The document outlines a weekly work plan for July 2018, which includes revising and submitting method statements to HEC, checking materials for installations, reviewing drawings, following up on replacement parts, and coordinating with subcontractors for public lighting and appointments. Key activities are completing method statements, preparing for inspections, and planning installations of lighting, panels, and cable schedules at the power house and switchyard. The plan is to progress installation work, check on additional materials needed, and follow up on responses required.
The document outlines a weekly work plan for July 2018, which includes revising and submitting method statements to HEC, checking materials for installations, reviewing drawings, following up on replacement parts, and coordinating with subcontractors for public lighting and appointments. Key activities are completing method statements, preparing for inspections, and planning installations of lighting, panels, and cable schedules at the power house and switchyard. The plan is to progress installation work, check on additional materials needed, and follow up on responses required.
The document outlines a weekly work plan for July 2018, which includes revising and submitting method statements to HEC, checking materials for installations, reviewing drawings, following up on replacement parts, and coordinating with subcontractors for public lighting and appointments. Key activities are completing method statements, preparing for inspections, and planning installations of lighting, panels, and cable schedules at the power house and switchyard. The plan is to progress installation work, check on additional materials needed, and follow up on responses required.
- During request list for all material / equipment
installation to HO of Hyosung
- Make BQ for Lighting for PH & Installation for
WLS - Make BQ for additional material - During recapitulation material on site ( WLS, PA/PAGING ) - Review for method work for installation lighting at 1st Floor of Power House and Installation water level system
- Cordination with Subcon for Public Lighting
Access Road than make appointment on July 06,2018. Plan of work ( July 2 Status 1st
- Complete all method statement &
submitted to HEC submit to HEC
- Check Material for Installation
on Progress FA/PA/CCTV/etc at Switchyard & Power House
- Check Additional Material for
on Progress Installation Support at Switchyard & Power House - Review Drawing for Installation at a wait response from Mr. Mangesh Power House & Switchyard
- follow up replacement material of
a wait response from HO of Hyosung interlock key from CG
- Purpose for Cable Schdule Plan
on Progress ( SWYD & PH ) Follow up to supplier
on Progress
on Progress
Confirmed to Meeting & discuss on July
06,2018 Plan of work ( July 2018 ) / Weekly Plan
2nd 3rd
- Complete all method statement - Complete all method statement &
& submit to HEC submit to HEC
- Check Material for Installation - Execution work for all material of
FA/PA/CCTV/etc at Switchyard & Installation FA/PA/CCTV already on site Power House
- Check Additional Material for - Prepare for Inspection partially for
Installation Support at Switchyard equipment & installation on switchyard & Power House area - Purpose for Installation of - Purpose for Installation of Lighting Panel at Building Control Building Control & Switchyard
- Review Drawing for Installation - Purpose for Installation of Panel at