RC-T10-Task 17
12E-C01 Site Preparation for Industrial Waste Management Facility (IWMF)
Activity ID Activity Name Original Start Finish Week
Duration
-2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 4950
12E-C01 Site Preparation for Industrial Waste Management Facility (IWMF) 205 04-Dec-17 16-Sep-18 16-Sep-18, 12E-C01 Site Preparation for Indus

Milestones 205 04-Dec-17 16-Sep-18 16-Sep-18, Milestones

DMS100 Project Start 0 04-Dec-17


Project Start
DMS110 10% Stage Submission 0 30-Jan-18
10% Stage Submission
DMS120 30% Stage Submission 0 18-Apr-18
30% Stage Submission
DMS130 90% Stage Submission 0 17-Jul-18
90% Stage Submission
DMS140 100% Stage Submission 0 16-Aug-18
100% Stage Submission
DMS150 IFB Submission 0 16-Sep-18
IFB Submission
Notice To Proceed (NTP) 4 04-Dec-17 07-Dec-17 07-Dec-17, Notice To Proceed (NTP)

NTP100 NTP, Prepare WBS, EPPR, Staffing Plan, Forecast Expenditure Graph 4 04-Dec-17 07-Dec-17
NTP, Prepare WBS, EPPR, Staffing Plan, Forecast Expenditure Graph
Site Investigation, Data Collection & Reports and Requriements 7 10-Dec-17 18-Dec-17 18-Dec-17, Site Investigation, Data Collection & Reports and Requriements

GEN100 Kick-off Meeting 1 10-Dec-17 10-Dec-17


Kick-off Meeting
GEN110 List of Unknown data/ Unresolved Issues for Discussions 1 10-Dec-17 10-Dec-17
List of Unknown data/ Unresolved Issues for Discussions
GEN120 Project Quality Plan 2 11-Dec-17 12-Dec-17
Project Quality Plan
GEN130 Site Visit and Data collection 1 13-Dec-17 13-Dec-17
Site Visit and Data collection
GEN140 Site Condition Report 2 14-Dec-17 17-Dec-17
Site Condition Report
GEN150 Submit Topographical & Geotechical Survey Requirements 1 18-Dec-17 18-Dec-17
Submit Topographical & Geotechical Survey Requirements
Conceptual Presentation & 10% Stage Submission 32 18-Dec-17 30-Jan-18 30-Jan-18, Conceptual Presentation & 10% Stage Submission

10DD100 Prepare Conceptual Grading Plans 22 18-Dec-17 16-Jan-18


Prepare Conceptual Grading Plans
10DD110 Prepare Conceptual Drainage Plans 18 24-Dec-17 16-Jan-18
Prepare Conceptual Drainage Plans
10DD120 Prepare Initial DBR 18 24-Dec-17 16-Jan-18
Prepare Initial DBR
10DD130 Preliminary Cost Estimate 10 03-Jan-18 16-Jan-18
Preliminary Cost Estimate
10DD140 Conceptual Design Presentation to RC Management 1 17-Jan-18 17-Jan-18
Conceptual Design Presentation to RC Management
10DD150 Design Conceptual Work shop 1 18-Jan-18 18-Jan-18
Design Conceptual Work shop
10DD160 Prepare Final Plan, Drawings, 10% DBR and 10% RFP 5 21-Jan-18 25-Jan-18
Prepare Final Plan, Drawings, 10% DBR and 10% RFP
10DD170 QA/QC Checks 2 28-Jan-18 29-Jan-18
QA/QC Checks
10DD180 Printing and Prepare Package 1 30-Jan-18 30-Jan-18
Printing and Prepare Package
10DD190 Issued for 10% Review 0 30-Jan-18
Issued for 10% Review
10% Design Review & Comments 11 31-Jan-18 14-Feb-18 14-Feb-18, 10% Design Review & Comments

10DR100 Design Review/Design Comments Recieved from RC 10 31-Jan-18 13-Feb-18


Design Review/Design Comments Recieved from RC
10DR110 Incorporate of Comments 5 07-Feb-18 13-Feb-18
Incorporate of Comments
10DR120 Comments Review Meeting 1 14-Feb-18 14-Feb-18
Comments Review Meeting
GIR and Topographical Survey Data, Review and Comments 6 06-Mar-18 13-Mar-18 13-Mar-18, GIR and Topographical Survey Data, Review and Comments

