Repair Mhada D.S.R. 2012
Repair Mhada D.S.R. 2012
\1
DSR NOTES
1. The rates of the items ·in this schedule of rates are worked out assuming
average lead for Greater Mumbai are for all sorts of materials . While arriving
basic rates of material falling under the category of Minor Mineral Act,
2. The rates of the items in this schedule are derived from the rate analysis
of individual item. The Rate analysis are prepared on t he basis of
competitive market rates & PWD DSR material and labour rates.
3. Since the basic rates of materials adopted while preparing the rate abstract
of items are as per market rates, which include VAT and other taxes, no
•
separate provision is required to be made in DSR items i.e. rates considered
'
in the DSR are inclusive of VAT & other taxes.
5. Provision of 1% for ldbuur amenities has been made in the item rate.
6. No provision of turn over tax has been made in the item rate.
Cement - Rs. 5400 /-per M.T. i.e. Rs. 270 /-per bag
8. Items not included in this schedule of rate shall be taken/ opted fro the
.. .
-3-
, 9. The items of tiled flooring and dado under section Bd/M are inclusive of
bedding and plastering respective ly. Hence wh ile preparing the estimates,
10. Under sect ion Bd/W, the items pertaining to polymer repairs shall only be
included and executed only after issue of specific order by Dy. Chief Engineer
11. Schedule of rates prepared for the year 2012-2013 is operative from
12. In case of an extra item & recovery of salvage, the rates mentioned in this
11 11
S.R. shall not be applicable for the works having the estimate /schedule 8
13. The schedule of rates will be applicable to the tenders which are received by
Sd/- Sd/-
Dy. Chief Engineer {Zone-I} Dy. Chief Engineer (Zone-II}
M.B.R. & R. Board, Mumbai M.B.R. & R. Board, Mumbai
Sd/- Sd/-
Dy. Chief Engineer (ZonP.-111) Dy. Chief Engineer {Zone-IV)
M.B.R. & R. Board, Mumbai M.B.R. & R. Board,Mumbai
I '
-4-
l
_ .... :« c l c .,
0
I
IRONWORK
(Bd/C)
' .
. r.
Sr. Specificati Item of Work Unit Rate
No. on No. proposed for
2012-2013
-5-
,
\
I
REINFORCED CEMENT I
CONCRETE
(Bd/F)
11 ·
1
Sr. Specificati I:::em of Wo rk Unit Rate
No. on No. proposed
for
2012-2013
BD/F- REINFORCED CEMENT
CONCRETE
304, Bd/F- concrete upto (50 mm) cover, cleaning old cubic
5 P-300 and concrete removing rust from the existing meter
as per reinforcement, providing reinforcement and
wording of propping to other members as per design and
item drawings, and providing and casting in situ
cement concrete M-20 of trap metal as
directed including cement, slurry compaction
and roughening the surface if special finish is
to be provided & curing, necessary as
required (Reinforcement will be separately
paid for).
5. As per Providing and carrying out cement slurry One 199 per
wording of grouting in cracks with grout holes oft32 mm Junction One
item. dia at the top and as well as on the sides one spot junction
metre center to center staggering lOC?tions if spot
possible under pressure of 1 kg/sq.cm. to
1.50 kg /sq.cm. commencing with sealing
face of the crack with putty 24 hours fore
grouting with 'cement water mixture 1:10
stepping gradually and finally to 1:1 at any
level including scaffolding staging etc. as
directed etc. complete.( Cement water ratio
should be gradually stepped up from 1:10,
1:5 1:4, 1:3, 1:2, 1:1).
l I
. BRICKWORK
(Bd/G)
! .
Sr. Specificati Item of Work Unit Rate
No. on No. proposed
for
2012-13
-
BD/ G - BRICK WORK
-7-
WATERPROOFING
(Bd/J)
'
. ..
Sr. Specificatio Item of Work Unit Rate
No. n No. proposed
for
2012-13
BD / J-WATER PROOFING
l. As per Provid ing and laying cemertt brick bat coba Per 2510.00
wording of with one part 9f cement mortar (1:4) and cubic
item two parts of broken bricks bats to be mixed meter
and laid to required slopes properly rammed
as directed including curing etc. complete.
