Professional Documents
Culture Documents
Mandor Unyil - Harco Glodok
Mandor Unyil - Harco Glodok
Mandor Unyil - Harco Glodok
Expose
Kolom lantai LG
1 As. A / 6' K29 m2 8.78 - 13,500 -
2 As. A / 8 K29 m2 8.78 - 13,500 -
TOTAL 7,505,480.25
Pelaksana :
Jakarta, 26 Desember 2015
Kepala Tukang Costing, Site Manager, Project Manager
C RETENSI 5 % (375,274.01)
G DIBULATKAN 523,000.00
Expose
73 As. 9' / A CR6 0.6 x 1.2 unit 1.00 90 0.90 80,000 72,000
74 As. 9'' / A CR6 0.6 x 1.2 unit 1.00 90 0.90 80,000 72,000
75 As. 10' / B' CR7 0.6 x 1 unit 1.00 90 0.90 80,000 72,000
76 As. 10' / C' CR7 0.6 x 1 unit 1.00 90 0.90 80,000 72,000
77 As. 10 / C' CR8 0.6 x 1.2 unit 1.00 90 0.90 80,000 72,000
78 As. 9' / D CR1 0.7 x 1.2 unit 1.00 90 0.90 80,000 72,000
79 As. 8'' / D' CR2 0.6 x 1.2 unit 1.00 90 0.90 80,000 72,000
80 As. 8' / D' CR2 0.6 x 1.2 unit 1.00 90 0.90 80,000 72,000
81 As. 8' / C CR2 0.6 x 1.2 unit 1.00 90 0.90 80,000 72,000
82 As. 8' / A-B CR5 0.6 x 1.2 unit 1.00 90 0.90 80,000 72,000
TOTAL 3,872,000.00
Pelaksana :
Jakarta, 26 Desember 2015
Kepala Tukang Costing, Site Manager, Project Manager
C RETENSI 5 % (193,600.00)
G DIBULATKAN 212,000.00
Scaffolding
TOTAL 306,300.00
Pelaksana :
Jakarta, 26 Desember 2015
Kepala Tukang Costing, Site Manager, Project Manager
C RETENSI 5 % (15,315.00)
G DIBULATKAN 17,000.00
Scaffolding
TOTAL 117,112.50
Pelaksana :
Jakarta, 26 Desember 2015
Kepala Tukang Costing, Site Manager, Project Manager
C RETENSI 5 % (5,855.63)
G DIBULATKAN 9,000.00
INDIVIDU
HARGA
NO JENIS PEKERJAAN SAT VOL SPK NILAI SPK
SATUAN
SEKARANG
( Rp ) ( Rp )
Grouting
TOTAL 80,000.00
Grouting
TOTAL 80,000.00
Pelaksana :
Jakarta, 8 Agustus 2015
Kepala Tukang Costing, Site Manager, Project Manager
C RETENSI 5 % (4,000.00)
G DIBULATKAN 76,000.00
INDIVIDU
HARGA
NO JENIS PEKERJAAN SAT VOL SPK NILAI SPK
SATUAN
SEKARANG
( Rp ) ( Rp )
Finishing
7 Plester kamprot bekas bobokan dinding RetWall As. 11/G-H ls 1.00 300,000 300,000
2org, 08-16, 2hari
8 - Pasang bongkar scaffolding inc catwalk untuk pekerjaan m2 27.36 6,000 164,160
plester dinding RetWall as. 11/G-H
TOTAL 2,121,080.00
Finishing
7 Plester kamprot bekas bobokan dinding RetWall As. 11/G-H ls 1.00 100 1.00 300,000 300,000
2org, 08-16, 2hari
8 - Pasang bongkar scaffolding inc catwalk untuk pekerjaan m2 27.36 100 27.36 6,000 164,160
plester dinding RetWall as. 11/G-H
TOTAL 2,121,080.00
Pelaksana :
Jakarta, 17 Oktober 2015
Kepala Tukang Costing, Site Manager, Project Manager
C RETENSI 5 % (106,054.00)
G DIBULATKAN 2,015,000.00
INDIVIDU
HARGA
NO JENIS PEKERJAAN SAT VOL SPK NILAI SPK
SATUAN
SEKARANG
( Rp ) ( Rp )
1 Bobok sambungan kolom Ramp Turun Lt. LG karena ngeplin m2 14.05 15,000 210,750
CR3 As. 8/B', CR11 As. 8/C', CR2 As. 8'/C', CR10 As. 8'/D'
As. 8''/C', CR1 As. 9'/C', CR9 As. 9'/D'
2 Plester + Aci Kolom Ramp Turun Lt. LG karena tidak lot, m2 84.30 19,500 1,643,850
CR3 As. 8/B', CR11 As. 8/C', CR2 As. 8'/C', CR10 As. 8'/D'
As. 8''/C', CR1 As. 9'/C', CR9 As. 9'/D'
3 Cipping dan concrete fill kolom Ramp Turun Lt. LG, m2 84.30 5,000 421,500
CR3 As. 8/B', CR11 As. 8/C', CR2 As. 8'/C', CR10 As. 8'/D'
As. 8''/C', CR1 As. 9'/C', CR9 As. 9'/D'
4 Perapihan kropos kepala kolom Ramp Naik Lt. LG, CR5 As. 8'/A-B unit 3.00 45,000 135,000
CR2 As. 8'/B', CR7 As. 8'/B ( 3 kepala kolom )
5 - Plester balok Ramp Naik Lt. LG, G8 As. 9/A, G8 As. 10/C' m2 84.30 11,500 969,450
- Plester kolom GF1, As. 4/D-E, 8/G m2 32.40 11,500 372,600
- Aci kolom GF1, As. 4/D-E, 8/G m2 32.40 10,000 324,000
6 Pembersihan serbuk gergaji area Balok Ramp Naik Lt. LG m2 9.12 5,000 45,600
As. 9/A, 10/C'
7 Cipping + concrete fill, plester kolom Lt. GF1, As. 4/D, 4/E, 8/G m2 35.00 18,500 647,500
8 Bongkar bekisting kepala kolom Lt. GF1, As. 3-5/A-F, 1/D-F unit 13.00 10,000 130,000
9 Bobok kepala kolom Lt. GF1, As. 3-5/A-F, 1/D-F unit 13.00 35,000 455,000
TOTAL 5,355,250.00
1 Bobok sambungan kolom Ramp Turun Lt. LG karena ngeplin m2 14.05 100 14.05 15,000 210,750
CR3 As. 8/B', CR11 As. 8/C', CR2 As. 8'/C', CR10 As. 8'/D'
As. 8''/C', CR1 As. 9'/C', CR9 As. 9'/D'
2 Plester + Aci Kolom Ramp Turun Lt. LG karena tidak lot, m2 84.30 100 84.30 19,500 1,643,850
CR3 As. 8/B', CR11 As. 8/C', CR2 As. 8'/C', CR10 As. 8'/D'
As. 8''/C', CR1 As. 9'/C', CR9 As. 9'/D'
3 Cipping dan concrete fill kolom Ramp Turun Lt. LG, m2 84.30 100 84.30 5,000 421,500
CR3 As. 8/B', CR11 As. 8/C', CR2 As. 8'/C', CR10 As. 8'/D'
As. 8''/C', CR1 As. 9'/C', CR9 As. 9'/D'
4 Perapihan kropos kepala kolom Ramp Naik Lt. LG, CR5 As. 8'/A-B unit 3.00 100 3.00 45,000 135,000
CR2 As. 8'/B', CR7 As. 8'/B ( 3 kepala kolom )
