DELIVERY SUMMARY (November - December - 2017)

Reinforcement Wiremesh
Sl.No. Description of work Unit Current
Supplied Supplied Current Total
month Total supply Previously
Previously month supply supply
supply
1 Cut, bend and supply steel 8mm Tonne 20.000 0.906 20.906
2 Cut, bend and supply steel 10mm Tonne 187.258 48.163 235.421
3 Cut, bend and supply steel 12mm Tonne 75.714 8.888 84.602
4 Cut, bend and supply steel 16mm Tonne 535.396 74.456 609.852
5 Cut, bend and supply steel 20mm Tonne 138.620 18.265 156.885
6 Cut, bend and supply steel 25mm Tonne 843.413 57.540 900.953
7 Cut, bend and supply steel 32mm Tonne 246.440 0.000 246.440
8 Straight bar supply 8mm Tonne 0.000 0.000 0.000
9 Straight bar supply 10mm Tonne 0.000 0.000 0.000
10 Straight bar supply 12mm Tonne 0.000 0.000 0.000
11 Straight bar supply 16mm Tonne 0.000 0.000 0.000
12 Straight bar supply 20mm Tonne 0.000 0.000 0.000
13 Straight bar supply 25mm Tonne 0.000 0.000 0.000
14 Straight bar supply 32mm Tonne 0.000 0.000 0.000
15 Wiremesh Nos. 1000 2400 3400
TOTAL WEIGHT IN MT 2046.841 208.218 2255.059

Page 1 of 20
Weight Delivery Note Delivery
BBS No. Load ID Drawing Reference (MT) Date Note No.

8 516 002 - Zone 1-Pile cape Reinforcement 2 of 2 5.734 24.08.2017 84489


6 514 002 - Zone 1-Pile cape Reinforcement 1 of 2 22.757 24.08.2017 84485
9 517 001 - Zone 1-Pile cape Reinforcement PC-16 1 of 3 26.808 24.08.2017 84490
7 515 002 - Zone 1-Pile cape Reinforcement 2 of 2 29.038 24.08.2017 84488
10 518 001 - Zone 1-Pile cape Reinforcement PC-16 2 of 3 20.544 26.08.2017 84515
11 519 001 - Zone 1-Pile cape Reinforcement PC-16 3 of 3 18.358 27.08.2017 84523
5 520 004 - Zone 1 Column Starter Reinforcement 10.407 28.08.2017 84532
2 524 001 - Zone 1-Pile Starter Reinforcement (Core-4, C25, C37 & C38) 21.203 28.08.2018 84537
14 525 Crane Foundation (9000x9000x300) 2.035 28.08.2019 84538
12 526 Pile cape Reinforcement (PC-1, PC-3 & PC-39) - Site Request 18.346 29.08.2017 84562
13 527 Pile cape Reinforcement (PC-2 & PC-2a) - Site Request 20.442 30.08.2017 84575
16 529 004a - Column Starter Zone 2,3 & 4 (Site Request) 10.276 06.09.2017 84652
15 528 005 - Pile Cap PC-39 & Tie Beam TB1 1.556 06.09.2017 84651
19 533 006 - Zone 4-Pile cape Reinforcement PC-15 (T3&T4) 27.282 09.09.2017 84724
18 532 006 - Zone 4-Pile cape Reinforcement PC-15 (Bottom) 29.202 09.09.2017 84713
20 534 006 - Zone 4-Pile cape Reinforcement PC-15 (T1 & T2) 20.802 10.09.2017 84730
25 537 006 - Zone 4-Pile Starter Reinforcement (Core-3) 26.014 11.09.2017 84752
24 535 Zone 3-Pile cape Reinforcement 24.598 12.09.2017 84779
26 538 006 - Zone 4-Pile Starter Reinforcement - C31, C39 & C40 0.992 13.09.2017 84799
29 541 Zone 3 & 4 -Pile cape Reinforcement 13.565 13.09.2017 84788
27 540 Zone 3-Pile cape Reinforcement 19.564 13.09.2017 84787
30 542 Zone 3 & 4 -Pile cape Reinforcement 19.595 13.09.2017 84800

