COMPUTATION OF DURATION PER ACTIVITY

1. Move In
No. of Laborers: 0
Duration: 7 days

2. General Technical Requirements


No. of Carpenters: 4
No. of Laborers: 4
Duration: 3 days

3. Earthworks
3.1 Clearing and Grubbing
𝑀𝐻
Rate: 0.25 𝑚3

Total Volume: 478𝑚3


𝑀𝐻 119.5𝑀𝐻
MD = 0.25 𝑚3 × 478𝑚3 = = 104.938𝑀𝐷
8𝐻/𝐷

No. of Laborers: 5
104.938𝑀𝐷
Duration = = 2.988 𝑑𝑎𝑦𝑠
5𝑀

Duration: 3 days

3.2 Excavation for Foundation


𝑀𝐻
Rate: 0.44 𝑚3

Total Volume: 1,904𝑚3


𝑀𝐻 837.76𝑀𝐻
MD = 0.44 𝑚3 × 1,904𝑚3 = = 104.72𝑀𝐷
8𝐻/𝐷

No. of Laborers: 15
104.72𝑀𝐷
Duration = = 6.981 𝑑𝑎𝑦𝑠
15𝑀

Duration: 7 days

Page | 97
3.3 Backfilling and Compaction
𝑚3
Rate: 4.15 ℎ𝑟

Total Volume: 2,095𝑚3


2,095 × 1𝑀
MD = 𝑚3 𝐻
= 63.102MD
4.15 ×8
ℎ𝑟 𝐷

No. of Laborers: 15
63.102𝑀𝐷
Duration = = 4.207 𝑑𝑎𝑦𝑠
15𝑀

Duration: 5 days

3.4 Soil Poisoning


𝑚2
Rate: 320 ℎ𝑟

Total Area: 629𝑚2


629𝑚2 ×1𝑀
MD = 𝑚2 𝐻
= 0.25𝑀𝐷
320 ×8
ℎ𝑟 𝐷

No. of Laborers: 2
0.25𝑀𝐷
Duration = = 0.123 𝑑𝑎𝑦𝑠
2𝑀

Duration: 1 day

3.5 Gravel Bed


𝑚3
Rate: 0.3 ℎ𝑟

Total Volume: 48𝑚3


48𝑚3 × 1𝑀
MD = 𝑚3 𝐻
= 20MD
0.3 𝑥8
ℎ𝑟 𝐷

No. of Laborers: 10
20𝑀𝐷
Duration = = 2 𝑑𝑎𝑦𝑠
10𝑀

Duration: 2 days

Page | 98
3.6 Embankment/ Earth Fill
𝑚3
Rate: 3.60 ℎ𝑟

Total Volume: 574𝑚3


574 × 1𝑀
MD = 𝑚3 𝐻
= 19.931MD
3.60 ×8
ℎ𝑟 𝐷

No. of Laborers: 10
19.931𝑀𝐷
Duration = = 1.993 𝑑𝑎𝑦𝑠
10𝑀

Duration: 2 days

4. Concrete Works
4.1 Concrete Footing
Total Volume: 83𝑚3
𝑚3
Rate: 2 𝑚𝑒𝑛 = 1.60 𝑑𝑎𝑦
𝑚3
1 𝑚𝑎𝑛 = 0.80 𝑑𝑎𝑦
83 m³ X 1M
MD = = 103.75MD
0.8m³/D

No. of Laborers: 15
103.75𝑀𝐷
Duration: = 6.917𝑑𝑎𝑦𝑠
15𝑀

Duration: 7 days

4.2 Column Neck


Total Volume: 10𝑚3
𝑚3
Rate: 2 𝑚𝑒𝑛 = 1.60 𝑑𝑎𝑦
𝑚3
1 𝑚𝑎𝑛 = 0.80 𝑑𝑎𝑦
10 m³ X 1M
MD = = 12.5MD
0.8m³/D

