Professional Documents
Culture Documents
Glycol Contactor - Retro Fit PDF
Glycol Contactor - Retro Fit PDF
prevent carryover
A revamp of glycol contactor column internals, following CFD studies, resolved
problems with gas production caused by glycol carryover
T
he gas production rate on an condensate was sufficient at 18 000
offshore platform was t/d. This gas throughput became
constrained due to a high constrained by glycol carryover
level of glycol carryover from losses. It was decided by the
glycol contactors. The existing customer to revamp the third train
column internals were investigated in early 2012 and leave the other
and it was found that the area of trains to a later date. This would
the mesh pad in the top of the allow confidence and experience to
column was around half of the be gained with minimum exposure
column area. In addition, the gas (a single train rather than all three
outlet location and associated trains). Sulzer was selected to
piping arrangement appeared to revamp the internals of the contac-
create vapour maldistribution. A tor to minimise the TEG losses at
N2
high-capacity Shell Swirltube higher gas rates in the customer’s
separator and Sulzer structured complex.
packing internals were proposed in In the late 1980s, to increase
conjunction with a new gas outlet throughput, the original bubble cap
arrangement and the existing trays in the glycol contactor were
separator support system. CFD upgraded to structured packing
studies were carried out to evaluate Figure 1 Sketch of the existing mesh pad (GEMPAK 3A, which is comparable
the possible vapour distribution, and the gas outlet arrangement to Sulzer Mellapak 350Y). In the
based on which a revamp proposal column top, a mesh pad was
was fine-tuned. New internals were than 4 m3/d to prevent onshore installed to prevent glycol losses. It
manufactured and installed on site upsets. covered about half of the column
in 2012. Recently, the design was During a trial in 2007, dehydration area (see Figure 1). A lean glycol
validated in high-rate trial runs, capacity as well as TEG losses were distributor was installed above the
with significantly lower triethylene evaluated at various flow rates. The structured packing, and in the
glycol (TEG) carryover. gas rate was increased to around bottom there was a chimney tray to
All together, there are three trains 18 000 t/d per train, at which point collect the rich TEG before being
on the platform. The facility dehy- it was found that the glycol losses directed to the glycol regeneration
drates the gas and condensate reached the maximum limit of system (see Figure 2). This was the
separately, and then recombines the 4m3/d (total of three trains). Dew column internal configuration to be
dried products before transporta- points were found to increase and revamped. To avoid having to stress
tion via trunkline(s) to the gas were worse at the higher rates. release the column after revamp,
plant. Subsequently, the gas plant Condensate dehydration was estab- welding to the column wall was not
processes these fluids to produce lished to be adequate. Overall, permitted. The existing separator
LNG, condensate and LPGs. dehydration performance was found support system had to be reused for
In 2006, a customer in the Asia to be acceptable for the first and the various revamp options.
Pacific region decided to proceed second trunklines, where the satura-
with the design of a new bridge- tion specification had basically not Gas-liquid separator in the column’s
linked facility to its plant. The been affected and remained at top section
compression installed on the new around 25% and 19%, respectively, The location and arrangement of the
plant would allow 20 000 t/d of which was less than the integrity gas outlet was relatively unique, as
gas throughput per train. limit of 75% and the operating limit the gas outlet nozzle is located later-
Specification of the glycol content of 65%. Therefore, it was concluded ally below the mesh pad. An
of the export gas plant must be less that the dehydration of both gas and elbow-shaped internal pipe passes
∆p = k H ρ v2/2, (2)
Figures 5a-d CFD vapour flow velocity vector plots: a) above the liquid distributor;
b) below the mistmat; c) across the high-capacity separator ;and d) at the downcomer Where k is dependent on the oper-
entry after the separator ating condition and the type of
mat above the deck serves to catch mistmat.
backup is calculated, where H is these droplets. Unfortunately, the Porous media has replaced the
the backup height of fluid in the available space above the separator mesh pad in the CFD model config-
drainpipe, ρ is the density of the would not be sufficient to fit a uration. The liquid distributor and
fluid, and g is the gravitational secondary KnitMesh for the glycol high-capacity separator are
acceleration constant. Figure 3 contactors, as this involves extend- modelled as accurately as possible
demonstrates the principles of this ing the primary gas outlet, and the to represent the actual pressure
consideration: resultant space between the outlet drop through these devices.
and the vessel head would become Separator drain downpipes and the
ΔP (1) too small. The final proposal liquid distributor feed pipe are not
H fluid =
ρ fluid × g consisted of a coalescer mistmat included in this study, as they are
plus a deck. It is worth noting that not needed to simulate the vapour
A typical arrangement of the the overall glycol entrainment flow inside the vessel. The
Swirltube separator consists of a could be decreased further if using projected horizontal cross-sectional
Sulzer KnitMesh mistmat placed in a secondary KnitMesh in this case. area perpendicular to the vapour
front of and at the back of the A new distributor was proposed flow direction of the liquid distrib-
Swirltube deck. They both serve to eliminate a concern of entrain- utor feed pipe (T-shaped pipe) and
different purposes. The one below ment caused by the distributor separator downpipes with respect
the deck is the coalescer mistmat itself. The revamp also included the to the column cross-sectional area
and serves to coalesce the small installation of a better support grid is less than 2%.
droplets coming from below. To suitable for the expected higher CFD analysis results of the load
help collection and drainage of the loads. case corresponding to 20 000 t/d are
collected droplets by the swirltubes, used to validate the models against
some purge gas guides the liquids CFD verifications the available plant test data for this
into the liquid collection chambers. CFD tools can provide more load case. Figures 4b and 4c demon-
A small amount of liquid droplets detailed insights using the actual strate the CFD vapour flow
might be carried with this purge tower configuration and process trajectories and vector plots repre-
gas. The secondary KnitMesh mist- loading conditions.1 The cramped sented by velocity magnitude,
Bottom arrangement
Sulzer Mellapak Sulzer MellapakPlus At the bottom section, there is an
inlet sparger, immediately above
Figure 7 Progressive change of the corrugation angle at the both ends of the element which a chimney tray is installed.