5 - Plester balok Ramp Naik Lt. LG, G8 As. 9/A, G8 As. 10/C' m2 84.30 100 84.30 11,500 969,450
- Plester kolom GF1, As. 4/D-E, 8/G m2 32.40 100 32.40 11,500 372,600
- Aci kolom GF1, As. 4/D-E, 8/G m2 32.40 100 32.40 10,000 324,000
6 Pembersihan serbuk gergaji area Balok Ramp Naik Lt. LG m2 9.12 100 9.12 5,000 45,600
As. 9/A, 10/C'
7 Cipping + concrete fill, plester kolom Lt. GF1, As. 4/D, 4/E, 8/G m2 35.00 100 35.00 18,500 647,500
8 Bongkar bekisting kepala kolom Lt. GF1, As. 3-5/A-F, 1/D-F unit 13.00 100 13.00 10,000 130,000
9 Bobok kepala kolom Lt. GF1, As. 3-5/A-F, 1/D-F unit 13.00 100 13.00 35,000 455,000
TOTAL 5,355,250.00
Pelaksana :
Jakarta, 31 Oktober 2015
Kepala Tukang Costing, Site Manager, Project Manager
C RETENSI 5 % (267,762.50)
G DIBULATKAN 5,087,000.00
Expose
2 As. A
3/A K27 m2 13.82 95 13.13 13,500 177,293
4/A K28 m2 13.82 95 13.13 13,500 177,293
5/A K26 m2 13.82 - 13,500 -
6'/A K28 m2 13.82 - 13,500 -
3 As. C
1/C K27 m2 9.22 95 8.76 13,500 118,195
3/C K14 m2 13.82 95 13.13 13,500 177,293
4/C K15 m2 13.82 95 13.13 13,500 177,293
5/C K26 m2 13.82 95 13.13 13,500 177,293
6/C K26 m2 13.82 - 13,500 -
7'/C K28 m2 13.82 - 13,500 -
4 As. D
1/D K23 m2 9.22 95 8.76 13,500 118,195
3/D K24 m2 13.82 95 13.13 13,500 177,293
4/D K15 m2 13.82 95 13.13 13,500 177,293
5/D K26 m2 13.82 95 13.13 13,500 177,293
6/D K26 m2 13.82 - 13,500 -
7'/D K28 m2 13.82 - 13,500 -
5 As. E
1/E K23 m2 9.22 95 8.76 13,500 118,195
3/E K24 m2 13.82 95 13.13 13,500 177,293
4/E K15 m2 13.82 95 13.13 13,500 177,293
5/E K16 m2 13.82 95 13.13 13,500 177,293
7/E K23 m2 13.82 - 13,500 -
8/E K23 m2 13.82 - 13,500 -
9/E K23 m2 13.82 - 13,500 -
6 As. E'
10/E' KB3 m2 19.49 - 13,500 -
11/E' KB3 m2 19.49 - 13,500 -
12/E' K16 m2 19.49 - 13,500 -
7 As. F
1/F K19 m2 11.66 - 13,500 -
3/F K20 m2 13.82 - 13,500 -
4/F K21 m2 13.82 95 13.13 13,500 177,293
5/F K22 m2 13.82 95 13.13 13,500 177,293
7/F K23 m2 13.82 95 13.13 13,500 177,293
8/F K23 m2 13.82 95 13.13 13,500 177,293
9/F K22 m2 13.82 95 13.13 13,500 177,293
10/F KB3 m2 19.49 - 13,500 -
11/F KB3 m2 19.49 - 13,500 -
13/F K16 m2 19.49 - 13,500 -
PT. MULTIBANGUN ADHITAMA KONSTRUKSI
PROYEK HARCO GLODOK
JAKARTA
10 As. I
1/I K6 m2 11.66 90 10.50 13,500 141,718
13/I K6 m2 17.50 90 15.75 13,500 212,576
11 As. J
2/J K1 m2 17.50 - 13,500 -
3/J K1 m2 17.50 - 13,500 -
4/J K2 m2 17.50 95 16.62 13,500 224,386
5/J K3 m2 17.50 95 16.62 13,500 224,386
7/J K2 m2 17.50 95 16.62 13,500 224,386
8/ K4 m2 17.50 95 16.62 13,500 224,386
9/J K5 m2 17.50 - 13,500 -
10/J K5 m2 17.50 - 13,500 -
11/J K6 m2 17.50 - 13,500 -
12/J K6 m2 17.50 - 13,500 -
TOTAL 5,790,009.60
Pelaksana :
Jakarta, 26 Desember 2015
Kepala Tukang Costing, Site Manager, Project Manager
C RETENSI 5 % (289,500.48)
G DIBULATKAN 277,000.00
Expose
2 As. A
2/A K27 unit 1.00 - 80,000 -
3/A K27 unit 1.00 95 0.95 80,000 76,000
4/A K28 unit 1.00 95 0.95 80,000 76,000
5/A K26 unit 1.00 80 0.80 80,000 64,000
6'/A K28 unit 1.00 80 0.80 80,000 64,000
3 As. B
1/B K27 unit 1.00 - 80,000 -
4 As. C
1/C K27 unit 1.00 95 0.95 80,000 76,000
3/C K14 unit 1.00 95 0.95 80,000 76,000
4/C K15 unit 1.00 95 0.95 80,000 76,000
5/C K26 unit 1.00 95 0.95 80,000 76,000
6/C K26 unit 1.00 80 0.80 80,000 64,000
7'/C K28 unit 1.00 80 0.80 80,000 64,000
5 As. D
1/D K23 unit 1.00 95 0.95 80,000 76,000
3/D K24 unit 1.00 95 0.95 80,000 76,000
4/D K15 unit 1.00 95 0.95 80,000 76,000
5/D K26 unit 1.00 95 0.95 80,000 76,000
6/D K26 unit 1.00 - 80,000 -
7'/D K28 unit 1.00 - 80,000 -
6 As. E
1/E K23 unit 1.00 95 0.95 80,000 76,000
3/E K24 unit 1.00 95 0.95 80,000 76,000
4/E K15 unit 1.00 95 0.95 80,000 76,000
5/E K16 unit 1.00 95 0.95 80,000 76,000
7/E K23 unit 1.00 - 80,000 -
8/E K23 unit 1.00 - 80,000 -
9/E K23 unit 1.00 - 80,000 -
7 As. E'
10/E' KB3 unit 1.00 - 80,000 -
11/E' KB3 unit 1.00 - 80,000 -
12/E' K16 unit 1.00 - 80,000 -
8 As. F
1/F K19 unit 1.00 95 0.95 80,000 76,000
3/F K20 unit 1.00 95 0.95 80,000 76,000
4/F K21 unit 1.00 95 0.95 80,000 76,000
5/F K22 unit 1.00 95 0.95 80,000 76,000
7/F K23 unit 1.00 95 0.95 80,000 76,000
8/F K23 unit 1.00 - 80,000 -
9/F K22 unit 1.00 - 80,000 -
10/F KB3 unit 1.00 - 80,000 -
11/F KB3 unit 1.00 - 80,000 -
13/F K16 unit 1.00 - 80,000 -
PT. MULTIBANGUN ADHITAMA KONSTRUKSI
PROYEK HARCO GLODOK
JAKARTA
10 As. H
1/H KB3 unit 1.00 - 80,000 -
1/H KB3 unit 1.00 - 80,000 -
3/H K7 unit 1.00 - 80,000 -
4/H K8 unit 1.00 95 0.95 80,000 76,000
5/H K8 unit 1.00 95 0.95 80,000 76,000
7/H K9 unit 1.00 95 0.95 80,000 76,000
8/H K18 unit 1.00 - 80,000 -
9/H K11 unit 1.00 - 80,000 -
10/H K11 unit 1.00 - 80,000 -
11/H K10 unit 1.00 - 80,000 -
