CWSS TO 1766 HABITATIONS IN 7 UNIONS OF PUDUKOTTAI DISTRCT AND 125 HABITATIONS IN 2 UNIONS OF SIVAGANGAI

DISTRICT
COMPONENTS PROPOSED FOR MAINTENANCE
Proposed for the
Total Quantity contractor
Sl.No. Name of Components executed as per Balance Remarks
Maintenance
agreement ( Nos.)

1 2 3 4 5 6
I HEAD WORKS
Collector well ( 6 m dia x 18.20 m Depth) Cum
1 1 No 1 No. Nil
Pumphouse (8.5 m dia)
7669 lpm x 76 m Turbine (200 HP) 50%
2 standby 3 Nos 3 Nos. Nil

3 Construction of Control room 9 m x 5 m 1 No. 1 No. Nil

Construction of Transformer Yard size 18m x


4 9m, Transformer Capacity 500 KVA, 3 Phase 50 1 Nos. 1 Nos. Nil
HZ, 11 KV - 433 voltage

II BOOSTER SUMPS

A BOOSTER SUMP AT MADHAYANAPATTY

1 5.90 LL Sump Cum pump house 1 No. 1 No. Nil

2 2.45 LL Sump 1 No. 1 No. Nil

3 Control Room 12.00 x 7.00 m 1 No. 1 No. Nil

4 Chlorination Room 9.00 x 5.00 m 1 No. 1 No. Nil

5 Scada Room 9.00 x 5.00 m 1 No. 1 No. Nil

5918 lpm x 74 m Turbine (150 HP) 50%


6 3 Nos. 3 Nos. Nil
standby
Transformer capacity 400 KVA, 3 Phase 50 HZ,
7 2 Nos. 2 Nos. Nil
11 KV - 433 Voltage

B BOOSTER SUMP AT RAPPOSAL

1 4.55 LL Sump Cum pump house 1 No. 1 No. Nil

6069 lpm x 51 m Turbine Pumpset (100 HP)


2 2 Nos. 2 Nos. Nil
100% standby

3 Control Room 6.00 x 4.00 m 1 No. 1 No. Nil

4 Chlorination Room 9.00 x 5.00 m 1 No. 1 No. Nil

C BOOSTER SUMP AT EDYAPATTY

1 2.55LL Booster sump 1 No. 1 No. Nil

3712 LPM x 64 m Head Horizontal Split Case


2 2 Nos 2 Nos Nil
pumpset, 75 H.P (100% Standby)

3 Control Room 9.00 x 5.00 m 1 No. 1 No. Nil

D BOOSTER SUMP AT THERKATHUPATTY

1 0.45LL Booster sump 1 No. 1 No. Nil

625 LPM x 41 m Head Submersible pumpset


2 (100% Standby) 2 Nos 2 Nos Nil
Proposed for the
Total Quantity contractor
Sl.No. Name of Components executed as per Balance Remarks
Maintenance
agreement ( Nos.)

3 Pump Room 3.00 x 3.00 m 1 No. 1 No. Nil

III Tapping sumps 12 Nos. 7 Nos. 5 Nos. Due to permanent power suppy

Due to temporary EB Supply along with


Voltage drop issues and due to Forest ROW
IV Group sumps 233 Nos. 89 Nos 144 Nos Clearance, continuous pumping got
affected in 93 Nos. of GS and balance 51
Nos. Trial run under progress

V Pumproom

a 4mx3m 45 Nos. 15 Nos. 30 Nos. Due to temporary EB Supply along with


Voltage drop issues and due to Forest ROW
Clearance, continuous pumping got
affected in 93 Nos. of GS and balance 51
b 3mx3m 206 Nos. 78 Nos. 128 Nos. Nos. Trial run under progress

VI GRAVITY MAIN, PUMPING MAIN AND BRANCH PUMPING MAIN

1 700 mm MS pipe 32533 m 32533 m Nil

2 150 MM DI to 600 mm DI pipes 140003m 135243m Nil

Due to temporary EB Supply along with


Voltage drop issues and due to Forest ROW
3 50 mm PVC pipes to 200 mm PVC pipes 683486 m 286405 m 398144m Clearance, continuous pumping got
affected in 93 Nos. of GS and balance 51
Nos. Trial run under progress

4 Construction of Foot Bridge in River Cauvery 465 m 465 m Nil

5 Pipe carrying Bridge at Analai (11m) 1 No. 1 No. Nil

6 Pipe carrying birdge at Manalpokki (98m) 1 No. 1 No. Nil

7 Pipe carrying bridge at Ettarai (36 m) 1 No. 1 No. Nil

8 Pipe carrying bridge at Keerikalmedu (18m) 1 No. 1 No. Nil

9 Pipe carrying bridge at Keerikalmedu (11m) 1 No. 1 No. Nil

10 Pipe carrying bridge at Ariyavoor (123m) 1 No. 1 No. Nil

11 Pipe carrying bridge at Thuraikudi (96 m) 1 No. 1 No. Nil

12 Pipe carrying bridge at Kilikudi (80 m) 1 No. 1 No. Nil

13 Pipe carrying bridge at Ammapatty (22 m) 1 No. 1 No. Nil

Pipe carrying bridge at Maravamadurai (32


14 1 No. 1 No. Nil
m)