No. of Laborers: 5
12.5𝑀𝐷
Duration: = 2.5 𝑑𝑎𝑦𝑠
5𝑀

Duration: 3 days

Page | 99
4.3 Ground Floor Column
Total Volume: 26𝑚3
𝑚3
Rate: 2 𝑚𝑒𝑛 = 1.10 𝑑𝑎𝑦
𝑚3
1 𝑚𝑎𝑛 = 0.55 𝑑𝑎𝑦
26 m³ X 1M
MD = = 47.273MD
0.55m³/D

No. of Laborers: 8
47.273𝑀𝐷
Duration: = 5.909 𝑑𝑎𝑦𝑠
8𝑀

Duration: 6 days

4.4 Second Floor Column


Total Volume: 26𝑚3
𝑚3
Rate: 2 𝑚𝑒𝑛 = 1.10 𝑑𝑎𝑦
𝑚3
1 𝑚𝑎𝑛 = 0.55 𝑑𝑎𝑦
26 m³ X 1M
MD = = 47.273MD
0.55m³/D

No. of Laborers: 8
47.273𝑀𝐷
Duration: = 5.909 𝑑𝑎𝑦𝑠
8𝑀

Duration: 6 days

4.5 Roof Extended Column


Total Volume: 5𝑚3
𝑚3
Rate: 2 𝑚𝑒𝑛 = 1.30 𝑑𝑎𝑦
𝑚3
1 𝑚𝑎𝑛 = 0.65 𝑑𝑎𝑦
5m³ X 1M
MD = = 7.692MD
0.65m³/D

No. of Laborers: 4
7.692𝑀𝐷
Duration: = 1.923 𝑑𝑎𝑦𝑠
4𝑀

Duration: 2 days

Page | 100
4.6 Ground Tie Beam
Total Volume: 10𝑚3
𝑚3
Rate: 2 𝑚𝑒𝑛 = 1.30 𝑑𝑎𝑦
𝑚3
1 𝑚𝑎𝑛 = 0.65 𝑑𝑎𝑦
10m3 X 1M
MD = 0.65m3
= 15.385MD
D

No. of Laborers: 6
15.385𝑀𝐷
Duration: = 2.564 𝑑𝑎𝑦𝑠
6𝑀

Duration: 3 days

4.7 Floor Beam


Total Volume: 32𝑚3
𝑚3
Rate: 2 𝑚𝑒𝑛 = 1.10 𝑑𝑎𝑦
𝑚3
1 𝑚𝑎𝑛 = 0.55 𝑑𝑎𝑦
32m³ X 1M
MD = = 58.182MD
0.55m³/D

No. of Laborers: 10
58.182𝑀𝐷
Duration: = 5.818 𝑑𝑎𝑦𝑠
10𝑀

Duration: 6 days

4.8 Roof Beam


Total Volume: 32𝑚3
𝑚3
Rate: 2 𝑚𝑒𝑛 = 1.10 𝑑𝑎𝑦
𝑚3
1 𝑚𝑎𝑛 = 0.55
𝑑𝑎𝑦

32m³ X 1M
MD = = 58.182MD
0.55m³/D

No. of Laborers: 10
58.182𝑀𝐷
Duration: = 5.818 𝑑𝑎𝑦𝑠
10𝑀

Duration: 6 days

Page | 101
4.9 Ground Floor Slab
Total Volume: 72𝑚3
𝑚3
Rate: 2 𝑚𝑒𝑛 = 1.80 𝑑𝑎𝑦
𝑚3
1 𝑚𝑎𝑛 = 0.90 𝑑𝑎𝑦
72m³ X 1M
MD = = 80MD
0.90m³/D

No. of Laborers: 12
80𝑀𝐷
Duration: = 6.667 𝑑𝑎𝑦𝑠
12𝑀

Duration: 7 days

4.10 Second Floor Slab


Total Volume: 74𝑚3
𝑚3
Rate: 2 𝑚𝑒𝑛 = 1.80 𝑑𝑎𝑦
𝑚3
1 𝑚𝑎𝑛 = 0.90 𝑑𝑎𝑦
74m³ X 1M
MD = = 82.222MD
0.90m³/D