13/H K12 unit 1.00 - 80,000 -
11 As. I
1/I K6 unit 1.00 50 0.50 80,000 40,000
13/I K6 unit 1.00 - 80,000 -
12 As. J
2/J K1 unit 1.00 - 80,000 -
3/J K1 unit 1.00 75 0.75 80,000 60,000
4/J K2 unit 1.00 95 0.95 80,000 76,000
5/J K3 unit 1.00 95 0.95 80,000 76,000
7/J K2 unit 1.00 95 0.95 80,000 76,000
8/ K4 unit 1.00 95 0.95 80,000 76,000
9/J K5 unit 1.00 - 80,000 -
10/J K5 unit 1.00 - 80,000 -
11/J K6 unit 1.00 - 80,000 -
12/J K6 unit 1.00 - 80,000 -
TOTAL 2,636,000.00
Pelaksana :
Jakarta, 26 Desember 2015
Kepala Tukang Costing, Site Manager, Project Manager
C RETENSI 5 % (131,800.00)
G DIBULATKAN 254,000.00
INDIVIDU
HARGA
NO JENIS PEKERJAAN SAT VOL SPK NILAI SPK
SATUAN
SEKARANG
( Rp ) ( Rp )
Schaffolding
TOTAL 54,000.00
Schaffolding
TOTAL 42,600.00
Pelaksana :
Jakarta, 26 Desember 2015
Kepala Tukang Costing, Site Manager, Project Manager
C RETENSI 5 % (2,130.00)
G DIBULATKAN 20,000.00
INDIVIDU
HARGA
NO JENIS PEKERJAAN SAT VOL SPK NILAI SPK
SATUAN
SEKARANG
( Rp ) ( Rp )
Finishing
TOTAL 368,000.00
Finishing
TOTAL 368,000.00
Pelaksana :
Jakarta, 17 Oktober 2015
Kepala Tukang Costing, Site Manager, Project Manager
C RETENSI 5 % (18,400.00)
G DIBULATKAN 349,000.00
INDIVIDU
HARGA
NO JENIS PEKERJAAN SAT VOL SPK NILAI SPK
SATUAN
SEKARANG
( Rp ) ( Rp )
Finishing
TOTAL 138,000.00
Finishing
TOTAL 138,000.00
Pelaksana :
Jakarta, 17 Oktober 2015
Kepala Tukang Costing, Site Manager, Project Manager
C RETENSI 5 % (6,900.00)
G DIBULATKAN 131,000.00
INDIVIDU
HARGA
NO JENIS PEKERJAAN SAT VOL SPK NILAI SPK
SATUAN
SEKARANG
( Rp ) ( Rp )
Bobokan
1 - Bobok kolom yang bunting karena bekisting jebol. As. 5/H hp 1.00 75,000 75,000
As. 7/F, 1 org, 08-16
( Potong Mandor Maskuri )
2 - Bobok dan plester kepala kolom ( 6 kolom ) As. 5/A-G hp 12.00 75,000 900,000
2org ( 1kolom ),
TOTAL 975,000.00
Bobokan
1 - Bobok kolom yang bunting karena bekisting jebol. As. 5/H hp 1.00 100 1.00 75,000 75,000
As. 7/F, 1 org, 08-16
( Potong Mandor Maskuri )
2 - Bobok dan plester kepala kolom ( 6 kolom ) As. 5/A-G hp 12.00 100 12.00 75,000 900,000
2org ( 1kolom ),
TOTAL 975,000.00
Pelaksana :
Jakarta, 17 Oktober 2015
Kepala Tukang Costing, Site Manager, Project Manager
C RETENSI 5 % (48,750.00)
G DIBULATKAN 926,000.00
INDIVIDU
HARGA
NO JENIS PEKERJAAN SAT VOL SPK NILAI SPK
SATUAN
SEKARANG
( Rp ) ( Rp )
Finishing
2 - Grouting Kolom Ramp Turun Lt. LG lubang tierot titik 56.00 2,000 112,000
CR3 As. 8/B', CR11 As. 8/C', CR2 As. 8'/C', CR10 As. 8'/D'
As. 8''/C', CR1 As. 9'/C', CR9 As. 9'/D'
- Grouting balok ramp turun Lt. LG As. 8-9'/C'-D' titik 120.00 2,000 240,000
TOTAL 352,000.00
Finishing
2 - Grouting Kolom Ramp Turun Lt. LG lubang tierot titik 56.00 100 56.00 2,000 112,000
CR3 As. 8/B', CR11 As. 8/C', CR2 As. 8'/C', CR10 As. 8'/D'
As. 8''/C', CR1 As. 9'/C', CR9 As. 9'/D'
- Grouting balok ramp turun Lt. LG As. 8-9'/C'-D' titik 120.00 100 120.00 2,000 240,000
TOTAL 352,000.00
Pelaksana :
Jakarta, 31 Oktober 2015
Kepala Tukang Costing, Site Manager, Project Manager
C RETENSI 5 % (17,600.00)
G DIBULATKAN 334,000.00
INDIVIDU
HARGA
NO JENIS PEKERJAAN SAT VOL SPK NILAI SPK
SATUAN
SEKARANG
( Rp ) ( Rp )
1 Balok Melintang
1 ( 8'/A ) El. -9000 m2 8.13 13,500 109,783
2 ( 8''/A ) El. -8691 m2 8.42 13,500 113,697
3 ( 9'/A' ) El. -8366 m2 8.15 13,500 109,984
4 ( 10/A ) El. -7778 m2 8.14 13,500 109,850
5 ( 10'/A ) El. -7386 m2 8.38 13,500 113,115
6 ( 10'/B ) El. -6944 m2 8.13 13,500 109,805
7 ( 10'/B' ) El. -6533 m2 8.37 13,500 112,981
8 ( 10'/C' ) El. -6101 m2 8.13 13,500 109,783
9 ( 10'/B'' ) El. -5889 m2 8.36 13,500 112,914
10 ( 10'/B''' ) El. -5426 m2 5.82 13,500 78,629
11 ( 9''/D ) El. -4903 m2 8.05 13,500 108,665
12 ( 9'/D ) El. -4380 m2 8.54 13,500 115,352
13 ( 8'/D ) El. -3858 m2 8.04 13,500 108,598
14 ( 8/D ) El. -3465 m2 8.55 13,500 115,396
15 ( 8/C' ) El. -3073 m2 8.13 13,500 109,716
16 ( 8/B' ) El. -2530 m2 8.21 13,500 110,901
17 ( 8/A ) El. -2004 m2 8.63 13,500 116,515
18 ( 8'/A ) El. -1750 m2 5.65 13,500 76,313
19 ( 8''/A ) El. -1750 m2 8.55 13,500 115,396
3 Balok Tengah
Ramp Naik LG - GF2 m2 83.84 13,500 1,131,849
TOTAL 8,774,438.65
INDIVIDU
HARGA
NO JENIS PEKERJAAN SAT VOL SPK NILAI SPK
SATUAN
SEKARANG
( Rp ) ( Rp )
UNYIL WELLY KURNIAWAN
Kepala Tukang Project Manager
PT. MULTIBANGUN ADHITAMA KONSTRUKSI
PROYEK HARCO GLODOK
JAKARTA
1 Balok Melintang
1 ( 8'/A ) El. -9000 m2 8.13 - 13,500 -
2 ( 8''/A ) El. -8691 m2 8.42 - 13,500 -
3 ( 9'/A' ) El. -8366 m2 8.15 - 13,500 -
4 ( 10/A ) El. -7778 m2 8.14 - 13,500 -
5 ( 10'/A ) El. -7386 m2 8.38 - 13,500 -
6 ( 10'/B ) El. -6944 m2 8.13 - 13,500 -
7 ( 10'/B' ) El. -6533 m2 8.37 - 13,500 -
