Professional Documents
Culture Documents
Instrument Field Engineering: Prepared By: M.P.ALAM
Instrument Field Engineering: Prepared By: M.P.ALAM
Instrument Field Engineering: Prepared By: M.P.ALAM
1 GENERAL
1.1 Purpose
1.2 Scope
1.3 Responsibility
1.4 Reference
1.5 Testing Equipment
2 FIELD SUPERVISION
2.1 Instrument Calibration
2.2 Field Revision Work
2.3 Material Control
2.4 Vendor Supervision
3 INSTALLATION CHECK
3.1 Field Installation Check
3.2 Punchlist Preparation
3.3 Installation Check Sheet and Pre-installation Calibration Sheet
5 TROUBLE SHOOTING
5.1 Control Valve
5.2 Field transmitter
GROUP
SIGNATURE
DATE 200 . . . 200 . . . 200 . . . 200 . . . 200 . . .
TITLE 1. GENERAL PAGE 2 OF 98
1.1 PURPOSE
The purpose of this Field Engineering Handbook is to establish the basic requirements for the controlling,
field inspection and testing of instrument work in job site during construction.
1.2 SCOPE
This handbook is for instrument field engineer to ensure that instrumentation work (consistiong of material
storage, calibration, installation, testing and all appropriate records) is completed in accordance with
the requirements of the applicable codes, specifications and drawings.
1.3 RESPONSIBILITY
1.3.1 Responsibility for field instrumentation work shall be drawing issue for field revision work,
arrangement of supervision work for the specific items, and installation check.
1.3.2 The site supervisor shall be assigned to monitor instrument construction activities and witness tests
thereof to ensure compliance to specifications and drawings.
1.3.3 Quality control shall be advised on all engineering phases of the work by the assigned instrument
engineer and/or instrument supervisor.
1.3.4 As required and requested by the material control department, quality control shall assist in
the receiving inspection of instrumentation material and also monitor storage conditions to
ensure compliance to all requirement pertaining thereto.
1.3.5 Instrument engineer shall provide technical direction and guidance in all matters relative to
interpretation of codes, specifications, drawing and special procedure.
1.3.6. Instrument engineer shall establish procedures and modify existing one pertaining to calibration,
bench testing and final testing to ensure compliance with reference spec.
1.4 REFERENCES
· ANSI - American National Standards Institute.
· API - American Petroleum Institute.
· ISA - Instrument Society of America
· Applied Instrumentation in the Process Industries, Volume I, II and III
W.G. Andrew, Gulf Publishing Company.
· Instrument Engineers'Handbook, Volume I, II and III
B.G. Liptak, Chilton Book Company.
TITLE 1. GENERAL PAGE 3 OF 98
- CONTENTS -
2.1.1 General
2.1.16 Converter
(1) Current to Air Converter
(2) Air to Current Converter
(3) Voltage to Current Converter
(4) Current to Voltage/Current Converter
(5) Pulse Rate to Voltage/Current Converter
(6) Voltage/Current to Pulse Rate Converter (Integrator)
2.1.18 Controller
(1) Input (Process Variable) Calibration
(2) Set Point Calibration (Alignment) - Manual Set
(3) Remote set (Cascade Control)
(4) Output Meter and Manual Output Control Unit
(5) Control Action Check
(6) Gap Action (on-off Control)
(7) Special Function Check/Calibration
2.1.21 Recorder/Indicator
2.1.1 General
(1) The purpose of instrument calibration procedure is ensure that each instrument has been
supplied in accordance with specifications, is functionally correct and is in working order.
(2) The calibrations shall be performed in accordance with this procedure and any adjustments
being made shall be in accordance with the engineering data sheet.
(3) All shipping stops shall be miscellaneous components such as charts, mercury and oil
shall be in accordance with the engineering data sheet.
(4) No tests shall be carried out on electronic instrument until an adequate warm-up
period has elapsed.
(5) The approval of the instrument engineer shall be obtained in writing before any
non-standard modification or adjustments made.
(6) Upon completion, Pre-installation Calibration Sheet shall be completed with signatures
and distributed as indicated on the sheet.
(7) The calibrated instrument shall be identified with appropriate identification tag.
(8) Visual inspection shall be made prior to any calibration/adjustment process and the results are
to be recorded on each Pre-installation Calibration Sheet to ensure the identification,
physical condition and accord with specification. Any off-spec. item must be reported to
instrument engineer for resolution.
(9) The acceptable error limit to each instrument depend on process requirement and
instrument's accuracy which stated by manufacturer.
If the above condition is not specified, the following table of expected error limits of
commercially available instruments may be utilized as a guide.
TITLE 2.1 INSTRUMENT CALIBRATION PAGE 8 OF 98
Level :
Measuring Elements Total Error Measuring Elements Total Error
Gauge glass ±.02 inch Conductivity probe ±½ %
Bubbler ±1 % Nuclear ±1-2 %
Differential pressure ±½-2 % Manometer ±1 %
Displacer ±1-3 % Capacitance (continuous) ±1 %
Float and tap ±1-2 % Capacitance (switch) ±2-3 %
Float and pointer ±1 % Diaphragm switch within diaphragm
Diaphragm transmitter ±¼-2 % diameter
Ultrasonic ±3 % Vibrating probe or paddle ±.25 inch
Cable and drum ±.2 inch Rotating paddle within paddle
RF probe ±1½ % diameter
Pressure :
Measuring Elements Total Error Measuring Elements Total Error
Bourdon ±.1-2 % Piezoelectric ±1 %
Bellows transmitter ±½ % Dead weight ±.01-.1 %
Bellows/indicator ±2 % Manometer ±.02-1 %
Diaphragm ±½-1¼ % McLeod Gauge (vacuum) ±1 %
Strain gauge ±.1-2 % Thermal transfer (vacuum) ±10-20 %
Variable impedance ±¼-½ %
Capacitance ±.1-2 %
TITLE 2.1 INSTRUMENT CALIBRATION PAGE 9 OF 98
Temperature :
Measuring Elements Total Error Measuring Elements Total Error
Glass thermometers ±¼-½ % Manual optical pyrometer ±½-1 %
Thermocouples ±¼-5 % Radiation pyrometer ±½-1 %
Resistance detectors ±.2-.5 % Infrared pyrometer ±½-2 %
Thermistors ±½ % Color pencils, paint, etc. ±1 %
Filled systems ±½-1 % Acoustic thermometer ±2 %
Bimetallic ±½-2 % Quartz crystal ±.05 %
Weight :
Measuring Elements Total Error Measuring Elements Total Error
Mechanical Lever ±.1-.5 % Spring Balance ±.1-.5 %
Load Cells ±.1-.5 %
Analyzers:
Device Total Error Device Total Error
Viscosity
Ultrasonic ±2 % Gas chromatograph ±½-1 %
Vibrating reed ±1 % Infrared ±1 %
1-float ±4 % pH ±.005-.05 pH units
2-float ±2-4 % Moisture ±2-5 %
Combustion ±2 % Conductivity ±½-3 %
Refractometer ±.006-.01 % Specific gravity
Oxygen ±3 % Mechanical weighing ±1 %
Dissolved oxygen ±1-5 % Vibrating tube or paddle ±1 %
Sulfur dioxide ±5 % Sonic ±.01 %
Total hydrocarbon ±2-10 % Density
Total organic carbon ±2-10 % Vibrating tube ±1 %
Carbon Dioxide ±½ % Radiation ±1 %
Chlorine ±5 % Turbidity ±2-5 %
Sodium ±5 %
No2, No±No2 ±10 %
Miscellaneous :
Device Total Error Device Total Error
Converters Velocimeter ±.01-½ %
Current-current ±½-1 % Vibration ±5 %
Current-pneumatic ±¼-½ % Torque transmeters ±½-1 %
Pneumatic-current ±¼-½ % Accelerometer (strain gauge type) ±¼-1 %
Resistance-current ±½ % Electronic indicator ±1-3 %
Voltage-current ±½ % (D'Arsonval type)
Voltage-Pneumatic ±½ % Electronic indicator ±.01-.5 %
ORP transmitters ±¼-½ % (digital readout)
Speed transmitters ±½ %
TITLE 2.1 INSTRUMENT CALIBRATION PAGE 10 OF 98
Step 3 : When no pressure is applied to the high side, the indicator should indicates zero.