Page 2 of 20
28 543 Zone 3 & 4 -Pile cape Reinforcement 21.987 14.09.2017 84805
34 546 007 - Zone 3-Pile cape Reinforcement PC-14 25.301 14.09.2017 84813
35 547 007 - Zone 3-Pile cape Reinforcement PC-14 22.42 15.09.2017 84828
31 544 004B - Zone 3&4 Column Starter Reinforcement 13.497 15.09.2017 84815
38 550 005 - Zone 1 Basement Slab B1 & B2 27.511 16.09.2017 84836
36 548 007 - Zone 3-Pile cape Reinforcement PC-14 18.668 16.09.2017 84832
39 552 005 - Zone 1 Basement Slab T1 & T2 27.029 17.09.2017 84860
33 551 007 - Zone 3-Pile cape Starter Reinforcement PC-14 - Core 2 & C8 30.755 17.09.2017 84846
43 554 005 - Zone 1 Basement Slab T1 & T2 9.875 18.09.2017 84864
45 556 008 - Zone 1-Wall Reinforcement-Core 4 - Basement to Level 1 11.375 18.09.2017 84865
46 558 Grade Slab Basement - Zone 1 2.003 18.09.2017 84863
44 555 008 - Zone 1-Wall Reinforcement-Core 4 - Basement to Level 1 17.294 18.09.2017 84873
40 553 005 - Zone 1 Basement Slab - Chair 0.963 18.09.2017 84862
48 560 Retaining Wall Pile Cap Reinforcement Zone 1&4 26.261 19.09.2017 84893
47 559 005 - Zone 1 Basement Slab @EL +3.5 8.013 19.09.2017 84892
50 561 009 - Zone 2 - Pile cape Reinforcement PC-13 - B1&B2 22.68 20.09.2017 84906
56 572 Basement Slab Reinforcement - Zone 4 30.127 20.09.2017 84907
51 562 009 - Zone 2 - Pile cape Reinforcement PC-13 - B3 & B4 24.476 20.09.2017 84913
55 571 009 - Zone 2 - Pile cape Reinforcement PC-13 (T1&T2) 24.791 20.09.2017 84914
57 573 Zone 2 -Pile cape Reinforcement 13.565 20.09.2017 84916
54 570 009 - Zone 2 - Pile cape Reinforcement PC-13 (T3&T4) 21.01 20.09.2017 84915
59 575 Zone 2 - Pile cape Reinforcement (PC-5a) 13.258 20.09.2017 84917
58 574 Zone 2-Pile cape Reinforcement (PC-8) 16.959 21.09.2017 84928
60 576 Tie Beam TB1 @Grid BL - Zone 4 0.383 21.09.2017 84925
61 577 Zone 4 Basement Slab - Chair 0.963 21.09.2017 84926

