CONSTRUCTION AND UPGRADING OF E-RING ROAD - NORTH/SOUTH LINK (P008-C2)

Rev. 01 Baseline Program (Architectural Lighting Schedule)


Activity ID Activity Name Original BL1 Start BL1 Finish 2018 2019 2020
Duration May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep t
-1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 9
601 15-Oct-18 14-Apr-20 E-Ring Road-N
E-Ring Road-North/South
Road-North/So Link (P008-C2) - Rev.01_07-June-18_Update_Weekly Report
601 15-Oct-18 14-Apr-20 POST CONTRA
POST CONTRACT MANAGEMENT
MAN
CONSTRUCTION 601 15-Oct-18 14-Apr-20 CONSTRUCTI
JUNCTION3 495 26-Nov-18 14-Apr-20 JUNCTION3
UTILITIES 495 26-Nov-18 14-Apr-20 UTILITIES
DRY UTILITIES 495 26-Nov-18 14-Apr-20 DRY UTILITIES
Architectural Lighting 495 26-Nov-18 14-Apr-20 Architectural Lighting
J3-UP6 57 26-Jan-19 24-Mar-19 J3-UP6
P8-C-J3_CM-AL-3330 [J3-UP6 Arch. Lighting] Install Lighting Fixture / Cabling /Install Power Supply Panel 30 26-Jan-19 03-Mar-19 [J3-UP6 Arch. Lighting] Install Lighting Fixture / Cabling /Install Power Supply Panel
P8-C-J3_CM-AL-3340 [J3-UP6 Arch. Lighting] Test & Commissioning (SCADA) 21 03-Mar-19 24-Mar-19 [J3-UP6 Arch. Lighting] Test & Commissioning (SCADA)
J3-UP5 61 26-Nov-18 26-Jan-19 J3-UP5
P8-C-J3_CM-AL-3300 [J3-UP5 Arch. Lighting] Install Lighting Fixture / Cabling /Install Power Supply Panel 30 26-Nov-18 01-Jan-19 [J3-UP5 Arch. Lighting] Install Lighting Fixture / Cabling /Install Power Supply Panel
P8-C-J3_CM-AL-3310 [J3-UP5 Arch. Lighting] Test & Commissioning (SCADA) 25 01-Jan-19 26-Jan-19 [J3-UP5 Arch. Lighting] Test & Commissioning (SCADA)
J3-UP4 49 23-May-19 18-Jul-19 J3-UP4
P8-C-J3_CM-AL-3270 [J3-UP4 Arch. Lighting] Install Lighting Fixture / Cabling /Install Power Supply Panel 30 23-May-19 04-Jul-19 [J3-UP4 Arch. Lighting] Install Lighting Fixture / Cabling /Install Power Supply
P8-C-J3_CM-AL-3280 [J3-UP4 Arch. Lighting] Test & Commissioning (SCADA) 14 04-Jul-19 18-Jul-19 [J3-UP4 Arch. Lighting] Test & Commissioning (SCADA)
J3-UP7 56 28-Mar-19 23-May-19 J3-UP7
P8-C-J3_CM-AL-3360 [J3-UP7 Arch. Lighting] Install Lighting Fixture / Cabling /Install Power Supply Panel 30 28-Mar-19 02-May-19 [J3-UP7 Arch. Lighting] Install Lighting Fixture / Cabling /Install Power Supply Panel
P8-C-J3_CM-AL-3370 [J3-UP7 Arch. Lighting] Test & Commissioning (SCADA) 21 02-May-19 23-May-19 [J3-UP7 Arch. Lighting] Test & Commissioning (SCADA)
J3-UP2 91 14-Aug-19 13-Nov-19 J3-UP2
P8-C-J3_CM-AL-3240 [J3-UP2 Arch. Lighting] Install Lighting Fixture / Cabling /Install Power Supply Panel 60 14-Aug-19 23-Oct-19 [J3-UP2 Arch. Lighting] Install Lighting Fixture / Cabling /I
P8-C-J3_CM-AL-3250 [J3-UP2 Arch. Lighting] Test & Commissioning (SCADA) 21 23-Oct-19 13-Nov-19 [J3-UP2 Arch. Lighting] Test & Commissioning (SCADA
