Download as pdf or txt
Download as pdf or txt
You are on page 1of 6

IMPROVING DISTRIBUTION NETWORK RESILIENCE

AGAINST EARTHQUAKES
A. Navarro-Espinosa*, R. Moreno*,**, T. Lagos*, F. Ordoñez*, R. Sacaan†, H. Rudnick†

*Universidad de Chile, Chile, **Imperial College of London, UK, †Pontificia Universidad Católica de Chile, Chile.

Keywords: Distribution Networks, Resilience, High Impact types of contingency are not usually considered for planning
Low Probability Events (HILP), Earthquake impacts, Risk (e.g., sizing and redundancy levels of transmission lines and
Management Reduction. further infrastructure) and operational purposes (e.g., sizing of
maintenance crews, tele-control manoeuvre devices for
topological configuration). In this context, Power System
Abstract Resilience, defined as the capability of a system to recover the
original state, as fast and as much as possible, after a severe
Historically, reliability analysis has ignored the occurrence of disturbance [4], emerges as a promising concept to overcome
natural hazards such as those associated with extreme weather, effects of HILP events such as those originated from
flooding, earthquakes and tsunamis, which are becoming more earthquakes, floods, tsunamis, etc.
and more relevant due to recent events. In this context, we
present an assessment methodology to determine the resiliency The resilience of key infrastructure (communication, roads,
levels of a distribution system exposed to a major earthquake. water, and power systems) is a topic getting increasing
The proposed 4-stage methodology models (i) the earthquake, attention from the policy making and academic community.
(ii) the fragility of network components, (iv) the network Particularly on power systems, a pioneer study about the
outages, and (v) the impacts on network operation (including seismic vulnerability of power transmission network was
the energy not supplied) through sequential Monte Carlo presented in [5]. Then, the authors in [4] present a
simulations. This methodology is used to study the resilience comprehensive framework to asses resilience at generation and
of distribution networks under two particular strategies: one transmission levels, showing specific example applications in
that hardens substations infrastructure in order to reduce their [6] by using a simplified version of the bulk UK system.
fragility levels, and the other one that uses additional network However, only a few studies have been reported on distribution
infrastructure in the form of transfer cables to shift load among networks [7],[8].
substations in case a major event occurs. Through several case
studies based on a real distribution network in Chile, we The distribution network is very important since, after a large
demonstrate that hardening substations infrastructure may be a disturbance occurs (e.g., earthquake) and after generation and
more resilient way to deal with earthquakes, even when transmission networks have been fully recovered, load may
compared to an alternative, extreme case where a vast number remain unserved due to failures in the distribution systems that
of transfer cables are installed to support damaged substations. can last longer than those in the generation and transmission
networks. In fact, this situation happened after the 8.8 Mw
earthquake in Chile, where it took almost two weeks to re-
1 Introduction connect the load nearby the epicentre area, albeit generation
and national transmission network infrastructure did not
Power systems, including transmission and distributions present any important failure [9].
networks, have been historically designed to satisfy certain
levels of reliability, dealing with the occurrence of the so- Hence, this paper will focus on distribution network resilience
called credible outages, such as the disconnection of a large and the application of two mitigation actions to increase
power plant, disconnection of one or more transmission lines resilience, namely, i) hardening the primary substation
and/or power transformers (N-1 or N-2), etc. This reliability infrastructure and ii) smart tele-control manoeuvre devices for
framework has been critical in power system, being focus load transferring among substations. This modelling allows
mainly on adequacy and security [1]. Adequacy refers to the assessing the effects of an earthquake and thus properly
system capability to supply the peak demand (i.e., enough quantify the energy not supplied (ENS) that can be used in
installed capacity) and security refers specifically to the system tandem with generation-transmission resilience models to
ability to recover after a contingency (i.e., enough reserve to assess the whole-system effects of natural hazards.
overcome credible outages) [2]. Furthermore, we demonstrate the value of hardening
That traditional reliability framework (adequacy/security) infrastructure and the utilization of smart grid technologies in
ignores high impact and low probability (HILP) events, terms of minimising the expected energy not supplied (EENS)
common mode failures and natural hazards [3] and hence, these under severe and rare events, which can be used to inform
4
review and development of innovative security standards and x 10
network incentive frameworks.
2

