SUMMARY OF PROJECTION OF WORK PROGRESS FOR APRIL & MAY 2018

AS AT AS AT AS AT
NO DESCRIPTION
14.04.2018 30.04.2018 31.05.2018
PROJECTION OF WORK PROGRESS FOR APRIL & MAY 2018 BASED ON ORIGINAL MIP (REV.00 - NO EOT)
1 SCHEDULE % COMPLETE 88.62% 95.82% 99.90%
2 ACTUAL % COMPLETE 44.15% 52.34% 82.30%
3 CURRENT % DELAY -44.47% -43.48% -17.60%
PROJECTION OF WORK PROGRESS FOR APRIL & MAY 2018 BASED ON REVISED MIP (REV.01 - 1 MONTH EOT)
1 SCHEDULE % COMPLETE 66.91% 76.79% 94.28%
2 ACTUAL % COMPLETE 48.05% 57.09% 86.75%
3 CURRENT % DELAY -18.86% -19.70% -7.53%