No. of Laborers: 12
82.222𝑀𝐷
Duration: = 6.852 𝑑𝑎𝑦𝑠
12𝑀

Duration: 7 days

4.11 Roof Deck


Total Volume: 95𝑚3
𝑚3
Rate: 2 𝑚𝑒𝑛 = 2.40 𝑑𝑎𝑦
𝑚3
1 𝑚𝑎𝑛 = 1.20 𝑑𝑎𝑦
95m³ X 1M
MD = = 79.167MD
1.20m³/D

No. of Laborers: 12
79.167𝑀𝐷
Duration: = 6.597 𝑑𝑎𝑦𝑠
12𝑀

Duration: 7 days

Page | 102
4.12 Stair Case
Total Volume: 3𝑚3
𝑚3
Rate: 2 𝑚𝑒𝑛 = 1.60 𝑑𝑎𝑦
𝑚3
1 𝑚𝑎𝑛 = 0.80 𝑑𝑎𝑦
3m³ X 1M
MD = = 3.75MD
0.80m³/D

No. of Laborers: 4
3.75𝑀𝐷
Duration: = 0.9375 𝑑𝑎𝑦
4𝑀

Duration: 1 day

4.13 Septic Tank


Total Volume: 2𝑚3
𝑚3
Rate: 2 𝑚𝑒𝑛 = 2.40 𝑑𝑎𝑦
𝑚3
1 𝑚𝑎𝑛 = 1.20 𝑑𝑎𝑦
2m³ X 1M
MD = = 1.667MD
1.20m³/D

No. of Laborers: 2
1.667𝑀𝐷
Duration: = 0.833 𝑑𝑎𝑦
2𝑀

Duration: 1 day

4.14 Concrete Parapet


Total Volume: 5𝑚3
𝑚3
Rate: 2 𝑚𝑒𝑛 = 1.80 𝑑𝑎𝑦
𝑚3
1 𝑚𝑎𝑛 = 0.90 𝑑𝑎𝑦
5m³ X 1M
MD = = 5.556MD
0.90m³/D

No. of Laborers: 3
5.556𝑀𝐷
Duration: = 1.852 𝑑𝑎𝑦𝑠
3𝑀

Duration: 2 days

Page | 103
5. Reinforcement Bars
5.1 Concrete Footing
No. of bars = 5641pcs @16mm diameter
Rate: .015MH/ kg
Total weight of bars = 5641 x 9.47 = 53240.27kg
𝑀𝐻
.015
𝑘𝑔
MD = 53240.27x 8𝐻 = 79.86 MD
𝐷

No. of Laborers: 12
Duration = 79.86 / 12 = 6.655 days say, 7 days

5.2 Column Neck


No. of bars = 1698 @ 25mm diameter
No. of bars = 830 @ 20mm diameter
No. of bars = 1,100 @ 8mm diameter
Rate: .006MH/ kg
Total weight of bars = (1698x23.1) + (830 x 14.82) +
(1100 x 2.34) = 54098.4kg
𝑀𝐻
.006
𝑘𝑔
MD = 54098.4 x 8𝐻 = 40.57 MD
𝐷

No. of Laborers: 6
Duration = 40.57 / 12 = 6.76 days say, 7 days

5.3 Ground Floor Column


No. of bars = 3687 @ 25mm diameter
No. of bars = 1802 @ 20mm diameter
No. of bars = 3201 @ 8mm diameter
Rate: .007MH/ kg
Total weight of bars = (3687x23.1) + (1802 x 14.82) +
(3201 x 2.34) = 119365.68kg
𝑀𝐻
.007
𝑘𝑔
MD = 119365.68 8𝐻 = 104.44 MD
𝐷

