Professional Documents
Culture Documents
14 Computation of Duration Per Activity
14 Computation of Duration Per Activity
14 Computation of Duration Per Activity
1. Move In
No. of Laborers: 0
Duration: 7 days
3. Earthworks
3.1 Clearing and Grubbing
𝑀𝐻
Rate: 0.25 𝑚3
No. of Laborers: 5
104.938𝑀𝐷
Duration = = 2.988 𝑑𝑎𝑦𝑠
5𝑀
Duration: 3 days
No. of Laborers: 15
104.72𝑀𝐷
Duration = = 6.981 𝑑𝑎𝑦𝑠
15𝑀
Duration: 7 days
Page | 97
3.3 Backfilling and Compaction
𝑚3
Rate: 4.15 ℎ𝑟
No. of Laborers: 15
63.102𝑀𝐷
Duration = = 4.207 𝑑𝑎𝑦𝑠
15𝑀
Duration: 5 days
No. of Laborers: 2
0.25𝑀𝐷
Duration = = 0.123 𝑑𝑎𝑦𝑠
2𝑀
Duration: 1 day
No. of Laborers: 10
20𝑀𝐷
Duration = = 2 𝑑𝑎𝑦𝑠
10𝑀
Duration: 2 days
Page | 98
3.6 Embankment/ Earth Fill
𝑚3
Rate: 3.60 ℎ𝑟
No. of Laborers: 10
19.931𝑀𝐷
Duration = = 1.993 𝑑𝑎𝑦𝑠
10𝑀
Duration: 2 days
4. Concrete Works
4.1 Concrete Footing
Total Volume: 83𝑚3
𝑚3
Rate: 2 𝑚𝑒𝑛 = 1.60 𝑑𝑎𝑦
𝑚3
1 𝑚𝑎𝑛 = 0.80 𝑑𝑎𝑦
83 m³ X 1M
MD = = 103.75MD
0.8m³/D
No. of Laborers: 15
103.75𝑀𝐷
Duration: = 6.917𝑑𝑎𝑦𝑠
15𝑀
Duration: 7 days
No. of Laborers: 5
12.5𝑀𝐷
Duration: = 2.5 𝑑𝑎𝑦𝑠
5𝑀
Duration: 3 days
Page | 99
4.3 Ground Floor Column
Total Volume: 26𝑚3
𝑚3
Rate: 2 𝑚𝑒𝑛 = 1.10 𝑑𝑎𝑦
𝑚3
1 𝑚𝑎𝑛 = 0.55 𝑑𝑎𝑦
26 m³ X 1M
MD = = 47.273MD
0.55m³/D
No. of Laborers: 8
47.273𝑀𝐷
Duration: = 5.909 𝑑𝑎𝑦𝑠
8𝑀
Duration: 6 days
No. of Laborers: 8
47.273𝑀𝐷
Duration: = 5.909 𝑑𝑎𝑦𝑠
8𝑀
Duration: 6 days
No. of Laborers: 4
7.692𝑀𝐷
Duration: = 1.923 𝑑𝑎𝑦𝑠
4𝑀
Duration: 2 days
Page | 100
4.6 Ground Tie Beam
Total Volume: 10𝑚3
𝑚3
Rate: 2 𝑚𝑒𝑛 = 1.30 𝑑𝑎𝑦
𝑚3
1 𝑚𝑎𝑛 = 0.65 𝑑𝑎𝑦
10m3 X 1M
MD = 0.65m3
= 15.385MD
D
No. of Laborers: 6
15.385𝑀𝐷
Duration: = 2.564 𝑑𝑎𝑦𝑠
6𝑀
Duration: 3 days
No. of Laborers: 10
58.182𝑀𝐷
Duration: = 5.818 𝑑𝑎𝑦𝑠
10𝑀
Duration: 6 days
32m³ X 1M
MD = = 58.182MD
0.55m³/D
No. of Laborers: 10
58.182𝑀𝐷
Duration: = 5.818 𝑑𝑎𝑦𝑠
10𝑀
Duration: 6 days
Page | 101
4.9 Ground Floor Slab
Total Volume: 72𝑚3
𝑚3
Rate: 2 𝑚𝑒𝑛 = 1.80 𝑑𝑎𝑦
𝑚3
1 𝑚𝑎𝑛 = 0.90 𝑑𝑎𝑦
72m³ X 1M
MD = = 80MD
0.90m³/D
No. of Laborers: 12
80𝑀𝐷
Duration: = 6.667 𝑑𝑎𝑦𝑠
12𝑀
Duration: 7 days
No. of Laborers: 12
82.222𝑀𝐷
Duration: = 6.852 𝑑𝑎𝑦𝑠
12𝑀
Duration: 7 days
No. of Laborers: 12
79.167𝑀𝐷
Duration: = 6.597 𝑑𝑎𝑦𝑠
12𝑀
Duration: 7 days
Page | 102
4.12 Stair Case
Total Volume: 3𝑚3
𝑚3