The rest of the paper is structured as follows. Section II 1.9


describes the proposed methodology to evaluate resilience at
1.8
distribution networks. The case study and the corresponding
sensitivities are developed in section III. Section IV presents 1.7

the simulation results for a real distribution system and finally, 1.6
the main conclusions are drawn in section IV.
1.5

2 Methodology 1.4

To assess potential mitigation actions to reduce the impacts of 1.3

earthquake at distribution networks, it is important to properly 1.2


model the distribution system, the effect of the earthquake on 3.3 3.4 3.5 3.6 3.7 3.8 3.9 4 4.1
4
the electrical infrastructure and then, the corresponding x 10

impacts on power system operation. In fact, given the large Figure 1: Distribution Network Example
scale characteristic of these systems with substations and loads
located in a widespread area, the only way to assess the impact 4. Sequential Monte Carlo Simulations: the impacts on the
of an earthquake is through the topological modelling of the distribution system operation will depend on the period
network infrastructure. As an example, Fig. 1 shows the of time when the event occurs (with certain probability)
geographic information system (GIS) representation of a and the restoration times for the damaged infrastructure
portion of a distribution system. (according to distribution probabilities). Thus, the time
series analysis is fundamental to assess the resilience
In general terms, the core of the proposed methodology to performance of distribution networks. Furthermore, the
comprehensively assess the impacts of earthquakes and the impacts on the infrastructure are also probabilistic, in
potential mitigation actions can be summarised in the fact, a particular magnitude can produce a problem with
following steps: a given probability. Consequently, to cope with the
time-series dimension of the problem and the
stochasticity of the model, a Sequential Monte Carlo is
1. Earthquake modelling: Given an earthquake location implemented.
and intensity, the model must be able to calculate the
distance attenuation from the epicentre for each 2.1 Earthquake Modelling
network element, this means the intensity at each point
(i.e., X and Y coordinates on a 2-dimentional map) in In order to measure the intensity of a particular earthquake on
the distribution network will be determined. This a widespread area, such as a distribution network, the
requires the GIS representation of the distribution magnitude attenuation from the epicentre is modelled. This
network, which corresponds to the specific location attenuation can be determined by using the peak ground
(e.g., universal transverse Mercator –UTM– acceleration (PGA) equation.
coordinates) for each distribution network element
(e.g., power substations, distribution transformers, PGA corresponds to the input magnitude in the Fragility
loads, etc.) Curves (i.e., X axis) of power infrastructure due to the action
of an earthquake. The PGA attenuation used in this work was
2. Fragility Modelling: Having the intensity of the presented in [10] based on an extensive ground motion data
earthquake at each point, it is possible to determine the base (i.e., 697 PGA values for the regression analysis) for the
intensity in each infrastructure element, and then, subduction zone in the Pacific. Thus, the equation obtained is
through the analysis of Fragility curves [5],[6] representative for the Chilean distribution network used in this
determine the level of damage in each of them. work.
. )
3. Outage Modelling: After determine the outage status of ln = 6.36 + 1.76 − 2.73 ln( + 1.58 (1)
each element, the effect in the system operation can be + 0.00916ℎ
determined. Indeed, if certain infrastructures are
partially or totally outaged/damaged, and the Where M is the moment magnitude (earthquake intensity), R is
reconfiguration strategies are in place, the amount of the distance to the epicentre in km, and h is the focal depth in
customers not served and the energy not supplied can km. PGA is the peak ground acceleration in gals. Hence, given
be determined and minimise. a combination of magnitude and depth is possible to calculate
the PGA magnitude in each position of the distribution system.
6
As an example, Fig. 2 shows a realistic distribution system x 10
used in [11]. For visualization purposes, only the poles and 6.35
underground chambers are represented (black dots). The total
dimension for the system is 4,485 km2 (65 km times 68 km), 6.34

