J048 - CADANGAN MEMBINA KEMUDAHAN PENGURUSAN ENAPCEMAR DI LRA PALONG TIMUR, SEGAMAT, JOHOR.

PAKEJ 1 - CADANGAN MEMBINA, MENYIAP DAN MENTAULIAH KEMUDAHAN PENGURUSAN ENAPCEMAR, BANGUNAN POLIMER DAN PELANTAR
GEOTUBE SERTA KERJA-KERJA BERKAITAN.

ACTIVITIES SCHEDULED TO START BY MID-APRIL 2018

NO TEAM ACTIVITY ORIGINAL RESCHEDULE REASON OF RESCHEDULING


DATE DATE

1 Last concreting works for WWCT & SBT 12/4/2018 18/4/2018 replacement of site team

2 Full completion of WWCT & SBT 16/4/2018 21/4/2018 replacement of site team

3 Partial backfilling works 17/4/2018 22/4/2018 activities for WWCT & SBT not yet done

4 Repair of cold joints & honeycomb 13/4/2018 19/4/2018 activities for WWCT & SBT not yet done

5 Pipeworks - installation of pipes (300mm & 200mm) from 15/4/2018 17/4/2018 poor planning - no log pipes & marking on-
sedimentation tank to WWCT & SBT site were prepared

6 Construction of Geotube Platform 20/4/2018 23/4/2018 partial backfilling works not yet done

7 Repair of damaged Flowmeter 15/4/2018 ? supplier problem

8 Construction of Polymer Building ? ? partial backfilling works not yet done

9 Installation of Submersible Sludge Pump at Existing ? ?


upon completion of pipeworks
Sedimentation Tank