Work Diary (July 21,2012)
Work Diary (July 21,2012)
Work in Progress
Description of Work Done Today
-Pouring of concrete blinding
-Fabrication of forms works for foundation of footing slabs
-Cutting and bending of re-bars for foundation footing slabs and pedestals
Obstruction None
(存在问题)
Summary of Resources (资源汇总)
No of labor(工人人数) 1-project engineer,1-site supervisor,1 - Driver
Worker : 1.Dev Narayan 2.Sat Nerayan 3.Kishori Yadav 4.Ram Kumar
5.Kahmud Mandal 6.BJ Mochi
List of Tools (工具清单) 1 unit- Plate compactor ,1 unit- Bar cutter machine, 1 unit- wood cutter
machine, 4- knipex, 2- shovel , 1- wheel borrow, 1 –Fabricated wooden
box, 1 roll- extension wire
Material / Consumable Petrol ,plywood, wooden, re- bars
Work in detailed Progress -Pouring of concrete blinding - completed
-Fabrication of forms works for foundation of footing slabs – on going
-Cutting and bending of re-bars for foundation footing slabs and
pedestals – on going bending
Work Planned for Next Day :
-To continue fabrication of Formworks footing slab atleast 50 %
-Cutting and bending of re bars for footing slab and pedestal – to complte cutting and
bending and star assemble per footing rebars