No. of Laborers: 17
Duration = 104.44 / 6 = 6.14 days say, 7 days

Page | 104
5.4 Second Floor Column
No. of bars =3064 @ 16mm diameter
No. of bars = 3428@ 10mm diameter
Rate: .017MH/ kg
Total weight of bars = (3064 x 9.47) + (3428 x 3.70) =
41699.7kg
𝑀𝐻
.017
𝑘𝑔
MD = 41699.7 x 8𝐻 = 88.6 MD
𝐷

No. of Laborers: 13
Duration = 88.6 / 13 = 6.81 days say, 7 days

5.5 Ground Tie Beam


No. of bars =1020 @ 16mm diameter
No. of bars = 362 @ 10mm diameter
Rate: .02MH/ kg
Total weight of bars = (1020 x 9.47) + (362 x 3.70) =
10998.8kg
𝑀𝐻
.02
𝑘𝑔
MD = 10998.8 x 8𝐻 = 27.5MD
𝐷

No. of Laborers: 10
Duration = 27.5 /10 = 2.75 days say, 3 days

5.6 Floor Beam


No. of bars = 1565 @ 20mm diameter
No. of bars = 2086 @ 16mm diameter
No. of bars = 2006 @ 10mm diameter
Rate: .012MH/ kg
Total weight of bars = (1565x14.82) + (2086 x 9.47) +
(2006 x 3.7) = 50369.92kg
𝑀𝐻
.012
𝑘𝑔
MD = 50369.92 8𝐻 = 75.55 MD
𝐷

No. of Laborers: 12
Duration = 75.55 / 12 = 6.29 days say, 7 days

Page | 105
5.7 Roof Beam
No. of bars = 1565 @ 20mm diameter
No. of bars = 1656 @ 16mm diameter
No. of bars = 553 @ 12mm diameter
No. of bars = 2283 @ 10mm diameter
Rate: .012MH/ kg
Total weight of bars = (1565x14.82) + (1656 x 9.47) + (553 x
5.34) + (2283 x 3.7) = 50275.74 kg
𝑀𝐻
.012
𝑘𝑔
MD = 50275.74 8𝐻 = 75.41 MD
𝐷

No. of Laborers: 12
Duration = 75.41 / 12 = 6.28 days say, 7 days

5.8 Ground Floor Slab


No. of bars = 3289 @ 10mm diameter
Rate: .02MH/ kg
Total weight of bars = (3289 x 3.70) = 12169.3kg
𝑀𝐻
.02
𝑘𝑔
MD = 12169.3 8𝐻 = 30.42 MD
𝐷

No. of Laborers: 7
Duration = 30.42 / 7 = 4.34 days say, 5 days

5.9 Second Floor Slab


No. of bars = 5948 @ 12mm diameter
Rate: .015MH/ kg
Total weight of bars = (5948 x 5.34) = 31762.32kg
𝑀𝐻
.015
𝑘𝑔
MD = 31762.32 8𝐻 = 59.55 MD
𝐷

No. of Laborers: 9
Duration = 59.55 / 9 = 6.61days say, 7 days

Page | 106
5.10 Roof Deck
No. of bars = 6213 @ 12mm diameter
Rate: .015MH/ kg
Total weight of bars = (6213 x 5.34) = 33177.4kg
.015𝑀𝐻
MD = 33177.4 8𝐻 = 62.2MD
𝐷

No. of Laborers: 9
Duration = 62.2 / 9 = 6.91 days say, 7 days

5.11 Stair Case


No. of bars = 408 @ 12mm diameter
Rate: .01MH/ kg
Total weight of bars = (408 x 5.34) = 2178.72kg
𝑀𝐻
.01
𝑘𝑔
MD = = 2178.72 8𝐻 = 2.7234 MD
𝐷

No. of Laborers: 2
Duration = 2.7234 / 2 = 1.36 days say, 2 days

5.12 Stair Footing


No. of bars = 60 @ 12mm diameter
Rate: .02MH/ kg
Total weight of bars = (60 x 5.34) = 320.4kg
𝑀𝐻
.02
𝑘𝑔
MD = 320.4 8𝐻 = .801 MD
𝐷

