Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

citgo 12/7/04 10:07 PM Page 1

Steam reboiler system


operations
Basic heat exchange principles are used to explain gas plant thermosiphon
reboiler hydraulic constraints. Field measurements help clarify “off-design”
operations that were not apparent and were causing high condensate levels
Ken Weston CITGO Petroleum Corporation
Steve White Process Consulting Services Inc

P
rocess equipment performance is
sometimes baffling. An FCC gas
plant thermosiphon reboiler
installed at CITGO Petroleum Corpor-
ation’s Corpus Christi, Texas refinery
showed symptoms that indicated
hydraulic constraints. High condensate
levels occurred – the flow control valve
went 100% open even though the steam
flow rate was less than 15% of design. It
appeared the exchanger would not meet
its design duty due to condensate LCO
hydraulic limits. pumparound
Field measurements and further
analysis using fundamental engineering
principles showed high condensate
levels were a result of inherent operating
characteristics and not problems with
design or operation. Further testing Steam Debutanized
confirmed the exchanger met its design (start-up) gasoline
duty. Basic heat exchange principles will
be used to explain the observed steam
reboiler operation.

FCC stripper reboilers


A supplemental steam reboiler was
installed in the deethaniser (stripper) to
eliminate flaring during startup. In Figure 1 Reboiler system
normal operation, the FCC deethaniser
strips most of the hydrogen sulphide main column pumparound or product temperatures. As a result, the
(H2S), ethane, ethylene and lighter rundown. CITGO’s design uses a supplemental steam reboiler was added.
hydrocarbons from the debutaniser feed. thermosiphon in series with a kettle While this is increasingly common,
Sufficient reboiler heat is needed to reboiler to supply reboiler heat. During adding a third reboiler is fraught with
reduce the ethylene content to normal operation, the supplemental design challenges and care must be
acceptable levels, because ethylene reboiler is operated at a very low duty. taken to ensure system hydraulics are
reacts with benzene in the downstream Debutanised gasoline product not compromised.
cumene unit to form ethylbenzene, a supplies about 60–65% of the total
contaminant in the cumene product. reboiler duty, with LCO pumparound Reboiler fundamentals
During startup, the stripper reboiler’s providing the remainder. Since the Thermosiphon reboiler performance is
duty must be high enough to prevent liquid leaving the bottom tray in the governed by basic heat transfer and
non-condensibles from reaching the stripper column is only 190–205°F, hydraulic principles. Heat transfer
downstream equipment. Figure 1 shows gasoline product heat is exchanged in theory includes the heat transfer
the process flow scheme of CITGO’s the first reboiler, heating the stripper’s coefficient, exchanger surface area and
deethaniser reboiler system, including bottom tray liquid to 220–235°F prior to log mean temperature difference
the supplemental reboiler. feeding the kettle reboiler. The kettle (LMTD). Computer modelling tools such
During normal operation, the stripper uses main column LCO pumparound as Heat Transfer Research Institutes’
reboiler’s duty is relatively high and heat between 450°F and 465°F, with the (HTRI) IST program are used to design
shell-side operating temperatures vary outlet temperature varying from heat exchangers and there are many
between 190°F and 260°F, making it a 240–260°F. Throughout startup, there is hydraulic system design programs
good low- and medium-temperature little heat available from either available. Yet when problems occur,
heatsink. Although some stripper debutanised gasoline or LCO field temperatures and pressure
reboilers use steam for heat, most utilise pumparound due to low stream measurements are key to identifying