supplying approximately 1,700,000 customers with a yearly


consumption of 12,477 GWh. Here, an 8.0 Mw earthquake is 6.33

simulated with a focal depth of 23 km in the northeast of the


city, indicating the PGA for each position in the map through 6.32

[m]
colours (brown refers to higher PGA and blue refers to lower
6.31
PGA).
6.3
It is important to highlight that the earthquake model used in
this work is a good approximation to the phenomena but it is
6.29
not the full earthquake representation (i.e., consideration of the
soil mechanical structure [12]) and therefore the impacts 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8
determined here are only referential. Nonetheless, they still [m]
x 10
5

allow the comparison among different case studies. Figure 2: PGA distribution on the distribution system.

2.2 Fragility Curves and Restoration Time Curves 1

0.9
After having the PGA values for each position in the network
0.8
(Fig. 2), the impact on the power system infrastructure can be
determined. Those effects are calculated from fragility curves, 0.7

which relate the PGA magnitude with a damage state.


Probability [pu]
0.6

Mathematically speaking, the fragility curve describes the 0.5


cumulative probability of reaching or exceeding different
0.4
states of damage for a specific peak ground acceleration. These
0.3 Minor
fragility curves are modelled as cumulative lognormal Moderate
distributions [13]. 0.2 Extensive
Complete
0.1
Fig. 3 shows the fragility curve for primary substations 0
0 0.2 0.4 0.6 0.8 1 1.2 1.4
specified in [13]. Here, four possible damage states can be PGA [g]
observed, namely, minor, moderate, extensive and complete
substation damage. Hence, for example, if the PGA is 0.6 g, Figure 3: Fragility Curve for unanchored primary substations.
then the probability of being or exceeding the minor damage 0.8
state is 0.99 (i.e., almost certainly the substation is having
minor problems) and the probability of being in a complete 0.7
Minor
damage state is about 0.3. This implies that the probability of Moderate
0.6
being in a particular state is the difference between the Extensive
Complete
probabilities of exceeding the particular state and the 0.5
Probability

probability of exceeding the above damage state. Finally, the


0.4
probability of having no damage is the difference between one
and the probability of exceeding the minor damage state. 0.3

Each damage state represents a specific percentage of damage 0.2

of the corresponding infrastructure. For instance, in the case of 0.1


primary substation, according to Hazus report: Multi-hazard
Loss Estimation Methodology [13], the minor, moderate, 0
0 10 20 30 40 50 60 70
extensive and complete damage states imply a capacity days

substation reduction of 5%, 40%, 70% and 100%, respectively. Figure 4: Restoration times for substations