Page 3 of 20
62 578 Zone 1 & 4 Basement Slab - Chair 0.963 21.09.2017 84929
70 582 Basement Slab Reinforcement - Zone 3 30.127 23.09.2017 84968
66 580 009 - Zone 2-Pile cape Starter Reinforcement PC-13 - Core 1 & C8 30.423 23.09.2017 84969
64 579 Zone 3 -Retaining Wall Pile cape Reinforcement 11.628 23.09.2017 84954
68 581 Zone 3 -Retaining Wall Pile cape Reinforcement 22.093 24.09.2017 84981
67 584 010 - Columns - Basement to Level 1 - Zone 1 12.011 24.09.2017 84995
72 585 Zone 2 Pile Cap Reinforcement. 6.461 24.09.2017 84988
69 583 Zone 3 -Retaining Wall Pile cape Reinforcement 12.565 24.09.2017 84987
73 586 004B - Zone 2&3- Column Starter Reinforcement. 7.958 24.09.2017 84996
74 588 Zone 3 -Retaining Wall Pile cape Reinforcement 22.589 26.09.2017 85014
76 589 Zone 3 Basement Slab - Chair 0.963 26.09.2017 85015
78 591 Basement Slab Reinforcement - Zone 2 30.127 26.09.2017 85023
75 587 Zone 3 -Retaining Wall Pile cape Reinforcement 21.672 26.09.2017 85033
81 594 Zone 3 -Retaining Wall Pile cape Reinforcement 6.953 27.09.2017 85034
79 592 Zone 2 Pile cap reinforcement 13.17 27.09.2017 85046
80 593 Zone 2 Pile cap reinforcement 17.512 27.09.2017 85045
85 596 Basement Slab Reinforcement - Zone 2 30.127 27.09.2017 85053
88 598 Retaining Wall Starter 6.259 28.09.2017 85075
77 590 Zone 3 Basement Slab - Chair 0.413 28.09.2017 85072
83 597 Zone 4 Basement Slab - Section 5-5 & Starter 3.608 28.09.2017 85074
89 600 Basement Slab Zone - 2 4.017 28.09.2017 85076
90 604 Basement Slab Zone - 2 16.068 28.09.2017 85079
82 595 001A - Zone 2- Pile Cap Reinforcement. 16.058 28.09.2017 85073
87 599 010 - Columns - Basement to Level 1 - Zone 2, 3 & 4 9.333 01.10.2017 85113
93 63 Basement Slab Reinforcement - Zone 2 & 3 20.085 01.10.2017 85110

Page 4 of 20
91 612 Zone 2 -Retaining Wall Pile cape Reinforcement 25.193 01.10.2017 85111
86 609 004B - Column Starter Reinforcement - Zone 2 3.906 01.10.2017 85112
92 613 Zone 2 -Retaining Wall Pile cape Reinforcement 5.019 01.10.2017 85114
84 614 011 - Zone 4-Wall Reinforcement-Core 3 - Basement to Level 1 29.624 03.10.2017 85141
95 615 Retaining Wall Pile cap Reinforcement & Grade Slab 21.797 03.10.2017 85140
98 618 012 - Zone 3 & 4 -Retaining Wall Reinforcement 4.344 04.10.2017 85165
94 617 012 - Zone 1 & 2 -Retaining Wall Reinforcement 6.09 04.10.2017 85163
97 616 Retaining Wall Starter @Water Tank Area 5.238 04.10.2017 85164
101 619 Basement Slab - Zone 2 & 3 20.085 05.10.2017 85183
96 622 013 - Column Reinforcement Basement to Level 1 ( Zone 4) 9.077 05.10.2017 85198
99 621 013 - Column Reinforcement Basement to Level 1 ( Zone 3 & 4) 5.974 05.10.2017 85199
100 623 013 - Column Reinforcement Basement to Level 1 ( Zone 3 ) 14.92 08.10.2017 85222
105 626 Retaining Wall Reinforcement 4.007 09.10.2017 85246
102 624 014 - Retaining Wall @ Water Tank (BSMT-L1) 9.77 09.10.2017 85245
107 628 015 - 1st Floor Slab Zone 1 - Top Bars 4.001 11.10.2017 85286
106 627 015 - 1st Floor Slab Zone 1 - Main Bars (B) & Drop Bars 6.908 11.10.2017 85285
103 625 013 - Column Reinforcement Basement to Level 1 ( Zone 2) 15.53 11.10.2017 85283
113 633 Zone-2 Basement to 1st floor Retaining wall Reinforcement 4.017 12.10.2017 85304
109 629 015 - Level 01 - Bottom Reinforcement Zone 1 6.941 12.10.2017 85318
110 630 015 - 1st Floor Slab Spiral Rings 0.542 12.10.2017 85319
112 632 015 - Level 01 Slab Zone 1 - Chair Reinforcement 2.05 14.10.2017 85337
111 631 015 - Level 01 - Top Reinforcement Zone 1 11.915 14.10.2017 85336
118 636 016 - Zone 3-Wall Reinforcement-Core 2 - Basement to Level 1 5.165 14.10.2017 85340
117 634 016 - Zone 3-Wall Reinforcement-Core 2 - Basement to Level 1 26.745 15.10.2017 85358
115 637 017 - Column Reinforcement Basement to Level 2 ( Zone 1) 16.87 16.10.2017 85384