If not, reset zero adjusting screw until the indication read zero.
Step 4 : Increase input signal to full range (100%) as shown in the specification sheet.
The indication should read full scale (100%). If not, adjust span adjustment.
Step 5 : Recheck zero after span adjustment. Repeat until both are correct.
Step 6 : Check indication for 0,25,75 and 100% of range with signal rising and falling.
Every indication shall be within error limit. If not, adjust linearity adjustment and repeat
step 3 to 6 until every indication corresponds with input signal within acceptable error.
(3) Differential Pressure Indicating Switch (PdIS) and Differential pressure Switch (PdS)
Step 1 : Determine set point and action of switching.
Example : 5 PSID-High, 20PSID-Low etc.
Step 3 : When no pressure is applied to the high side, the transmitter output should be 0% of
output range. If it is not, adjust zero adjustment until the output indicates 0%
Step 4 : Increase input signal to full range (100%) as shown in the specification sheet.
The transmitter output should be 100% of its range. If not, adjust span adjustment.
TITLE 2.1 INSTRUMENT CALIBRATION PAGE 14 OF 98
Step 5 : Recheck zero after span adjustment. Repeat until both are correct.
Step 6 : Check output for 0,25,75 and 100% of range with signal rising and falling.
Step 7 : Every output reading shall be within error limit. If not, adjust linearity adjustment and
repeat step 3 to 7 until every output reading corresponds with input signal within
acceptable error limit.
Step 8 : If the instrument equiped with high/low range limit mechanism, adjust it to meet
proper requirement.
Step 2 : Calsurate pulse per second and pulse duration at 0,10,25,50,75 and 100% of flow which
indicated in instrument specification.
Example ; Full range of transmitter/indicator : 300 GPM.
Pulse rate : 16 pulse/gallon.
300 GPM ÷ 60 = 5 Gallon/Sec.
16 Pulse/Gallon x 5 Gallon/Sec = 80 Pulse/Sec.
1/80 = 0.0125 Sec. (Pulse duration)
TITLE 2.1 INSTRUMENT CALIBRATION PAGE 15 OF 98
Step 7 : Inject 100% of pulse signal to input terminal and check output/indication.
If any error is found, correct them with proper adjustment.
Step 9 : Check output/indication for 10,25,50 and 75% of range with signal rising and falling.
Every output reading should be within error limit. If not, adjust linearity adjustment and
repeat step 5 to 9 until every reading corresponds with input signal within acceptable error limit.
Step 10 : If the instrument equiped with temperature compensating function, simulate temperature
change and check output/indication at 0,25,50,75 and 100% of flow.
If output/indication does not properly correspond with temperature change, adjust
compensation factors with proper adjustment until every output/indication corresponds
input pulse and temperature within acceptable error limit.
Step 11 : If the instrument equiped with pressure compensating function, simulate pressure
change and check output/indication 0,25,75 and 100% of flow and temperature.
If the output/indication do not properly correspond with pressure change, adjust
compensation factors with proper adjustment until the output/indication correspond input
pulse, temperature and pressure within acceptable error limit.
Step 2 : When no pressure is applied to the instrument, the output of transmitter should be 0%
of its range. If it is not, adjust zero adjustment until the output indicates 0% of its range.
Step 3 : Increase input signal to full range (100%) as shown in the specification sheet.
The transmitter output should be 100% of its range. If not, adjust span adjustment.
Step 4 : Recheck zero after span adjustment. Repeat until both are correct.
Step 5 : Check output for 0,25,75 and 100% of range with signal rising and falling.
Step 6 : Every output reading shall be within error limit. If not, adjust linearity adjustment and repeat
step 2 to 6 until every output reading correspond with input signal within acceptable error limit.
Step 4 : Increase input signal to 100% of its range and read output.
The output should be 100% of its range. If not, adjust span adjustment.
Step 6 : Check output for 0,25,75 and 100%of range with signal rising and falling.
Step 4 : When error is found, adjust set point adjustment and repeat until desired value obtained.
Step 3 : Connect water (calibrating fluid) line and clear vinyl hose and other testing equipments
as per the Fig.2.1.7-1 below ;
Step 5 : Mark zero and span on the transmitter body and divide into four section evenly so that they
represent 0,25,50,75 and 100% of calibrating range.
Step 7 : Inject water upto 100% of calibrating level and read the output.
The output should be 100% of its range. If not, adjust span adjustment.
Step 8 : Recheck zero after span adjustment and repeat step 6 to 8 until 0% of output obtained.
TITLE 2.1 INSTRUMENT CALIBRATION PAGE 20 OF 98
Step 9 : Check output for 0,25,75 and 100% of range with level rising and falling.
Step 10 : Every output reading shall be within error limit. If not, adjust linearity adjustment and repeat
step 6 to 10 until every output corresponds with level signal within acceptable error limit.
Step 2 : Perform the step 2 and 3 of normal level transmitter on chapter 2.1.7
Step 3 : Calculate calibration range which converted into water (Calibrating liquid) level as follows ;
⊙ Spen = Operating Range x (lower Fluid's S.G.-Upper Fluid's S.G.)
⊙ Zero = Reference level + Operating Range x Upper Fluid's S.G.
Where : S.G. = Specific Gravity
Step 4 : Mark zero and span on the transmitter body and divide into four section evenly so that they
represent 0,25,50,75 and 100% of calibrating range.
NOTE : If the purging system occupy liquid for purging fluid, a special installation method shall be used
and a zero adjustment shall be performed with operating condition to eliminate error due to
pressure drop on the purging system piping.
Step 4 : Mark switching level on level switch so that the mark can be used as a reference
during field installation.
Step 5 : Compare output against input and adjust zero and span until both are correct.
Normally three point calibration is acceptable.
Step 4 : When error found, adjust set point adjustment and repeat until desired value obtained.
Step 1 : Determine mV value at 0,25,75 and 100% of temperature range from temperature
conversion table.
Step 3 : If the transmitter equped with type and/or range changing jumpers or switches,
put them on proper position.
Step 4 : Measure ambient temperature and determine mV value from the conversion table.
(See Appendix 4.)
Step 5 : Calculate calibration value at each calibration point using the formula below ;
mVcal. = mVoper. - mVamb.
Where
mVcal. = millivolt value of calibration
mVoper. = millivolt value of operating temperature
mVamb. = millivolt value of ambient temperature
Step 6 : Simulate 0% of calibration signal and check output. The output should be 0% of its range.