It is important to remark that a particular PGA does not produce In fact, according to the Hazus report, the probability for these
always the same problem, on the contrary, a specific PGA can restoration times follows a normal distribution and it is
cause different consequence with certain probabilities, adding different for different damage states. For instance, Fig. 4
a stochastic dimension to the impact assessment. In this line, indicates the probability distribution of restoration times for
another source of stochasticity to be considered is the minor, moderate, extensive and complete damage state. These
restoration time for the failed infrastructure. curves have a median and standard deviation values of 1 and
0.5, 3 and 1.5, 7 and 3.5 and 30 and 15 days, respectively.
2.3 Sequential Monte Carlo Simulations b. If there is not an earthquake in t:
i. For every network element b in B: Generate a
From the previous subsection is clear that the stochasticity random number, Z, and compare the failure
added by fragility and restoration curves must be incorporated. rate (λ) with Z.
ii. Check time in failure and time left to be
Given the large number of elements included in a distribution recovered for b.
networks and their widespread location, it is not possible to iii. Update b status (damaged or recovered)
model all the potential scenarios with their corresponding
probabilities through an analytical formulation (i.e., large c. Update case with the status of all elements.
number of combinations when considering damage states, d. Quantify the energy not supplied for the period t
infrastructure elements and earthquake realizations). Thus, to and moves to t+1.
avoid the full enumeration of all combinations, a Monte Carlo
simulation is used for sampling, representing adequately the When t reached the last hour of the simulation horizon T, one
stochastic nature of this distribution network problem [14]. Sequential Monte Carlo simulation has been completed. For
Moreover, since the time-series dimension is important in this each Monte Carlo run, the power system case is reset to its
analysis due to the interdependence among the event default values. Thus, after N Monte Carlo simulations (we run
occurrence, the demand variation and the recovery period for steps 2 and 3, N times), it is possible to obtain a probability
different infrastructure elements with different damage status, distribution for the Energy not supplied during period 1 to T.
a Sequential Monte Carlo Simulation (SMC) is implemented,
and therefore the chronological time dependence is fully
considered [15]. Specifically, for this work the SMC has fixed-
3 Case Study
intervals of one hour for a total period of one month. The main To test the proposed methodology and to use it to improve the
steps are described below: resilience of distribution network against earthquakes, a
realistic distribution network is implemented (Fig. 2). In this
1. Set the inputs: case study, the specific SMC characteristic are i) one
a. Fragility and restoration time curves for each earthquake realization is simulated (8.0 Mw, 23 km of depth,
network infrastructure and damage state. Northeast location as the one shown in Fig. 2), ii) 100,000
b. Definition of the set of earthquakes to test, Monte Carlo simulations are run, iii) the time step is set in one
indicating location, magnitude and depth (e.g., set hour and the total horizon is 1 month (720 hours) and iv) the
of most likely earthquakes in the zone, worst case network infrastructure considered corresponds to the set of
scenario: strongest one, etc.). primary substations (i.e., 41 for the real network under
c. Failure rates and recovery times for the so-called analysis). A base case plus two strategies to improve the
credible outages at distribution level (i.e., low resilience of the distribution system are examined.
impact and high probability events).
3.1 Base Case
2. Earthquake representation:
a. Select randomly one of the earthquake from the The base case is given by the consideration of the fragility
feasible set. curves presented in Fig. 3 and the restoration times of Fig. 4
b. Calculate the PGA at each network location for the without any capability of transferring load among substations
selected earthquake. (i.e., this represents a counterfactual scenario where all the
c. Select randomly the occurrence of the earthquake substation are isolated from each other).
between 1 and T (T refers to the last hour in the
simulation horizon). 3.2 Improving Resilience – Case 1

3. Sequential steps for hour t over the horizon 1 to T. This alternative represents the possibility of hardening the
substations design in order to be more resistant to the
a. If there is an earthquake in t: earthquake action. To do that, a new set of fragility curves is
i. For every network element b in B (set of incorporated from [13]. These curves represent the cumulative
indexes of network elements): Generate a distribution of being or exceeding a damage state, namely,
random number, Z. Having Z and the PGA for minor, moderate, extensive and complete, for a certain PGA in
b determine the damage state of b and a substation with seismic considerations (Fig. 5). Hence, for a
consequently the available installed capacity. given PGA, the probability of being in a state of complete
ii. Determine the restoration time from the damage is larger in the base case than under this case 1.
probability distribution curves.
iii. Check time in failure and time left to be To allow a fair comparison with the base case, this action does
recovered for b. not include load transfers among substations. It is also worth
iv. Update b status (damaged or recovered) mentioning that this structure reinforcement is feasible in
reality and the fragility curve used come also from [13].
1
4 Results
0.9

0.8 The proposed methodology indicated in section 2.3 with the


0.7
specifications defined in section 3 is applied over the three
cases under analysis: i) Base Case, ii) Case 1: Hardening
Probability [pu]