GEN160 Reciept of GIR and Topographical Survey data 1 06-Mar-18 06-Mar-18


Reciept of GIR and Topographical Survey data
GEN170 Review and Comments on factual data 5 07-Mar-18 13-Mar-18
Review and Comments on factual data
30% Stage Submission 45 15-Feb-18 18-Apr-18 18-Apr-18, 30% Stage Submission

30DD100 10% Review Comments Closeout logs 2 15-Feb-18 18-Feb-18


10% Review Comments Closeout logs
30DD110 Prepare Final DBR 35 15-Feb-18 04-Apr-18
Prepare Final DBR

  Actual Work Critical Remaining Work Summary Page 1 of 3 Date Revision Checked Approved
04-Dec-17 Issued for Approval PVS JP
Remaining Work Milestone
DAR PROJECT NO. 1957DF , RC CONTRACT NO. RC-027-T10; 12E-C01
. RC-T10-Task 17
12E-C01 Site Preparation for Industrial Waste Management Facility (IWMF)
Activity ID Activity Name Original Start Finish Week
Duration
-2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 4950
30DD120 Prepare Calculations, GDR/EDR Reports, Risk Assessment Reports 39 20-Feb-18 15-Apr-18
Prepare Calculations, GDR/EDR Reports, Risk Assessment Reports
30DD130 Prepare Design Drawings and Technical Specifications 39 20-Feb-18 15-Apr-18
Prepare Design Drawings and Technical Specifications
30DD140 Quantities and Cost Estimates, RFP Documents 24 13-Mar-18 15-Apr-18
Quantities and Cost Estimates, RFP Documents
30DD150 QA/QC Checks 2 16-Apr-18 17-Apr-18
QA/QC Checks
30DD160 Printing and Prepare Package 1 18-Apr-18 18-Apr-18
Printing and Prepare Package
30DD170 Third Party Submission 0 18-Apr-18
Third Party Submission
30DD180 Issued for 30% Review 0 18-Apr-18
Issued for 30% Review
30% Design Review & Comments 11 19-Apr-18 03-May-18 03-May-18, 30% Design Review & Comments

30DR100 Design Review/Design Comments Recieved from RC 10 19-Apr-18 02-May-18


Design Review/Design Comments Recieved from RC
30DR110 Incorporate of Comments 5 26-Apr-18 02-May-18
Incorporate of Comments
30DR120 Comments Review Meeting 1 03-May-18 03-May-18
Comments Review Meeting
LUP/LAR Request, Value Eng Workshop and Q&C Workshop 27 19-Apr-18 27-May-18 27-May-18, LUP/LAR Request, Value Eng Workshop and Q&C Workshop

GEN180 Submit Borrow Pits LUP/LAR Requests 1 19-Apr-18 19-Apr-18


Submit Borrow Pits LUP/LAR Requests
GEN190 Value Engineering Workshop 1 09-May-18 09-May-18
Value Engineering Workshop
GEN200 Quality and Constructability Workshop 1 10-May-18 10-May-18
Quality and Constructability Workshop
GEN210 Reciept of Borrow pit and others survey reports 1 27-May-18 27-May-18
Reciept of Borrow pit and others survey reports
90% Stage Submission 53 06-May-18 17-Jul-18 17-Jul-18, 90% Stage Submission

90DD100 30% Review Comments, Value Engineering and Q&C Workshop Closeout logs 5 06-May-18 10-May-18
30% Review Comments, Value Engineering and Q&C Workshop Closeout logs
90DD110 Prepare DBR 35 06-May-18 21-Jun-18
Prepare DBR
90DD120 Prepare Calculations, GDR/EDR Reports, Risk Assessment Reports 45 09-May-18 10-Jul-18
Prepare Calculations, GDR/EDR Reports, Risk Assessment Reports
90DD130 Prepare Design Drawings and Technical Specifications 45 09-May-18 10-Jul-18
Prepare Design Drawings and Technical Specifications
90DD140 Quantities and Cost Estimates, RFP Documents 35 23-May-18 10-Jul-18
Quantities and Cost Estimates, RFP Documents
90DD150 QA/QC Checks 4 11-Jul-18 16-Jul-18
QA/QC Checks
90DD160 Printing and Prepare Package 1 17-Jul-18 17-Jul-18
Printing and Prepare Package
90DD170 Third Party Submission 0 17-Jul-18
Third Party Submission
90DD180 Issued for 90% Review 0 17-Jul-18
Issued for 90% Review
90% Design Review & Comments 10 18-Jul-18 31-Jul-18 31-Jul-18, 90% Design Review & Comments

