Bill PROJECT : ONE & ONLY ROYAL MIRAGE – PHASE III

INSTALLATION CHECK LIST FOR FAN COIL UNIT

DRAWING NO. REV.


SYSTEM LOCATION
DESCRIPTION

Sl.
Description Yes No Remarks
No.
Confirm that unit is approved by Consultant and all relevant
1 drawings are available.

Check all critical dimensions for pipes, wires, ducting


2 connection requirements are as per approved drawings.

Identify the correct location of unit as per approved drawing.


3

Identify the correct unit and ensure that location of unit is


4 accessible for inspection and maintenance.

Install the approved vibration isolators and proper


5 supporting arrangement is done.

Ensure the correct height of unit considering the drainage.


6

7 Ensure protection of unit from damages by job site activities

Check the rotation of blower


8

Tag No. of unit is fixed


9

Check that valve package is easily accessible.


10

DOCUMENT NUMBER ISSUE PAGE NO. DATE

BILT/J-225/QAP/AC-11 REV. 0 1 of 2 16-09-2009


Bill PROJECT : ONE & ONLY ROYAL MIRAGE – PHASE III

INSTALLATION CHECK LIST FOR FAN COIL UNIT

DRAWING NO. REV.


SYSTEM LOCATION
DESCRIPTION

11 FCU control box and thermostat installed at easily


accessible area and all BMS, wiring is done as per approved
control schematic and manufacturer’s recommendation.

Sl.
Description Yes No Remarks
No.
Filters are properly fixed and are accessible for cleaning
12 purpose.

Chilled water piping/ducting/condensate drain pipes are


13 connected properly.

CONSULTANTS COMMENTS:

ENGINEER/SUPERVISOR (BILT) NAME SIGN.

QA / QC ENGINEER (BILT) NAME SIGN.

CONSULTANT/CLIENT NAME SIGN

DOCUMENT NUMBER ISSUE PAGE NO. DATE

BILT/J-225/QAP/AC-11 REV. 0 1 of 2 16-09-2009