00
P T Q REVAMPS & OPERATIONS
citgo 12/7/04 10:07 PM Page 2

manipulated to meet the desired


exchanger duty. In theory, the level
controller attached to the channel head
controlled the condensate flow from the
220
100 exchanger to the header. However,
366 during initial testing, the condensate
level was above 100%, so the level was
Condensate level in the exchanger tubes above the
LC controller range.
190
When an exchanger is designed, the
engineer often assumes that all the
Deethanizer exchanger surface area is available for
column bottoms Condensate
condensing. However, when condensate
floods the exchanger, the surface area
Pressure, psig
becomes a variable. While this is not
Temperature, °F the designer’s intention, when an
exchanger is clean, duty is low and the
steam condensing pressure approaches
Figure 2 Reboiler operation the condensate header pressure.
Condensate then floods the exchanger.
root cause performance. While Where: When the steam reboiler surface area
computer models are essential for UD = heat transfer coefficient, dirty is not flooded, the temperature required
design, field measurements help explain Uc = heat transfer coefficient, clean to provide sufficient exchanger LMTD
2
off-design operations that may not be RF = overall fouling factor (Ft °F Hr / Btu) determines the condensing pressure of
apparent. the steam. As the steam rate is increased,
Steam reboilers exchange heat by A stripper reboiler’s heat transfer the pressure downstream of the flow
condensing steam at the pressure coefficient (U-value) can be as high as control valve rises to satisfy Equation 1.
2
needed to meet the process duty. The 130 btu/hr-ft -°F, but when it is fouled it As long as the exchanger is not flooded,
2
amount of heat exchanged is a function may be as low as 65 btu/hr-ft -°F. The pressure downstream of the steam
of the heat transfer coefficient, exchanger LMTD varies from start-of- control valve sets the condensing
exchanger surface area and the LMTD of run (SOR) when the exchanger is clean temperature. When the exchanger is
the shell- and tube-side streams. Once to end-of-run (EOR) when it is fouled. clean, the LMTD and steam condensing
an exchanger is installed, both the When a high fouling factor is used for pressure are low. As the exchanger fouls,
surface area and mechanical design, the exchanger is over-surfaced a higher LMTD is needed and the
configuration are fixed. Although the for start-of-run conditions, thus the condensing temperature must increase.
heat transfer coefficient is a function of exchanger LMTD must be very low. Thus, steam pressure downstream of the
many process variables, actual In a steam reboiler, understanding the flow control valve rises to adjust the
performance largely depends on mechanism that adjusts exchanger exchanger LMTD to meet the required
whether the exchanger is clean or dirty. LMTD is essential to appreciate the duty. Table 1 shows the saturation
When the exchanger is clean, the heat observed symptoms. Shell- and tube-side temperature of steam at various
transfer coefficient is high. A clean temperatures both affect exchanger pressures.
exchanger requires a low LMTD to LMTD, but during normal operation
satisfy Equation 1. shell-side process temperatures change Steam and condensate systems
relatively slowly and are primarily CITGO’s design provides for direct
Q = U A LMTD Equation (1) dependent variables. At startup when the control of the steam flow to the reboiler.
unit is transitioning to normal operation, The control valve changes the steam
Q = btu/hr Exchanger duty temperatures are variable until normal flow to the reboiler, which consequently
2
U = btu/h-ft -°F Heat transfer coefficient operation is reached. In this case, field changes the condensing pressure in
2
A = ft Exchanger surface area tests were performed during normal the reboiler as needed. Varying
LMTD = ºF Log mean temperature operation so the shell-side process the condensing pressure alters the
difference temperatures were stable and did not condensing temperature, which
vary. Thus, only steam conditions can be controls the exchanger duty. The level
Conversely, when the exchanger is used to adjust the exchanger LMTD. controller spans a portion of the tubes
dirty, the heat transfer coefficient is low, Figure 2 is a schematic of the reboiler to compensate for the clean exchanger
and the exchanger LMTD must be showing some operating temperatures over-surface. A minimum level should
higher to meet the desired duty. and pressures. Saturated 100 psig steam be kept in the condensate pot to prevent
Equation 2 shows how the dirty heat was supplied from the refinery header steam “blow-by” into the condensate
transfer coefficient is calculated. Since on flow control, with the rate system.
fouling is the largest resistance to heat Steam and condensate hydraulics are
Steam tables –
transfer in most refinery services, it linked. The condensate return and
saturated conditions
plays a major role in exchanger steam supply header pressures are fixed.
performance. A clean steam reboiler The steam condensing pressure must be
Pressure (PSIG) Temperature (°F)
requires much lower condensing 30 270 high enough to meet the condensing
temperature than a fouled exchanger. 50 298 temperature inside the exchanger, and
Thus, the condensing pressure of the 70 316 the condensing pressure must be
steam is much lower. 100 338 sufficient to allow condensate to flow
150 366 into the return header through the
Equation (2) condensate control valve without
Table 1 flooding the exchanger. In this case, the