Page 5 of 20
119 638 019 - First Floor Slab Bottom Reinforcement (Zone3) 7.915 18.10.2017 85411
125 643 019 - Zone 3 1st Floor Slab Bottom 8.023 18.10.2017 85413
124 640 020 - Zone 2-Wall Reinforcement-Core 1 - Basement to Level 1 6.376 18.10.2017 85412
123 645 020 - Zone 2-Wall Reinforcement-Core 1 - Basement to Level 1 25.424 19.10.2017 85421
126 644 019 - Zone 3 1st Floor Slab Top 6.001 19.10.2017 85423
120 641 019 - First Floor Slab Top Reinforcement (Zone3) 14.694 19.10.2017 85422
128 647 022 - First Floor Slab Bottom Reinforcement (Zone4) 5.32 19.10.2017 85431
129 648 022 - First Floor Slab Top Reinforcement (Zone4) 10.604 19.10.2017 85432
127 646 021 - Column Reinforcement Level 1 to Level 2 ( Zone 1) 13.915 19.10.2017 85430
130 649 023 - First Floor Slab RC Slab & Beam (Zone - 3) 20.599 20.10.2017 85441
131 652 023 - Ramp Reinforcement Basement to Level 1 19.94 22.10.2017 85464
135 655 Level 01 Slab Top Reinforcement - Zone 4 6.001 23.10.2017 85480
121 642 019 - 1st Floor Slab Spiral Rings Zone 3 0.542 23.10.2017 85479
116 653 018 - Column Reinforcement Basement to Level 2 ( Zone 4) 13.982 23.10.2017 85478
134 654 026 - Zone 1-Wall Reinforcement-Core 4 - Level 1 to Level 2 23.502 23.10.2017 85484
137 656 027 - First Floor Slab Bottom Reinforcement (Zone2) 5.72 24.10.2017 85504
138 657 019 - 1st Floor Slab Spiral Rings Zone 2 0.813 24.10.2017 85505
144 33 10mm SP Wire Mesh - 200 Sheets 24.10.2017 85509
142 660 1st Floor Slab Zone 2 & 4 4.001 24.10.2017 85507
141 659 1st Floor Slab Zone 2 & 4 6.019 24.10.2017 85506
133 658 025 - Column Reinforcement Level 1 to Level 2 ( Zone 3) 25.645 25.10.2017 85522
149 663 Zone-2 Basement to 1st floor water tank walls 4.017 25.10.2017 85534
146 21 10mm SP Wire Mesh - 200 Sheets 25.10.2017 85531
150 665 032 - Zone 4 - Wall Reinforcement-Core 3 - Level 1 to Level 2 25.71 26.10.2017 85562
151 666 019 - 1st Floor Slab Spiral Rings Zone 2 0.271 26.10.2017 85561