No. of Laborers: 1
Duration = .801 / 1 = .801 days say, 1 day

Page | 107
5.13 CHB Temperature Bars
No. of bars = 2094 @ 10mm diameter
Rate: .07MH/ kg
Total weight of bars = (2094 x 3.70) = 7747.8kg
𝑀𝐻
.07
𝑘𝑔
MD = 7747.8 8𝐻 = 67.8 MD
𝐷

No. of Laborers: 10
Duration = 67.8 / 10 = 6.78 days say, 7 days

6. Masonry Works
6.1 CHB Walls and Partition
Total Volume: 792𝑚3
𝑚3
Rate: 2 𝑚𝑒𝑛 = 30.50 𝑑𝑎𝑦
𝑚3
1 𝑚𝑎𝑛 = 15.25 𝑑𝑎𝑦
792m³ X 1M
MD = = 51.934MD
15.25m³/D

No. of Laborers: 4
51.934𝑀𝐷
Duration: = 12.984 𝑑𝑎𝑦𝑠
4𝑀

Duration: 13 days

6.2 Wall Plaster


Total Volume: 1,662𝑚3
𝑚3
Rate: 2 𝑚𝑒𝑛 = 37 𝑑𝑎𝑦
𝑚3
1 𝑚𝑎𝑛 = 18.50 𝑑𝑎𝑦
1,662m³ X 1M
MD = = 89.838MD
18.50m³/D

No. of Laborers: 6
89.838𝑀𝐷
Duration: = 14.973 𝑑𝑎𝑦𝑠
6𝑀

Duration: 15 days

Page | 108
6.3 Concrete Topping and Tile Work (Toilet)
Total Volume: 1,104𝑚3
𝑚3
Rate: 2 𝑚𝑒𝑛 = 86 𝑑𝑎𝑦
𝑚3
1 𝑚𝑎𝑛 = 43 𝑑𝑎𝑦
1,104m³ X 1M
MD = = 25.674MD
43m³/D

No. of Laborers: 2
25.674𝑀𝐷
Duration: = 12.837 𝑑𝑎𝑦𝑠
2𝑀

Duration: 13 days

7. Water Proofing for Toilet and Roof Deck Slab


𝑚2
Rate: 2 𝑚𝑒𝑛 = 15.2 𝑑𝑎𝑦

𝑚2
1 𝑚𝑎𝑛 = 7.6
𝑑𝑎𝑦
Total Area: 532𝑚2
532m2 X 1M
MD = = 70MD
7.6m2 /D

No. of Laborers: 7
70𝑀𝐷
Duration: = 10 𝑑𝑎𝑦𝑠
7𝑀

Duration: 10 days

8. Carpentry Works
8.1 Scaffolding
𝑏𝑑𝑓𝑡
𝑅𝑎𝑡𝑒 𝑜𝑓 1 𝑚𝑎𝑛 = 232
𝑑𝑎𝑦
Total Area: 18,520𝑏𝑑𝑓𝑡
18,520𝑏𝑑𝑓𝑡 X 1M
MD = 𝑏𝑑𝑓𝑡 = 79.828MD
232
𝑑𝑎𝑦

No. of Laborers: 5
79.828𝑀𝐷
Duration: = 15.966 𝑑𝑎𝑦𝑠
5𝑀

Duration: 16 days

Page | 109
8.2 Form Works
𝑏𝑑𝑓𝑡
𝑅𝑎𝑡𝑒 𝑜𝑓 1 𝑚𝑎𝑛 = 89
𝑑𝑎𝑦
Total Area: 6,948𝑏𝑑𝑓𝑡
6,948𝑏𝑑𝑓𝑡 X 1M
MD = 𝑏𝑑𝑓𝑡 = 78.067MD
89
𝑑𝑎𝑦

