Practical 3.

1:
Resource Management

Resources include the people and equipment needed to


complete the tasks in a project. There are two aspects of
resources:-
their availability and their costs.

Setting up People Resources

Project works with three types of resources: work, material, and


cost resources. Work resources are the people and equipment
that do the work of the project.

1. On the View menu, click Resource Sheet


2. In the Resource Sheet view, click the cell directly below
the Resource Name column heading.
3. Type any employee name, press Enter
4. Project creates a new Resource
5. Type the fields such as type,Max. Units field and press
Enter
6. In Project, you set up people and equipment resources in
exactly the same way because people and equipment are
both examples of work resources.