2. As per Extra for adding approved waterproofing Per 25.50
Manufacture compound as per manufacturers kilo
s specifications, (Sisco, Impermo, Accoproof, gram
specification or Seoth waterproofing compound shall be
selected for u se). etc. complete as directed.
3. As per Removing the old cement vata & cleaning Per 5.00
wording of the site etc. complete as directed. Running
Item. meter
4. As per Providing Cement vata in C.C. 1:2:4 to Per 5626.00
wording of the junction of terrace parapet & the cubic
Item. Bd/E- elsewhere, with finishing the same with meter
5, neat cement and curing the same for 7 days
p-290 etc. complete. (Only metal No. 1 should be
used) .
5. As per Removing ex isting cement concrete of per 17.00
wording of any thicknes s including cement plaster of square
item. columns bea m s and ceiling for preparing meter
the surface fo r guniting including breaking
concrete by chiselling wedging without
causing dust nuisance and stacking the
debris upto a distance of 50 metre or
spreading and cleaning the site as directed.
-8-
PLASTERING ·
(Bd/L)
' .
-
Sr. Specificati Item of Work Unit Rate
No . on No. proposed
for
2012-13
BD/ L - PLASTERING
-9-
PAYING, FLOORFINISHING
•
&DADO
(Bd/M)
\
1 • '
• Sr. Specificati Item of Work Unit Rate
No. on No. proposed
for
2012-13
BD/M - PAVING , FLOOR FINISHING AND
DADO
7. As per Providing & laying in position R.S.J.Ladi coba Per 2459 .00
wording of Ladi flooring for clear span between 13'-0" square
item. Bd/C- to 15'-0" with R.S.J. I.S.M.B. 150 placed at meter
2, P-275, - 0.45 .m. centre to centre and cast in situ
Bd/E-2, P- concrete 1:3:6 -to form 3n thick slab over
288, Bd/M- bottom rough shahbad ladi of 25mm to 30mm
1, P-399, thick 'including necessary scaffolding with all
Bd/P-1, P- lead and lift and curing finishing the soffit with
411, Bd/O- two coats of white wash. The item also
6, P-406 includes, providing painting to all structural
.
steel members with one coat of red lead and 2
coats of .oil paint of approved shade etc.
complete (Excluding top ladi).
Note -(Measurements shall be between clear
internal finished wall surface of room).
8. As per Providing & laying rough shahabad stone Per 196.00
'
wording of flooring 25mm to 30mm thick as bott_om square
item. Bd / ladi on top of the wooden / R.S. joist for meter
M- 1, P-379, flooring including cement pointing in cemept
Bd/L-15, P- mortar 1:3 curing and cleaning excluding bed
372 of cement mortar 1:6 etc. complete as directed .
9. Bd/M-1 Providing and laying with old rough Shahabad Per 142.00
P-379, Bd / L stone of any thickness on a bed of cement square--
-15, P, 372 mortar ( 1:6) including cement float and cement meter
pointing in mortar 1:3 curing and cleaning et .
complete.
10. Bd / L-15 p- Providing cement pointing in cement mortar Per 51.00
37-2 & as 1:3 to tandur or Shahabad pavement including square
per wording curing etc. complete. · meter
of Item.
11. As per Filling in gaps between joists (Kodias) \\ith Per 66.1 '
wording of brick masonry in cement mortar (1:6) and running
Item. plastered in cement mortar (1:5) on one or meter
both sides as required etc. complete .
12. As per Providing & laying polished cuddappa tone Per 587.00
wording of slal? (visible one side polished ) 25mm to 30 square
item Bd/M- mm thick for treads & riser of steps & meter
22 P-390 staircase with rounded nosing for treads on
bed of 1:4 cement mortar including cement
float filling joint with neat cement slurry
curing polishin-g, cleaning complete .
