Professional Documents
Culture Documents
Test Report: Bushing Current Transformers TEST
Test Report: Bushing Current Transformers TEST
TSG Technical Team visited 220kV G/S Ghazi Road Lahore for the testing of Bushings and
Bushing Current Transformers on dated results are as under.
C&DF TEST OF PT
Red Phase Yellow Phase Blue Phase
Sr. Applied
Capacitance Capacitance DF (%) Capacitance DF (%)
No Voltage DF (%)
(nF) (nF) (nF)
1. 1 kV 1.038 0.020 1.034 0.028 1.034 0.028
2. 2 kV 1.037 0.028 1.034 0.029 1.034 0.029
3. 5 kV 1.037 0.036 1.034 0.034 1.034 0.040
On the basis of above results, Tested PT of bus bar is fit for service.