If not, adjust zero adjustment until correct value obtained.
Step 8 : Recheck zero after span adjustment and repeat step 7 to 9 until both are correct.
Step 9 : Check output at 0,5,75 and 100% of input range with signal rising and falling.
Every output reading shall be within error limit. If not, adjust linearity adjustment and repeat
step 7 to 10 until every output reading correspond with input signal within acceptable error limit
Step 11 : If the instrument equiped with burn-out option, check this function by opening the input
terminal and check output changing. When improper burn-out action observed, correct it
by changing jump or switching in accordance with the manufacturer's instruction.
Step 1 : Determine R.T.D. (Resistance Temperature Detector) type and operating temperature
convertion table.
Step 2 : Determine Resistance value at 0,25,75 and 100% of input range from temperature conversion ta
(See Appendix 4.)
TITLE 2.1 INSTRUMENT CALIBRATION PAGE 26 OF 98
Step 5 : Increase input signal upto 100% of its range and check output.
The output shall be 100% of its range. If not, adjust span adjustment.
Step 6 : Recheck zero after span adjustment and repeat until both are correct.
Step 7 : Check output for 0,25,75 and 100% of range with signal rising ad falling.
Step 8 : Every output reading shall be within error limit. If not, adjust linearity adjustment and repeat
step 4 to 8 until every output reading corresponds with input signal within acceptable error limit.
TITLE 2.1 INSTRUMENT CALIBRATION PAGE 27 OF 98
Step 4 : Adjust micrometer upto manufacturer's referance gap and tune proximiter so that the DC㎂
meter indicates maximum.
NOTE : Some of manufactuers calibrate the proximiter in their factory.In this case,
the proximiter shall not be adjusted.
Step 5 : Compare the maximum reading and the value specified by the manufacturer.
Both values should be same or reasonably close. If not, the proximiter shall be replaced.
TITLE 2.1 INSTRUMENT CALIBRATION PAGE 28 OF 98
Step 3 : Put monitoring indicator on gap mode by pressing push button or switching toggle switch.
Step 4 : Adjust gap by adjusting micrometer upto 10% of range and check monitor indication.
Adjust zero when error exist.
Fig. 2. 1. 14-3
Step 2 : Read maximum indication variance on dial gauge while turning WOBBLE PLATE
manually and adjust the PROBE HOLDER ARM so that the maximum indication reach to
calibration points such as 0,25,50,75 and 100% of vibration range.
TITLE 2.1 INSTRUMENT CALIBRATION PAGE 29 OF 98
Step 3 : At each calibration point, lock the PROBE HOLDER ARM and replace dial gauge with
probe as per the Fig.2.1.14-4 below ;
Fig. 2. 1. 14-4
Step 4 : Adjust the average gap upto reference value of the instrument while observing the
monitoring indicator and lock the probe.
Step 5 : Put the monitoring indicator on vibration mode and rotate WOBBLE PLATE by energizing
motor and read the vibration indication and output signal.
Step 7 : Every indication and output reading should be within error limit.
If not, recheck proximiter and monitor unit and repeat until desird accuracy obtained.
(2.3.2) If the instrument equiped with two point (X-Y) monitoring system, each measuring
circuit shall be checked and/or calibrated individually.
TITLE 2.1 INSTRUMENT CALIBRATION PAGE 30 OF 98
Step 1 : Put monitoring indicator on alarm set point mode by pressing push button or switching toggle sw
Step 2 : Adjust alarm set point adjustment until the monitoring indicator indicates desired value.
Step 4 : Adjust alarm set point adjustment until the monitoring indicator indicates desird value.
Step 6 : Adjust the average gap upto reference value and put monitoring indicator on vibration mode.
Step 7 : Rotate wobble plate by energizing motor and simulate vibration by adjusting probe holder
arm to activate the alarm and/or shutdown function.
Step 8 : Check activating value on monitoring indicator while increasing the vibration slowly with
observing alarm and/or shutdown outputs which normally include indicating lamps and contact
outputs. Special care shall be taken when the instrument ha a time delay function.
Step 9 : Check reset function by pressing the reset button, which normally provided on power supply un
and the external reset button which connected on external reset terminal.
TITLE 2.1 INSTRUMENT CALIBRATION PAGE 31 OF 98
Step 1 : The machine or measuring subject shall be mechanically stop condition and whole vibration
monitoring system shall be calibrated before probe installation.
Step 1 : Put monitoring indicator on positive alarm mode and adjust positive alarm set point until
the desired value indicated.
Step 2 : Adjust the set points of negative alarm, positive shutdown and negative shutdown with same wa
Step 4 : Adjust spindle micrometer and check alarm and/or shutdown function.
Step 5 : Every actual activating value shall be same as adjusted value described step 1 and 2.
If not, recheck proximitor and monitor unit.
Step 3 : Position the measuring subject to its mid-position (See note below) which determined from step
NOTE : If the manufacturer of the equipment specify the measuring reference point,
position the measuring subject to the recommended point. The indication and
alarm/shutdown set points are to be determined with this reference point.
TITLE 2.1 INSTRUMENT CALIBRATION PAGE 33 OF 98
Step 5 : Tighten every threaded parts of probe housing. (Refer to Fig.2.1.14-6, Chapter 2.1.14(3)).
Step 6 : Insert probe into measuring point until the monitoring indicator indicates reference gap.
Fig. 2. 1. 15-2
TITLE 2.1 INSTRUMENT CALIBRATION PAGE 34 OF 98
Step 3 : When no pulse injected to input terminal, the output shall be 0% of its range and,
if the speedometer equiped with indicator, the indication shall be zero.
If it is not, adjust zero until proper output/indication obtained.
Step 4: Inject 100% of pulse signal to input terminal and check output/indication.
Adjust span when error found.
2.1.16 Converter
(1) Current to Air Converter
Step 1 : Hook up teating equipments as per Fig.2.1.16-1 below ;
Step 4 : Recheck zero after span adjustment and repeat step 2 to 4 until both are correct.
Step 5 : Simulate input signal 0,25,75 and 100% and check output with input rising and falling.
Every output reading shall be within error limit. If not, adjust linearity and repeat step 2 to 5
until desired input-output character obtained.
TITLE 2.1 INSTRUMENT CALIBRATION PAGE 35 OF 98
(1.2) Great care shall be taken to choose the input and output type (current, voltage, pulse rate,
logic, contact closure, etc.) to prevent damage.
(1.3) In case of complex computation, it is preferred to prepare calibration table which is helpful to
find output value at various input condition.
TITLE 2.1 INSTRUMENT CALIBRATION PAGE 37 OF 98
Step 2 : Determine every ratio/bias factors by comparing specification and corresponding equation.
Prepare calibration table.
TITLE 2.1 INSTRUMENT CALIBRATION PAGE 38 OF 98
Step 2 : Determine every ratio/bias factors by comparing specification and corresponding equation.
Prepare calibration table.
TITLE 2.1 INSTRUMENT CALIBRATION PAGE 39 OF 98
Step 2 : Hook up testing equipments as per the Fig.2.1.17-1 on general procedure of computing relay
chapter 2.1.17(1.4).
Step 3 : Calibrate each factor in accordance with the calibration table and the manufacturer's instruction
Step 1 : Hook up testing equipments as per the Fig.2.1.17-1 on general procedure of computing
relay chapter 2.1.17(1.4).