13. As per Providing & laying cast in situ concrete 1:3:6 Per • 346.00
wording of to form 3" thick slab over bottom rough square
item. Bd/E- shahbad ladi of 25mm to 30m.m thick n...;·er
1, P-287, including necessary scaffolding with all lead
Bd/L-15, P- and lift and curing fmishing and filling the
372 joints of ladi with cement mortar etc. complete '
as directed. (Excluding top 1adi) .
-11-
OIL PAINTING
(Bd/O)
..
' .
Sr. Specificati Item of Work Unit Rate
No . on No . proposed
for I
2012-13 I
BD /O - OIL PAINTING
..
- 12-
WOODWORK
(Bd/Q)
...
_
' . .
Sr. Specificati Item of Work Un it Rate
No. on No. proposed
for
2012-13
BD/ Q - WOOD WORK
1. As per Labour charges for removing woo den p'lsts Per 341.00
wording of and sarrahas including cutting down number
item. masonry on alr sides and propping required
and stacking the dismantled materials in the
compound. & scaffolding etc. complete
including all leads and lifts of all material
(Reinstatement of masonry will be paid
separately).
2. As per Labour charges for removing wooden Per 527.00
wording of beams including propping cutting down number
·item. masonry and stacking the dismantled
materials in the compound & scaffolding etc,
complete. including all leads and lifts of all
material (Reinstatement of masonry will be
paid separately).
3. As per Labour charges for removing wooden posts Per 213.50
wording of in varandahs or passages including number
item. propping, scaffolding including stacking the
dismantled materials in the compound etc.
complete including all leads and lifts of all
material (cutting of brick masonry will be
paid separately) .
4. As per Labour charges for removing beams
including propping scaffolding including
Per I 239 .00
wording of number
item . stacking, the dismantled materials in the
compound etc. complete including all leads
and lifts of all material (Cutting of brick
masonry will be paid separately).
,.&. Bd/T-2,P- Providing and fixing country teak wood in Per 60058.00
478 Bd/Q- rectangular / square scantlings of any cubic
1&2, section in door and window frames, lintels, meter
p-419 trusses, joists rafters, ridges , purlins, post
Bd/Nl-6 plates, wall plates etc. upto any length
P-400 and including planing coal taring and applying
as per one coat of primer etc. complete including
wording of fixing screws nails iron straps wherever
item. required & as directed (Iron straps will be
paid separately) .
6 Bd/Q-2&3 Providing and fixing country teak wood in Per 57451.00
P-420 /42 1 rectangular/square sections for posts and cubic
Bd/ Nl-6 p- beams of all sizes and of any lengh1 meter
400 and as including planing one coats of primer
per wording including coal tarring and fixing screws nails
of item. iron straps wherever required as directed .
(Iron straps will be paid separately)
7. Bd/N-f-6 Reusing owner's serviceable wood Per 15235.00
p-400 including cutting to required section, cubic
Bd/0-5,P- planing , sawing, fixi.n it in position with m ter
405 & as nails screws, iron straps, nuts, bolts, and
per wording painting with two coats of oil paint with one
of item. coat of primer and / or coal tarring for
joists, lintels, trusses doors and windows
etc. complete as directed (Smaller sections
size of 15.5cms in width.)
Sr. Specifica t i Item of Work Unit Rate
No . on No . proposed
for
2012- 13
-14-
ROOFING & CEILLING . ·
(Bd/R)
.. .
.I
I Ra te I
Sr. Specificati It..!m of\VJ::;: Unit
i
No. on No. proposed
for
!lOl!l- 1'.l
BD /R - ROOFING AND CEILING
l. As per Removing the battens from the roof and Per 7.5
wording of stacking the samv on ground in the square
item. compound including scaffolding if required meter
etc. coupleted .as directed.
2. As per Ren:ioving the Mangalore tiles hips and Per 11.00
wording of rid ge tiles and stacking the same on the square
3.
item.
As per
wording of
item.
ground in the compound
scaffolding if required
required.
including
etc. complete as meter
I
Sr. Specificati Item of Work Unit Rate
No. on No . proposed
for
2012-13
BD/ T- DOORS AND WINDOWS
..
