 31.74 31.74 ,,
7.1 Total 20mm plaster = 193.95 M2

b 12.5 mm thick c/s plaster (1:4)


Outside - front + back 2 7.81 15.62 – 3.20 49.98 M2
side 2 4.97 9.94 – 3.20 31.81 ,,
parapet wall 2 24.60 49.20 – 1.00 49.20 ,,
Copping of parapet wall 1 24.60 24.60 0.40 9.84 ,,
below plinth 1 25.56 25.56 0.450 11.50 ,,
ramp side wall 2 5.40 10.80 0.225 2.43 ,,
steps 1 1.50 1.50 0.60 0.90 ,,
Deduction
D2D 0.5 1.00 0.50 – 2.60 -1.30 M2
W2 1 1.20 1.20 – 1.40 -1.68 ,,
V2 0.5 1.20 0.60 – 0.60 -0.36 ,,
V3 2.5 0.60 1.50 – 0.80 -1.20 ,,
7.2 Total 12.5 mm plaster = 151.12 M2

c 12.5 mm thick 1:3 cement plaster on ceiling

Prepared by- Checked by- Recommended by- Approved by-


92 of 123
Construction of Toilet Block
Thalajung, Gorkha

Item Total
S.N. Description No Length Breadth Height Quantity Remarks
No Length
Inside ceiling
Female toilet 1 3.07 3.07 4.49 – 13.78 M2
male toilet 1 2.24 2.24 3.36 – 7.53 ,,
1 1.65 1.65 2.12 – 3.50 ,,
disabled toilet 1 1.65 1.65 2.24 – 3.70 ,,
outside corridor 1 2.51 2.51 1.25 3.14 ,,
outside ceiling 2 9.01 18.02 0.60 10.81 ,,
2 4.97 9.94 0.60 5.96 ,,
7.3 Total ceiling plaster = 48.42 M2

12 3mm cement punning in (1:1) Same as below plinth & step plaster 14.83 M2
Copping of parapet wall 1 24.60 24.60 0.40 9.84 ,,
8.2 Total punning = 24.67 M2

13 a) Floor tiles work in c/s mortar (1:4) -


Inside female toilet 1 3.07 3.07 4.490 13.78 M2
Inside male toilet 1 2.24 2.24 3.360 7.53 ,,
1 1.65 1.65 2.120 3.50 ,,
disabled toilet 1 1.65 1.65 2.240 3.70 ,,
8.4 Total floor tile = 28.51 M2

b) Glazed wall tiles work in c/s mortar (1:4)


Inside female toilet 1 11.88 11.88 – 1.80 21.38 M2
3 4.90 14.70 – 1.80 26.46 ,,
Inside male toilet 1 11.20 11.20 – 1.80 20.16 ,,
1 5.30 5.30 – 1.80 9.54 ,,
disabled toilet 1 7.78 7.78 – 1.80 14.00 ,,
urinal partation 4 0.75 3.00 – 1.50 4.50 ,,
Deduction
D2A 1 1.00 1.00 – 1.80 -1.80 M2
D2D 0.5 1.00 0.50 – 1.80 -0.90 ,,
D4 5 0.75 3.75 – 1.80 -6.75 ,,
W2 1 1.20 1.20 – 0.60 -0.72 ,,
8.5 Total wall tile = 85.87 M2

14 38mm thick P.C.C(1:2:4) punning


Terrace 1 9.01 9.01 6.17 55.59 M2
ramp floor 1 5.40 5.40 1.50 8.10 ,,
outside corridor 1 2.51 2.51 1.250 3.14 ,,
8.6 Total = 66.83 M2

15 Painting work
a 2 coats readymade enamel paints over one coats primer factor
D2A 2 1.00 2.00 2.25 2.60 11.70 M2
D2A1 1 1.00 1.00 2.25 2.60 5.85 ,,
D4 5 0.75 3.75 2.25 2.10 17.72 ,,
W2 2 1.20 2.40 1.125 1.40 3.78 ,,
V2 1 1.20 1.20 1.125 0.60 0.81 ,,
V3 5 0.60 3.00 1.125 0.80 2.70 ,,
same as area of grill 3.66 3.66 ,,
9.1 Total enamel paint = 46.22 M2

b Two coat Distemper paint Same as inside plaster + inside ceiling area 225.60 M2
Deduction of Inside tile wall area -85.87 ,,
Deduction of Inside tile floor area -28.51 ,,

Prepared by- Checked by- Recommended by- Approved by-


93 of 123
Construction of Toilet Block
Thalajung, Gorkha

Item Total
S.N. Description No Length Breadth Height Quantity Remarks
No Length
Deduction of punning area -3.14 ,,
9.2 Total distemper paint 108.08 M2

c Two coats weather proof paint (apex) for outside


area-
Same as outside plaster area 151.12 M2
Deduction of punning area -24.67 ,,
9.3 Total = 126.45 M2

Prepared by- Checked by- Recommended by- Approved by-


94 of 123
Construction of Toilet Block
Thalajung, Gorkha

Item Total
S.N. Description No Length Breadth Height Quantity Remarks
No Length
16 Doors & windows Works
a Salwood Doors chaukhat
D2A 2 7.20 14.40
D2A1 1 7.20 7.20
D4 5 4.95 24.75
W2 2 5.20 10.40
V2 1 3.60 3.60
V3 5 2.80 0.60
60.95 0.125 0.075 0.571 M3
10.01 Total 0.571 M3

b 38mm thick Ready made water proof Teak wood shutter


D2A 2 0.875 1.750 2.04 3.57 M2
D2A1 1 0.875 0.875 2.04 1.78
D4 5 0.625 3.125 2.04 6.37
10.04 Total 11.72 M2

c Glazed shutter
W2 2 1.075 2.150 1.275 2.74
V2 1 1.075 1.075 0.475 0.51
V3 5 0.475 0.600 0.675 0.41
10.05 Total 3.66 M2

d Mosquito proof shutter


Same as glazed shutter area 3.66
10.06 Total 3.66 M2

e 5mm thick fixed glass


D2A 2 0.875 1.750 0.375 0.66 M2
D2A1 1 0.875 0.875 0.375 0.33
10.07 Total 0.99 M2

17 10mmx10mm square m.s steel grill work


Same as glazed shutter area 3.66
Total 3.66 M2
area kg/m2
10.09 3.66 21.50 Total 78.69 Kg

18 Providing and laying 2 coats of water


proofing materials for terrace roof
(elastocrate cementious
elastrometric water proofing coating
two components) capacity per Kg 6 l b a
sq ft as per specification and
direction complete works.