Step 3 : Adjust zero and span adjustment until the output corresponds with input within
acceptable error limit.
Step 1 : Check instrument specification and determine break points and ratio value which most conform
to desired character.
Fig. 2. 1. 17-5
TITLE 2.1 INSTRUMENT CALIBRATION PAGE 41 OF 98
Step 3 : Hook up testing equipments as per the Fig.2.1.17-1 on general procedure of computing relay,
chapter 2.1.17(1.4).
Step 1 : Determine the limiting value, both high and low, from the instrument specification.
Fig. 2. 1. 17-6
Step 2 : Hook up testing equipments as per the Fig.2.1.17-1 on general procedure of computing relay,
chapter 2.1.17(1.4).
Step 3 : Simulate input signal and check the output limiting function and adjust low and high
set point (limiting value) until the desired values obtained.
Step 2 : If the instrument equiped with low range drop-out function, adjust it to minimum so that
the output do not affect with it.
Step 3 : inject input signal 6.25% of its range and check output.
The output should be 25% od output signal range.
If not, adjust zero adjustment until the error eliminated.
Step 4 : Inject input signal 100% of its range and check output.
The output should be 100%.
If not, adjust span and recheck zero and repert until both are correct.
General equation ;
Output(%) = Input (%)
Output = Input - ZERO input x SPANoutput + ZEROoutput
SPANinput
Step 7 : The error may be increased when the output is less than 10% (or input is less than 1%).
Therefore, the drop-out function might be required to eliminate this unaccurate output.
Fig. 2. 1. 17-8
Step 8 : If the instrument equiped with drop-out function, adjust it to desired value.
Step 2 : Hook up testing equipments on general procedure of computing relay chapter 2.1.17(1.4).
(11.2) The deviation alarm switching module initiates an alarm signal when a deviation between two
input signals exceeds a preset value.
(11.3) The rate monitor alarm switching module generates an alarm signal as the rate of change
in the input signal exceeds the preset rate.
Step 2 : Select proper function, high or low, by changing jumpers, switching function selecting
switch or arranging input/output.
Step 4 : Check setpoint with increasing signal for high alarm service and decreasing for low
while observing output.
Step 6 : Adjust setpoint and dead band, repeat step 4 to 6 until desired switching action obtained.
2.1.18 Controller
(1) Input (Process Variable) Calibration
Step 1 : Hook up testing equipments as per Fig.2.1.18-1 below ;
Step 3 : Adjust gain(Proportional band), integral (reset) and derivative (rate) as follows ;
⊙ Gain = 1 or proportional Band = 100%
⊙ Integral (reset time) = medium value.
⊙ Derivative (rate time) = minimum value.
Step 4 : Inject 50% of input signal and adjust set point knob so that the output indicates as follows ;
⊙ P mode : 50% of output range
⊙ PI or PID mode : Stop between 40 and 60% of output range.
Step 5 : Read setpoint indication and compare with input signal. If the difference between input and
set point indication is greater than 2% of scale, adjust set point zero adjustment and
repeat step 4 and 5 until the difference eliminated.
Step 6 : Inject 90% of input signal and adjust set point adjustment so that the output indicates 50% of
scale for P-mode controller and stop between 40 and 60% of scale for PI and PDI mode.
Step 7 : Read setpoint indication and compare with input signal. If he difference is greater than 2% of
scale, adjust setpoint span adjustment and repeat step 4 to 7 until both are correct.
Step 8 : Inject 10% of input signal and check set point indication same way as step 4 and step 6.
TITLE 2.1 INSTRUMENT CALIBRATION PAGE 47 OF 98
Step 9 : If the difference is greater than 2% of scale, adjust set point linearity adjustment and
repeat step 4 to 9 until all of three point check outs are correct within 2%.
Step 10 : If the instrument equiped with control unit alignment adjustment, adjust it as follow.
⊙ Increase gain upto 5(Proportional band 20%) and check set point according to step 4.
⊙ Read setpoint indication and compare with input signal.
⊙ If the difference is greater than 2% of scale, adjust control unit alignment and repeat
step 4 to 10 until the proper alignment obtained.
Step 3 : Inject remote set signal 0,25,75 and 100% of its range and adjust setpoint indications zero and
span adjustment so that the indication of remote set works properly.
NOTE : The set point indication zero and span adjustment are different from set
point zero and span which described on manual set point calibration.
Step 4 : Align control unit as per manual set point calibration step 3 to 10, chapter 2.1.18(2).
TITLE 2.1 INSTRUMENT CALIBRATION PAGE 48 OF 98
Step 3 : Adjust manual output adjusting knob and check output at 0,25,75 and 100% and minimum/
maximum value.
Step 4 : Compare integal output meter/gauge and external testing meter/gauge reading.
Adjust output meter/gauge when error found.
Step 3 : Adjust gain (proportional band), integral (reset) and derivative (rate) as follows ;
⊙ Gain(Proportional band) = 1 - 1.5 (70 - 100%)
⊙ Integral (reset time) = medium
⊙ Derivative (rate time) = medium
Step 4 : Adjust set point by adjusting set point knob (manyal set) or set point signal (remote set).
Step 5 : The input indicator should be followed up to set point within 2% of scale through entire scale
range. If not, proper adjustment shall be executed to eliminate the error.
Step 2 : Determine action and acting points from the instrument specification sheet and/or P. & I.D.
Fig. 2. 1. 18-6
Step 3 : Put control action (direct or reverse) to proper position as determined from step 2.
TITLE 2.1 INSTRUMENT CALIBRATION PAGE 50 OF 98
Step 5 : If the instrument equiped with set point and gap width indications, it shall be calibrated
with proper adjustment.
Step 3 : Put the selector switch on auto position and check output and output meter.
The output should be same as input signal.
Step 4 : Put the selector switch on manual position and adjust output adjusting knob from zero to full sc
The output should be close to the indication of manual output.
If not, adjust zero and span until proper output obtained.
TITLE 2.1 INSTRUMENT CALIBRATION PAGE 51 OF 98
Step 3 : Set bias adjusting knob to zero and inject 0% of input signal.
Step 4 : Check output while adjusting ratio from minimum through maximum.
The output should stay at 0% of output range. If not, adjust bias zero and ratio zero
adjustment until the output stay 0% of its range while changing ratio.
Step 5 : Set bias adjusting knob to zero and inject various input signal.
Check output while edjusting ratio.
The output should be same as calculated value using formula below ;
Input - ZERO input
Output = x Ratio x SPANoutput + ZERO output
SPAN input
Step 6 : If the ouput dose not correspond properly, adjust ratio span adjustment and repeat
step 3 to 6 until the output correspond within error limit.
Step 7 : If the instrument equiped with bias indicating scale, calibrate it as injecting various input
and comparing output with calculated value using formula below ;
Output(%) = Input(%) x Ratio ± Bias(%)
Input - ZERO input
Output = x Ratio x SPANoutput + ZERO output ± Bias
SPAN input
Fig. 2. 1. 21 Recorder/Indicator
Step 2 : Inject 0% signal and adjust zero adjustment.
Step 3 : Inject 100% signal and adjust span adjustment. Repeat step 2 and 3 until both are correct.
Step 4 : Inject 25% and 75% of input signal and check indication with signal rising and falling.
Every indication should be within error limit.