-17-
WATER SUPPLY &
SANTITARY
(Bd/V)
Sr. Specificati Item of Work Unit Rate
No. on No. proposed
for
2012-13
BD/V-WATER SUPPLY AND
SANTITARY
- 19-
. --- -. -
MISCELLENIOUS,
STAIRCASE, GUNITING .
(Bd/W)
' ' .
r
Sr. Specification Item of Work Unit Rate
No . No . proposed
for
2012-13
BD/W - MISCELLENIOUS
STAIRCASE
1. As per wording Labour charges for removing existing T.W. One 26.00
of item staircase of any size including vide stringer step
treads & risers, making good the damage to
adjoining structure, stacking the materials in the
compound etc. complete as directed .
2. As per wording Labour cnarges for removing existing wasteful One 17.00
of item treads and risers includ ing stacking dismantled step
materials in the compound etc. complete as
directed,
3. As per wording Removing & refixing treads & riser as directed One
of item . with one coat of primer including fastening and step
fixing nails etc. complete as directed .
4. As per wording Providing & fixing C.T.W. staircase 'X' Mtr. wide one step 530
of item. with 6.25cm X 30 cm. stringer and treads meter +
25rnm to 30mm thick and 27.5 cm in width width 537 x
and risers 19mm thick and 15cm in height
including fixing and fastening with bolts, nuts
nails etc. with one coat of wood primer and two
coats of oil painting etc. complete as directed
where X stand for width of staircase in meters
5. As per wording Providing & fixing C.T.W.staircase 'X' mtr. wide One step 549
of item . with 6.25cm X 30 cm. stringer 25mm to +
30mm thick and 27.5 cm in wide treads 432X
including fixing and fastening with bolts, nuts
nails etc. with one coat of wood primer and two
coats of oil painting etc. complete as directed
where X stands for width of staircase in meter .
6. As per wording Providing & fixing C.T.W. staircase 'X' mtr . wide one step 605X
of item. with treads of 25mm to 30mm thick and 27.5 meter
cm in width & riser of 19mm. thick and 15cm. v.idth
in height :including fixing and fastening with
bolts, nuts, nails, etc. with one coat of wood
primer and two coats of oil paint etc. complete as
directed where X stands for width of staircase
in meters.
7. As per wording Providing & fixing country teak wood staircase one step 430X I
of item. 'X' Mtr. wide with treads of 25mm to 30mm
thick and 27.5 cm in width including fixing &
fastening with bolts, nuts, nails, etc. with one
coat of wood primer and two coats of oil paint etc.
complete as directed) where X stands for width
or staircase in meters.
8. As per wording Removing any type or railing as directed. Per 21.00
of item. -. Runni ng
meter
9. As per wording Removing & Refixing any e of i:ailing as Per 108.00
of item. directed with two coats of painting etc. complete . Runni ng I
meter
..l
Sr Specification Item of Wo r k U nit Rate
No . No. proposed
for
2012-13
10. As per wording Providing & fixing in position country teak wood per 1354.00
of item. railing consisting of 38mm X 38mm ballustrades square
10 cm. X 6.25 cm. top and bottom runners and meter
sides posts including fixtures complete as
directed. (spacing shall not be more than 75 mm.)
11. As per wording Providing & fixing in position railing consisting of per 1149.00
of item. 12mm X 12mm M.S. square bars (ballustrades) square
with SOmm X 3mm M.S. flat covered v.rith P.V.C. meter
hand rail at top including fixtures and fastening,
with one coat of primer & two coats of synthetic
enamel paint etc. complete as directed.
GUINITING SECTION
12. Bd/L-2, P-368, Guininting by dry mix process as per I. S. 9012- per 562.00
(a) Bd/P-2, P-412 1978 to the surface of ceiling / tanks chaijas / square
and As per fins and R.C.C . pardi in cement mortar1:3-1/2 meter
wording of item. wi th an average thickness of 20mm to 25mm to
form even surface under pressure of 2. 10
kg/ sq.cm to 2.80kg/ sq. cm including forms a..-id
fixing the I.RC. fabrics (welded mesh) of size 100
mmx lOOmm and lOgauge ( 3.25 mm thick )
including scaffolding & plastering the surface •
with 12mm thick singal coat in cement mortar
1:3 with neeru finish and applying two coats of
white wash & colour wash including curing the
surface for 14 days etc. complete as directed. (
Excluding steel reinforcement)
(c) Bd/L-2, P-368, to Beam side & bottom ... per 564.50
Bd/P-2, P-412 (20mm thick) square
and As per meter
wording of item.