J3-UP1 69 05-Feb-20 14-Apr-20 J3-UP1
P8-C-J3_CM-AL-3210 [J3-UP1 Arch. Lighting] Install Lighting Fixture / Cabling /Install Power Supply Panel 40 05-Feb-20 24-Mar-20 [J3-UP1 Arch. Lighting] Install Lig
P8-C-J3_CM-AL-3220 [J3-UP1 Arch. Lighting] Test & Commissioning (SCADA) 21 24-Mar-20 14-Apr-20 [J3-UP1 Arch. Lighting] Test &
ERR-PB-01 21 29-Apr-19 23-Nov-19 ERR-PB-01
P8-C-J3_CM-AL-3060 [ERR-PB-01 Arch. Lighting] Install Lighting Fixture / Cabling /Install Power Supply Panel 10 29-Apr-19 15-May-19 [ERR-PB-01 Arch. Lighting] Inst
P8-C-J3_CM-AL-3070 [ERR-PB-01 Arch. Lighting] Test & Commissioning (SCADA) 10 13-Nov-19 23-Nov-19 [ERR-PB-01 Arch. Lighting] Te
ERR-PB-05 26 16-Dec-19 12-Jan-20 ERR-PB-05
P8-C-J3_CM-AL-3120 [ERR-PB-05 Arch. Lighting] Install Lighting Fixture / Cabling /Install Power Supply Panel 14 16-Dec-19 02-Jan-20 [ERR-PB-05 Arch. Lighting] Install Lighting Fi
P8-C-J3_CM-AL-3130 [ERR-PB-05 Arch. Lighting] Test & Commissioning (SCADA) 10 02-Jan-20 12-Jan-20 [ERR-PB-05 Arch. Lighting] Test & Commiss
JUNCTION5 33 15-Oct-18 24-Jan-19 JUNCTION5
UTILITIES 33 15-Oct-18 24-Jan-19 UTILITIES
DRY UTILITIES 33 15-Oct-18 24-Jan-19 DRY UTILITIES
ARCHITECTURAL LIGHTING
LIGHTIN 33 15-Oct-18 24-Jan-19 ARCHITECTURAL LIGHTING
FRR-PB-01 23 15-Oct-18 07-Nov-18 FRR-PB-01
P8-C-J5-CM-AL-3150 [FRR-PB-01 Arch. Lighting] Install Lighting Fixture / Cabling /Install Power Supply Panel 14 15-Oct-18 31-Oct-18 [FRR-PB-01 Arch. Lighting] Install Lighting Fixture / Cabling /Install Power Supply Panel
P8-C-J5-CM-AL-3160 [FRR-PB-01 Arch. Lighting] Test & Commissioning (SCADA) 7 31-Oct-18 07-Nov-18 [FRR-PB-01 Arch. Lighting] Test & Commissioning (SCADA)
AWB-PB-01 23 01-Jan-19 24-Jan-19 AWB-PB-01
P8-C-J5-CM-AL-3180 [AWB-PB-01 Arch. Lighting] Install Lighting Fixture / Cabling /Install Power Supply Panel 14 01-Jan-19 17-Jan-19 [AWB-PB-01 Arch. Lighting] Install Lighting Fixture / Cabling /Install Power Supply Panel
P8-C-J5-CM-AL-3190 [AWB-PB-01 Arch. Lighting] Test & Commissioning (SCADA) 7 17-Jan-19 24-Jan-19 [AWB-PB-01 Arch. Lighting] Test & Commissioning (SCADA)
JUNCTION6 17 23-Feb-20 10-Mar-20 JUNCTION6
UTILITIES 17 23-Feb-20 10-Mar-20 UTILITIES
DRY UTILITIES 17 23-Feb-20 10-Mar-20 DRY UTILITIES
ARCHITECTURAL LIGHTING
LIGHTIN 17 23-Feb-20 10-Mar-20 ARCHITECTUR
FRR-PB-02 17 23-Feb-20 10-Mar-20 FRR-PB-02
P8-C-J6_CM-AL-3090 [ERR-PB-02 Arch. Lighting] Install Lighting Fixture / Cabling /Install Power Supply Panel 8 23-Feb-20 02-Mar-20 [ERR-PB-02 Arc
P8-C-J6_CM-AL-3100 [ERR-PB-02 Arch. Lighting] Test & Commissioning (SCADA) 8 03-Mar-20 10-Mar-20 [ERR-PB-02 Ar

Level of Effort Critical Remaining Work Primary Baseline Page 1 of 1 Document No. : EXW-P008-0002-PL-DEC-SH-00003_01
Actual Work Milestone Summary