8 ( 10'/C' ) El. -6101 m2 8.13 - 13,500 -
9 ( 10'/B'' ) El. -5889 m2 8.36 - 13,500 -
10 ( 10'/B''' ) El. -5426 m2 5.82 - 13,500 -
11 ( 9''/D ) El. -4903 m2 8.05 - 13,500 -
12 ( 9'/D ) El. -4380 m2 8.54 - 13,500 -
13 ( 8'/D ) El. -3858 m2 8.04 - 13,500 -
14 ( 8/D ) El. -3465 m2 8.55 - 13,500 -
15 ( 8/C' ) El. -3073 m2 8.13 - 13,500 -
16 ( 8/B' ) El. -2530 m2 8.21 - 13,500 -
17 ( 8/A ) El. -2004 m2 8.63 - 13,500 -
18 ( 8'/A ) El. -1750 m2 5.65 - 13,500 -
19 ( 8''/A ) El. -1750 m2 8.55 - 13,500 -
3 Balok Tengah
Ramp Naik LG - GF2 m2 83.84 10 8.38 13,500 113,185
TOTAL 420,079.82
Pelaksana :
Jakarta, 28 November 2015
Kepala Tukang Costing, Site Manager, Project Manager
PT. MULTIBANGUN ADHITAMA KONSTRUKSI
PROYEK HARCO GLODOK
JAKARTA
C RETENSI 5 % (21,003.99)
G DIBULATKAN -
TERBILANG Rupiah
1 Balok Melintang
1 ( 10/D ) El. -1750 m2 5.84 - 13,500 -
2 ( 10'/C' ) El. -1945 m2 5.65 80 4.52 13,500 61,000
3 ( 10'/B' ) El. -2341 m2 8.55 80 6.84 13,500 92,317
4 ( 10'/B ) El. -2773 m2 5.65 80 4.52 13,500 60,975
5 ( 10'/A ) El. -3141 m2 8.55 80 6.84 13,500 92,317
6 ( 10'/A'-A) El. -3509 m2 5.65 80 4.52 13,500 61,050
7 ( 9'/A'-A ) El. -4061 m2 5.65 80 4.52 13,500 61,000
8 ( 8'/A-A ) El. -4523 m2 8.55 80 6.84 13,500 92,317
9 ( 8'/A ) El. -4986 m2 5.65 80 4.52 13,500 61,050
10 ( 8/A-B ) El. -5461 m2 8.55 80 6.84 13,500 92,317
11 ( 8/B' ) El. -5950 m2 5.65 80 4.52 13,500 61,050
12 ( 8/C' ) El. -6592 m2 5.66 80 4.53 13,500 61,100
13 ( 8'/D ) El. -7051 m2 8.53 80 6.83 13,500 92,156
14 ( 8"'/D ) El. -7510 m2 5.60 80 4.48 13,500 60,453
15 ( 9'/D ) El. -8000 m2 8.54 80 6.84 13,500 92,281
16 ( 9''/D ) El. -8000 m2 5.60 80 4.48 13,500 60,428
3 Balok Tengah ( R )
Ramp Turun LG - GF2 m2 76.66 80 61.33 16,500 1,011,970
TOTAL 7,487,789.89
Pelaksana :
Jakarta, 26 Desember 2015
Kepala Tukang Costing, Site Manager, Project Manager
PT. MULTIBANGUN ADHITAMA KONSTRUKSI
PROYEK HARCO GLODOK
JAKARTA
C RETENSI 5 % (374,389.49)
G DIBULATKAN -
TERBILANG Rupiah
Finishing
TOTAL 258,400.00
Pelaksana :
Jakarta, 26 Desember 2015
Kepala Tukang Costing, Site Manager, Project Manager
C RETENSI 5 % (12,920.00)
G DIBULATKAN 12,000.00
INDIVIDU
HARGA
NO JENIS PEKERJAAN SAT VOL SPK NILAI SPK
SATUAN
SEKARANG
( Rp ) ( Rp )
1 - Ciping + concrete fill kolom ramp, CR2 as. 8'/B', CR5 as. 8'/A-B m2 78.30 5,000 391,500
CR6 as. 9'/A, dari elvasi ramp turun - ramp naik,
- Plester + Aci kolom ramp, CR2 as. 8'/B', CR5 as. 8'/A-B m2 78.30 19,500 1,526,850
CR6 as. 9'/A, dari elvasi ramp turun - ramp naik,
- Pasang bongkar scaffolding pada area kolom ramp m2 24.30 6,000 145,800
2 - Concrete fill kolom K28 As. 4/A, Lt. GF2, m2 13.76 2,500 34,400
- Plester + Aci kolom K28 As. 4/A, Lt. GF2, m2 13.76 19,500 268,320
3 - Bobok kepala kolom karena ngplin, Lt. GF1, As. 3-5/G, 3/H, 5-7/H m2 28.80 7,500 216,000
4-7/J,
4 - Bongkar bekisting stopcor bondek pada kepala kolom Lt. GF1 titik 13.00 10,000 130,000
As. 4-7/F-J, 7/E
5 - Bobok ex cor pada kaki kolom Lt. GF1, As. 3-5/C, 4/D, 1-3/E, titik 11.00 25,000 275,000
5/E, 3-4/F, 5/G-H
6 - Bobok sisi kepala kolom karena ngplin, area ramp turun titik 4.00 112,500 450,000
CR2 As. 8'/C', CR2 As. 8'/B', CR5 As. 8'/A-B, CR6 As. 9'/A
2org, 3 hari
TOTAL 3,437,870.00
1 - Ciping + concrete fill kolom ramp, CR2 as. 8'/B', CR5 as. 8'/A-B m2 78.30 100 78.30 5,000 391,500
CR6 as. 9'/A, dari elvasi ramp turun - ramp naik,
- Plester + Aci kolom ramp, CR2 as. 8'/B', CR5 as. 8'/A-B m2 78.30 100 78.30 19,500 1,526,850
CR6 as. 9'/A, dari elvasi ramp turun - ramp naik,
- Pasang bongkar scaffolding pada area kolom ramp m2 24.30 100 24.30 6,000 145,800
2 - Concrete fill kolom K28 As. 4/A, Lt. GF2, m2 13.76 100 13.76 2,500 34,400
- Plester + Aci kolom K28 As. 4/A, Lt. GF2, m2 13.76 100 13.76 19,500 268,320
3 - Bobok kepala kolom karena ngplin, Lt. GF1, As. 3-5/G, 3/H, 5-7/H m2 28.80 90 25.92 7,500 194,400
4-7/J,
4 - Bongkar bekisting stopcor bondek pada kepala kolom Lt. GF1 titik 13.00 100 13.00 10,000 130,000
As. 4-7/F-J, 7/E
5 - Bobok ex cor pada kaki kolom Lt. GF1, As. 3-5/C, 4/D, 1-3/E, titik 11.00 100 11.00 25,000 275,000
5/E, 3-4/F, 5/G-H
6 - Bobok sisi kepala kolom karena ngplin, area ramp turun titik 4.00 100 4.00 112,500 450,000
CR2 As. 8'/C', CR2 As. 8'/B', CR5 As. 8'/A-B, CR6 As. 9'/A
2org, 3 hari
TOTAL 3,416,270.00
Pelaksana :
Jakarta, 14 November 2015
Kepala Tukang Costing, Site Manager, Project Manager
C RETENSI 5 % (170,813.50)
G DIBULATKAN 3,245,000.00
TERBILANG Tiga Juta Dua Ratus Empat Puluh Lima Ribu Rupiah
TOTAL 2,366,863.75
Pelaksana :
Jakarta, 12 Desember 2015
Kepala Tukang Costing, Site Manager, Project Manager