00
P T Q REVAMPS & OPERATIONS
citgo 12/7/04 10:07 PM Page 3

exchanger is located at grade about 16ft


below the condensate return header. Refinery condensate header

Case study 23 8,000


During normal FCC operation, a test
was conducted to determine whether FI
the supplemental reboiler would meet To kettle
its design duty. However, after commis- reboiler 15%
sioning, there were problems flowing
condensate from the accumulator pot
Steam
into the condensate system. The 30 100 100 psig
condensate level was above 100% and
23⬘- 0⬙
the condensate control valve was wide
open. Also, the steam flow rate was only Condensate level
8000 lb/hr, about half its design rate.
LC
The flow-control valve controls the
steam flow rate. Pressure downstream of 7⬘- 0⬙
the valve provided the exchanger with
100%
the LMTD needed to meet the desired
exchanger duty. Condensate forms as
the steam condenses and it accumulates
in a pot attached to the exchanger head. 33 33
Pressure, psig
Level control sets flow into the
condensate return header. In this case,
the low-pressure condensate header Figure 3 Pressure survey – low duty
operated at approximately 23–25 psig.
Pressure inside the channel head must
be high enough for condensate to flow
Refinery condensate header
to the condensate header.
A pressure survey is critical when
evaluating operations, because measure- 23 15,600
ments are reality, not the results of a
FI
computer model. Figure 3 shows
measured pressure throughout the To kettle
reboiler 30%
system. Condensing pressure was only
30 psig inside the exchanger, because the
exchanger was clean and duty was low. Steam
55 100 100 psig
Pressures upstream and downstream of
the condensate flow control valve were 23⬘- 0⬙
33 psig, thus the valve consumed very
little pressure drop. The condensate
return header was operating at 23 psig. LC
Since the condensate control valve is
located at grade 23ft below the
condensate header, the operating 60%
pressure downstream of the condensate
control valve was 33 psig due to the
static head of the condensate. Pressure, psig 56 33
When the condensing pressure inside
an exchanger is high enough for
condensate to flow on level control and Figure 4 Pressure survey – higher duty
the exchanger has no condensate in it,
condensing pressure is solely dependent pressure in the exchanger increased to pressure and it is self-regulating. After
on equation 1. However, when the 55 psig and the condensate level working through basic principles, the
exchanger duty and LMTD are below dropped into the level control range. observed performance made sense even
that needed to flow condensate to the Often, fundamental principles are though there appeared to be a problem.
header, the exchanger floods. Once the needed to understand equipment
exchanger tubes are flooded, both the operation. In this example, the
exchanger surface area and the LMTD exchanger has a minimum duty for Ken Weston is a process engineer at
become variables and the condensing operation in a non-flooded condition or CITGO Petroleum Corporation’s refinery in
pressure is determined by the in this case even partially flooded due to Corpus Christi, Texas.
condensate system hydraulics. the condensate header pressure. Once Steve White is a chemical engineer for
Another test was conducted to the pressure for the required condensing Process Consulting Services Inc, Houston,
determine whether the exchanger temperature drops below the pressure Texas, providing revamp front-end process
would meet its design duty. The steam needed for the level control system to engineering to the refinery industry. He
flow rate was slowly increased to 15 600 maintain condensate level in the has more than 25 years of process design
lb/hr, which provided enough steam to control range, the exchanger floods experience, previously working for Jacobs
meet the design duty. Figure 4 shows the even more. At this point, condensate Engineering, UOP and ARCO.
pressure survey data. The condensing system hydraulics set the condensing Email: swhite@revamps.com

00
P T Q REVAMPS & OPERATIONS

You might also like