BILT MIDDLE EAST LLC

INSPECTIONS AND TESTING PLAN

QUALITY CONTROL AND WORK INSPECTION

JOB: ONE & ONLY ROYAL MIRAGE – PHASE III

ITEM : INSTALLATION OF FAN COIL UNITS

SL
DESCRIPTION BME CONSULTANT
NO
Material Receiving Inspections:
a) Quantity, Sizes etc.
1. b) Compliance with specifications and W R /S
approved material submittals.

Site Installations :
a) Location, orientation, height of unit. W W
b) Supporting arrangement including W S
vibration isolator
c) Fixing of valve package W S
d) Connecting the ducting, piping, W S
condensate drain
2.
e) Operation and maintenance accessibility W W
for unit
f) Final inspection of unit installation W S
g) Thermostat and control wiring/BMS W W
wiring interface W W

W– Witness / S --Spot – Checks / R - Review –documents

BILT/J-225/ITP/AC-11