C RETENSI 5 % (118,343.19)
G DIBULATKAN -
TERBILANG Rupiah
Finishing
2 - Concrete fill kepala kolom Lt. GF1, As. 1/I, 2/J m2 17.28 95 16.42 2,500 41,040
- Plester Aci kepala kolom Lt. GF1, As. 1/I, 2/J m2 17.28 95 16.42 19,500 320,112
TOTAL 6,502,370.24
Pelaksana :
Jakarta, 26 Desember 2015
Kepala Tukang Costing, Site Manager, Project Manager
C RETENSI 5 % (325,118.51)
G DIBULATKAN 1,969,000.00
TERBILANG Satu Juta Sembilan Ratus Enam Puluh Sembilan Ribu Rupiah
INDIVIDU
HARGA
NO JENIS PEKERJAAN SAT VOL SPK NILAI SPK
SATUAN
SEKARANG
( Rp ) ( Rp )
Bongkar Material
2 Plester dan perekat bata ringan, SJ D1656958, tgl 2-11-2015 zak 190.00 1,000 190,000
3 Bata Ringan uk. 10 dan 7,5, BPB 890, tgl 2-11-2015, jam 02 bh 1,320.00 150 198,000
4 Bata Ringan uk. 10 dan 7,5, BPB 888, tgl 3-11-2015, jam 03.20 bh 990.00 150 148,500
5 Bata Ringan uk. 10 dan 7,5, BPB 887, tgl 3-11-2015, jam 03.25 bh 990.00 150 148,500
6 Bata Ringan uk. 10 dan 7,5, BPB 889, tgl 3-11-2015, jam 03.20 bh 990.00 150 148,500
7 Tambah bongkar Bata Ringan BPB 887, 888, 889 ls 1.00 200,000 200,000
TOTAL 1,233,500.00
Bongkar Material
1 Semen Gresik, SJ SI-1521333, tgl 6-11-2015 zak 200.00 100 200.00 1,000 200,000
2 Plester dan perekat bata ringan, SJ D1656958, tgl 2-11-2015 zak 190.00 100 190.00 1,000 190,000
3 Bata Ringan uk. 10 dan 7,5, BPB 890, tgl 2-11-2015, jam 02 bh 1,320.00 100 1,320.00 150 198,000
4 Bata Ringan uk. 10 dan 7,5, BPB 888, tgl 3-11-2015, jam 03.20 bh 990.00 100 990.00 150 148,500
5 Bata Ringan uk. 10 dan 7,5, BPB 887, tgl 3-11-2015, jam 03.25 bh 990.00 100 990.00 150 148,500
6 Bata Ringan uk. 10 dan 7,5, BPB 889, tgl 3-11-2015, jam 03.20 bh 990.00 100 990.00 150 148,500
7 Tambah bongkar Bata Ringan BPB 887, 888, 889 ls 1.00 100 1.00 200,000 200,000
TOTAL 1,233,500.00
Pelaksana :
Jakarta, 14 November 2015
Kepala Tukang Costing, Site Manager, Project Manager
C RETENSI 5 % (61,675.00)
G DIBULATKAN 1,171,000.00
5 - Sloof pada area basah Lt. LG ( R.Wudhu - ToiletPublic ) m' 26.72 95 25.38 30,000 761,520
Uk. 25x10 cm
6 - Bor stek celcon dinding area musolla lt. LG, As. 2-4/J-J' titik 21.00 100 21.00 1,000 21,000
- Las stek kolom praktis pada balok baja lt. LG, As. 4/J-J' titik 4.00 100 4.00 2,000 8,000
TOTAL 6,971,154.30
Pelaksana :
Jakarta, 26 Desember 2015
Kepala Tukang Costing, Site Manager, Project Manager
C RETENSI 5 % (348,557.72)
G DIBULATKAN -
TERBILANG Rupiah
6 - Bor stek celcon dinding Kios GF1 as 4-7/G-J ttk 217.00 85 184.45 1,000 184,450
- Las stek kolom praktis pada balok baja Kios GF1 as 4-7/G-J ttk 256.00 85 217.60 2,000 435,200
9 - Expose Gutter melintang pada Ramp Turun (GF2) el. -1.750 m' 9.80 90 8.82 15,000 132,300
TOTAL 23,662,327.96
Pelaksana :
Jakarta, 26 Desember 2015
Kepala Tukang Costing, Site Manager, Project Manager
C RETENSI 5 % (1,183,116.40)
G DIBULATKAN -
TERBILANG Rupiah
INDIVIDU
HARGA
NO JENIS PEKERJAAN SAT VOL SPK NILAI SPK
SATUAN
SEKARANG
( Rp ) ( Rp )
Bongkar Material
1 Bata Ringan uk. 10 dan 7,5, BPB 940, tgl 24-11-2015, jam 22.00 bh 990.00 150 148,500
2 Bata Ringan uk. 10 dan 7,5, BPB 937, tgl 24-11-2015, jam 22.00 bh 990.00 150 148,500
3 Bata Ringan uk. 10 dan 7,5, BPB 932, tgl 23-11-2015, jam 21.50 bh 990.00 150 148,500
4 Acian Plester & perekat celcon, BPB 927, tgl 20-11-2015 zak 150.00 1,000 150,000
TOTAL 595,500.00
Bongkar Material
1 Bata Ringan uk. 10 dan 7,5, BPB 940, tgl 24-11-2015, jam 22.00 bh 990.00 100 990.00 150 148,500
2 Bata Ringan uk. 10 dan 7,5, BPB 937, tgl 24-11-2015, jam 22.00 bh 990.00 100 990.00 150 148,500
3 Bata Ringan uk. 10 dan 7,5, BPB 932, tgl 23-11-2015, jam 21.50 bh 990.00 100 990.00 150 148,500
4 Acian Plester & perekat celcon, BPB 927, tgl 20-11-2015 zak 150.00 100 150.00 1,000 150,000
TOTAL 595,500.00
Pelaksana :
Jakarta, 28 November 2015
Kepala Tukang Costing, Site Manager, Project Manager
C RETENSI 5 % (29,775.00)
G DIBULATKAN 565,000.00
INDIVIDU
HARGA
NO JENIS PEKERJAAN SAT VOL SPK NILAI SPK
SATUAN
SEKARANG
( Rp ) ( Rp )
5 - Bor stek celcon dinding Kios GF1 as 8-10/G-J ttk 24.00 1,000 24,000
8 - Las stek kolom praktis ketemu bondek dan baja titik 88.00 2,000 176,000
TOTAL 28,654,332.60
5 - Bor stek celcon dinding Kios GF1 as 8-10/G-J ttk 24.00 25 6.00 1,000 6,000
8 - Las stek kolom praktis ketemu bondek dan baja titik 88.00 25 22.00 2,000 44,000
TOTAL 1,823,496.80
Pelaksana :
Jakarta, 12 Desember 2015
Kepala Tukang Costing, Site Manager, Project Manager
C RETENSI 5 % (91,174.84)
G DIBULATKAN 1,732,000.00
TERBILANG Satu Juta Tujuh Ratus Tiga Puluh Dua Ribu Rupiah
5 - Bor stek celcon dinding Lobby Escalator, LG. As. 3'/G-H ttk 16.00 50 8.00 1,000 8,000