Page 6 of 20
143 662 029 - Column Reinforcement Level 1 to Level 2 ( Zone 4) 15.167 26.10.2017 85563
147 664 030 - Zone 3-Wall Reinforcement-Core 2 - Level 1 to Level 2 26.351 26.10.2017 85560
153 39 8mm SP Wire Mesh - 250 Sheets 26.10.2017 85559
152 6 8mm & 10mm SP Wire Mesh - Each 100 Sheets 26.10.2017 85549
140 661 027 - First Floor Slab Top Reinforcement (Zone2) 10.568 26.10.2017 85548
154 70 8mm SP Wire Mesh - 150 Sheets 28.10.2017 85585
156 668 Ramp Slab 3.013 29-10-2017 85594
139 667 028 - Column Reinforcement Level 1 to Level 2 ( Zone 2) 24.065 29-10-2017 85593
155 669 031 - Zone 2-Wall Reinforcement-Core 1 - Level 1 to Level 2 22.167 30-10-2017 85615
157 670 034 - Level 1 - RC Slab Reinforcement (Zone 2) 9.271 31-10-2017 85625
160 73 035 - Level 2 - PT Slab Bottom Reinforcement (Zone 1) 1.335 1/11/2017 85648
161 75 Wire Mesh A-252=100 Sheets & A-393=250 Sheets 1/11/2017 85649
159/ 672 035 - Level 2 - PT Slab Bottom Reinforcement (Zone 1) 10.674 2/11/2017 85666
132 650 019 - 1st Floor Slab Spiral Rings Zone 4 0.813 2/11/2017 85665
162/ 673 035 - Level 2 - PT Slab Top Reinforcement (Zone 1) 22.903 4/11/2017 85685
165 65 Wire Mesh A-252=400 Sheets 4/11/2017 85684
163 674 033 - Columns Reinf. Details (2nd to 3rd Level) - Zone 1 8.176 5/11/2017 85711
166 676 Swimming Pool Wall Vertical 2.724 5/11/2017 85713
164 675 Level 2 Beams Zone 1 0.58 5/11/2017 85712
169 5 Wire Mesh A-252=400 Sheets - mm 6/11/2017 85729
168 677 2nd Floor Slab Spiral Rings Zone 3 1.084 7/11/2017 85761
176 17 Wire Mesh A-393=300 Sheets - mm 7/11/2017 85762
171 54 2nd Floor - Zone 1 Reinforcement 6.025 7/11/2017 85758
167 678 036 - Zone 1-Wall Reinforcement-Core 4 - Level 2 to Level 3 15.541 7/11/2017 85760
170 679 2nd Floor Zone 3 - Corbel Details 3.294 8/11/2017 85780

Page 7 of 20
172/ 100 037 - Zone-3 - 2nd Level PT Slab - Bottom Bars 10.874 8/11/2017 85781
178 131 033 - Columns Reinf. Details (2nd to 3rd Level) Zone-3 14.445 9/11/2017 85799
177/ 123 037 - Zone-3 - 2nd Level PT Slab - Top Bars 15.64 9/11/2017 85790
158 671 2nd Floor Slab Spiral Rings Zone 1 1.084 9/11/2017 85800
174 130 039 - Zone 3-Wall Reinforcement-Core 2 - Level 2 to Level 3 18.465 9/11/2017 85795
179 21 Wire Mesh A-393=300 Sheets 9/11/2017 85792
182 3 Wire Mesh A-252=100 Sheets & A-393=150 Sheets 12/11/2017 85828
181 166 038 - Zone-4 - 2nd Level PT Slab - Bottom Bars (Drop Panels) 0.741 12/11/2017 85829
185 169 038 - Zone-4 - 2nd Level PT Slab - Bottom Bars 0.444 13-11-2017 85862
184 126 038 - Zone-4 - 2nd Level PT Slab - Bottom Bars 10.212 13-11-2017 85861
187 216 038-2nd Floor PT Slab-Top Bars-Zone-4 (Opening Extra Bars) 2.439 14-11-2017 85879
186/ 220 038 - 2nd Floor PT Slab - Top Bars - Zone-4 16.414 14-11-2017 85878
188 224 Zone-2 Corbel Reinf. Details (Level -02) 5.493 14-11-2017 85889
192 255 039 - 2nd Floor PT Slab - Top Bars - Zone-2 9.756 15-11-2017 85901
193 256 039 - 2nd Floor PT Slab - Top Bars - Zone-2 (Chairs & Hooks) 2.623 15-11-2017 85902
189 236 2nd Floor Slab Spiral Rings Zone 4 1.084 16-11-2017 85916
194 257 040 - Zone 2-Wall Reinforcement-Core 1 - Level 2 to Level 3 18.022 16-11-2017 85917
190 260 033 - Columns Reinf. Details (2nd to 3rd Level) Zone-2 11.858 16-11-2017 85930
195 259 038 - Zone-4 - 2nd Level PT Slab - Bottom Bars 5.794 16-11-2017 85929
180 263 033 - Columns Reinf. Details (2nd to 3rd Level) Zone-4 6.971 18-11-2017 85961
196 265 038 - Zone 4-Wall Reinforcement-Core 3 - Level 2 to Level 3 16.51 18-11-2017 85962
197 25 Wire Mesh A-252=400 Sheets 19-11-2017 85978
198 66 040 - 3rd Level - PT Beams Reinforcement - Zone-1 2.085 20-11-2017 85999
199 106 040 - 3rd Level - PT Slab - Bottom Bars (Zone-1) 8.509 20-11-2017 86005
200 149 040 - 3rd Level - PT Slab - Top Bars (Zone-1) 8.597 21-11-2017 86018