Terrace 1 9.01 6.17 55.59 55.59 M2


11.13 Total = 55.59 M2

Prepared by- Checked by- Recommended by- Approved by-


95 of 123
Construction of compound wall

Government of Nepal
Ministry of Urban Development
Department of Urban Development & Building Construction
Division Office
Gorkha
Detailed Estimate

Name of works :- Compound wall and landscaping Fiscal Year :- 070/71


Place :- Thalajung, Gorkha

Item Total
S.N Description No Length Breadth Height Quantity Remarks
no length
1 E/W cutting by machine
Site levelling 1 35.00 35.00 7.50 1.20 315.00
1 22.00 22.00 15.00 1.70 561.00
1 15.00 15.00 5.00 0.75 56.25
1 24.00 24.00 2.70 0.20 12.96
approach road leveling 1 60.00 60.00 4.00 0.50 120.00
1.1.4 Total E/W = 1065.21 M3

2 E/W excavation in foundation in ordinary soil


side Retaining Wall 1 19.00 19.00 0.83 0.75 11.76
Gate pillar 3 0.90 2.70 0.90 1.00 2.43
For levelling for flagstone part 1 area= 60.00 0.15 9.00
For Concrete pole 126 0.30 37.80 0.30 0.45 5.10
Compound wall 1 25.00 25.00 0.60 0.60 9.00
2.1 Total E/W = 37.29 M3

3 Stone soiling in foundation


side Retaining Wall 1 19.00 19.00 0.83 0.15 2.35
Gate pillar 3 0.90 2.70 0.90 0.15 0.36
For flag stone portion 1 area= 60.00 0.15 9.00
Compound wall 1 25.00 25.00 0.60 0.15 2.25
3.1.2 Total stone soling = 13.97 M3

4 P.C.C. 1:3:6
Gate pillar 3 0.90 2.70 0.90 0.075 0.18
For flag stone portion 1 area= 60.00 0.05 3.00
Compound wall 1 25.00 25.00 0.60 0.075 1.13
4.1 Total= 4.31 M3

5 P.C.C. 1:2:4
side Retaining Wall 1 19.00 19.00 0.83 0.100 1.57
Retaining Wall top 1 19.00 19.00 0.45 0.05 0.43
For fixing Concrete pole 126 0.30 37.80 0.30 0.450 5.10
deduction 126 0.125 15.75 0.075 0.45 -0.53
4.2 Total= 6.57 M3

6 Stone masonry in 1:6 cement sand mortar


Wall
side Retaining Wall 1 19.00 19.00 0.83 0.50 7.84
side Retaining Wall 1 19.00 19.00 0.64 1.50 18.17
Compound wall 1 25.00 25.00 0.60 0.375 5.63
1 25.00 25.00 0.35 1.500 13.13

Prepared by- Checked by- Recommended by- Approved by-


96 of 123
Construction of compound wall

Item Total
S.N Description No Length Breadth Height Quantity Remarks
no length
Compound above retaining wall 1 20.00 20.00 0.35 1.500 10.50
3.6 Total stone masonry = 47.42 M3

7 P.C.C 1:1.5:3 for R.C.C. work


Gate column base 3 0.90 2.70 0.90 0.15 0.36
3 area= 0.51 0.25 0.38
Column 3 0.300 0.90 0.300 2.35 0.63
Kerb stone on outer edge of flag stone
portin 1 175.00 175.00 0.10 0.20 3.50
4.3 Total P.C.C. for R.C.C. = 4.88 M3

8 Reinforcement
Footing mesh 12mm dia 14 0.90 12.60 0.89 kg/m 11.21
16 mm dia for gate column 12 3.20 38.40 1.58 kg/m 60.67
8mm dia stirrups 57 1.07 60.99 0.39 kg/m 23.79
16 mm dia for gate column 3 2.60 7.80 1.58 kg/m 12.32
In Kerb stone 1 1% of p.c.c 274.75
5.1 Total Reinforcement = 382.75 kg

9 12.5mm Cement plaster (1:4) -


Gate pillar 3 1.2 3.60 2.00 7.20
7.2 Total= 7.20 M2

10 Cement pointing (1:3)


side Retaining Wall 1 19.00 19.00 1.50 28.50
Compound wall 1 25.00 25.00 3.00 75.00
1 20.00 20.00 3.00 60.00
7.4 Total pointing = 163.50 M2

Main Grill gate and subgate with


11
painting all complete
1.5" dia black pipe frame 2 2.00 4.00
2 1.70 3.40
4 1.55 6.20
2 1.63 3.26
1 1.60 1.60
sub gate 2 1.70 3.40
2 0.90 1.80
23.66 3.61 Kg/m 85.41
1" dia black pipe sub gate frame 2 1.60 3.20
2 0.85 1.70
4.90 2.46 Kg/m 12.05
1" square pipe 2 1.55 3.10
2 1.45 2.90
36 0.575 20.70
sub gate 2 0.900 1.80
12 0.650 7.80
36.30 1.47 Kg/m 53.36
20*4.5 mm m.s, grill plate 24 0.15 3.60
butta 2 0.45 0.90
2 1.05 2.10
sub gate 10 0.15 1.50
8.10 0.71 Kg/m 5.75
18 gauge MS Sheet 2 1.55 0.45 9.80 Kg/m2 13.67

Prepared by- Checked by- Recommended by- Approved by-


97 of 123
Construction of compound wall

Item Total
S.N Description No Length Breadth Height Quantity Remarks
no length
sub gate 1 0.90 0.30 9.80 Kg/m2 2.65

Hinges, tower bolt, aldrops, plates etc. @ 10% of total weight 17.29
11.09 Total= 190.19 Kg

12 60mm thick interlock paving works


Interlock portion 1 area= 198.00 198.00
11.10 Total paving = 198.00 M2

13 Flag stone paving works


flag stone portion 1 area= 60.00 60.00
11.16 Total paving = 60.00 M2

14 11.11 Concrete pole 126 126.00 No

15 Barbed wire fencing


On Concret pole 5 250 1250.00 1250.00
Diagonal 250 2.47 617.50 617.50
11.12 Total = 1867.50 Rm

Supplying and planting outdoor


16 11.17 gardening plants (Dhupi, Kapur etc.) 20 20.00 Tree
and flowering plants

Prepared by- Checked by- Recommended by- Approved by-


98 of 123
Government of Nepal
Ministry of Urban Development
Department of Urban Development & Building Construction
Division Office
Gorkha
Detailed Estimate

Name of works :- Electrification works


Place :- Thalajung, Gorkha

SN Item No Particulars QTY Unit Remarks


A. 12.1 LUMINAIRES ( FIXTURES)
Accessories:screws, gripes, pvc tape, choke, starter,
12.1.0 Tube, bulbs, holder, flexible wire,GI pipe/ chain etc all
complete.
Ceiling ligh/Dome light 8" heavy carrier with CFL etc all
1 12.1.1 66.00 Set
complete.
Wall lamp with CFL lamp decorative etc all complete.
2 12.1.2 8.00 Set

Wall lamp with GLS lamp decorative etc all complete.


