Resource Information:
Name Availa Availa Cost/ Idle Firing Hiring Show Firing Hiring Minim Maxim
ble ble Period Cost/ Cost Cost Up Lead Lead um um
Units Units Period Proba Time Time Units Units
in bility
Lead (%)
Time
LV 2 2 400 100 30 30 96 1 1 1 12
HV 2 2 400 100 30 30 96 1 1 1 12
Quality
Task Information:
Requirements:
The PTB Simulation Report
Mode Optimistic Most Likely Pessimistic Fixed Cost Worker LV Needed HV Needed
Name Duration Duration Duration Needed
Subcontrac 10 11 12 0 0 0 0
tor A
The PTB Simulation Report
Mode Optimistic Most Likely Pessimistic Fixed Cost Worker LV Needed HV Needed
Name Duration Duration Duration Needed
Subcontrac 1 3 8 7000 5 0 0
tor A
Subcontrac 3 4 5 5000 3 0 0
tor B
Subcontrac 7 9 17 500 2 0 0
tor C
The PTB Simulation Report
Mode Optimistic Most Likely Pessimistic Fixed Cost Worker LV Needed HV Needed
Name Duration Duration Duration Needed
Subcontrac 1 3 7 5000 5 0 0
tor A
Subcontrac 2 3 4 1200 3 0 0
tor B
Subcontrac 7 9 18 700 1 0 0
tor C
The PTB Simulation Report
Mode Optimistic Most Likely Pessimistic Fixed Cost Worker LV Needed HV Needed
Name Duration Duration Duration Needed
Subcontrac 4 5 6 1000 0 0 3
tor A
Subcontrac 5 7 12 900 0 0 2
tor B
The PTB Simulation Report
Mode Optimistic Most Likely Pessimistic Fixed Cost Worker LV Needed HV Needed
Name Duration Duration Duration Needed
Subcontrac 1 3 5 3500 0 0 3
tor A
Subcontrac 2 4 5 1100 1 0 2
tor B
Subcontrac 3 5 10 800 0 0 2
tor C
The PTB Simulation Report
Mode Optimistic Most Likely Pessimistic Fixed Cost Worker LV Needed HV Needed
Name Duration Duration Duration Needed
Subcontrac 1 3 7 3700 2 0 3
tor A
Subcontrac 2 4 5 1250 1 0 2
tor B
Subcontrac 3 7 14 1000 0 0 2
tor C
The PTB Simulation Report
Mode Optimistic Most Likely Pessimistic Fixed Cost Worker LV Needed HV Needed
Name Duration Duration Duration Needed
Subcontrac 8 9 9 2000 0 0 3
tor A
Subcontrac 7 11 17 1500 0 0 2
tor B
The PTB Simulation Report
Mode Optimistic Most Likely Pessimistic Fixed Cost Worker LV Needed HV Needed
Name Duration Duration Duration Needed
Subcontrac 4 6 8 4000 0 5 0
tor A
Subcontrac 5 7 9 1000 0 3 0
tor B
The PTB Simulation Report
Mode Optimistic Most Likely Pessimistic Fixed Cost Worker LV Needed HV Needed
Name Duration Duration Duration Needed
Subcontrac 1 2 3 5000 1 2 1
tor A
Subcontrac 2 3 4 1200 1 1 1
tor B
The PTB Simulation Report
Mode Optimistic Most Likely Pessimistic Fixed Cost Worker LV Needed HV Needed
Name Duration Duration Duration Needed
Subcontrac 1 2 6 12200 0 3 0
tor A
Subcontrac 3 4 9 6100 0 2 0
tor B
The PTB Simulation Report
Mode Optimistic Most Likely Pessimistic Fixed Cost Worker LV Needed HV Needed
Name Duration Duration Duration Needed
Subcontrac 1 3 4 11000 0 5 0
tor A
Subcontrac 2 4 6 5500 0 3 0
tor B
The PTB Simulation Report
Mode Optimistic Most Likely Pessimistic Fixed Cost Worker LV Needed HV Needed
Name Duration Duration Duration Needed
Subcontrac 1 2 3 4700 1 2 1
tor A
Subcontrac 2 3 4 2300 1 1 1
tor B