15 Pipe carrying bridge at Nerunjukudi (66 m) 1 No. 1 No. Nil

16 Pipe carrying bridge at Kadiyapatty (70 m) 1 No. 1 No. Nil

17 Pipe carrying bridge at Seeranoor (55 m) 1 No. 1 No. Nil


Proposed for the
Total Quantity contractor
Sl.No. Name of Components executed as per Balance Remarks
Maintenance
agreement ( Nos.)

18 Pipe carrying bridge at Pazuvinipatty (40 m) 1 No. 1 No. Nil


Proposed for the
Total Quantity contractor
Sl.No. Name of Components executed as per Balance Remarks
Maintenance
agreement ( Nos.)

VII FEEDER MAIN TO SERVICE RESERVIORS

Due to temporary EB Supply along with


Voltage drop issues and due to Forest ROW
a 50 mm to 110 mm PVC pipes (In Mtr) 1778901 847846 931055 Clearance, continuous pumping got
affected in 93 Nos. of GS and balance 51
Nos. Trial run under progress

VIII SERVICE RESERVIOR

a 10000 Lit 65 Nos. 38 Nos 27 Nos


Due to EB Power suply issues & ROW Issue
in Forest Area
b 30000 Lit 3 Nos. 1 Nos. 2 Nos

Due to temporary EB Supply along with


Voltage drop issues and due to Forest ROW
IX HABITATION COVERAGE 1891 756 1135 Clearance, continuous pumping got
affected in 93 Nos. of GS and balance 51
Nos. Trial run under progress

Due to temporary EB Supply along with


Voltage drop issues and due to Forest ROW
XI Submersible Pumpset 592 Nos. 212 Nos. 380 Nos Clearance, continuous pumping got
affected in 274 Nos. of GS and balance
106 Nos. Trial run under progress

XII DISTRIBUTION SYSTEM - PVC 63mm 62400 M 17700 M 45000 M

Executive Engineer, TWAD Board,


Urban Division, Trichy
CWSS TO 1766 HABITATIONS IN 7 UNIONS OF PUDUKOTTAI DISTRCT AND 125 HABITATIONS IN 2 UNIONS OF SIVAGANGAI
DISTRICT
COMPONENTS PROPOSED FOR CONTRACTOR MAINTENANCE

Proposed for the


Total Quantity
contractor
Sl.No. Name of Components executed as per Balance Remarks
Maintenance
agreement ( Nos.)

1 2 3 4 5 6
I HEAD WORKS
Collector well ( 6 m dia x 18.20 m Depth) Cum
1 1 No 1 No. Nil
Pumphouse (8.5 m dia)
7669 lpm x 76 m Turbine (200 HP) 33%
2 3 Nos 3 Nos. Nil
standby
3 Construction of Control room 9 m x 5 m 1 No. 1 No. Nil
Construction of Transformer Yard size 18m x
4 9m, Transformer Capacity 500 KVA, 3 Phase 50 1 Nos. 1 Nos. Nil
HZ, 11 KV - 433 voltage

II BOOSTER SUMPS

A BOOSTER SUMP AT MADHAYANAPATTY

1 5.90 LL Sump Cum pump house 1 No. 1 No. Nil

2 2.45 LL Sump 1 No. 1 No. Nil

3 Control Room 12.00 x 7.00 m 1 No. 1 No. Nil

4 Chlorination Room 9.00 x 5.00 m 1 No. 1 No. Nil

5 Scada Room 9.00 x 5.00 m 1 No. 1 No. Nil

5918 lpm x 74 m Turbine (150 HP) 33%


6 3 Nos. 3 Nos. Nil
standby
Transformer capacity 400 KVA, 3 Phase 50 HZ,
7 11 KV - 433 Voltage 2 Nos. 2 Nos. Nil

C BOOSTER SUMP AT RAPPOSAL

1 4.55 LL Sump Cum pump house 1 No. 1 No. Nil

6069 lpm x 51 m Turbine Pumpset (100 HP)


2 2 Nos. 2 Nos. Nil
50% standby

3 Control Room 6.00 x 4.00 m 1 No. 1 No. Nil

4 Chlorination Room 9.00 x 5.00 m 1 No. 1 No. Nil

C BOOSTER SUMP AT EDYAPATTY

1 2.55LL Booster sump 1 No. 1 No. Nil

3712 LPM x 64 m Head Horizontal Split Case


2 2 Nos 2 Nos Nil
pumpset, 75 H.P (50% Standby)

3 Control Room 9.00 x 5.00 m 1 No. 1 No. Nil

D BOOSTER SUMP AT THERKATHUPATTY

1 0.45LL Booster sump 1 No. 1 No. Nil


Proposed for the
Total Quantity contractor
Sl.No. Name of Components executed as per Balance Remarks
Maintenance
agreement ( Nos.)

