Item Code: RR02

Random rubble masonry with hard stone in superstructure above plinth level and upto floor five level
including leveling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate
20 mm nominal size) at window sills, ceiling level and the like - Cement mortar 1:6 (1 cement : 6 coarse sand).
Details of Cost for : 1.00 Cum
Code Description Unit Quantity Rate Amount
MATERIALS:
1157 Stone for masonry work cum 1.00 675.00 675.00
1154 Through and bond stone 100 N 7.00 1100.00 77.00
2215 Carraige of Soling stone & masonry stone cum 1.16 103.06 119.55
Bond stone Qty :
7.00 x 24 cm x 24cm x 39 cm = 0.16 cum
Total : 1.00 cum + 0.16 cum = 1.16 cum
03.011 Cement mortar 1:6 (1 cement : 6 coarse sand). Cum 0.33 3602.27 1188.75
LABOUR:
0125 Mason (for plain stone work) 2nd class Day 1.34 946.00 1267.64
0114 Beldar Day 1.45 910.00 1319.50
0115 Coolie Day 0.71 747.00 530.37
0101 Bhisti Day 0.09 879.00 79.11
Cement concrete 1:6:12
9999 Sundries L.S. 56.55 1.49 84.26
Extra labour required for lifting of material upto floor five
level
0115 Coolie Day 1.13 747.00 844.11
9999 Sundries L.S. 15.21 1.49 22.66
Total: 6207.95
Add water charges @ 1% on 6207.95 62.08
6270.03
Add C.P & OH @15% on 6270.03 940.50
Cost for 1.00 Cum 7210.53

Rate per One Cum ₹ 7,210.53