8 - Las stek kolom praktis ketemu bondek dan baja titik 28.00 50 14.00 2,000 28,000
TOTAL 1,335,384.24
Pelaksana :
Jakarta, 26 Desember 2015
Kepala Tukang Costing, Site Manager, Project Manager
C RETENSI 5 % (66,769.21)
G DIBULATKAN 770,000.00
sember 2015
UNYIL PRAMA WELLY KURNIAWAN
Kepala Tukang Costing Project Manager
PT. MULTIBANGUN ADHITAMA KONSTRUKSI
PROYEK HARCO GLODOK
JAKARTA
3 - Pasang bongkar scaffolding untuk pek expose plat musolla m2 71.68 100 71.68 6,000 430,056
dan parkir lantai LG, As. 1-2/H'-J'
2 - Plester Aci, Kolom LG. As. 1/H m2 13.22 80 10.58 19,500 206,271
- Plester Aci, Kolom LG. As. 1/H' m2 12.26 80 9.80 19,500 191,178
- Plester Aci, Kolom LG. As. 1/I m2 11.61 95 11.03 19,500 215,075
- Plester Aci, Kolom LG. As. 2/J m2 11.61 95 11.03 19,500 215,075
- Plester Aci, Kolom LG. As. 3/J m2 11.61 95 11.03 19,500 215,075
3 - Plester Aci, pertemuan sudut RetWall LG. As. 1'/A' m2 4.30 100 4.30 19,500 83,850
- Plester Aci, pertemuan sudut RetWall LG. As. 0/A m2 4.30 100 4.30 19,500 83,850
- Plester Aci, pertemuan sudut RetWall LG. As. 0/B m2 4.30 100 4.30 19,500 83,850
- Plester Aci, pertemuan sudut RetWall LG. As. 5'/A' m2 4.30 100 4.30 19,500 83,850
- Plester Aci, pertemuan sudut Mushola LG. As. 4/J' m2 4.30 100 4.30 19,500 83,850
4 - ConcreteFill Dinding RetWall ( pertemuaan ex bekisting dan m2 81.15 95 77.09 2,500 192,732
pertemuan dinding dan plat ), As. 0/H'-J', 0-4/J'
- Plester+Aci Dinding RetWall ( pertemuaan ex bekisting dan m2 81.15 95 77.09 19,500 1,503,313
pertemuan dinding dan plat ), As. 0/H'-J', 0-4/J'
5 - ConcreteFill Dinding RetWall ( pertemuaan ex bekisting dan m2 27.84 95 26.45 2,500 66,126
pertemuan dinding dan plat ), As. 2-3/A', 4-5/A'
- Plester+Aci Dinding RetWall ( pertemuaan ex bekisting dan m2 27.84 95 26.45 19,500 515,782
pertemuan dinding dan plat ), As. 2-3/A', 4-5/A'
6 - Concrete fill balok luar sisi dalam Ramp Turun As. 9'/D-10'/C m2 21.83 90 19.65 2,500 49,122
- Plester+ Aci balok luar sisi dalam Ramp Turun As. 9'/D-10'/C m2 21.83 90 19.65 19,500 383,152
7 - Concrete fill balok tengah Ramp Turun As. 9/A - 10/D m2 53.98 90 48.58 2,500 121,453
- Plester + Aci balok tengah Ramp Turun As. 9/A - 10/D m2 53.98 90 48.58 19,500 947,331
8 - Grouting lubang ex tierod pada balok tengah Ramp Turun titik 410.00 95 389.50 2,000 779,000
As. 9/A - 10/D
9 - Ciping + ConcreteFill Kolom (luar) Ramp Turun, m2 51.45 95 48.88 5,000 244,388
CR4,CR12,CR13,CR14,CR4,CR9,CR10
- Ciping + ConcreteFill Kolom (luar) Ramp Turun, m2 51.45 95 48.88 19,500 953,111
CR4,CR12,CR13,CR14,CR4,CR9,CR10
TOTAL 9,100,963.93
Pelaksana :
Jakarta, 26 Desember 2015
Kepala Tukang Costing, Site Manager, Project Manager
C RETENSI 5 % (455,048.20)
G DIBULATKAN 135,000.00
INDIVIDU
HARGA
NO JENIS PEKERJAAN SAT VOL SPK NILAI SPK
SATUAN
SEKARANG
( Rp ) ( Rp )
Bongkat Material
1 - Bata Ringan ( uk. 10cm ), tgl 11-12-2015, SJ SJ/SLI/1512009 bh 1,050.00 150 157,500
2 - Bata Ringan ( uk. 10cm ), tgl 14-12-2015, SJ SJ/SLI/1512016 bh 1,050.00 150 157,500
3 - Bata Ringan ( uk. 10cm ), tgl 11-12-2015, SJ SJ/SLI/1512010 bh 1,050.00 150 157,500
4 - Bata Ringan ( uk. 10cm ), tgl 14-12-2015, SJ SJ/SLI/1512015 bh 1,050.00 150 157,500
5 - MU 830, 40 kg, tgl 5-12-2015, No. 990 zak 70.00 1,000 70,000
6 - Semen Gresik, 40 kg, tgl 5-12-2015, No. 994 zak 200.00 1,000 200,000
7 - Aka Mortar 300, 40 kg, tgl 8-12-2015, No. 999 zak 250.00 1,000 250,000
TOTAL 1,150,000.00
1 - Bata Ringan ( uk. 10cm ), tgl 11-12-2015, SJ SJ/SLI/1512009 bh 1,050.00 100 1,050.00 150 157,500
2 - Bata Ringan ( uk. 10cm ), tgl 14-12-2015, SJ SJ/SLI/1512016 bh 1,050.00 100 1,050.00 150 157,500
3 - Bata Ringan ( uk. 10cm ), tgl 11-12-2015, SJ SJ/SLI/1512010 bh 1,050.00 100 1,050.00 150 157,500
4 - Bata Ringan ( uk. 10cm ), tgl 14-12-2015, SJ SJ/SLI/1512015 bh 1,050.00 100 1,050.00 150 157,500
5 - MU 830, 40 kg, tgl 5-12-2015, No. 990 zak 70.00 100 70.00 1,000 70,000
6 - Semen Gresik, 40 kg, tgl 5-12-2015, No. 994 zak 200.00 100 200.00 1,000 200,000
7 - Aka Mortar 300, 40 kg, tgl 8-12-2015, No. 999 zak 250.00 100 250.00 1,000 250,000
TOTAL 1,150,000.00
Pelaksana :
Jakarta, 12 Desember 2015
Kepala Tukang Costing, Site Manager, Project Manager
C RETENSI 5 % (57,500.00)
G DIBULATKAN 1,092,000.00
INDIVIDU
HARGA
NO JENIS PEKERJAAN SAT VOL SPK NILAI SPK
SATUAN
SEKARANG
( Rp ) ( Rp )
Finishing
1 - Potong Besi stek ex tierod, area ramp As. 8-9, pada kolom titik 20.00 2,500 50,000
dinding, dan balok,
2 - Bobok+ buang puing bata ringan pertemuan dengan balok baja hp 6.00 75,000 450,000
Lt. GF1 AS. 3-5/I-J, karena pekerjaan fireproof akan dikerjakan.