If not, adjust linearity and repeat step 2 to 4 until the instrument works properly.
Step 5 : If the instrument equiped with low and high over range stopping mechanism, adjust it properly.
Step 6 : For recorder, check inking system and chart driving mechanism.
Step 4 : Read the pneumatic signal value and compare it with the actuator's range.
If the difference is greater than 2%, adjust spring adjusting nut and repeat step 3 and 4 until
the desired value obtained.
If the desired value cannot obtain with spring adjustment, change stem length by adjusting
connector assembly and repeat step 3 and 4.
Step 5 : Adjust pneumatic signal so that the valve open slowly, and stop when the valve fully opened.
Step 6 : Read the pneumatic signal value and compare it with the actuator's range.
If the difference is greater than 15%, change spring and recheck closing and opening.
Step 7 : Adjust position indicator scale so that the indication works correctly
Step 8 : Inject pneumatic signal 0,25,75 and 100% of its range and read valve position
with signal rising and falling.
Step 2 : Connect power supply and/or air supply to the positioner and actuator
Step 4 : Adjust input signal so that the valve close slowly, and stop when the valve fully closed.
Step 5 : Read the input signal and adjust zero adjustment when error found.
Repeat step 4 and 5 until the valve corresponds with closing signal within error limit.
Step 6 : Adjust input signal so that the valve open slowly, and stop when the valve fully opened.
Step 7 : Read the input signal and adjust span adjustment when error found.
Repeat step 4 to 7 until the valve corresponds with closing and opening signal within error limit.
Step 8 : Inject signal 0,25,75 and 100% of its range and read valve position with signal rising and falling
Step 9 : Analyze the stroke characteristic curve and figure out the reproducibility which includes
deadband and hysteresis.
Step 10 : If the character or the reproducibility are not acceptable, check feel back can style
and/or mechanical condition of all moving parts and correct deficiency if exist.
Repeat step 4 to 10 until desired character obtained.
TITLE 2.1 INSTRUMENT CALIBRATION PAGE 55 OF 98
(4.2) If the control valve equiped with special accessories for the action of supply failure,
the functional check and/or calibration shall be executed for them.
2.1.23 Motion Transmitter
Step 1 : Hook up testing equipments as per Fig.2.1.23-1 below ;
Step 3 : Simulate 0% input, i.e., simulate mechanical movement which is the position input to
produce 0% output.
Step 4 : Check output and adjust zero adjustment when error found.
Step 6 : Recheck zero and repeat step 3 to 6 until both are correct.
(2) The miscellaneous type of instrument which is not described in this Q.C. procedure such as
thermal flowmeter, magnetic flowmeter, targetmeter type flowmeter, ultrasonic instrument,
radiographic type instrument and infrared type instrument,etc. shall be checked and/or
calibrated in accorance with each manufacturer's instruction.
TITLE 2.2 FIELD REVISION WORK PAGE 57 OF 98
Field engineer should check the contruction material including field instrument when a
instrument or bulk material is delivered to job site.
The delivered material shall be checked with purchase order and vendor print.
Typical material can be checked by random sampling as partial.
When field engneer has found something wrong with delivered material, that should be
informed to material controller.
Field engineer also has to monitor the delivery date comparing with delivery schedule which prepared
by procurement group.
If there is any delayed item as per the schedule, field engineer shall notify the delayed item
to procurement manager for expediting material delivery.
TITLE 2.4 VENDOR SUPERVISION PAGE 59 OF 98
Field engineer should confirm the following work to arrange a supervisor schedule.
1 DCS
- UPS power for DCS to be available
- System interconnection cable to be connected between each DCS system cabinet.
- Grounding wire to be connected.
2 ANALYZER
- Utility line to be available
- Power in shelter to be available
- Standard gas and carrier gas to be available.
3 TMR
- UPS power for TMR to be available.
- System interconnection cable to be connected.
4 NUCLEAR INSTRUMENT.
- Power supply for instr.
- Mounting of nuclear instr. to be same as drawing.
5 METERING STATION
- Service material to be available.
- Flow computer cabinet to be installed.
- Power to be available for flow computer cabinet.
- Prover to be available.
- Interface cable between metering skid and flow computer to be completed.
TITLE 3.1 FIELD INSTALLATION CHECK PAGE 60 OF 98
The instrument supervisior shall check physical condition of all instrument installations to ascertain
that the installations agree with instrumentation drawing and requirement.
The following field inspection check guide represent a list of basic items which should be
checked as the instrumentation work progresses prior to testing the system.
The details are described on individual installation check sheet, chapter 3.3.
The following is an outline of the punch list to be established and used in the completion of
construction for individual testing of system.
3.2.1 The instrument supervisor of higher authority is responsible to establish the punchlist.
3.2.2 The punch lists will be established by reviewing the P. & I.D., Piping isometric drawing,
instrument list and the hydrostatic testing scope of equipments, valve, pipe, instrument, etc.,
and reviewing the actual field installation in detail.
The punch list preparation will start at the beginning of the testing phase.
3.2.3 The punch lists are to be included all the items which are not complete whether they are
construction, engineering or material deficiencies.
Engineering and procurement items shall include the identification of correspondence, vendor names,
status and latest delivery information.
3.2.4 The instrument supervisor shall review his punch list with piping engineer who will add any piping
items before distribution to responsible craft supervision.
3.2.5 Instrument engineer is responsible for correcting the engineering and material deficiencies.
Construction deficiencies will be corrected by field supervision.
As items are completed, supervision is to advise the instrument supervisor with a marked up
copy of the punch list.
The instrument supervisior will then reinspect the deficiency and delete the item.
DESCRIPTION :
CHECK
ITEM TO CHECK / INSPECTION
(SIGNATURE/DATE)
1. Instrument damage during or after installation.
2. Nameplate and compare with instrument data sheet.
3. Tag fastened securely.
4. Accessibility and visibility of instructions and indication.
5. Accordance with appropriate drawings, standards and spec.
6. Lubrication of all removable parts such as cover, cap, etc.
7. Adequate protection from moisture, corrosive vapor, dust and freezing.
8. Proper action of controller,i,e., direct or reverse.
9. Support of instruments and related piping to insure min. vib.
10. Painting of instrument surfaces requiring corrosion resistance.
11. Seal weld of thermowell requiring socket weld.
12. Instrument mounted securely and neatly.
13. Instrument mounting stanchion properly supported and painted.
14. Proper leveling of instrument.
15. The condition of name plates and sight glasses.
16. Are all instruments free from access ways?
17. Is the flow element comply with flow direction?
REMARKS :
DISTRIBUTION SIGNATURE
DESCRIPTION :
CHECK
ITEM TO CHECK / INSPECTION
(SIGNATURE/DATE)
1. Are instrument piping to process in correct location?
2. Accordance with appropriate drawings, standards and spec.
3. Proper continuity of high and low pressure connections.
4. Seal pot requirements of flow meter and its support.
5. The piping/tubing installed in an orderly manner.
6. Proper support of piping/tubing.
7. Are tubing unions accessible for maintenance?
8. Is tubing routed so as not to impede access to instrument/valve?
9. Are all piping/tubing thoroughly cleaned?
10. Is the blow(vent) or drain piping installed up to safe location?
11. Proper slope of piping/tubing.
12. Are all support and its fittings painted/lubricated?
13. Is the pressure regulator set properly?
REMARKS :
DISTRIBUTION SIGNATURE
DESCRIPTION :
CHECK
ITEM TO CHECK / INSPECTION
(SIGNATURE/DATE)
1. Instrument panel damage during or after installation.
2. Proper location of instrument per the appropriate drawings,
standards and specification.