No. of Laborers: 5
78.067𝑀𝐷
Duration: = 15.613 𝑑𝑎𝑦𝑠
5𝑀

Duration: 16 days

8.3 Ceiling
𝑏𝑑𝑓𝑡
𝑅𝑎𝑡𝑒 𝑜𝑓 1 𝑚𝑎𝑛 = 12
𝑑𝑎𝑦
Total Area: 993.6𝑏𝑑𝑓𝑡
993.6𝑏𝑑𝑓𝑡 X 1M
MD = 𝑏𝑑𝑓𝑡 = 82.8MD
12
𝑑𝑎𝑦

No. of Laborers: 4
82.8𝑀𝐷
Duration: = 20.7 𝑑𝑎𝑦𝑠
4𝑀

Duration: 21 days

9. Doors and Windows


9.1 Doors
Rate: 2 men = 2.75 pcs/ day
No. of jambs: 21pcs
21𝑝𝑐𝑠
MD = 2.75𝑝𝑐𝑠 = 7.636 say 8 days for 2 men
𝑑𝑎𝑦

Duration: 8 days

9.2 Windows
Rate: 5 men = 2.10 pcs/ day
No. of jambs: 28pcs
28𝑝𝑐𝑠
MD = 2.10𝑝𝑐𝑠 = 13.33 say 14 days for 5 men
𝑑𝑎𝑦

Duration: 14 days

Page | 110
10. Wall Cladding
𝑚2
Rate: 2 𝑚𝑒𝑛 = 11 𝑑𝑎𝑦

𝑚2
1 𝑚𝑎𝑛 = 5.5
𝑑𝑎𝑦
Total Area: 146𝑚2
146m2 X 1M
MD = = 26.545MD
5.5m2 /D

No. of Laborers: 2
26.545𝑀𝐷
Duration: = 13.273 𝑑𝑎𝑦𝑠
2𝑀

Duration: 14 days

11. Painting Works


11.1 External Painting
𝑚2
Rate: 12.5𝑚𝑑

A = 342𝑚2
342𝑚2
MD = 𝑚2
= 27.36MD
12.5
𝑚𝑑

No. of Laborers: 4
27.36𝑚𝑑
Duration = = 6.84 days
4𝑚

Duration: 7 days

11.2 Internal Painting


𝑚2
Rate: 17𝑚𝑑

A = 432𝑚2
432𝑚2
MD = 𝑚2
= 25.412MD
17
𝑚𝑑

No. of Laborers: 4
25.412𝑚𝑑
Duration = = 6.353 days
4𝑚

Duration: 7 days

Page | 111
12. Plumbing Works
A = 1 lot (629m2)
Rate for 1 man: 29𝑚2
629𝑚2
MD = 𝑚2
= 21.690MD
29
𝑚𝑑

No. of Laborers: 2
21.690𝑚𝑑
Duration = = 10.845 days
2𝑚

Duration: 11 days

13. Electrical Works


A = 1 lot (629m2)
Rate for 1 man: 5.25𝑚2
629𝑚2
MD = 𝑚2
= 119.810MD
5.25
𝑚𝑑

No. of Laborers: 4
19.810𝑚𝑑
Duration = = 29.953 days
4𝑚

Duration: 30 days

14. Catch Basin


Length = 112 linear meter (lm)
Rate for 1 man: 8.5𝑙𝑚
112𝑚2
MD = 𝑚2
= 13.176MD
8.5
𝑚𝑑

No. of Laborers: 2
13.176𝑚𝑑
Duration = = 6.588 days
2𝑚

Duration: 7 days

Page | 112
15. Steel Works
𝑀𝐻
Rate: 0.12 𝑘𝑔

Weight of bars: 1414pcs x 3.7 kg = 5231.8kg


𝑀𝐻
0.12
𝑘𝑔
MD =5231.8𝑘𝑔 × = 78.477𝑀𝐷
8𝐻

No. of Laborers: 8
78.477𝑀𝐷
Duration: = 9.810 𝑑𝑎𝑦𝑠
8𝑀

Duration: 10 days

16. Move Out


No. of Laborers: 0
Duration: 7 days

Page | 113