625 LPM x 41 m Head Submersible pumpset


2 2 Nos 2 Nos Nil
(50% Standby)

3 Pump Room 3.00 x 3.00 m 1 No. 1 No. Nil

III Tapping sumps 12 Nos. 8 Nos. 4 Nos. Due to permanent power suppy

Due to temporary EB Supply along with


Voltage drop issues and due to Forest ROW
IV Group sumps 233 Nos. 101 Nos 132 Nos Clearance, continuous pumping got
affected in 93 Nos. of GS and balance 39
Nos. Trial run under progress

V Pumproom

a 4mx3m 45 Nos. 22 Nos. 23 Nos. Due to temporary EB Supply along with


Voltage drop issues and due to Forest ROW
Clearance, continuous pumping got
affected in 93 Nos. of GS and balance 39
b 3mx3m 206 Nos. 112 Nos. 94 Nos. Nos. Trial run under progress

VI GRAVITY MAIN, PUMPING MAIN AND BRANCH PUMPING MAIN

1 700 mm MS pipe 32533 m 32533 m Nil

2 150 MM DI to 600 mm DI pipes 140003m 135243m Nil

Due to temporary EB Supply along with


Voltage drop issues and due to Forest ROW
3 50 mm PVC pipes to 200 mm PVC pipes 683486 m 286405 m 398144m Clearance, continuous pumping got
affected in 93 Nos. of GS and balance 39
Nos. Trial run under progress

4 Construction of Foot Bridge in River Cauvery 465 m 465 m Nil

5 Pipe carrying Bridge at Analai (11m) 1 No. 1 No. Nil

6 Pipe carrying birdge at Manalpokki (98m) 1 No. 1 No. Nil

7 Pipe carrying bridge at Ettarai (36 m) 1 No. 1 No. Nil

8 Pipe carrying bridge at Keerikalmedu (18m) 1 No. 1 No. Nil

9 Pipe carrying bridge at Keerikalmedu (11m) 1 No. 1 No. Nil

10 Pipe carrying bridge at Ariyavoor (123m) 1 No. 1 No. Nil

11 Pipe carrying bridge at Thuraikudi (96 m) 1 No. 1 No. Nil

12 Pipe carrying bridge at Kilikudi (80 m) 1 No. 1 No. Nil

13 Pipe carrying bridge at Ammapatty (22 m) 1 No. 1 No. Nil

Pipe carrying bridge at Maravamadurai (32


14 1 No. 1 No. Nil
m)

15 Pipe carrying bridge at Nerunjukudi (66 m) 1 No. 1 No. Nil

16 Pipe carrying bridge at Kadiyapatty (70 m) 1 No. 1 No. Nil


Proposed for the
Total Quantity contractor
Sl.No. Name of Components executed as per Balance Remarks
Maintenance
agreement ( Nos.)

17 Pipe carrying bridge at Seeranoor (55 m) 1 No. 1 No. Nil

18 Pipe carrying bridge at Pazuvinipatty (40 m) 1 No. 1 No. Nil

VII FEEDER MAIN TO SERVICE RESERVIORS

Due to temporary EB Supply along with


Voltage drop issues and due to Forest ROW
a 50 mm to 110 mm PVC pipes (In Mtr) 1778901 847846 931055 Clearance, continuous pumping got
affected in 93 Nos. of GS and balance 39
Nos. Trial run under progress

VIII SERVICE RESERVIOR

a 10000 Lit 65 Nos. 38 Nos 27 Nos


Due to EB Power suply issues & ROW Issue
in Forest Area
b 30000 Lit 3 Nos. 1 Nos. 2 Nos

Due to temporary EB Supply along with


Voltage drop issues and due to Forest ROW
IX HABITATION COVERAGE 1891 862 1029 Clearance, continuous pumping got
affected in 93 Nos. of GS and balance 39
Nos. Trial run under progress

Due to temporary EB Supply along with


Voltage drop issues and due to Forest ROW
XI Submersible Pumpset 592 Nos. 240 Nos. 352 Nos Clearance, continuous pumping got
affected in 274 Nos. of GS and balance 78
Nos. Trial run under progress

XII DISTRIBUTION SYSTEM - PVC 63mm 62400 M 17700 M 45000 M

Executive Engineer, TWAD Board,


Urban Division, Trichy