3. Name plates and instrument tags installed properly.
4. Is the panel located within tolerance?
5. Is the panel leveled properly?
6. Are the panels stand in a row?
7. Is touch-up painting carried out?
8. Is the panel supported to base properly?
9. Are all lamps installed with correct size and ratings?
10. Proper grounding of panels.
11. Is the air header connected to the air supplier properly?
12. Are the tubings installed in an orderly manner and supported?
13. Tagging or color code of tubing connectiond
14. Do all tubing/wiring maintain accessibility of instruments?
15. Proper identification of all electrical wirings.
16. Cleanness of panel or equipment.
REMARKS :
DISTRIBUTION SIGNATURE
DESCRIPTION :
CHECK
ITEM TO CHECK / INSPECTION
(SIGNATURE/DATE)
1. Are the indication gauges and valve position indicator located for easy
observation by operator?
2. Is the inside of valve body cleaned before installed?
3. Are sufficient clearance and accessibility provided for removal,
service and manual operation?
4. Control valve damage during or after installation.
5. Are all control valve accessories such as valve positioner electro-pneumatic
transducer, handwheel, air booster, trip valve, volume tank, air filter/regulator,
position transmitter and associated tubings installed properly per the drawing,
standard and specification?
6. Are the valve body and actuator painted properly?
7. Are all links connected properly and sufficient clearance provided?
8. Is valve inlet and outlet comply with flow direction?
REMARKS :
DISTRIBUTION SIGNATURE
REMARKS :
DISTRIBUTION SIGNATURE
4.1.1 All testing and function check shall be executed with appropriate documentation and witnessed
by client and/or consultant.
4.1.2 Discrepant items which arise during the testing or function check should be listed and
corrected as a punch list item.
4.1.3 Instrument piping pressure test should be executed by proper method as follows ;
(1) Impulse piping/tubing : Chapter 4.2.1.
(2) Signal transmission tubing : Chapter 4.2.2.
(3) Air supply piping : Chapter 4.2.3.
4.1.4 The method and policy of witness for the safety/relief valves are to be discussed between
client and contractor prior to check and/or test.
4.1.5 Special tests or adjustments which require costly test equipment and a high degree of technical
skill may be performed by vendor representative, under contract wherever they are available.
4.1.6 All proposed testing will be informed at least 24 hours in advance by contractor in notification.
(form No. G-1000-01)
4.1.7 The testing will be informed by client in writing, at least 24 hours in advance, the extent and duration
of all proposed test, indicating areas that will come under restricted access conditions.
TITLE 4.2 INSTRUMENTATION PRESSURE TEST PAGE 69 OF 98
(3.3) If the differential type level instrument is not equiped with bypass line, close block valves
at the vessel and add temporary bypass line between the high pressure and low pressure
sides to prevent excess differential pressure at the instrument.
(3.4) All joint, including welds, are to be left uninsulated and exposed for examination during the test.
(3.5) Vacuum service lines shall be tested at minimum pressure of 20 PSIG unless limited.
(3.6) Analyzer unit shall be disconnected before pressure testing of sampling lines.
Step 5 : Increase testing pressure gradually in steps with providing sufficient time to allow
the piping equalize the strains during test.
Step 6 : The pressure is to be reached the testing pressure which determined on chapter 4.2.1(2).
Step 7 : The test pressure shall be maintained for a sufficient time to determine if there are
any leaks, but not less than 10 minutes.
TITLE 4.2 INSTRUMENTATION PRESSURE TEST PAGE 70 OF 98
Step 8 : Accurate records shall be maintained for all the lines tested on the form No. I-405-01
(3.3) Identify positively the air circuit from air supply valve through instrument to air-operated
element by setting instrument to deliver air and observing air leakage at the disconnected
air line at the air-operated element.
(3.4) Before any test of pneumatic line, instruments which would consume air from the line must be
disconnected and the line be blocked at the point of disconnection.
Step 2 : Connect the bubbler unit to the open end of the line to be tested.
(Refer to Fig.4.2.2-1)
Step 4 : Open the air supply valve and adjust regulator so that the pressure reach to testing pressure.
Step 5 : Open the valve A and allow the line to be fully pressurized.
Step 9 : The line shall be considered acceptable when the bubbles are slowed to a rate
of no more than three per minute.
Step 10 : It must be stressed that air supply pressure to the bubble unit must be stable.
Step 11 : Accurate records shall be maintained for all the lines tested on the from No. I-405-02.
Step 2 : Put drain traps and air dryer into operation, and check quality of instrument air at
the down-stream of air dryers.
Step 3 : Test pressure shall be the maximum operation pressure of the instrument air supply
piping system.
Step 4 : Open the end of air supply pipe at the nearest union or coupling from the instruments and
blow air pipes clean removing all the foreign object and drain trapped inside pipes.
Step 5 : After blowing is finished, reconnect all the supply piping to the instruments.
Step 6 : Apply soap solution around all the possible source of leaks (union, coupling, etc.).
Step 8 : Mark on the leak points and depressurized the leaking section of the air supply
piping for maintenance.
Step 10 : Accurate recrds shall be maintained for all the line tested on the form No. I-405-03.
TITLE 4.3 SAFETY/RELIEF VALVES PAGE 73 OF 98
4.3.1 Scope
This procedure covers a pneumatic relief and leakage test of spring loaded relief valves,
pilot operated relief valves, vacuum relief valves and safety valves.
(2) Test medium used for pressure relief valves shall be nitrogen gas or compressed air
and free of any solids.
(3) Vacuum producing device shall be used for inbreathing relief valves.
(4) All piping used shall be purged to ensure there are no solids.
(5) Valves shall be cleaned of sand and dirt on exposed surfaces before testing.
(6) All data on valve nameplate shall be checked against design data sheets before testing.
(7) During testing all personnel not directly involved shall be cleared from the immediate area.
(8) Personnel involved in testing will wear ear plugs to protect ears from the popping noise.
(9) The outlet of the valve to be tested shall be placed to the opposite side of the operator.
4.3.3 Pneumatic Pop Test for Thermal Relief Valves and Full Lift Test for all PSVs using Test Stand.
(1) The valve shall be calibrated by poping pneumatically at the cold differential test pressure
(factory set pressure) listed on data sheets.
(2) The valve will be preinstalled on the test bench in accordance with the size of the valve,
and the test gauge shall be selected and installed after considering the range of the
specified test pressure.
(3) The pressure source shall be connected to the test bench and the pressure shall be gradually
increased to the set pressure of the valve as stated on valve data sheet by a throttling valve.
(4) When poping, the test gauge shall be checked whether in accordance with the set pressure or not.
In case the test pressure is above or under the specified set pressure, spring adjusting nut
shall be adjusted according to the Vendor's instruction.
(5) After adjusting, retest the valve and read the popping pressure and reset pressure.
TITLE 4.3 SAFETY/RELIEF VALVES PAGE 74 OF 98
(6) The testing shall be stopped and the valve readjusted when popping is not carried out at
the set pressure.
