RC-T10-Task 17
12E-C01 Site Preparation for Industrial Waste Management Facility (IWMF)
Activity ID Activity Name Original Start Finish Week
Duration
-2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 4950
12E-C01 Site Preparation for Industrial Waste Management Facility (IWMF) 205 04-Dec-17 16-Sep-18 16-Sep-18, 12E-C01 Site Preparation for Indus
NTP100 NTP, Prepare WBS, EPPR, Staffing Plan, Forecast Expenditure Graph 4 04-Dec-17 07-Dec-17
NTP, Prepare WBS, EPPR, Staffing Plan, Forecast Expenditure Graph
Site Investigation, Data Collection & Reports and Requriements 7 10-Dec-17 18-Dec-17 18-Dec-17, Site Investigation, Data Collection & Reports and Requriements
Actual Work Critical Remaining Work Summary Page 1 of 3 Date Revision Checked Approved
04-Dec-17 Issued for Approval PVS JP
Remaining Work Milestone
DAR PROJECT NO. 1957DF , RC CONTRACT NO. RC-027-T10; 12E-C01
. RC-T10-Task 17
12E-C01 Site Preparation for Industrial Waste Management Facility (IWMF)
Activity ID Activity Name Original Start Finish Week
Duration
-2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 4950
30DD120 Prepare Calculations, GDR/EDR Reports, Risk Assessment Reports 39 20-Feb-18 15-Apr-18
Prepare Calculations, GDR/EDR Reports, Risk Assessment Reports
30DD130 Prepare Design Drawings and Technical Specifications 39 20-Feb-18 15-Apr-18
Prepare Design Drawings and Technical Specifications
30DD140 Quantities and Cost Estimates, RFP Documents 24 13-Mar-18 15-Apr-18
Quantities and Cost Estimates, RFP Documents
30DD150 QA/QC Checks 2 16-Apr-18 17-Apr-18
QA/QC Checks
30DD160 Printing and Prepare Package 1 18-Apr-18 18-Apr-18
Printing and Prepare Package
30DD170 Third Party Submission 0 18-Apr-18
Third Party Submission
30DD180 Issued for 30% Review 0 18-Apr-18
Issued for 30% Review
30% Design Review & Comments 11 19-Apr-18 03-May-18 03-May-18, 30% Design Review & Comments
90DD100 30% Review Comments, Value Engineering and Q&C Workshop Closeout logs 5 06-May-18 10-May-18
30% Review Comments, Value Engineering and Q&C Workshop Closeout logs
90DD110 Prepare DBR 35 06-May-18 21-Jun-18
Prepare DBR
90DD120 Prepare Calculations, GDR/EDR Reports, Risk Assessment Reports 45 09-May-18 10-Jul-18
Prepare Calculations, GDR/EDR Reports, Risk Assessment Reports
90DD130 Prepare Design Drawings and Technical Specifications 45 09-May-18 10-Jul-18
Prepare Design Drawings and Technical Specifications
90DD140 Quantities and Cost Estimates, RFP Documents 35 23-May-18 10-Jul-18
Quantities and Cost Estimates, RFP Documents
90DD150 QA/QC Checks 4 11-Jul-18 16-Jul-18
QA/QC Checks
90DD160 Printing and Prepare Package 1 17-Jul-18 17-Jul-18
Printing and Prepare Package
90DD170 Third Party Submission 0 17-Jul-18
Third Party Submission
90DD180 Issued for 90% Review 0 17-Jul-18
Issued for 90% Review
90% Design Review & Comments 10 18-Jul-18 31-Jul-18 31-Jul-18, 90% Design Review & Comments
Actual Work Critical Remaining Work Summary Page 3 of 3 Date Revision Checked Approved
04-Dec-17 Issued for Approval PVS JP
Remaining Work Milestone
DAR PROJECT NO. 1957DF , RC CONTRACT NO. RC-027-T10; 12E-C01