3 12.1.3 9.00 Set
4 12.1.4 Down light (concealed ) with CFL etc all complete. 6.00 Set
Hanging light with CFL lamp decorative etc all
5 12.1.5 1.00 Set
complete.
1X40watt Tube light box type Wipro /Ge or eqvt. etc
6 12.1.6 24.00 Set
all complete.
2x40 watt tube light box type Wipro/Ge or eqvt.etc all
7 12.1.7 4.00 Set
complete.
2x40 watt tube light box mirror optic Wipro/Ge or
8 12.1.8 4.00 Set
eqvt.etc all complete.
Mirror light with CFL lamp decorativeor eqvt etc all
9 12.1.9 9.00 Set
complete.
10 12.1.10 Electrical bell musical type. 2.00 Set
B 12.2 FAN / EXHAUST FAN
Accssories:as per sn A +nut, bolt, hook,clamp,
12.2.0
regulator, flexible wire etc all complete.
42'' ceiling fan Almonard/Bajaj or eqvt.etc all
11 12.2.1 16.00 Set
complete.
9"exhaust fan Almonard /Bajaj or eqvt.etc all complete.
12 12.2.2 10.00 Set

16'' wall fan Almonard/Bajaj or eqvt.etc all complete.


13 12.2.3 1.00 Set

C 12.3 SOCKET,SWITCH ,JUNCTION BOX (Flush type)


Accessories: metal box ,screws ,gripes, flexible wire
12.3.0
etc all complete.
14 12.3.1 Dimmer switch for ceiling fan etc all complete. 16.00 Set
15 12.3.2 Bell push switch Anchor or eqvt etc all complete. 2.00 Set
16/6 Amps combined S/socket flush type with child lock
16 12.3.3 65.00 Set
Anchor or eqvt.etc all complete.
1 gang 1,2 way switch Anchor or eqvt.etc all complete.
17 12.3.4 22.00 Set

2gang one way switch Anchor or eqvt.etc all complete.


18 12.3.5 18.00 Set

3 gang one way switch Anchor or eqvt.etc all


19 12.3.6 12.00 Set
complete.

Prepared by- Checked by- Recommended by- Approved by-


99 of 123
SN Item No Particulars QTY Unit Remarks
4 gang one way switch Anchor or eqvt.etc all
20 12.3.7 14.00 Set
complete.
6 gang one way switch Anchoror eqvt. etc all
21 12.3.8 2.00 Set
complete.
Junction box made of metal with cover size 6"X4" etc.
22 12.3.9 20.00 Set
all complete.
D. 12.4 MAIN SWITCH / DISTRIBUTION BOARD
Accessories ;screws, gripes, nut bolt,cu bus bar,earth
bus bar, neutral bus bar,fuse, porcelin base ,cu. Strip
12.4.0
for connection, cable shoe ,phase bar,pvc tape etc all
complete.
60 Amps Panel board made of mild steel sheet with
cu. busbar double cover floor mount suitable size &
23 12.4.1 1.00 Set
color push type lock for housing the following items all
complete.(space for 4 no. MCCB).
40- 50 Amps TP MCCB Siemens ,Ge or eqvt. for
a 12.4.1.1 1.00 No
incoming.
20-30 Amps TP MCCB Siemens, Geor eqvt. for
b 12.4.1.2 3.00 No
outgoing.
10 Amps DP MCB Siemens Ge,Merlin gerain or eqvt.
c 12.4.1.3 2.00 No
for main .
d 12.4.1.4 Ammeter 0-500A 1.00 No
e 12.4.1.5 Voltmeter 0-500 v 1.00 No
f 12.4.1.6 Selector switch 2.00 No
g 12.4.1.7 CT coil of suitable ratio for panel board. 3.00 No
h 12.4.1.8 Indicator with fuse 3.00 No
Distribution board 6 way TPN made of mild steel sheet
24 12.4.2 double cover lockable Geco,Standard,Nepal made 3.00 Set
flush type etc all complete.
25-32 Amps TP MCB Siemens Ge,Merlin gerain or
a 12.4.2.1 3.00 No
eqvt. for main.(1x3=3)
6,16,25 Amps. SP MCB Siemens,Ge,Merlin gerain or
b 12.4.2.2 54.00 No
eqvt. for light & power circuit.(18x3=54)
Distribution board 12 way SPN made of mild steel
25 12.4.3 sheet double cover lockable Geco,Standard, Nepal 2.00 Set
made flush type etc all complete.
20 Amps DP MCB Siemens Ge,Merlin gerain or eqvt.
a 12.4.3.1 2.00 No
for main .(1x2=2)
6,16,25 Amps. SP MCB Siemens,Ge,Merlin gerain or
b 12.4.3.2 24.00 No
eqvt. for light , power & A/C circuit.(2x12=24)
Distribution board 6 way SPN made of mild steel sheet
26 12.4.4 double cover lockable Geco,Standard, Nepal made 1.00 Set
flush type etc all complete.
10 Amps DP MCB Siemens Ge,Merlin gerain or eqvt.
a 12.4.4.1 1.00 No
for main .
6 Amps. SP MCB Siemens,Ge,Merlin gerain or eqvt.
b 12.4.4.2 2.00 No
for light , power & A/C circuit.
E 12.5 POINT WIRING / WIRES/CABLES (concealed wiring )
Accessories:HDPE polythene pipe,screws,pvc tape,
12.5.0
grips, circular box etc all complete.
2x2.50 sq mm multi strand flexible cu .wire for light &
27 12.5.1 166.00 Point
fan point in 1/2"HDPE polythene pipe etc all complete.

Prepared by- Checked by- Recommended by- Approved by-


100 of 123
SN Item No Particulars QTY Unit Remarks
2x4.0+1x1.50 sq.mm multi strand flexible cu wire for
28 12.5.2 power point in 3/4" HDPE polythene pipe etc all 65.00 Point
complete.
10 sq.mm 4 core unarmoured copper cable for main
29 12.5.3 panel board to DB, through polythene pipe etc all 65.00 Rm
complete.
2x6.0+1.50 sq.mm copper cable from panel board
30 12.5.4 to( toilet block) DB-3, DB-4 to DB-5,DB -6 through 1" 60.00 Rm
HDPE polythene pipe etc all complete.
8 swg copper wire for earth continuity from panel board
31 12.5.5 to DB,main switch & earthing site in 1/2"HDPE 75.00 Rm
polythene pipe etc all complete.
F. 12.6 EARTHING
Accessories :salt, coal, cu plate, HDPE polythene
12.6.0
pipe., etc all complete.
Earthing with cu plate size 65 cmx65cmx3.15mm
with 8 swg copper wire for earth continuity from panel
board to earthing site including excavation of 6 ft deep
32 12.6.1 1.00 Set
trench in moist area and refilling the tranch with cubical
salt and charcoal in alternet layer with watering
arrangement etc all complete.