(2) Commercial seat tightness of safety/relief valves with metal-to-metal seats. (API Standard No.527)
(2.1) Scope
The maximum acceptable leakage rates are defined for commercial safety/relief valves with
metal-to-metal seats for set pressures up to 6000 pounds per square inch gage (41 megapascals).
If greater tightness is required, it can be supplied but must be specified on the purchase
order or inquiry.
NOTE : The cover plate should be fitted with a suitable device to relieve body pressure in
case of accidental popping of the valve.
TITLE 4.3 SAFETY/RELIEF VALVES PAGE 75 OF 98
(2.3) Procedure
With the valve mounted vertically, as shown in Figure 4.3.4-1, the leakage rate in bubbles
per minute shall be determined with pressure at the safety/relief valve inlet held at 90
percent of the set pressure immediately after popping.
For valves set at 50 pounds per square inch gage (354 kilopascals) or below,
the pressure shall be held at 5 pounds per square inch gage (35 kilopascls) below the set
pressure immediately after popping. The test pressure shall be applied for a minimum of
1 minute for valves of inlet sizes through 2 inch (50.8 milli meters);
2 minutes for sizes 2 1/2, 3, and 4 inch (63.5, 76.2 and 101.6 millimeters);
and 5 minutes for sizes 6 inch and 8 inch (152.4 and 203.2 millimeters).
Air at approximately atmospheric temperature shall be used as the pressure medium.
Table 1 - Leakagee Rates for Safety/Relief Valves for Set Pressures to 1000 Pounds
per Square inch Gage (6.9 Megapascals)
Approximate Leakage Rate
Type of Manufactuer's Maximum Leakage Rate (Standard Cubic Feet (Standard Cubic
Valve Orifice Size (Bubbles per Minute) Per 24 Hour) meter Per 24 Hour)
Convention F and smaller 40 0.6 0.017
al G and larger 20 0.3 0.085
Balanced F and smaller 50 0.75 0.021
bellows G and larger 30 0.45 0.031
Step 1 : Install the pilot valve on the test fixture, per Figure 4.3.5-1 for pressure plots,
on Figure 4.3.5-3 for vacuum pilots. The "Dome" port is connected to a pressure gauge
to indicate the degree of pressure change achieved while the pilot valve is venting.
On vacuum valves only, apply a positive pressure equal to the positive reciprocal value of
the vacuum set pressure.
Step 2 : Adjust the pressure adjusting bolt to obtain the correct set pressure.
Clockwise rotation increases the relief pressure.
NOTE : Set pressure (actuation) of vacuum pilots is evidenced by the rapid change of
dome pressure from atmospheric (zero gauge) to accumulator pressure.
Step 3 : Adjust the blowdown adjusting screw to obtain the desired reseat pressure. Clockwise rotation
will lengthen the blowdown. Tighten the locknut sfter adjustment is completed. A small
interaction between set pressure and blowdown may occur. If so, readjust the set pressure.
NOTE : The reseat value of the complete valve (pilot pluse main valve) with internal pressure
pickup will be approximately 2% less than the reseat value of the pilot only on snap
action pilots due to the loss in the dipper tube (total pressure pickup).
Step 4 : Cycle the pilot valve a minimum of five times to assure that it is relieving and reseating
consistently. Increase the pressure very slowly in order to obtain an accurate reading of
the cracking and relieving pressure and to expose any erratic performance.
NOTE : Cracking pressure on vacuum pilots is that pressure at which the initial dome
pressure change is noted.
Step 5 : Flow the pilot valve at set pressure to obtain the dome pressure reading.
For modulating pilots, dome pressure shall be read with the inlet at 110% of set pressure.
Steps 1 through 4 shall be completed before step 5 is undertaken.
(3.3) If the pilot internal leak test required, the test shall be performed in accordance with Fig. 4.3.5-5.
(3) Lead seals will be attached by the client after completion of test.
(4) All valves are to be stored in an upright position with inlet and outlet flange covered
(5) All valves which ready for installation shall have proper identification.
(6) The form No. I-405-04 should be used for test record.
TITLE 4.4 INSTRUMENT LOOP CHECK PAGE 80 OF 98
4.4.1 General
This procedure shall cover the requirements for the quality control of instrument loop check.
The loop check should be witnessed by client and all results of check shall be recorded on
loop check sheet, I-405-11.
The purpose of loop check is to prove the installed instrumentation functions and fit
condition for commissioning.
When the loop related with multiplexer unit, the entire loop should be checked following
vendor's instructions.
The procedure to be adopted in carrying out loop check is detailed following, but in general
the complete instrument loop shall be tested as one system, and where necessary,
adjustments shall be made for calibration.
All of associated instrumentation such as alarms, trips, data logger, indicating lights and
push buttons shall be checked during loop check.
During loop check, the power supply for correct identification of loop power switch, circuit
breakers or fused isolating switches are to be checked.
Step 3 : Inject input signal 10%, 50% and 90% of full scale and check all corresponding
instruments at each input value.
Step 4 : If the flow loop consist with control valve and controller. adjust the controller
output manually 0,25,75 and 100% of valve operating signal and check valve stroke.
Check tight closing of control valve, if necessary.
Step 5 : Reassemble the impulse piping or turbine meter and complete loop check sheet I-405-11.
Step 3 : Inject input signal 10%, 50% and 90% of full scale and check all corresponding
instruments at each input value.
Step 4 : If the pressure/vacuum loop consist with control valve and controller adjust the controller
output manually 0,25,75 and 100% of valve operating signal and check valve stroke.
Check tight closing of control valve, if necessary.
Step 5 : Reassemble the impulse piping and complete loop check sheet I-405-11.
Step 3 : Inject input signal 10%, 50% and 90% of full scale and check all corresponding
instruments at each input value.
For displacer type level transmitter the input signal of water level should be
compensated as per the chaper 2.1.7, I-0203.
Step 4 : If the level loop consist with control valve and controller, adjust the controller output
manually 0,25,75 and 100% of valve operating signal and check valve stroke.
Check tight closing of control valve, if necessary.
Step 5 : Reassemble the impulse piping or transmitter body to original condition and complete
Loop Check Sheet I-405-11.
Step 3 : Inject input signal 10%,50% and 90% of full scale and check all corresponding
instrument at each input value. If the system equiped with burn out function,
check it by opening the temperature element circuit while observing the output.
Step 4 : If the temperature loop consist with control valve and controller, adjust the controller
output manually 0,25,75 and 100% of valve operating signal and check valve stroke.
Check tight closing of control valve, if necessary.
Step 5 : Reassemble the temperature element to the original condition and complete
Loop check sheet. I-405-11.
TITLE 4.4 INSTRUMENT LOOP CHECK PAGE 85 OF 98
NOTE : Where the method described above is impractical and the switching function is proved
by other means, the alternate method such as manual actuation of switching mechanism
may be used.
Step 2 : Actuate switching action and check all related system such as alarm, trip, trip signal,
indicating lamp, etc.
Step 3 : Reassemble the switching mechanism to its original installation and complete
loop check sheet I-405-11.
REMARKS :
DISTRIBUTION SIGNATURE
REMARKS :
DISTRIBUTION SIGNATURE
LINE TEST
FROM TO RESULT REMARKS
SIZE PRESSURE
REMARKS :
DISTRIBUTION SIGNATURE
BEFORE ADJUST
AFTER ADJUST
TIGHTNESS TEST (LEAKAGE CHECK) UNIT : BUBBLES/MIN.
