Professional Documents
Culture Documents
Itp For Steel Structure Erection (Content) Rev.1
Itp For Steel Structure Erection (Content) Rev.1
- Material Certificates
GIR, OS&D,
1.1 Receiving Material Check Visual Examination - Material Test Results 100% I H W
MGMER
- Shop inspection reports
No crack, No blowhole, No
1.2 Foundation Check Handover documents Visual Examination exposed reinforcement bars/ 100% I H W LP1-UMA-S-002
Drawing
As per Drawing, LP1-UMA-S-003
1.3 Pad Plate Check AISC 303 Survey I H W
EL: ±2mm Material Certificate
2. Inspection for
Bolt Connection 100%
2.1 Contact Surface Check AISC 348-14 Visual Examination Clean and not rusty I H W LP1-UMA-S-004
2.2.1 Anchor bolts AISC 348-14 Visual Examination Snug tightened condition 100% I H W LP1-UMA-S-005
3. Welding
Inspection (if
required)
- Welding Procedure
AWS D1.1 2015 Review WPS/PQR 100% I R R WPS/PQR
Specification
6 of 27
LONG PHU 1 THERMAL POWER PLANT PROJECT
3.2 Inspection during Welding AWS D1.1 2015 Visual check WPS 100% I S S
(2) Column Base Plate Elevation AISC 303 Survey Approved Drawing 100% I H W LP1-UMA-S-007
(3) Plumbness AISC 303 Survey H/500 but not over 25mm 100% I H W LP1-UMA-S-007
7 of 27
LONG PHU 1 THERMAL POWER PLANT PROJECT
5.2 Number of fastener Approved Drawing Visual Examination As per Drawing 100% I H W LP1-UMA-S-008
6. Final Visual
Check
100%
(W/Touch-up
Painting)
LP1‐TKC‐10XXX‐M‐G1‐S
6.1 Verification of materials Visual examination As per Specification 100% I H W LP1-PA-001
PC‐2022
LP1‐TKC‐10XXX‐M‐
G1‐SPC‐2022 LP1-PA-001
6.3 Total dry film thickness Measuring As per painting specification 100% I H W
SSPC PA2 LP1-PA-002
ISO 12944-5
LP1‐TKC‐10XXX‐M‐G1‐S
Coats of paint shall be uniformly
PC‐2022
6.4 Finished application Visual examination applied without sags, runs, spots, I H W LP1-PA-001
LP1-TKC-10XXX-C-C1-
damage or contamination
DRD-0002
7. Wall and
Roof Cladding 100%
Installation
- Side laps and wall panel fastened
, properly fixed and placed.
Wall claddig installation and -Vendor Documents
7.1 Visual Examination -Closeure/ Flashing/penetation as 100% I H W LP1-UMA-S-009
Inspection - Approval Drawing
per approed drawing. -
Gaps seal properly
8 of 27