Saint Louis University

SCHOOL OF ENGINEERING AND ARCHITECTURE


Department of Civil and Geodetic Engineering
A.Y. 2017-2018
2600 Baguio City

COMPANY: MOMENT DIAGRAM BUILDERS


ADDRESS: 3RD FLOOR NOBLE BLDG. CALDERON ST. BAGUIO CITY

TIME HOURS
DATE DAILY TASK ACCOMPLISHMENTS
SCHEDULE RENDERED
Introduction to the owner then orientation about the
scope of work to be done. Then Engr. Pulido of
DepED Division Office, Department Of Civil 8AM – 12PM
Jul. 21, 2017 8 HOURS
Engineering called and asked for office work 1PM-5PM
assistance for 2 weeks in preparation of upcoming
projects.
Engr. Daclili brought us to his project sites for site
Jul. 22, 2017 8AM – 5PM 9 HOURS
inspections.
Engr. Daclili brought us to DepED division office
engineering department to lend them a hand in some
office works. We proceed immediately to
8AM – 12PM 8.92
Jul. 24, 2017 registration office in order us to be acknowledged as
12:25-5:20PM HOURS
trainees in the office. Then, together with some
engineers we set up our temporary workplace,
lending us 2 units of desktop computers to work on.
OFFICE: Finishing installations and updates of
programs that are essential for works on the desktop
pc we were assigned to use. Took long because of 8AM – 12PM 8.75
Jul. 25, 2017
internet disconnections. Before going home, we 12:25-5:10PM HOURS
were asked to drop by Engr. Daclili’s office for
work report.
ON SITE: Engr. Paul brought asked us to
accompany him on his periodically site inspections, 9
Jul. 26, 2017 8AM–5PM
2 sites were inspected, Guisad Valley HighSchool HOURS
and Lucban ES
OFFICE: Engr. Paul showed some of his ongoing
projects in autocadd, plans for construction of
8AM – 12PM
Jul. 27, 2017 school annex. Then he ordered us to put some 8 HOURS
1PM-5PM
details and dimensions to those cadd files. Dropped
by Engr. Daclili’s Office for daily work report.
OFFICE: Engr. Aliswag, a louisian graduate, gave
us a complete plans for a school building
8AM – 12PM 8.75
Jul. 28, 2017 construction project and tasked us to estimate its
12:25-5:10PM HOURS
total cost and the cap will be P13M. Dropped by
Engr. Daclili’s Office for daily work report.
OFFICE: Continuation of the estimations, lectured 8AM – 12PM 8.58
Jul. 29, 2017
some estimates topic to my fellow trainee. 12:25-5:00PM HOURS
OFFICE: Continued with the estimations, left office
at 12pm for the enrollment for first semester of 5th
Jul. 31, 2017 8AM – 12PM 4 HOURS
year, Engr. Aliswag asked us to continue with the
estimations as take home assignment.
OFFICE: Engr. Aliswag thought us how to estimate
labor cost, then we applied it on the assigned task to
8AM – 12PM
Aug 1, 2017 us. On the afternood, Engr. Pulido asked us to 8.92 HOURS
12:25-5:20PM
accompany them together with a contractor to
inspect the finished projects on Gibraltar ES.
OFFICE: Continued with the estimations. Engr.
Daclili visited us at the division office, took me to 8AM – 12PM
his project and asked me to buy some doughnuts for 12:25-5:20PM
Aug 2, 2017 8.92 HOURS
us on the division office. Returned to the office and
Engr. Aliswag Asked me to download and install a
complete STAAD app on his laptop and desktop.
OFFICE: Continued with the final part of the
estimations and Engr. Aliswag made some
8AM – 12PM
Aug 3, 2017 corrections. After office hours, Engr. Sam brought 9.35 HOURS
12:25-6PM
us to the renovation of PFVR basketball court,
surveyed it and played some hoops.
OFFICE: Last day on helping DepEd. Finalized the
excel documents of the estimations we’ve done and
submitted it to Engr. Aliswag. DePED officers 8AM – 12PM 8.75
Aug 4, 2017
asked us to help on carrying school files and some 12:25-5:10PM HOURS
bidding documents. Dropped by Engr. Daclili’s
Office for daily work report.
Went to MDB’s office and waited for one of the
contractors. Visited the site where the contractor is 8AM – 12PM
Aug 5, 2017 6 HOURS
assigned and inspected their work and it is where 1-3PM
would my training in December will be.
Went to MDB’s office and waited for the contractor
assigned on the San Antonio Aurora hill Project,
8AM – 12PM
Dec 18, 2017 Engr. Joel who taught me the way to the project site 8 HOURS
1PM-5PM
so I will not be waiting for him at the office every
morning.
ON SITE: Removal of column formworks and
placement of scaffolding for support on the upper 8AM – 12PM