Rate: 2 𝑚𝑒𝑛 = 1.60 𝑑𝑎𝑦
𝑚3
1 𝑚𝑎𝑛 = 0.80 𝑑𝑎𝑦
3m³ X 1M
MD = = 3.75MD
0.80m³/D
No. of Laborers: 4
3.75𝑀𝐷
Duration: = 0.9375 𝑑𝑎𝑦
4𝑀
Duration: 1 day
No. of Laborers: 2
1.667𝑀𝐷
Duration: = 0.833 𝑑𝑎𝑦
2𝑀
Duration: 1 day
No. of Laborers: 3
5.556𝑀𝐷
Duration: = 1.852 𝑑𝑎𝑦𝑠
3𝑀
Duration: 2 days
Page | 103
5. Reinforcement Bars
5.1 Concrete Footing
No. of bars = 5641pcs @16mm diameter
Rate: .015MH/ kg
Total weight of bars = 5641 x 9.47 = 53240.27kg
𝑀𝐻
.015
𝑘𝑔
MD = 53240.27x 8𝐻 = 79.86 MD
𝐷
No. of Laborers: 12
Duration = 79.86 / 12 = 6.655 days say, 7 days
No. of Laborers: 6
Duration = 40.57 / 12 = 6.76 days say, 7 days
No. of Laborers: 17
Duration = 104.44 / 6 = 6.14 days say, 7 days
Page | 104
5.4 Second Floor Column
No. of bars =3064 @ 16mm diameter
No. of bars = 3428@ 10mm diameter
Rate: .017MH/ kg
Total weight of bars = (3064 x 9.47) + (3428 x 3.70) =
41699.7kg
𝑀𝐻
.017
𝑘𝑔
MD = 41699.7 x 8𝐻 = 88.6 MD
𝐷
No. of Laborers: 13
Duration = 88.6 / 13 = 6.81 days say, 7 days
No. of Laborers: 10
Duration = 27.5 /10 = 2.75 days say, 3 days
No. of Laborers: 12
Duration = 75.55 / 12 = 6.29 days say, 7 days
Page | 105
5.7 Roof Beam
No. of bars = 1565 @ 20mm diameter
No. of bars = 1656 @ 16mm diameter
No. of bars = 553 @ 12mm diameter
No. of bars = 2283 @ 10mm diameter
Rate: .012MH/ kg
Total weight of bars = (1565x14.82) + (1656 x 9.47) + (553 x
5.34) + (2283 x 3.7) = 50275.74 kg
𝑀𝐻
.012
𝑘𝑔
MD = 50275.74 8𝐻 = 75.41 MD
𝐷
No. of Laborers: 12
Duration = 75.41 / 12 = 6.28 days say, 7 days
No. of Laborers: 7
Duration = 30.42 / 7 = 4.34 days say, 5 days
No. of Laborers: 9
Duration = 59.55 / 9 = 6.61days say, 7 days
Page | 106
5.10 Roof Deck
No. of bars = 6213 @ 12mm diameter
Rate: .015MH/ kg
Total weight of bars = (6213 x 5.34) = 33177.4kg
.015𝑀𝐻
MD = 33177.4 8𝐻 = 62.2MD
𝐷
No. of Laborers: 9
Duration = 62.2 / 9 = 6.91 days say, 7 days
No. of Laborers: 2
Duration = 2.7234 / 2 = 1.36 days say, 2 days
No. of Laborers: 1
Duration = .801 / 1 = .801 days say, 1 day
Page | 107
5.13 CHB Temperature Bars
No. of bars = 2094 @ 10mm diameter
Rate: .07MH/ kg
Total weight of bars = (2094 x 3.70) = 7747.8kg
𝑀𝐻
.07
𝑘𝑔
MD = 7747.8 8𝐻 = 67.8 MD
𝐷
No. of Laborers: 10
Duration = 67.8 / 10 = 6.78 days say, 7 days
6. Masonry Works