TESTING MAX. ALLOWABLE ACTUAL RESULT REMARKS
PRESSURE LEAKAGE RATE LEAKAGE RATE
REMARKS :
DISTRIBUTION SIGNATURE
AIR SUPPLIES
VISUALLY INSPECTED, BLOWN CLEAR & LEAK TESTED
CORRECTLY CONNECTED TO HOOK-UP DRAWING
CONTROLLER ACTION : DIRECT □ REVERSE □
SUPPORTS CHECKED TAGGING CORRECT
GENERAL
TRANSMITTER OUTPUT TO RELEVANT ITEMS OF LOOP CHECKED
CONTROLLED OUTPUT TO RELEVANT ITEMS OF LOOP CHECKED
LOOP TEST Tx. INPUT Tx. OUTPUT LOCAL INST. PANEL INST. REMARKS
10%
50%
90%
REMARKS :
DISTRIBUTION SIGNATURE
TO : REQ. NO. :
DATA :
FROM : TIME :
I/We give you 24 hours notification that the following work will be ready for inspection/test.
Subject :
Area/Location :
Description of work completed
DISTRIBUTION SIGNATURE
Most pneumatic spring-and-diaphragm actuators utilize a molded diapragm for control valve service.
The molded diaphragm facilitates installation, provides a relatively uniform effective area
throughout the valve's travel range, ad permits greater travel than could be possible if a flat-sheet
diaphragm were used. If a flat-sheet diaphragm is used in an emergency repair situation,
it should be replaced with a molde diaphragm as soon as possible.
When re-assembling the diaphragm case, tighten the cap screws around the perimeter of
the case firmly and evenly to prevent leakage.
If the packing is of the split ring variety, it can be removed (with considerable difficulty) without
removing the actuator by digging it out of the packing box with a narrow, sharp tool.
This is not recommended, because the wall of the packing box or the stem could easily be scratched,
thereby causing leakage when the new packing was installed.
Don't try to blow out the old packing rings by applying pressure to the lubricator hole in the bonnet.
This can be dangerous and frequently doesn't work very well anyway. (Many packing
arrangements have about half of the ring below the lubricator opening.)
5. Clean the packing box. Inspect the stem for scratches or imperfections that could
damage new packing.
6. Check the valve plug, seat ring, and trim parts as appropriate.
7. Re-assemble the valve body and put the bonnet in position.
8. Tighten body/bonnet bolting in sequence.
9. Slide new packing parts over the stem in proper sequence, being careful that the stem
threads do not damage the packing rings.
10. Install the packing follower, flange, and packing nuts.
11. For spring-loaded TFE V-ring packing, tighten the packing nuts as far as they will go.
For other varieties, tighten in service only enough to prevent leakage.
12. Replace and tighten the actuator onto the body. Position and tighten the stem
connector to provide desired valve plu travel.
Before trying to remove the seat ring(s), check to see if the ring has been tack-welded to
the valve body. If so, cut away the weld and apply penetrating oil to the seat ring threads
before trying to remove the ring. The following procedure for seat ring removal assumes
that a seat ring puller, such as that shown in Figure 5-4, is being used. If a puller is not
available, a lathe or boring mill may be used to remove the ring(s).
1. Place the proper size seat lug bar across the seat ring so that the bar contacts the seat
lugs as shown.
2. Insert drive wrench and place enough spacer rings over the wrench so that the hold
down clamp will rest about 1/4-inch above the body flange.
Slip hold-down clamp onto drive wrench and secure the clamp to the body with two cap
screws (or hex nuts for steel bodies) from the bonnet.
Do not tighten cap screws or nuts.
3. Use turning bar to unscrew the seat ring. Stuck seat rings may require additional force
on the turning bar. Slip a 3-to 5-foot length of pipe over one end of the turning bar, and while
applying a steady force, hit the other end of the bar with a heavy hammer to break the ring loose.
In addition, a large pipe wrench can used on the drive wrench near the hold-down clamp.
4. After the seat ring is loose, alternately unscrew the flange bolts (or nuts) on the hold-down clamp
and continue to unscrew seat ring.
5. Before installing new ring(s), thoroughly clean threads in the body port(s).
Apply pipe compound to the threads of the new seat ring(s).
TITLE 5.1 CONTROL VALVE MAINTENANCE PAGE 95 OF 98
NOTE : On double-port bodies, one of the seat rings is smaller than the other. On direct-acting valves
(push-down-to-close action), install the smaller ring in the body port farther from the bonnet
before installing the larger ring. On reverse-acting valves (push-down-to-open action),
install the smaller ring in the body port closer to the bonnet before installing the larger ring.
Screw the ring(s) into the body. Use the seat ring puller, lathe,or boring mill to tighten seat
ring in the body. Remove all excess piping compound after tightening.
The seat ring can be spot welded in place to ensure that it does not loosen.
On double-port bodies, the top ring normally grinds faster tha the bottom ring.
Under these conditions, continue to use grinding compound and white lead on the bottom ring,
but use only a polishing compound (rottenstone and oil) on the ring. If either of the ports continues
to leak, use more grinding compound on the seat ring that is not leaking and polishing compound
on the other ring. This procedure grinds down the seat ring that is not leaking until both seats touch
at the same time. Never leave one seat ring dry while grinding the other.
After grinding, remove bonnet or bottom flange, clean seating surfaces, and test for shutoff.
Repeat grinding procedure if leakage is still excessive.
1. Assemble the body and mount the actuator. Screw the stem locknuts onto the valve plug
stem and set the travel indicator disc on the locknuts with the "cupped" portion downward.
Leave enough threads exposed above the disc for the stem connector.
2. Be sure the actuator stem is in the position that equates with the "closed" valve plug
position-flly "down" for push-down-to-close valve styles; fully "up"for push-down-to-open valve styles.
To achieve this condition, it will often be necessary to pressure load the actuator to
properly position the stem.
3. Move the valve plug to the "closed" position, contacting the seat ring.
4. Change actuator loading pressure in oder to move the actuator stem 1/8-inch.
Install the stem connector, clamping the actuator stem to the valve plug stem.
5. Cycle the actuator to check availablity of desired otal travel and that the valve plug sats
before the actuator contacts the upper travel stop. Minor adjustments in total travel can be made,
if necessary, by loosening the stem connector slightly, tightening the locknuts together, and screwing
the stem either into or out of the stem connector by means of a wrench on the locknuts.
If overall travel increase is desired, the increase must be less than the 1/8-inch the
actuator rod was moved in step 4 above, or the valve will not shut off.
6. If the total travel is adequate, tighten the stem connector secuely, lock the travel indicator disc
against the connector with the locknuts, and adjust the indicator plate on the yoke to show
valve plug poisition.
7. Provide a gauge to measure the pressure to the actuator. Make a final adjustment on the
actuator or its positioner to set the starting point of valve travel and to obtain full travel for
the desired instrument range.
TITLE 5.1 CONTROL VALVE MAINTENANCE PAGE 97 OF 98
For disc-style rotary vaalves, fine travel ajustment should be performed with the valve body
out of the pipline so that measurements can be made as suggested in Figure 5-9.
Refer to the manufacturer's instruction manuals for specific adjustment details for the
body and actuator being used.
TITLE 5.2 FIELD TRANSMITTER PAGE 98 OF 98