90DR100 Design Review/Design Comments Recieved from RC 10 18-Jul-18 31-Jul-18


Design Review/Design Comments Recieved from RC
90DR110 Incorporate of Comments 5 25-Jul-18 31-Jul-18
Incorporate of Comments
100% Stage Submission 12 01-Aug-18 16-Aug-18 16-Aug-18, 100% Stage Submission

100DD100 90% Review Comments Closeout logs 2 01-Aug-18 02-Aug-18


90% Review Comments Closeout logs
100DD110 Prepare Final DBR 9 01-Aug-18 13-Aug-18
Prepare Final DBR
100DD120 Prepare Final Calculations, GDR/EDR Reports, Risk Assessment Reports 9 01-Aug-18 13-Aug-18
Prepare Final Calculations, GDR/EDR Reports, Risk Assessmen
100DD130 Prepare Final Design Drawings and Technical Specifications 9 01-Aug-18 13-Aug-18
Prepare Final Design Drawings and Technical Specifications
100DD140 Final Quantities and Cost Estimates, Final RFP Documents 9 01-Aug-18 13-Aug-18
Final Quantities and Cost Estimates, Final RFP Documents
100DD150 Third Party Approval 5 01-Aug-18 07-Aug-18
Third Party Approval
100DD160 QA/QC Checks 2 14-Aug-18 15-Aug-18
QA/QC Checks
100DD170 Printing and Prepare Package 1 16-Aug-18 16-Aug-18
Printing and Prepare Package
  Actual Work Critical Remaining Work Summary Page 2 of 3 Date Revision Checked Approved
04-Dec-17 Issued for Approval PVS JP
Remaining Work Milestone
DAR PROJECT NO. 1957DF , RC CONTRACT NO. RC-027-T10; 12E-C01
. RC-T10-Task 17
12E-C01 Site Preparation for Industrial Waste Management Facility (IWMF)
Activity ID Activity Name Original Start Finish Week
Duration
-2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 4950
100DD180 Issued for 100% Review 0 16-Aug-18
Issued for 100% Review
100% Design Review & Comments 10 19-Aug-18 30-Aug-18 30-Aug-18, 100% Design Review & Comments

100DR100 Design Review/Design Comments Recieved from RC 10 19-Aug-18 30-Aug-18


Design Review/Design Comments Recieved from RC
100DR110 Incorporate of Comments 5 26-Aug-18 30-Aug-18
Incorporate of Comments
Issue IFB Package 11 02-Sep-18 16-Sep-18 16-Sep-18, Issue IFB Package

IFB100 Prepare Final Procurement and RFP Package 8 02-Sep-18 11-Sep-18


Prepare Final Procurement and RFP Package
IFB110 Prepare IFB Design Drawings 8 02-Sep-18 11-Sep-18
Prepare IFB Design Drawings
IFB120 Prepare Final Technical Specifications and Geotechnical Reports 8 02-Sep-18 11-Sep-18
Prepare Final Technical Specifications and Geotec
IFB130 Final Quantities and Cost Estimates 8 02-Sep-18 11-Sep-18
Final Quantities and Cost Estimates
IFB140 QA/QC Checks 2 12-Sep-18 13-Sep-18
QA/QC Checks
IFB150 Printing and Prepare Package 1 16-Sep-18 16-Sep-18
Printing and Prepare Package
IFB160 Issued for IFB 0 16-Sep-18
Issued for IFB

  Actual Work Critical Remaining Work Summary Page 3 of 3 Date Revision Checked Approved
04-Dec-17 Issued for Approval PVS JP
Remaining Work Milestone
DAR PROJECT NO. 1957DF , RC CONTRACT NO. RC-027-T10; 12E-C01