6.1 CHB Walls and Partition
Total Volume: 792𝑚3
𝑚3
Rate: 2 𝑚𝑒𝑛 = 30.50 𝑑𝑎𝑦
𝑚3
1 𝑚𝑎𝑛 = 15.25 𝑑𝑎𝑦
792m³ X 1M
MD = = 51.934MD
15.25m³/D
No. of Laborers: 4
51.934𝑀𝐷
Duration: = 12.984 𝑑𝑎𝑦𝑠
4𝑀
Duration: 13 days
No. of Laborers: 6
89.838𝑀𝐷
Duration: = 14.973 𝑑𝑎𝑦𝑠
6𝑀
Duration: 15 days
Page | 108
6.3 Concrete Topping and Tile Work (Toilet)
Total Volume: 1,104𝑚3
𝑚3
Rate: 2 𝑚𝑒𝑛 = 86 𝑑𝑎𝑦
𝑚3
1 𝑚𝑎𝑛 = 43 𝑑𝑎𝑦
1,104m³ X 1M
MD = = 25.674MD
43m³/D
No. of Laborers: 2
25.674𝑀𝐷
Duration: = 12.837 𝑑𝑎𝑦𝑠
2𝑀
Duration: 13 days
𝑚2
1 𝑚𝑎𝑛 = 7.6
𝑑𝑎𝑦
Total Area: 532𝑚2
532m2 X 1M
MD = = 70MD
7.6m2 /D
No. of Laborers: 7
70𝑀𝐷
Duration: = 10 𝑑𝑎𝑦𝑠
7𝑀
Duration: 10 days
8. Carpentry Works
8.1 Scaffolding
𝑏𝑑𝑓𝑡
𝑅𝑎𝑡𝑒 𝑜𝑓 1 𝑚𝑎𝑛 = 232
𝑑𝑎𝑦
Total Area: 18,520𝑏𝑑𝑓𝑡
18,520𝑏𝑑𝑓𝑡 X 1M
MD = 𝑏𝑑𝑓𝑡 = 79.828MD
232
𝑑𝑎𝑦
No. of Laborers: 5
79.828𝑀𝐷
Duration: = 15.966 𝑑𝑎𝑦𝑠
5𝑀
Duration: 16 days
Page | 109
8.2 Form Works
𝑏𝑑𝑓𝑡
𝑅𝑎𝑡𝑒 𝑜𝑓 1 𝑚𝑎𝑛 = 89
𝑑𝑎𝑦
Total Area: 6,948𝑏𝑑𝑓𝑡
6,948𝑏𝑑𝑓𝑡 X 1M
MD = 𝑏𝑑𝑓𝑡 = 78.067MD
89
𝑑𝑎𝑦
No. of Laborers: 5
78.067𝑀𝐷
Duration: = 15.613 𝑑𝑎𝑦𝑠
5𝑀
Duration: 16 days
8.3 Ceiling
𝑏𝑑𝑓𝑡
𝑅𝑎𝑡𝑒 𝑜𝑓 1 𝑚𝑎𝑛 = 12
𝑑𝑎𝑦
Total Area: 993.6𝑏𝑑𝑓𝑡
993.6𝑏𝑑𝑓𝑡 X 1M
MD = 𝑏𝑑𝑓𝑡 = 82.8MD
12
𝑑𝑎𝑦
No. of Laborers: 4
82.8𝑀𝐷
Duration: = 20.7 𝑑𝑎𝑦𝑠
4𝑀
Duration: 21 days
Duration: 8 days
9.2 Windows
Rate: 5 men = 2.10 pcs/ day
No. of jambs: 28pcs
28𝑝𝑐𝑠
MD = 2.10𝑝𝑐𝑠 = 13.33 say 14 days for 5 men
𝑑𝑎𝑦
Duration: 14 days
Page | 110
10. Wall Cladding
𝑚2
Rate: 2 𝑚𝑒𝑛 = 11 𝑑𝑎𝑦
𝑚2
1 𝑚𝑎𝑛 = 5.5
𝑑𝑎𝑦
Total Area: 146𝑚2
146m2 X 1M
MD = = 26.545MD
5.5m2 /D
No. of Laborers: 2
26.545𝑀𝐷
Duration: = 13.273 𝑑𝑎𝑦𝑠
2𝑀
Duration: 14 days
A = 342𝑚2
342𝑚2
MD = 𝑚2
= 27.36MD
12.5
𝑚𝑑
No. of Laborers: 4
27.36𝑚𝑑
Duration = = 6.84 days
4𝑚
Duration: 7 days
A = 432𝑚2
432𝑚2
MD = 𝑚2
= 25.412MD
17
𝑚𝑑
No. of Laborers: 4
25.412𝑚𝑑
Duration = = 6.353 days
4𝑚
Duration: 7 days
Page | 111
12. Plumbing Works
A = 1 lot (629m2)
Rate for 1 man: 29𝑚2
629𝑚2
MD = 𝑚2
= 21.690MD
29
𝑚𝑑
No. of Laborers: 2
21.690𝑚𝑑
Duration = = 10.845 days
2𝑚
Duration: 11 days
No. of Laborers: 4
19.810𝑚𝑑
Duration = = 29.953 days
4𝑚
Duration: 30 days
No. of Laborers: 2
13.176𝑚𝑑
Duration = = 6.588 days
2𝑚
Duration: 7 days
Page | 112
15. Steel Works
𝑀𝐻
Rate: 0.12 𝑘𝑔
No. of Laborers: 8
78.477𝑀𝐷
Duration: = 9.810 𝑑𝑎𝑦𝑠
8𝑀
Duration: 10 days
Page | 113