•
(e) Bd/L-2, P-368, to Beam side & bottom ... per 790.SO I
Bd/P-2, 412 (40mm thick) square
and As per meter
wording of item.
Sr Specification Item of Work Unit Rate
No. No. proposed
for
2012-13
bd/ L-2, P-368, to Beam side & bottom ... per 888.00
Bd/P-2, P-412 '"( SOrnm thick) square
and As per meter
wording of item.
(g) Bd/L-2, P-368, to column ... per 587.00
Bd/P-2, P-412 (25mm thick) square
and As per meter
wording of item .
(h) Bd / L-2, P-368, to column ... per 705.00
Bd / P 2 , P-412 (40mm thick) square
and As per meter
wording of item.
(i) Bd/L-2, P-368, to column ... per 875.00
Bd/ P-2 , P-412 (SOmm thick) square
and As per meter
wording of item.
Ul Bd/L-7, P-368, Beams & column ...40mm thick. ...with sand face per 969.00
Bd/P-2, P-412 plaster 22 mm thick in two coats in C.M. 1:4 and square
and As per two coats of colour wash. (40mm thick) meter
wording of item.
13. As per Wording Providing & fixing the non teak wood i.e 'saru' Per 202.00
of Item props of 75mm diameter in the middle solid & number
straight in single piece upto 3 mtrs . heigh t to
secure the dangerous floor beams, walls,
' I
galleries, balconies or other portion of dilapidated
bldg. by propping including top and bottom plates
patlies , wedges etc. as necessary including all
labours, materials & as per direction of Engineer-
in-charge. The props shall be fixed in workman
like manner and \vithout disturbing adjoining
structure etc. complete as directed.
I
14. As per Wording Providing & fixing the non teak wood i.e 'saru' Per 225.00
of Item props of lOOmm to 125mm diameter (inclusive number
125mm) in the middle solid & straight in single
piece upto 3 mtr s. height to Sl!cure the
dangerous floor, beams, walls, galleries, balconies
or other portion of dilapidated bldg. by propping
includin g top and bottom plates patties , wedges
etc. as necessary including all labours, materials
& as per direction of Engineer-in-charge . The
props shall be fixed in workman like manner and
without disturbing adjoining structure etc.
complete as directed.
-22-
Sr Specification Item of Work Unit Rate I
No. No. proposed
for
20.12-13
15. As Per Wording Providing & f'·«lng the non teak wood i.e 'saru' Per 248.00
of Item props of 125mrn to lSOmm diameter (exclusive number
12Smm) in the middle solid & straight in single
piece upto 3 mtrs. Height to secure the
dangerous floor, beams walls, galleries, balconies
or other portion of dilapidated bldg. by propping
including top and bottom plates patlies, wedges
etc. as necessary including all labours, materials
& as per direction of Engineer-in- charge . The
props shall be fixed in workman like manner and r-..
without disturbing adjoining structure etc.
complete as directed.
16. As Per Wording Providing & fixing the non teak wood i.e 'saru' Per 294.00
of Item props of lOOmm to 125mm diameter (inclusive number
125mm) in the middle solid & straight in single
piece between 3 mtrs. to 4.50 Mts. height to
secure the dangerous floor, beams, walls,
galleries, balcon ies or other portion of dilapidated
bldg. by propping including top and bottom plates
patlies , wedges & bracing etc. as necessary
including all labours, materials & as per
direction of Engineer- in-charge. The props shall
be fixed in workman likemanner and without
disturbing adjoining structure etc. complete as
directed.
