Project Activity Plan (Updated till 31st May 2018)
Wk Plan Task Description (Outcome) Status Action Required /
No Date Remark 1 2 – 6 May Submission of IIR Completed 2 7-13 May Reading of Literature Completed 14-20 3 May Submission of Project Proposal Completed (10 marks) 2 1– 27 4 May Literature Review Completed 28–3 5 May/June Developing Conceptual Completed 6 4-10 June Framework In progress 11-17 Data Collection primary and 7 June secondary, interviews and visit Pending 18-24 8 June to banks. Pending Submission of Interim Report 9 25-1 June/July & Industry Visit (40 marks) Pending 10 2-8 July Data Analysis and Pending 11 9-15 July Interpretation Pending 16-22 Submission of results and 12 July conclusion Pending 23-29 Submission of Final report to 13 July industry mentor Pending
30 – 31 Final Presentation and End of
14 July MIP 1 Pending 1-5 15 August Start of MIP 2 Pending 6-12 16 August Pending 13-19 17 August Pending 20-26 18 August Pending 19 27-2 Sept Pending Final presentation and End of 20 2-8 Sept MIP 2 Pending Submission of Final Report 21 9-15 Sept (40 marks) Pending Presentation & Viva (60 TBA TBA marks) Pending