Prepared by- Checked by- Recommended by- Approved by-


101 of 123
Government of Nepal
Ministry of Urban Development
Department of Urban Development & Building Construction
Division Office
Gorkha
Detailed Estimate

Name of works :- Sanitary works


Place :- Thalajung, Gorkha

Grou
S.N. Item No Description of Work Quantity Unit Remarks

Supplying and Fixing White glazed earthenware Indian pattern


Orissa Pan with low level Pvc flushing cistern ,trap,pipe connector
A 13.01
with complete accessories including bracket, flushing pipe,pipe
connector etc. all complete set. (Hindware, Parryware, Classi

Indian pattern W C 530mm Orissa Pan with PVC low level flushing
1 13.1.1 8.00 set
cistern all complete set.

Supplying and Fixing Porcelain clay Indian Pattern Comode P or S


B 13.02 trap, Pvc Cistern and Plastic seat cover with pipe connector all
complete set (Hindware, Parryware, Classica, bolan or equivalent.)

Indian pattern Comode with PVC low level flushing cistern and seat
2 13.2.1 2.00 set
cover all complete set. ###

Supplying and fixing White glaze Indian Pattern Porcelain clay


wash basin/Oval with brackets 32mm dia. Pvc bottle trap, 32mm
C 13.3
CP waste coupling , 15mmx450mm long c.p. pipe connector etc
all complete.Sanitaryware:-.( Parryware,Hindware, or equivalent

Indian pattern Porcelain clay white glaze 55X40 cm Wash Basin with
3 13.3.1 6.00 set
pedestal and swan type piller cock complete set.
Porcelain clay white glaze Indian Pattern 55X40 cm size , wash basin
4 13.3.2 with pedestal and central hole Aerator type basin mixer etc all 3.00 Set
complete.
Indian pattern Porcelain clay white glaze Oval Wash Basin 50x40cm
5 13.3.3 with inbuilt hole/over counter/under counter and swan type piller cock 4.00 set
complete set. ###
Indian pattern White glazed porceline clay Urinal 46.5X31.5X26.5cm
6 13.3.4 2.00 Set
with necessary accessories all complete set .
Porcelain clay white glaze Indian Pattern 68X30cm size Urinal
7 13.3.5 1.00 Set
partation all complete set .
Kitchen sink stainless steel 900x450x200mm depth with drain board
8 13.3.6 2.00 Set
1mm thickness with Aerator/swan type sink cock.

Kitchen sink stainless steel 900x450x200mm depth with drain board


9 13.3.7 5.00 one
1mm thickness with Aerator/swan type sink Mixer all complete set..

Supplying and Fixing ( Fabricated Scrub sink) The spalsh made of


304 qwality prime grade of Stainless steel 16 swg thickness,Floor
D 13.4
mounted with leg(stand),kantipur kitchen equipment, Qwality
kitchen or equivalent.Sample to be approved by project engineer

10 13.4.1 Stainless steel Scrub sink 1.5mt length,deep 500mm+150mm splash 1.00 set

Supplying and Fixing Indian pattern C.P. valves with wall flange
E 13.5
Including c.p. nipple all complete set.

Prepared by- Checked by- Recommended by- Approved by-


102 of 123
Grou
S.N. Item No Description of Work Quantity Unit Remarks
11 13.5.1 15mm C.P. concealed stop cock with sliding flange 9.00 Nos
12 13.5.2 Chrome plate shower rose 7.5 cm dia.with wall flange all complete set. 3.00 nos
13 13.5.3 15mm dia C.P. bath spout with wall flange. 3.00 Nos
14 13.5.4 C.P. Bibcock 15mm dia long neck type with wall flange 8.00 nos
15 13.5.5 15mm dia Angle valve with wall flange. 34.00 nos
16 13.5.6 15mm dia two way angle valve 5.00 nos ###
17 13.5.7 15 mm CP water spray with 1.2mt. Long flexiable pipe. 2.00 set
18 13.5.8 15mm dia. Urinal Auto Closing Valve with built in Control Cock 2.00 nos
Supplying and Fixing Indian pattern bathroom accessories all
F 13.6
complete set.
19 13.6.1 Chrome plated toilet paper holder flap type(cover type). 2.00 nos
20 13.6.2 Chrome plated soap tray(heavy). 18.00 nos
21 13.6.3 C p 15mm dia x450mm long towel rod. 15.00 nos
22 13.6.4 Looking Mirror Modi guard 450x600mm (18"x 24") 8.00 nos
23 13.6.5 European pattern Stainless steel 45cm long with bend type Grab Bar . 2.00 Set

Indian pattern Electric water heater (Geyser) with built up check


G 13.7 valve, pressure relief valve all complete set.
(Crompton,bajaj,Jaquar or equivalent.)
24 13.7.1 25 lit electric water heater (Geyser) 2.00 nos
Supplying and Fixing Pvc roof water tank With screw type cover
H 13.8 including drain hole ,inlet outlet, over flow etc.all complete set .Hill
take, Roof top or equivalent
25 13.8.1 1000 lit capacity PVC water tank. 3.00 nos
Supplying and Fixing Electric moter Pump single or three phase
I 13.9 phase with base, nut and bolts all complete set (Kirloskar,
Compton or equiv),
26 13.9.1 1HP Electric motor Pump monoblock. 1.00 nos
27 13.9.2 0.5HP Electric motor Pump monoblock type. 1.00 nos
28 13.9.3 Pressure sensor switch for pump auto switch off all complete set. 2.00 Set
Supplying and fixing PPR pipe (hot and cold). or equivalent with
PPR fittings/ specials (Tees, elbows, Unions etc) clamps(m.s
J 13.10
plate with nut and bolt with hexagonal screws for clamp in
ceiling,wall), nails, including
20 mm PPR pipe, PN-10 \SDR 11, Pachanya, Napatop or eqv, includes
29 13.10.1 24.00 Rm
fixing/laying with necessary fittings all complete.
25 mm PPR pipe, PN-10 \SDR 11, Pachanya, Napatop or eqv, includes
30 13.10.2 174.00 Rm
fixing/laying with necessary fittings all complete.
32 mm PPR pipe, PN-10 \SDR 11, Pachanya, Napatop or eqv, includes
31 13.10.3 127.00 Rm
fixing/laying with necessary fittings all complete.
40 mm PPR pipe, PN-10 \SDR 11, Pachanya, Napatop or eqv, includes
32 13.10.4 42.00 Rm
fixing/laying with necessary fittings all complete.
Supplying and fixing PPR valve including jointing materials. all
K 13.11
complete set as per specification and instruction.
33 13.11.1 20 mm dia PPR Brass Gate Valve all complete. 2.00 Nos
34 13.11.2 25 mm dia PPR Brass Gate Valve all complete. 10.00 Nos
35 13.11.3 32 mm dia PPR Brass Gate Valve all complete. 7.00 Nos
36 13.11.4 40 mm dia PPR Brass Gate Valve all complete. 2.00 Nos
Supplying and Fixing Gun metal gate valve/check valve full way
L 13.12
medium all complete set as per specification and instruction.
37 13.12.1 (G.M.) check valve 25mm dia 2.00 nos

Prepared by- Checked by- Recommended by- Approved by-


103 of 123
Grou
S.N. Item No Description of Work Quantity Unit Remarks

THERMAL INSULATION TUBES:-Providing and fixing in position


M 13.13 6mm thick wall thickness thermal insulation tubes for Insulation
to hot water line pipes as per need joining and covering .