17. As Per Wording Providing & fixing the non teak wood i.e 'saru' Per 374.00
of Item props of 125mm to 150mm diameter (exclusive number
125mm) in the middle solid & straight in single
piece between 3 mtrs.to 4.50 Mts. height to
secure the dangerous floor, beams, walls,
galleries, balconies or other portion of dilapidated
bldg. by propping including top and bottom plates
patlies , wedges & bracing etc. as necessary
including all labours, materials & as per
direction of Engineer- in- charge. The props shall
be fixed in workman like manner and without
disturbing adjoining structure etc. complete as
direckd.
18. As Per Wording Providing & fixing the non te It wood i.e 'saru' Per 426.00
of Item props of 125mm to lSOmm diameter in the number
middle solid & straight in single between upto
4.SOmts . to 6.00 mtrs. height fo secure the
dangerous floor, beams, walls, galleries, balconies
or other portion of dilapidated bld ._:. by propping
including top and bottom plates patlies , wedges
etc. as necessary including all labours, materials
& as per .rlirection of Engineer-in-charge. The
props shali be fixed in workman likemanner and
without disturbing adjoining structure etc.
complete as directed.
I
Sr Specification Item of Work Unit Rate
No. No . proposed
for
2012-13
19. As Per Wording Refixing fallen & loose props, of any height, Per 33.00
of Item includjng necessary wedges packing etc. & as number
directed by Engineer- in- charge . The items
includes the Labour charges and materials for
wedging packing patli etc. as necessary with
proper case and workmanship .
20 . As per wording Making holes in llOmm to 150mm brick walls Per 104.00
of item. for drainage pipes fittings etc. and making good number
Bd/G:.5 to the masonry walls with brick work in cement
P-315 Bd / P-2 mortar 1:3 or cement concrete 1:2:4 and finished
f P-412 on both sides with cement plaster and two coats
I of white wash and colour wash including
scaffolding if requ ired etc. complete .
( 21. As per wording Making holes in 230mm thick walls for Per 161.00
of item . Bd/G- drainage pipes fitting etc. and making good the number
35 P-315 . Bd / P- masonry with brick work in cement mortar (1:3)
2 or cement co!'lcrete 1:2:4 and finished on both
P-412 sides with cement plaster and 2 coats of white
wash or colour wash including scaffolding if
required etc. complete as directed.
22. As per wording Making holes in 350mm to 450mm brick or Per 268.00
of item: rubble walls for drainage pipes fittings etc. & number
Bd/G-5,P-315 making good the masonry with brick work in
Bd/p-2,p-412 cement mortar (1:3) or cement concrete 1:2:4 and
finished on both sides with cement plaster and
two coats of lime wash including scaffolding if
required etc. complete as directed. I
23. As Per Wording Removing existing nahanis completely including Per 77.00
of item . masonry walls of paniara and sill, flooring cement number
concrete bedding , if any, brick bat coba, cast iron
nal1aui trap and bend etc. and stacking the
debris in the compound etc. complete as directed .
24. As per wording Providing and construct ing nahani 1.0mtr. x Per 2539.00
ofltem. Bd/E-1 1.0 mt.clear size with 1.00 Mtr. in height & 23.00 number
P-287 cm. thick brick masonry paniara wall and front
Bd/ L-4 P- sill 23.00cm in height & width and 20.00mm
368 thick cement plaster in cement mortar 1:4 &
Bd/M-3 20mm thk . waterproofing cement plaster in
P-380 cement mortar 1:3 from inside with waterproofing
compound 2% by weight of cement and rendering
the inside plaster with neat finishing including
7. SOcm . thick
cement concrete 1:2:4 bedding & 25mm thick
waterproof bedding inc:m 1:3on c.c. bedding
laying tandur stone 25mm to 30.00mm thick on
floors and top of sill and paniara wall including
cement float including 75 mm C.I
I
nahani trap, bend C. I. Pipe and providing <!l!ment .
vata all around, curing etc. complete as directed .