0.6
Infrastructure and iii) Case 2: Load Transfer Capability,
0.5 obtaining the histograms for the energy not supplied (ENS)
0.4 presented in Fig. 7, 8 and 9, respectively. There, it is possible
0.3
to observe that both mitigation actions increase the resilience
Minor
Moderate
of the distribution network. Moreover, hardening the
0.2
Extensive infrastructure seems to have a better performance in the
0.1 Complete
reduction of the ENS. With the purpose of having a better
0
0 0.2 0.4 0.6 0.8 1 1.2 1.4
comparison, several statistical metrics are determined for the
PGA [g] three cases and summarised in Table 1. Here, it can be seen that
Figure 5: Fragility Curve for Seismic Substations, Case 1. for all the metrics, both mitigation actions have less energy not
supplied than the base case and also for all the metrics, the Case
3.3 Improving Resilience – Case 2 1 has a better performance.
4
x 10
3.5
This alternative adds to the base case, the possibility of
transferring load among substations (i.e., unanchored 3

substations) when there are connections and power capacity


2.5
available. This availability condition is particularly important
for the earthquake modelling because in a city, neighbours

Frequency
2

substations are close enough to face similar PGA values, and


1.5
therefore having similar chances to be in a similar state of
damage. Hence, the transfer of load will be possible if only if 1

the substations expected to provide backup have enough


0.5
capacity to do so (i.e., the damage state still allow the transfer
of a de-rated amount of power). 0
0 100 200 300 400 500 600
ENS GWh

In order to model a system in which every substation is backed Figure 7: ENS Histogram for Base Case.
up for at least three substations, the Delaunay triangulation is x 10
4

3.5
determined among all the primary substations in the
distribution network under analysis and this is shown in Fig. 6. 3
By using this triangulation (green lines in Fig. 6), all the
2.5
interconnections are made only among neighbours substations.
These neighbouring areas corresponds to Voronoi Diagrams
Frequency

whose centres are the substation location [16]. As observed, the


1.5
support network formed from transfer cables in Fig. 6 is very
interconnected and this provides an extreme case against which 1

case 1 can be compared.


0.5

6
x 10 0
0 100 200 300 400 500 600
6.35 ENS GWh

Figure 8: ENS Histogram for Case 1.


6.34 4
x 10
3.5

6.33
3

6.32 2.5
[m]

Frequency

2
6.31
1.5

6.3
1

6.29 0.5

3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 0


0 100 200 300 400 500 600
[m] 5
x 10 ENS GWh

Figure 6: Delaunay Triangulation among Substations, Case 2. Figure 9: ENS Histogram for Case 2.
Average Median Percentile Percentile References
95th 98th
Base Case 145.15 134.65 180.78 245.21 [1] R. Allan, “Power system reliability assessment-A
Case 1 90.66 81.41 115.29 171.57 conceptual and historical review,” Reliab. Eng. Syst. Saf.,
Case 2 116.03 106.52 145.96 203.41 vol. 46, no. 1, pp. 3–13, 1994.
[2] R. N. Allan and R. Billinton, “Probabilistic methods
Table 1: Statistical Comparison of ENS in GWh. applied to electric power systems - are they worth it?,”
Power Eng. J., pp. 121–129, 1992.
[3] R. Moreno and G. Strbac, “Integrating High Impact Low
1 Probability Events in Smart Distribution Network
Base Case
Security Standards Through CVaR Optimisation,” in
0.8
Case 1 Resilience of Transmission and Distribution Networks
Case 2
(RTDN) 2015, no. 2015.
[4] M. Panteli and P. Mancarella, “The grid: Stronger, bigger,
Probability

