Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

10/21/2016 (5) How do I calculate steel quantity for slab, footing, column?

 (assume the size yourself) ­ Quora

Well, you'll need to determine the area, so let's assume a 2' x 2' x 4' footing, just to keep it easy.  So we
determine area (length x width x height) so 2x2x4 is 16 cubic feet of concrete, divide by 9 to get cubic
yards (1.78 cu. yds)  I usually assume that I'll have rebar every 18 inches, and stirrups around my beams.  
Since this is a column, I have to figure out how much is going to go into my column.  Depending on what
the design calls for, this will vary, but an 18" matt across a slab has been pretty common through most of
the projects I've been on, you can assume that there will be a mat on a full slab.  Back to the hypothetical
column at hand, I'm going to assume two vertical stirrups, and some #3 rebar to tie it all together.  I can
get #3 for about $3 a 20ft piece, so 2 pieces should do me.  Stirrups I can get for about $1 a piece, so @$2
in stirrup.  Brings my rebar price up to $10 approx.

I can get concrete for about $95 a cubic yard, I'll add in a little for waste and order 2 yards.  $190 in
concrete.

Add concrete, rebar and labor together (1 finisher approx 2 hours to pour and finish @ $15/hr gives me
$30 in labor costs) total cost $230.

If you're looking for a way to estimate larger projects, look at some of the RSmeans values, they can give
you a pretty good idea of what it should cost to complete a project.
12.4k Views · View Upvotes · Answer requested by Gurbir Singh

Upvote 4 Downvote Comment

Abner T Yokum, Deal with many different engineer types, including CEs, in my line
of work.
Written Jun 1
It’s a direct function of design loads, and hard to pin down given such a generality. Obviously, on­grade
slab steel is entirely different from suspended slab steel. Column reinforcing entirely on the imposed loads
and the number of stories, especially in seismic/wind­loaded areas. Footing reinforcing is entirely
dependent on accurate load calculations and the type of soil.

“Assuming” a one­size­fits­all calculation is a recipe for disaster. That’s why CEs get paid what they do—
to take into account all of these variables to come up with a safe, efficient design.
4.6k Views · Answer requested by Mirwais Kakar

Upvote Downvote Comment

Prasanta Dey, 4 years of exprerience
Written Sep 3
If u meant to say the reinforcement steel quantity in RCC slab, footing & column then u have to prepare
the Bar Bending Schedule… However, for estimate purpose we use our practical experience and put a
tentative figure of Reinforcement per cu.m of concrete…

For e.g.­ For slab it is 95–100kg/cu.m of concrete, for footing it is 100kg/c.m, for column it is around
90Kg/cu.m… It may vary depending upon various conditions….
1.4k Views · Answer requested by Khaja Rahamthulla

Upvote Downvote Comment

Waheed Ur Rahman
Written Sep 8
Great question from you.
Let's start with the basics.

1.I am sure you must be quite conversant with the reading of RCC drawings so that you can find out the
following values from the drawing :

Length of the element :
Cross section:
No of bars
https://www.quora.com/How­do­I­calculate­steel­quantity­for­slab­footing­column­assume­the­size­yourself 1/3
10/21/2016 (5) How do I calculate steel quantity for slab, footing, column? (assume the size yourself) ­ Quora

Type of bars
Spacing between the bars.
Lap length ( horizontal/vertical)
Development length
Covers for footing/column/beam/slab.

2. Calculate the cutting length of the bars.
( total length ­ covers on bothside )+ development length.

3.Formula :
W = N*CL*U

W: Weight of reinforcement
N: No of bars
CL: cutting length
U:Unit weight

You can find out Unit weight from charts or from the formula :
U= D*D/162.

Just let me know whether you are able to get these steps.
Once you confirm , I can demontrate with an actual example.

All the best !
1.2k Views · View Upvotes

Upvote 3 Downvote Comment

Hardik Jain
Written Sep 4
Find out the dia of steel first

Assume diameter to be 20

D2 /162 = 20*20/162 = 1.62 kg/m

And then multiply with the length of reinforcement

i.e 1.62 * 12 ( 12 m is length of one bar)

= 32.4 kg

Nd now count the number of bar in detail steel drawing released by structural designer nd multiply no of
bars with with the weight of one bar as shown above

You will get the quantity of steel to place an order
1.2k Views · View Upvotes

Upvote 1 Downvote Comment

Raj Kiran, Civil Engineer
Written Sun
first of all in steel quantity calculation, we need to calculate the length of steel bar used according to
diameter and yield strength etc.,

the weight of steel bar per metre length (W)= (d^2)/162 (in kgs)

where d= diameter of the bar in mm

quantity of steel = (w) * total length of steel bar used (L)

example
https://www.quora.com/How­do­I­calculate­steel­quantity­for­slab­footing­column­assume­the­size­yourself 2/3
10/21/2016 (5) How do I calculate steel quantity for slab, footing, column? (assume the size yourself) ­ Quora

12 mm dia bar of total 16 nos in footing

length of each steel bar = 1.2 m

weight of steel bar per metre length (w) = 12*12/162 =0.889 kgs

total length of steel bar = 1.2*16 =19.2 m

quantity of steel = 0.889*19.2 = 16.896 kgs
213 Views · View Upvotes · Answer requested by Shakeel Ahmed Hussain

Upvote 1 Downvote Comment 1

Anju Merin Mathew
Written Sep 23, 2015
assume .8% for steel,thickness of slab be 100mm,900sqft area
900/10.27=87.63 sq metre
87.63x.1=8.763 cubic metre
.85x8.763x7850=550.31kg

https://www.quora.com/How­do­I­calculate­steel­quantity­for­slab­footing­column­assume­the­size­yourself 3/3

You might also like