15mm dia.6mm wall thickness insulation for hot water pipe all
38 13.13.1 6.00 Rm
complete.
39 13.13.2 20mm dia,6mm thick wall thickness insulation for hot water pipe 42.00 Rm

Supplying and Fixing solar water heater with 3.0 k.w. electric
booster with thermostat all complete set. Technical spe.:-Inside
N 13.14
boiler M.S sheet 4.0 mm thick with Expansion joint(over lap joint)
in cover and bottom with 25x25x3 mm angle welded,4.0 kg/sq

40 13.14.1 300 lit. 3 panel solar heater fixing with electric booster all complete. 1.00 Set

Supplying and Fixing uPVC pipe 6kg/sqcm all complete set as per
O 13.15 specification and instruction. (Dwv,Panchakanya,SN-4,
Prince,Supreme )
41 13.15.1 50mm PVC pipe of 6 kg/cm2 42.00 Rm
42 13.15.2 75mm PVC pipe of 6 kg/cm2 92.00 Rm
43 13.15.3 110mm PVC pipe of 6 kg/cm2 193.00 Rm
Supplying and Fixing UPVC specials with O ring rubber
washer,Pvc liquid(Solvent cement), Pvc cream,Pvc pipe clips with
P 13.16
screw,Vent cowl all complete set as per specification and
instruction. (Panchakanya,Prince,Supreme )
44 13.16.1 50 mm dia UPVC 90 degree bend 63.00 nos
45 13.16.2 50 mm dia UPVC 45 degree bend. 21.00 nos
46 13.16.3 50 mm dia UPVC plain Y-Tee. 3.00 nos
47 13.16.4 75 mm dia UPVC vent cowl 5.00 nos
48 13.16.5 75 mm dia UPVC plain. 5.00 nos
49 13.16.6 75 mm dia UPVC door tee. 8.00 nos
50 13.16.7 75 mm dia UPVC 90 degree bend. 18.00 nos
51 13.16.8 75 mm dia UPVC door bend. 8.00 nos
52 13.16.9 75 mm dia UPVC 45 degree bend. 12.00 nos
53 13.16.10 75 mm dia UPVC Y branch. 3.00 nos
54 13.16.11 75 mm dia UPVC pipe clip. 14.00 nos
55 13.16.12 110 mm dia UPVC vent cowl. 3.00 nos
56 13.16.13 110 mm dia UPVC plain . 2.00 nos
57 13.16.14 110 mm dia UPVC Door Tee 4.00 nos
58 13.16.15 110 mm dia UPVC 90 degree bend. 33.00 nos
59 13.16.16 110 mm dia UPVC Door bend. 6.00 nos
60 13.16.17 110 mm dia UPVC 45 degree bend 25.00 nos
61 13.16.18 110 mm dia UPVC Y branch 6.00 nos
62 13.16.19 110 mm dia UPVC pipe clip 40.00 nos
63 13.16.20 75x75mm dia.Pvc p-trap 10.00 Nos
64 13.16.21 110x110mm dia.Pvc p-trap 10.00 Nos
65 13.16.22 110x75 red. Socket 10.00 Nos
66 13.16.23 5 kg fire extinguiser with pressure guage type all complete set. 6.00 set
67 13.16.24 CI cover 45x45 cm size (medium).Round type set. 18.00 nos
C I Cover round type 60x60cm, with locking arrangement (16kg)
68 13.16.25 1.00 Set
complete set.

Supplying and Fixing HDP Pipe 4 kg/sq.cm all complete set as per
Q 13.17
specification and instruction. (Panchakanya or equivalent(N.S. )
69 13.17.1 4 kg/cm2 (110 mm) HDP pipe. 42.00 Rm
70 13.17.2 10 kg/cm2 (20 mm) HDP pipe including fittings & layings 200.00 Rm

Prepared by- Checked by- Recommended by- Approved by-


104 of 123
Grou
S.N. Item No Description of Work Quantity Unit Remarks

Providing and laying non-pressure NP2 class (light duty) RCC


pipes with collars jointed with stiff mixture of cement mortar in the
R 13.18
proportion of 1:2 (1 cement : 2 find sand) including testing of
joints etc. complete.
71 13.18.1 150 mm dia NP2 RCC Hume pipe including collar with all complete. 39.00 Rm

Prepared by- Checked by- Recommended by- Approved by-


105 of 123
Construction of SepticTank

Government of Nepal
Ministry of Urban Development
Department of Urban Development & Building Construction
Division Office
Gorkha
Detailed Estimate

Name of works :- Construction of Septic Tank


Place :- Thalajung, Gorkha Fiscal Year :- 070/71

Item Total
S.N.
no Description No Length Breadth Height Quantity
length
1 E/w excavation in all kinds of soil.
2.1 Found. 1 4.20 4.20 1.86 2.20 17.19

2 Flat Brick soling works


3.1.1 1 4.20 4.20 1.86 7.81
3 PCC (1:2:4)
base 1 4.20 4.20 1.86 0.10 0.78
4.2 0.78
4 RCC (1:1.5:3)
4.1 P.C.C
cover 1 4.00 4.00 1.66 0.10 0.66
4.3 0.66

4.2 5.1 Reinforcement bar works 0.66 100.00 66.40


cover(100kg/m3)
4.3 Form works
base 2 4.20 8.40
,, 2 1.86 3.72
cover 2 4.00 8.00
,, 2 1.66 3.32
23.44 0.10 2.34
1 3.54 1.20 4.25
6.1 Total 6.59
5 Brick works in 1:4 c/s mortar
long wall 2 4.00 8.00
s.w. 2 1.20 2.40
10.40 0.23 2.00 4.78
part. 1 1.20 1.20 0.12 2.00 0.28
3.4 Total 5.06
6 12.5 mm thick c/s 1:4 plaster
wall 2 1.94 3.88
2 1.48 2.96
4 1.20 4.80
11.64 2.00 23.28
floor 1 1.94 1.94 1.20 2.33
,, 1 1.48 1.48 1.20 1.78
7.2 Total 27.38
7 Cement punning works