2org, 08-16, tgl 08-10
TOTAL 500,000.00
1 - Potong Besi stek ex tierod, area ramp As. 8-9, pada kolom titik 20.00 100 20.00 2,500 50,000
dinding, dan balok,
2 - Bobok+ buang puing bata ringan pertemuan dengan balok baja hp 6.00 100 6.00 75,000 450,000
Lt. GF1 AS. 3-5/I-J, karena pekerjaan fireproof akan dikerjakan.
2org, 08-16, tgl 08-10
TOTAL 500,000.00
Pelaksana :
Jakarta, 12 Desember 2015
Kepala Tukang Costing, Site Manager, Project Manager
C RETENSI 5 % (25,000.00)
G DIBULATKAN 475,000.00
INDIVIDU
HARGA
NO JENIS PEKERJAAN SAT VOL SPK NILAI SPK
SATUAN
SEKARANG
( Rp ) ( Rp )
1 - Bongkar sisa bekisting angkur baja pertemuan dengan hp 4.00 75,000 300,000
Plat Lt.GF1
2 - Bongkar sisa bekisting kepala kolom pertemuan dengan hp 4.00 75,000 300,000
Plat Lt.GF2
TOTAL 1,500,000.00
1 - Bongkar sisa bekisting angkur baja pertemuan dengan hp 4.00 100 4.00 75,000 300,000
Plat Lt.GF1
2 - Bongkar sisa bekisting kepala kolom pertemuan dengan hp 4.00 100 4.00 75,000 300,000
Plat Lt.GF2
4 - Bobok Dinding RetWall ( pertemuaan ex bekisting dan hp 3.00 100 3.00 75,000 225,000
pertemuan dinding dan plat ), As. 4/A', 0/C, 0/D, 0/E, 2/J', 3/J'
- Plester+Aci Dinding RetWall ( pertemuaan ex bekisting dan hp 3.00 100 3.00 75,000 225,000
pertemuan dinding dan plat ), As. 4/A', 0/C, 0/D, 0/E, 2/J', 3/J'
5 - Bobok Dinding RetWall ( pertemuaan ex bekisting dan hp 3.00 100 3.00 75,000 225,000
pertemuan dinding dan plat ), As. 0/F', 1/G', 1/H, 1/H', 0/H', 0/J
- Plester+Aci Dinding RetWall ( pertemuaan ex bekisting dan hp 3.00 100 3.00 75,000 225,000
pertemuan dinding dan plat ), As. 0/F', 1/G', 1/H, 1/H', 0/H', 0/J
TOTAL 1,500,000.00
Pelaksana :
Jakarta, 12 Desember 2015
Kepala Tukang Costing, Site Manager, Project Manager
C RETENSI 5 % (75,000.00)
G DIBULATKAN 1,425,000.00
TERBILANG Satu Juta Empat Ratus Dua Puluh Lima Ribu Rupiah
INDIVIDU
HARGA
NO JENIS PEKERJAAN SAT VOL SPK NILAI SPK
SATUAN
SEKARANG
( Rp ) ( Rp )
6 - Bor stek celcon dinding Kios, As. 1-3/G'-J' ttk 70.00 1,000 70,000
- Las stek kolom praktis pada balok baja Kios, As. 1-3/G'-J' ttk 60.00 2,000 120,000
TOTAL 9,434,507.30
6 - Bor stek celcon dinding Kios, As. 1-3/G'-J' ttk 70.00 40 28.00 1,000 28,000
- Las stek kolom praktis pada balok baja Kios, As. 1-3/G'-J' ttk 60.00 20 12.00 2,000 24,000
TOTAL 3,282,460.24
Pelaksana :
Jakarta, 26 Desember 2015
Kepala Tukang Costing, Site Manager, Project Manager
C RETENSI 5 % (164,123.01)
G DIBULATKAN 3,118,000.00
INDIVIDU
HARGA
NO JENIS PEKERJAAN SAT VOL SPK NILAI SPK
SATUAN
SEKARANG
( Rp ) ( Rp )
Finishing
3 - Bongkar Pasang scaffolding untuk Expose Plat Lantai GF1, m2 345.00 6,000 2,070,000
As. 4-10/J', As. 0-5'/A-G. incl jembatan kerja
4 Plester dinding LG
- Area Toilet dan Ruang Wudhu, As. 3'/J m2 232.47 11,500 2,673,428
- Area Lobby Escalator, As. 3-4'/G-I m2 269.15 11,500 3,095,250
- Area Mushola, As. 2-4/J-J' m2 262.43 11,500 3,017,966
5 Aci dinding LG
- Area Toilet dan Ruang Wudhu, As. 3'/J m2 232.47 10,000 2,324,720
- Area Lobby Escalator, As. 3-4'/G-I m2 269.15 10,000 2,691,522
- Area Mushola, As. 2-4/J-J' m2 262.43 10,000 2,624,319
6 Screeding lantai LG
- Area Mushola, As. 2-4/J-J' m2 161.48 8,000 1,291,824
- Area Toilet dan Ruang Wudhu, As. 3'/J m2 55.28 8,000 442,212
8 Pasang Wiremesh Area Toilet dan Ruang Wudhu, As. 3'/J m2 55.28 3,500 193,468
TOTAL 27,200,080.48
Finishing
3 - Bongkar Pasang scaffolding untuk Expose Plat Lantai GF1, m2 345.00 90 310.50 6,000 1,863,000
As. 4-10/J', As. 0-5'/A-G. incl jembatan kerja
4 Plester dinding LG
- Area Toilet dan Ruang Wudhu, As. 3'/J m2 232.47 90 209.22 11,500 2,406,085
- Area Lobby Escalator, As. 3-4'/G-I m2 269.15 - 11,500 -
- Area Mushola, As. 2-4/J-J' m2 262.43 60 157.46 11,500 1,810,780
5 Aci dinding LG
- Area Toilet dan Ruang Wudhu, As. 3'/J m2 232.47 - 10,000 -
- Area Lobby Escalator, As. 3-4'/G-I m2 269.15 - 10,000 -
- Area Mushola, As. 2-4/J-J' m2 262.43 - 10,000 -
6 Screeding lantai LG