Dec 19, 2017 8 HOURS
floor slab and beams, laying out reinforcement steel 1PM-5PM
bars.
ON SITE: Construction of formworks and
8AM – 12PM
Dec 20, 2017 scaffoldings, placement of column reinforcements 8 HOURS
1PM-5PM
to be poured out in the afternoon.
ON SITE: Removal of some scaffoldings and
formworks, forming and cutting some steel bars for
8AM – 12PM
Dec 21, 2017 beam reinforcements, constructing formworks for 8 HOURS
1PM-5PM
beams and slab, placement of scaffoldings to
support third floor slab.
ON SITE: Delivery of additional materials such as 8AM – 12PM
Dec 22, 2017 8 HOURS
cement and other aggregates, Engr. Daclili came for 1PM-5PM
some inspections. Laying out reinforcement bars on
the slab.
ON SITE: Pouring of beams and slab. Taking Notes
on the process of pouring slab and beams for upper 8AM – 12PM
Dec 27, 2017 8.33 HOURS
floor. Dropped by MDB’s office for work report 1PM-5:20PM
and Christmas break report.
ON SITE: Removal of bottom floor’s wooden
scaffoldings, assisted on some removals of
8AM – 12PM
Dec 28, 2017 formworks and carrying them to the upper floor. 8 HOURS
1PM-5PM
Taking notes on how they arrange vertical
reinforcement on third floor columns
ON SITE: Placement of column formworks, and
scaffoldings for roof beams. Engr. Daclili came to 8AM – 12PM
Dec 29, 2017 8 HOURS
inspect the reinforcement of the column and roof 1PM-5PM
beams, gave out workers’ wages.
Went to MDB’s office to report that I will resume
8AM – 12PM
Jan 4, 2018 my training as of today. Engr. Daclili brought me to 8 HOURS
1PM-5PM
one of his subcontructoral project at leonila hill.
ON SITE: Went back to San Antonio Project.
Laying out of the rsbs and formworks for the 8AM – 12PM
Jan 5, 2018 8 HOURS
construction of the stairs. Placement of the 1PM-5PM
scaffoldings for the roofing process.
ON SITE: Laying out electrical wirings and outlets,
laying out pipes for plumbing works, laying out of 8AM – 12PM
Jan 6, 2018 8 HOURS
the CHB walls on first floor, and laying out doors 1PM-5PM
and windows.
ON SITE: Took notes on how they adjust and break
some CHBs, continue with the construction of walls 8AM – 12PM
Jan 8, 2018 8 HOURS
on upper floors, assisted on bringing CHBs and 1PM-5PM
RSBs.
ON SITE: Delivery of additional CHBs for the
8AM – 12PM
Jan 9, 2018 upper floors. Beginning of exterior plaster works for 8 HOURS
1PM-5PM
lower floors.
ON SITE: Interior Plaster works for lower floors,
8AM – 12PM
Jan 10, 2018 installation of interior doors, laying out plans for 8 HOURS
1PM-5PM
tileworks and cabinets.
Went out with Engr. Daclili for canvassing of
finishing materials such as paints and ceramic tiles. 8AM – 12PM
Jan 11, 2018 8 HOURS
Returned on the site, delivery of materials. Extetior 1PM-5PM
and Interior paintworks.
ON SITE: Exterior and Interior paintworks. On
8AM – 12PM
Jan 12, 2018 upper floors. Tileworks on the first floor. Took 8 HOURS
1PM-5PM
notes on proper cutting of tiles etc.
ON SITE: Some finishings on the lower floors.
Cleaning up. On the afternoon, went to MDB’s 8AM – 12PM
Jan 13, 2018 6 HOURS
office waited for Engr. Daclili and asked for the 1PM-3PM
evaluation.
249.22
TOTAL HOURS RENDERED
HOURS
DOCUMENTATIONS

Mural on DepEd Division Office Doing Some Estimations


Computations

DepEd Site Inspection (Guisad Valley National High School & Lucban ES)

With Fellow OJT Bryan Eslao

With Engr. Paul


Rooms Front of GVNHS On Going Annex of Lucban ES

Estimation of the cost of a 2 storey school building

On Going Annex of Lucban ES

Engr. Pulido and the contractor


talking to a school faculty of With Fellow OJT Bryan Eslao
Engr. Aliswag Recording
Gribraltar ES Measurements
Student Trainees with Engr. Paul,
Engr. Aliswag & Engr. Pulido

CONSTRUCTION OF MULTI-PURPOSE BUILDING SAN ANTONIO AURORA HILL

Laying out reinforcements of Laying out formworks of beams Laying out column formworks and
beams for the second floor for the second floor reinforcements for the 3rd floor

Laying out beam reinforcements and formworks on the third floor


Laying out beam reinforcements and formworks on the third Laying out Slab Reinforcement on the
floor third floor

Laying out column scaffoldings and reinforcements on third floor

Site Inspection with Engr. Daclili at the Leonila Hill Project

ASUNCION, JOHN HENRY M.


Student On-the-job-trainee