Prepared by- Checked by- Recommended by- Approved by-


106 of 123
Construction of SepticTank

Item Total
S.N.
no Description No Length Breadth Height Quantity
length
8.2 same as plaster area 27.38

Prepared by- Checked by- Recommended by- Approved by-


107 of 123
Construction of SepticTank

Government of Nepal
Ministry of Urban Development
Urban Development & Building Construction
Division Office
Gorkha
Detailed Estimate

Fiscal Year :- 070/71

Remarks

m3

m2

m3

m3

kg

m2

m2

m2

Prepared by- Checked by- Recommended by- Approved by-


108 of 123
Construction of SepticTank

Remarks

m2

Prepared by- Checked by- Recommended by- Approved by-


109 of 123
Construction of Soak-Pit

Government of Nepal
Ministry of Urban Development
Department of Urban Development & Building Construction
Division Office
Gorkha
Detailed Estimate

Name of works :- Construction of Soak-pit Fiscal Year :- 070/71


Place :- Thalajung, Gorkha

Item Total Quantity


S.N.
no Description No Length Breadth Height Quantity Remarks
length 2 nos
1 E/w excavation in all kinds of soil.
2.1 Found. 0.25 3.14 1.66 1.66 3.15 6.81 13.63 m3
(3.14xd2/4xh)

2 Flat Brick soling works


3.1.1 0.25 3.14 1.66 1.66 2.16 4.33 m2

3 Brick masonry works in 1:6 mortar.


0.25 3.14 1.66 1.66 3.00 6.49
0.25 3.14 1.20 1.20 3.00 3.39 (-)
3.2 Total 3.10 6.20 m3

4 Brick ballast filling works


2.4 0.25 3.14 1.20 1.20 2.50 2.83 5.65 m3

5 Rcc Cover works


5.1 4.3 PCC (1:1.5:3) 0.25 3.14 1.66 1.66 0.10 0.22 0.43 m3

5.2 Reinforcement works


5.1 100kg /m3 0.22 100.00 22.00 44.00 Kg

5.3 Form works 3.14 1.66 0.10 0.52


0.25 3.14 1.20 1.20 1.13
6.1 Total 1.65 3.30 m2

Prepared by- Checked by- Recommended by- Approved by-


110 of 123
Construction of Inspection Tank

Government of Nepal
Ministry of Urban Development
Department of Urban Development & Building Construction
Division Office
Gorkha
Detailed Estimate

Name of works :- Construction of Inspection Tank Fiscal Year :- 070/71


Place :- Thalajung, Gorkha

Item Total Quantity


S.N.
no Description No Length Breadth Height Quantity Remarks
length 19 Nos
1 E/w excavation in all kinds of soil.
2.1 Found. 1 0.90 0.90 0.90 0.75 0.61 11.54 m3
(inner size .45x.45x.45)

2 Flat Brick soling works


3.1.1 1 0.90 0.90 0.90 0.81 15.39 m2

3 PCC (1:2:4)
base 1 0.90 0.90 0.90 0.10 0.08
4.2 Total 0.08 1.54 m3

4 Brick works in 1:4 c/s mortar


long wall 2 0.90 1.80
s.w. 2 0.45 0.90
3.4 2.70 0.23 0.45 0.28 5.31 m3

5 12.5 mm thick c/s 1:4 plaster


wall 4 0.45 1.80 0.45 0.81
floor 1 0.45 0.45 0.45 0.20
7.2 Total 1.01 19.24 m2

6 Cement punning works


8.2 same as plaster area 1.01 19.24 m2

Prepared by- Checked by- Recommended by- Approved by-


111 of 123
Construction of Pump House

Government of Nepal
Ministry of Urban Development
Department of Urban Development & Building Construction
Division Office
Gorkha
Detailed Estimate

Name of works :- Construction of Pump house


Place :- Thalajung, Gorkha Fiscal Year :- 070/71

Item Total Quantity


S.N. no Description No Length Breadth Height Quantity
length 2 Nos
1 E/w excavation in all kinds of soil.
2.1 Found. 1 1.05 1.05 1.05 0.25 0.28 0.55
(inner size .45x.45x.45)

2 Boulder stone soling works


3.1.2 1 1.05 1.05 1.05 0.15 0.17 0.33

3 PCC (1:2:4)
base 1 1.05 1.05 1.05 0.10 0.11
fixing for pump 1 0.45 0.45 0.45 0.075 0.02
4.2 Total 0.13 0.25
4 RCC works
4.1 PCC (1:1.5:3)
cover 1 1.35 1.35 1.35 0.10 0.18
4.3 Total 0.18 0.36
4.2 5.1 Reinforcement bar works 0.18 75.00 13.67 27.34
Cover(75 kg/m3)
4.3 Form works
cover side 4 1.35 5.40
base ,, 4 1.05 4.20
9.60 0.10 0.96
base 1 0.90 0.90 0.90 0.81
6.1 Total 1.77 3.54
5 Brick works in 1:4 c/s mortar
long wall 2 1.05 2.10
s.w. 2 0.60 1.20
3.30 0.23 0.90 0.68
deduct door 1 0.60 0.60 0.23 0.90 -0.12
3.4 Total 0.56 1.12

6 12.5 mm thick c/s 1:4 plaster


wall 4 1.05 4.20 0.90 3.78
inner 1 0.60 0.60 0.90 0.54
cover side 4 1.35 5.40 0.10 0.54
cover 1 0.90 0.90 0.90 0.81
1 0.60 0.60 0.60 0.36
7.2 Total 6.03 12.06

7 M.s. door with locking arrangement


10.10 1 1.00 2.00

Prepared by- Checked by- Recommended by- Approved by-


112 of 123
Construction of Pump House

Government of Nepal
Ministry of Urban Development
Urban Development & Building Construction
Division Office
Gorkha
Detailed Estimate

Fiscal Year :- 070/71

Remarks

m3

m3

m3

m3
kg

m2

m3

m2

L.S.