- Area Mushola, As. 2-4/J-J' m2 161.48 20 32.30 8,000 258,365
- Area Toilet dan Ruang Wudhu, As. 3'/J m2 55.28 - 8,000 -
7 Waste celcon+pasir urugan 35 cm Area Toilet dan m2 55.28 20 11.06 27,500 304,020
Ruang Wudhu, As. 3'/J
8 Pasang Wiremesh Area Toilet dan Ruang Wudhu, As. 3'/J m2 55.28 - 3,500 -
TOTAL 10,602,716.28
Pelaksana :
Jakarta, 26 Desember 2015
Kepala Tukang Costing, Site Manager, Project Manager
C RETENSI 5 % (530,135.81)
G DIBULATKAN 10,072,000.00
INDIVIDU
HARGA
NO JENIS PEKERJAAN SAT VOL SPK NILAI SPK
SATUAN
SEKARANG
( Rp ) ( Rp )
1 - Bongkar sisa bekisting pada angkur baja dengan dinding RetWall hp 1.00 75,000 75,000
area STP. As. 4-10'/I-J. 1 orang. Jam 08-16
2 - Bongkar sisa bekisting kepala kolom pertemuan dengan hp 4.00 75,000 300,000
stop cor Plat Lt.GF2. As. 8-12/G-J. 2 orang. Jam 08-22
4 - Bongkar sisa bekisting di plat yang terjepit area Ramp turun dgn hp 2.00 75,000 150,000
STP. As. 4-9/I-J. 1 orang. Jam 08-22
TOTAL 525,000.00
1 - Bongkar sisa bekisting pada angkur baja dengan dinding RetWall hp 1.00 100 1.00 75,000 75,000
area STP. As. 4-10'/I-J. 1 orang. Jam 08-16
2 - Bongkar sisa bekisting kepala kolom pertemuan dengan hp 4.00 100 4.00 75,000 300,000
stop cor Plat Lt.GF2. As. 8-12/G-J. 2 orang. Jam 08-22
4 - Bongkar sisa bekisting di plat yang terjepit area Ramp turun dgn hp 2.00 100 2.00 75,000 150,000
STP. As. 4-9/I-J. 1 orang. Jam 08-22
0 - - 100 - - -
TOTAL 525,000.00
Pelaksana :
Jakarta, 26 Desember 2015
Kepala Tukang Costing, Site Manager, Project Manager
C RETENSI 5 % (26,250.00)
G DIBULATKAN 498,000.00
INDIVIDU
HARGA
NO JENIS PEKERJAAN SAT VOL SPK NILAI SPK
SATUAN
SEKARANG
( Rp ) ( Rp )
Finishing
1 - Potong Besi stek ex perkuatan dinding RetWall, area mushola titik 34.00 2,500 85,000
As. 2-4/J
2 - Pembersihan puing ex. Bobokan pekerjaan injeksi area Mushola hp 3.00 75,000 225,000
As. 2-4/J. 2 orang, jam 08-16
3 - Bongkar tanggulan air + kuras air. Lt. GF1 As. 1-2/G'H'. hp 3.00 75,000 225,000
2 orang. Jam 08-16
TOTAL 757,099.35
1 - Potong Besi stek ex perkuatan dinding RetWall, area mushola titik 34.00 100 34.00 2,500 85,000
As. 2-4/J
2 - Pembersihan puing ex. Bobokan pekerjaan injeksi area Mushola hp 3.00 100 3.00 75,000 225,000
As. 2-4/J. 2 orang, jam 08-16
3 - Bongkar tanggulan air + kuras air. Lt. GF1 As. 1-2/G'H'. hp 3.00 100 3.00 75,000 225,000
2 orang. Jam 08-16
4 - ConcreteFill Plat Lantai GF1. As. 5-6/A'-A m2 10.10 100 10.10 2,500 25,239
Plester+Aci Plat Lantai GF1. As. 5-6/A'-A m2 10.10 100 10.10 19,500 196,861
TOTAL 757,099.35
Pelaksana :
Jakarta, 26 Desember 2015
Kepala Tukang Costing, Site Manager, Project Manager
C RETENSI 5 % (37,854.97)
G DIBULATKAN 719,000.00
INDIVIDU
HARGA
NO JENIS PEKERJAAN SAT VOL SPK NILAI SPK
SATUAN
SEKARANG
( Rp ) ( Rp )
6 - Bor stek celcon dinding Kios GF1 as 4-7/G-J ttk 147.00 1,000 147,000
- Las stek kolom praktis pada balok baja Kios GF1 as 4-7/G-J ttk 248.00 2,000 496,000
TOTAL 31,234,455.20
6 - Bor stek celcon dinding Kios GF1 as 4-7/G-J ttk 147.00 - 1,000 -
- Las stek kolom praktis pada balok baja Kios GF1 as 4-7/G-J ttk 248.00 - 2,000 -
TOTAL 2,891,955.84
Pelaksana :
Jakarta, 26 Desember 2015
Kepala Tukang Costing, Site Manager, Project Manager
C RETENSI 5 % (144,597.79)
G DIBULATKAN 2,747,000.00
TERBILANG Dua Juta Tujuh Ratus Empat Puluh Tujuh Ribu Rupiah
INDIVIDU
HARGA
NO JENIS PEKERJAAN SAT VOL SPK NILAI SPK
SATUAN
SEKARANG
( Rp ) ( Rp )
Bongkat Material
1 - Bata Ringan ( uk. 10cm ), tgl 19-12-2015, SJ SJ/SLI/1512034 bh 1,050.00 150 157,500
2 - Bata Ringan ( uk. 10cm ), tgl 19-12-2015, SJ SJ/SLI/1512035 bh 1,050.00 150 157,500
TOTAL 315,000.00
1 - Bata Ringan ( uk. 10cm ), tgl 19-12-2015, SJ SJ/SLI/1512034 bh 1,050.00 100 1,050.00 150 157,500
2 - Bata Ringan ( uk. 10cm ), tgl 19-12-2015, SJ SJ/SLI/1512035 bh 1,050.00 100 1,050.00 150 157,500
TOTAL 315,000.00
Pelaksana :
Jakarta, 26 Desember 2015
Kepala Tukang Costing, Site Manager, Project Manager
C RETENSI 5 % (15,750.00)
G DIBULATKAN 299,000.00
-.00