ROCK IRRIGATION WEIR

Project: xyz
Profile View
Top of Channel Bank Elev = 60.0 MSL

Top of Riprap Elev. = 57 MSL


Ft. Downstream Channel Bottom
Riprap Length = 47
Transition Length
Upstream Channel
Bottom Transition 13.0 Ft.
25 Ft. 268.0 Ft.
50 Ft. 10 Ft. 6.0 Ft. 0.5 Ft.
100 Ft. Weir Elevation = 55.0 MSL

2.0 Ft.

3.0 : 1 Chute Slope


3 : 1 Upstream Slope
Keyway Riprap Thickness = 2.25 Ft.
Weir Ht. = 5.0 Ft.

Compacted Earth Fill


15 Ft.

Nonwoven geotextile over Keyway


3 inches of Concrete Sand

Top of Bank

3 : 1 Side Slope

1
Weir 8
3.0 : 1 Slope Width
3 : 1 Slope
Entrance 87 Ft.
Channel
Flow Width Flow
Centerline of the Channel

57.0 Ft.

8