0.6
smarter?: Presenting a conceptual framework of power
system resilience,” IEEE Power Energy Mag., vol. 13,
0.4 no. 3, pp. 58–66, 2015.
[5] J. A. Buritica, S. Tesfamariam, and M. Sanchez-Silva,
0.2 “Seismic vulnerability assessment of power transmission
networks using complex-systems based methodologies,”
0 in World Conference On Earthquake Engineering, 2012.
0 100 200 300 400 500 600
ENS GWh
[6] M. Panteli and P. Mancarella, “Modeling and Evaluating
the Resilience of Critical Electrical Power Infrastructure
Figure 10: Probability distribution of having more than X
to Extreme Weather Events,” IEEE Syst. Journal, pp. 1–
GWh of Energy not Supplied.
10, 2015.
[7] Imperial College London, “Review of Distribution
This information can be validated by determining the
Network Security Standards Extended Report,” 2015.
corresponding cumulative distribution from the previous
[8] G. Strbac, D. Kirschen, and R. Moreno, “Reliability
histograms. As a result, Fig. 10 shows the probability of having
Standards for the Operation and Planning of Future
more than a particular level of energy not supplied for the three
Electricity Networks,” Found. Trends® Electr. Energy
cases under analysis. Thus, for instance, the probability of
Syst., vol. 1, no. 3, pp. 143–219, 2016.
having more than 100 GWh of ENS is about 0.26, 0.51 and
[9] J. C. Araneda, H. Rudnick, S. Mocarquer, and P. Miquel,
0.79 for Case 1, Case 2 and the Base Case, respectively. In fact,
“Lessons from the 2010 Chilean earthquake and its
the probability function for Case 1 is always below the others.
impact on electricity supply,” in International
Conference on Power System Technology,
4 Conclusions POWERCON2010, 2010, pp. 1–7.
This work developed a 4-stage methodology and the [10] M. E. C.B. Crouse, “Ground Motion Attenuation
corresponding models to assess the impacts of earthquakes on Equations for Earthquakes on the Cascadian Subduction
power distribution networks. These stages are: (i) earthquake Zone,” Earthq. Spectra, vol. 7, no. 2, 1991.
modelling, (ii) the fragility of network components, (iv) the [11] A. Navarro and H. Rudnick, “Large-Scale Distribution
network outages, and (v) the impacts on network operation Planning—Part I: Simultaneous Network and
(including the energy not supplied) through sequential Monte Transformer Optimization,” IEEE Trans. Power Syst.,
Carlo simulations. This methodology was used for studying the vol. 24, no. 2, pp. 744–751, May 2009.
resilience of distribution networks under two mitigation [12] N. Abrahamson, N. Gregor, and K. Addo, “BC hydro
actions: hardening infrastructure and increasing transfer ground motion prediction equations for subduction
capabilities among primary substations. These studies were earthquakes,” Earthq. Spectra, vol. 32, n 1, 23–44, 2016.
carried out in a real distribution network in Chile, [13] A. Engineering, “Hazus -MH MR5,” 2001.
demonstrating that hardening substations infrastructure may be [14] R. Allan and R. Billinton, “Probabilistic assessment of
a more resilient way to deal with earthquakes. power systems,” Proc. IEEE, vol. 88, no. 2, pp. 140–162,
2000.
[15] R. Billinton, H. Chen, and R. Ghajar, “Time-series
models for reliability evaluation of power systems
Acknowledgements including wind energy,” Microelectron. Reliab., vol. 36,
The authors gratefully acknowledge the financial support of no. 9, pp. 1253–1261, 1996.
UK Research Council and Conicyt through the grant Newton- [16] A. Navarro and H. Rudnick, “Large-Scale Distribution
Picarte (MR/N026721/1) and the Complex Engineering Planning—Part II: Macro-Optimization With Voronoi’s
Systems Institute (ICM:P-05- 004-F, Conicyt:FBO16). Diagram And Tabu Search,” IEEE Trans. Power Syst.,
vol. 24, no. 2, pp. 752–758, May 2009.

You might also like