Prepared by- Checked by- Recommended by- Approved by-


113 of 123
Construction of water collection tank

Government of Nepal
Ministry of Urban Development
Department of Urban Development & Building Construction
Division Office
Gorkha
Detailed Estimate

Name of works :- Construction of water collection tank Fiscal Year :- 070/71


Place :- Thalajung, Gorkha

Item Total
S.N. Description No Length Breadth Height Quantity Remarks
no length
1 E/w excavation in all kinds of soil
2.1 Found. 1 3.70 3.70 2.70 2.55 25.47 m3

2 Boulder stone soling works


3.1.2 1 3.70 3.70 2.70 0.15 1.50 m3

3 PCC (1:3:6)
4.1 1 3.70 3.70 2.70 0.05 0.50 m3

4 RCC works
PCC (1:1.5:3) for RCC with silica
a
cement admixture
base 1 3.35 3.35 2.35 0.15 1.18
cover 1 3.35 3.35 2.35 0.15 1.18
Side walls 2 3.20 6.40 0.175 2.30 2.58
2 2.20 4.40 0.175 2.30 1.77
Haunching 1 10.80 10.80 area = 0.01 0.12
4 2.15 8.60 area = 0.01 0.10
4.4 Total 6.93 m3

b 5.1 Reinforcement bar works 914.02 kg

c Form works
Side walls inner 2 3.00 6.00
2 2.00 4.00
10.00 2.30 23.00
cover 1 3.00 3.00 2.00 6.00
6.1 Total 29.00 m2

5 Cement punning works


wall 2 3.00 6.00
2 2.00 4.00
10.00 2.50 25.00
floor 1 3.00 3.00 2.00 6.00
8.2 Total 31.00 m2

6 11.14 Iron sheet manhole cover (.60cmx.60cm) 1.00 Set

7 Brick work (1:4)


Side walls 2 3.58 7.16 0.115 2.45 2.02
2 2.35 4.70 0.115 2.45 1.32
3.4 Total 3.34 m3

Prepared by- Checked by- Recommended by- Approved by-


114 of 123
Government of Nepal
Ministry of Urban Development
Department of Urban Development & Building Construction
Division Office
Gorkha

Name of works :- Construction of water tank


Place :- Thalajung, Gorkha Fiscal Year :- 070/71

S.N Description No of fo No of bar Length(m)Total length(m) wt /m Quantity(kg)


1 Reinforcement for bottom slab
Along x- axis 10mm dia 17 3.35 56.95 0.62 35.31
17 3.35 56.95 0.62 35.31
Along y- axis 10 mm dia 35 2.35 82.25 0.62 51.00
35 2.35 82.25 0.62 51.00

Haunching bar in bottom slab 8mm 2 17 0.96 32.64 0.39 12.73


2 35 0.96 67.2 0.39 26.21

Reinforcement for shear wall


Vertical 10mm dia 2 25 3.8 190 0.62 117.80
2 35 3.8 266 0.62 164.92
Horizontal 10mm dia 2 18 11.4 410.4 0.62 254.45

Haunching bar in corners 8mm dia 4 18 1.34 96.48 0.39 37.63

Reinforcement for cover slab


Along x- axis 8mm dia bottom 1 25 3.35 83.75 0.39 32.66
Along y- axis 8mm dia bottom 1 35 2.35 82.25 0.39 32.08
Along x- axis 8mm dia top 2 25 1.005 50.25 0.39 19.60
Along y- axis 8mm dia top 2 35 0.705 49.35 0.39 19.25
Along x- axis 8mm dia tie bar 2 5 3.35 33.5 0.39 13.07
Along y- axis 8mm dia tie bar 2 6 2.35 28.2 0.39 11.00
Total = KG 914.02

Prepared by- Checked by- Recommended by- Approved by-


115 of 123
Construction of Placenta Pit

Government of Nepal
Ministry of Urban Development
Department of Urban Development & Building Construction
Division Office
Gorkha
Detailed Estimate

Name of works :- Construction of Placenta Pit Fiscal Year :- 070/71


Place :- Thalajung, Gorkha

Item Total
S.N.
no Description No Length Breadth Height Quantity Remarks
length
1 E/w excavation in all kinds of soil.
Found. 0.25 3.14 1.50 1.50 3.00 5.30
(3.14xd2/4xh)
19" wall 0.25 3.14 1.50 1.50 0.450 0.79
0.25 3.14 0.55 0.55 0.450 -0.11 (-)
Steps 1 0.60 0.60 1.05 0.20 0.13
2.1 Total 6.11 m3

2 Boulder stone soling works


(3.14xd2/4) 0.25 3.14 1.50 1.50 0.15 0.26
0.25 3.14 0.55 0.55 0.15 -0.04 (-)
Steps 1 0.60 0.60 1.05 0.15 0.09
3.1.2 Total 0.32 m3

3 Brick masonry works in 1:4 mortar.


14" wall 0.25 3.14 1.50 1.50 0.300 0.53
0.25 3.14 0.80 0.80 0.300 -0.15 (-)
9" wall 0.25 3.14 1.50 1.50 3.875 6.84
0.25 3.14 1.05 1.05 3.875 -3.35 (-)
Steps 1 0.60 0.60 1.050 0.30 0.19
1 0.60 0.60 0.825 0.15 0.07
1 0.60 0.60 0.600 0.15 0.05
4.19
Deduction of band 0.25 3.14 1.50 1.50 0.10 0.18
0.25 3.14 1.05 1.05 0.10 -0.09 (-)
0.09
3.4 Total 4.10 m3

4 Manhole cover Metal frame


11.14 1 1.00 Set

5 Rcc works
5.1 PCC (1:1.5:3)
Lower Band 0.25 3.14 1.50 1.50 0.10 0.18
0.25 3.14 0.55 0.55 0.10 -0.02 (-)
Upper Band 0.25 3.14 1.50 1.50 0.10 0.18
0.25 3.14 1.05 1.05 0.10 -0.09 (-)
Beam 0.25 3.14 1.50 1.50 0.175 0.31

Prepared by- Checked by- Recommended by- Approved by-


116 of 123
Construction of Placenta Pit

Item Total
S.N.
no Description No Length Breadth Height Quantity Remarks
length
0.25 3.14 1.05 1.05 0.175 -0.15 (-)
Cover 0.25 3.14 1.60 1.60 0.10 0.20
Deduction of metal cover 1 0.45 0.45 0.30 0.10 -0.01
4.3 Total 0.59 m3

5.2 Reinforcement works


5.1 100kg /m3 0.59 100.00 58.81 Kg

5.3 Form works


Lower Band (3.14xdxh) outer 1 3.14 1.50 0.10 0.47
inner 1 3.14 0.550 0.10 0.17
Upper Band 1 3.14 1.50 0.10 0.47
1 3.14 1.050 0.10 0.33
Beam 1 3.14 1.50 0.175 0.82
1 3.14 1.050 0.175 0.58
Cover 0.25 3.14 1.60 1.60 2.01
Deduction of metal cover 1 0.45 0.45 0.30 -0.14
6.1 Total 4.72 m2

6 12.5 mm thick 1:4 cement plaster


Above ground outer 1 3.14 1.50 1.050 4.95
Above cover slab 0.25 3.14 1.60 1.60 2.01
Deduction of metal cover 1 0.45 0.45 0.30 -0.14
7.2 Total 6.82 m2

Prepared by- Checked by- Recommended by- Approved by-


117 of 123
Construction of Waste Burner

Government of Nepal
Ministry of Urban Development
Department of Urban Development & Building Construction
Division Office
Gorkha
Detailed Estimate