Page 8 of 20
203 268 036 - Zone 1-Wall Reinforcement-Core 4 - Level 3 to Level 4 14.613 22-11-2017 86043
204 276 040A - RC Slab @ 3rd Level - Zone-1 1.56 22-11-2017 86044
202 269 033 - Columns Reinf. Details (3rd to 4th Level) - Zone-1 13.004 23-11-2017 86053
206 279 3rd Level PT Slab Spiral Rings Zone 1 0.813 23-11-2017 86058
207 278 041 - 3rd Level PT Beams Reinf. Details - Zone-2 1.168 23-11-2017 86059
205 264 040 - Zone 1-Wall Reinforcement-Core 1 - Level 3 to Level 4 18.177 23-11-2017 86057
208 282 041 - 3rd Level PT Slab - Bottom Bars - Zone-2 6.208 23-11-2017 86060
209 283 041 - 3rd Level PT Slab Top Bars - Zone-2 6.791 26-11-2017 86095
210 286 033 - Columns Reinf. Details (3rd to 4th Level) Zone-2 13.633 26-11-2017 86096
212 128 042 - 3rd Level PT Slab - Bottom Bars - Zone-3 5.25 27-11-2017 86121
211 126 042 - 3rd Level PT Beams Reinf. Details (Zone-3) 1.849 27-11-2017 86120
213 131 3rd Level PT Slab Spiral Rings Zone 2 0.813 29-11-2017 86140
219 33 Wire Mesh A-393=300 Sheets 29-11-2017 86150
214 137 042 - 3rd Level PT Slab Top Bars - Zone-3 6.555 29-11-2017 86141
216 23 040A - RC Slab @ 3rd Level - Zone-3 1.536 29-11-2017 86142
217 291 039 - Zone 3-Wall Reinforcement-Core 2 - Level 3 to Level 4 18.447 1/12/2017 86154
218 292 036 - Zone 3-Wall Reinforcement-Core 3 - Level 3 to Level 4 14.293 2/12/2017 86165
215 293 033 - Columns Reinf. Details (3rd to 4th Level) Zone-3 13.761 2/12/2017 86164
221 401 040 - 4th Level - PT Slab - Bottom Bars (Zone-1) 7.765 4/12/2017 86206
220 400 040 - 4th Level - PT Beams Reinforcement - Zone-1 1.612 4/12/2017 86205
222 402 040 - 4th Level - PT Slab - Top Bars (Zone-1) 8.647 5/12/2017 86224
223 129 033 - Columns Reinf. Details (4th to 5th Level) Zone-1 15.222 5/12/2017 86231
224 138 040 - Zone 1-Wall Reinforcement-Core 1 - Level 4 to Level 5 16.339 7/12/2017 86252
226 150 041 - 4th Level PT Beams Reinf. Details - Zone-2 0.972 7/12/2017 86253

Page 9 of 20
TOTAL WEIGHT IN MT 2255.066

Page 10 of 20
Y SUMMARY (November - December - 2017)

Remarks

Page 11 of 20
Remarks

Page 12 of 20
Page 13 of 20
Page 14 of 20
Page 15 of 20
Page 16 of 20
Page 17 of 20
Page 18 of 20
Page 19 of 20
Page 20 of 20

You might also like