.J
Sr Specification I Item of Work Unit R.Ate
No . No. proposed
I for
2012-13
25. As per wording Rectification of nahani by removing the top ladi Per 1493.00
of Item . Bd /E- 1, concrete, nahani trap, replacing the same with number
P-287 cement concrete (M-15) 1:2:4 and laying polished
Bd/L-4 Tandur stone flooring and making the nahani
P-368 Bd /-M-3 portion water tight finished the junction of walls
P-380 and floorjng in cement vatta by using water
proofing compound of approved quality,
plastering 20 mm in cement mortar 1:3 to the
existing walls from inside and finishing in neat
cement etc. complete as directed. (New nahani
. trap will be paid separately)
26. As per Wording Cutting down small trees upto 75mm dia Per 91.00
of item. including making the good damage portion and Tree
stacking the cut materials neatly on site etc.
complete as directed .
27. As per wording Cutting down small trees from 75mm dia to Per 150.00
of item. 150mm dia. including making the good damage Tree
portion and stacking the cut materials neatly on
site etc. complete as directed .
28. As per wording Cutting down small trees 150mm dia to Per 325..00
of item. 230mm dia including making the good damage Tree
portion and stacking the cut materials neatly on •
site etc. complete as directed .
29. As per Wording Removing excavated materials iucluding Per 240.00
of item . debris from the site of the work including all lead cubic
& lift to any distance as designated by BMC at metre
dumping centre or as directed.
I
30. As per Wording Removing and Refixing electrical points One 163.00
of item. including C.T.S. wiring, battens switches etc. Point
complete. (Through a licensed electrician /
wireman only) I
31. As per Wording Removing electrical points only Per 52.00
of item. number
32. As per Wording Providing & fixing aluminum thin sheets of 24 per 539.00
of item. guage thick 0.6 mtr. height of required length squ are
•
including making it into a box shape to cover the metre
four side T.W. posts in nahani portion dammering
the post including cutting fixing the sheets to the
existing T.W. posts with nails, screw etc, complete
as directed . I
33. As per wording Numbering the B.M.C's building number with Per 34.00 1
of item . .,. cast iron numbers 40 mm in height of approved Digit
design fixed complete with screws.
34. As per wording Numbering the B.M.C's building number with Per 17.00
of item. aluminimum numbers 40 mm in height of Digit
approved design fixed complete with screws.
I
Sr Specification Item of Work Unit Ra.te
No . No. proposed
for
2012-13
35. A per wording Cleaning of under Ground and overhead water Per 1000 63.00
of item. storage Tank by,.washing, cleaning the bottom Ltrs
slab, side, by washing powder, brush, brooming
etc. spreading potassium permagnate after
cleaning the tank complete or as directed by
Engineer iJl charge (Manual Cleaning).
36. As per wording · Cleaning sweeping, cleaning gutter and nallah T/ s Per 60.00
of itein. including inspection chamber and manholes upto month
any, washing place.Joilet, common passage area
etc. removing chokeup from sewer rain pipe
removin g, all rubbish filthies in municipal drain
the item includes all materials such as bamboo,
Kamties, bleaching power. Phynyle Acid and tool
and plants required for the above work etc
complete. As directed by the Engineer-in-charge. (
Consider cost for 100 T/ s Months )
I '
-26-
SALVAGE
Salvage Item Unit Rate for
2012-13
•
1 ,., Ihe rate for salvage in ca se of
.q i - -
a) For T.W. Joist ,,. Cum 30,780/-
111 The rate for salvage in case of steel bars, Metric 9,000/-
/
angle, joist etc. tonne
VII The rate for salvage in case of C.C.T. Wood Square 81.00
planking etc. meter
VIII The rate for salvage in case of burnt brick Cubic 231.45
masonry. Meter
Note 1. Quntitity of wood for items no. (a) & (b) to be considered 60% of total quantity
available as salvage for estimation purpose. The condition in the should be clear
- · - -'flllr and specific about this item.
J"i . Quantity to be taken as 50% of total quantity available for salvage for items No. II,
Ill, IV, VI, VII, VIII.
Sd/- Sd/-
Dy. Chief Engineer Dy.Chief Engineer
(Zone-I),. ·(Zone-II}
Sd/- Sd/-
Dy. Chief Engineer Dy.Chief Engineer
(Zone-Ill) (Zone-IV}
-27-
...
'