Name of works :- Construction of waste burner


Place :- Thalajung, Gorkha Fiscal Year :- 070/71

Item Total
S.N. no Description No Length Breadth Height Quantity Remarks
length
1 E/w excavation in all kinds of soil.
2.1 Found. 1 1.15 1.15 1.15 0.20 0.26 m3
(inner size .45x.45x.45)

2 Boulder stone soling works


3.1.2 1 1.15 1.15 1.15 0.15 0.20 m3

3 PCC (1:2:4)
sloping floor in base 1 0.49 0.49 0.72 0.05 0.02
4.2 Total 0.02 m3

4 RCC works
4.1 PCC (1:1.5:3)
base slab 1 1.15 1.15 1.15 0.10 0.13
feed plateform & ring beam 1 0.95 sectional area = 0.13 0.12
deduction center opening 1 0.49 0.49 0.37 0.07 -0.01
ash bar fix 2 0.37 0.74 0.23 0.08 0.01
cap slab with sloping front 1 0.95 sectional area = 0.13 0.12
4.3 Total 0.38 m3

4.2 5.1 Reinforcement bar works 1.75% of Total R.C.C. = 52.23 kg

4.3 Form works


base slab 4 1.15 4.60 0.10 0.46
feed plateform & ring beam 1 0.95 0.95 0.55 0.52
side bar 2 0.95 1.90 0.14 0.27
2 0.95 1.90 0.07 0.13
2 1.15 2.30 0.07 0.16
2 0.35 0.70 0.14 0.10
2 0.49 0.98 0.07 0.07
2 0.37 0.74 0.07 0.05
ash bar fix 4 0.37 1.48 0.08 0.12
cap slab with sloping front 1 1.005 1.01 0.49 0.49
side bar 2 0.950 1.90 0.10 0.19
2 1.100 2.20 0.15 0.33
6.1 Total 2.89 m2
5 Brick works in 1:4 c/s mortar
wall back 1 0.95 0.95
wall side 2 0.72 1.44
2.39 0.23 1.33 0.73
3.4 Total 0.73 m3

Prepared by- Checked by- Recommended by- Approved by-


118 of 123
Construction of Waste Burner

Item Total
S.N. no Description No Length Breadth Height Quantity Remarks
length
6 Cement pointing (1:3)
outside 1 3.31 3.31 1.33 4.40
inside 1 1.93 1.93 1.33 2.57
7.4 Total 6.97 m2

7 Structural steel pipe for chimney


11.15 100 mm dia structural pipe 1 2.15 2.15 9.97 kg/m 21.44 KG

Prepared by- Checked by- Recommended by- Approved by-


119 of 123
1 One 100000000000 1E+09 10000000 100000
2 Two Kharab Arab Crore Lacs
3 Three 0 6 84
4 Four Six
5 Five
6 Six
7 Seven
8 Eight
9 Nine
10 Ten
11 Eleven
12 Twelve
13 Thirteen
14 Fourteen Eighty Four
15 Fifteen
16 Sixteen
17 Seventeen Six
18 Eighteen Eighty Four
19 Nineteen Six Eighty Four
20 Twenty Six Eighty Four
21 Twenty One Six Crore Eighty Four Lacs
22 Twenty Two Enter the number 68476748.31 Six Crore Eighty Four Lacs Seventy Six Thousand Seven Hu
23 Twenty Three
24 Twenty Four
25 Twenty Five
26 Twenty Six
27 Twenty Seven
28 Twenty Eight
29 Twenty Nine
30 Thirty
31 Thirty One
32 Thirty Two
33 Thirty Three
34 Thirty Four
35 Thirty Five
36 Thirty Six
37 Thirty Seven
38 Thirty Eight
39 Thirty Nine
40 Forty
41 Forty One
42 Forty Two
43 Forty Three
44 Forty Four
45 Forty Five
46 Forty Six
47 Forty Seven
48 Forty Eight
49 Forty Nine
50 Fifty
51 Fifty One
52 Fifty Two
53 Fifty Three
54 Fifty Four
55 Fifty Five
56 Fifty Six
57 Fifty Seven
58 Fifty Eight
59 Fifty Nine
60 Sixty
61 Sixty One
62 Sixty Two
63 Sixty Three
64 Sixty Four
65 Sixty Five
66 Sixty Six
67 Sixty Seven
68 Sixty Eight
69 Sixty Nine
70 Seventy
71 Seventy One
72 Seventy Two
73 Seventy Three
74 Seventy Four
75 Seventy Five
76 Seventy Six
77 Seventy Seven
78 Seventy Eight
79 Seventy Nine
80 Eighty
81 Eighty One
82 Eighty Two
83 Eighty Three
84 Eighty Four
85 Eighty Five
86 Eighty Six
87 Eighty Seven
88 Eighty Eight
89 Eighty Nine
90 Ninety
91 Ninety One
92 Ninety Two
93 Ninety Three
94 Ninety Four
95 Ninety Five
96 Ninety Six
97 Ninety Seven
98 Ninety Eight
99 Ninety Nine
1000 100
Thousand Hundred unit Paisa
76 7 48 31
Seven

Thirty One

Forty Eight

Seventy Six

Seven Forty Eight Thirty One


Seventy Six
Seventy Six Seven Forty Eight Thirty One
Seventy Six Seven Forty Eight Thirty One
Seventy Six Thousand Seven HundredForty Eight Thirty One
nty Six Thousand Seven Hundred Forty Eight and Paisa Thirty One Only
Government of Nepal
Ministry of Urban Development
Department of Urban Development & Building Construction
Division Office
Gorkha

Summary of Cost Estimate

Project Name:- Construction of Thalajung Health Post Building.


Location:- Thalajung, Gorkha FY: 070/71

S No Description of work Amount Remarks


A Civil works
i Main Building 28,120,065.93
ii Toilet Block 10,132,216.51
iii Landscaping 7,095,238.35
iv Septic Tank 127,551.95
v Soak pit 2 Nos 134,724.33
vi Inspection Tank 19 Nos 119,284.63
vii Pump House 2 Nos 36,995.28
viii RCC water Tank 347,907.23
ix Placenta Pit 88,504.17
x Waste Burner 28,717.49
xi 4WD Vehicle 2 Months 254,552.81
B Sanitary Installation 1,210,731.65
C Electrical Installation 928,170.66
D Provisional (Insurance and etc..) 409,888.46
E Sum without contingencies 49,034,549.45
F Contingencies @ 5% of E 2,451,727.47
G Sum with contingencies (E+F) 51,486,276.92
H VAT @ 13% of G 6,693,216.00
I Sum with Vat (G+H) 58,179,492.92
For Budget Provision
I Physical Contingency @10% of E 5,148,627.69
J Price Adjustment Contingencies @10% of E 5,148,627.69
K Grand Total Cost (H+I+J) 68,476,748.30