Longest Path in Revised Schedule

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

STF PALONG TIMUR REV.

04 ALL NON-RUN Classic Schedule Layout 16-Apr-18 05:04 PM


Activity ID Activity Name Original Remaining Total Start Finish October 2017 November 2017 December 2017 January 2018 February 2018 March 2018 April 2018 May 2018 June 2018 July 2018 August 2018
Duration Duration Float 05
01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 04 11 18 25 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29
268.6d 268.6d 3.4d 02-Oct-17 08:00 AM 27-Jun-18 01:00 27-Jun-18 01:00 PM, STF PALONG TIMUR REV.04 ALL NON-RUN
STF PALONG TIMUR REV.04 ALL NON-RUN
PM
225.5d 225.5d 2.5d 02-Oct-17 08:00 AM 27-Jun-18 01:00 PM 27-Jun-18 01:00 PM, Milestone
Milestone
STF1000 Milestone Start STF 0.0d 0.0d 3.0d 02-Oct-17 08:00 AM* 02-Oct-17 08:00 AM
STF1010 Milestone Finish STF 0.0d 0.0d 2.5d 27-Jun-18 01:00 PM* 27-Jun-18 01:00 PM
32.0d 32.0d 3.0d 02-Oct-17 08:00 AM 07-Nov-17 05:00 PM 07-Nov-17 05:00 PM, General & Preliminaries
General & Preliminaries
Documentation 32.0d 32.0d 3.0d 02-Oct-17 08:00 AM 07-Nov-17 05:00 PM 07-Nov-17 05:00 PM, Documentation

Preparation & Submission 32.0d 32.0d 3.0d 02-Oct-17 08:00 AM 07-Nov-17 05:00 PM 07-Nov-17 05:00 PM, Preparation & Submission
STF1020 Preparation of Performance Bond 14.0d 14.0d 3.0d 02-Oct-17 08:00 AM 17-Oct-17 05:00 PM
STF1030 Preparation of Insurances Policies / Public Liability / Workmen's Compensation
14.0d 14.0d 3.0d 02-Oct-17 08:00 AM 17-Oct-17 05:00 PM
STF1040 Preparation & Submission of Levy of CIDB 14.0d 14.0d 3.0d 02-Oct-17 08:00 AM 17-Oct-17 05:00 PM
STF1050 Site Registration of JKKP (DOSH) 14.0d 14.0d 3.0d 02-Oct-17 08:00 AM 17-Oct-17 05:00 PM
STF1060 Submission Copy of SPAN Certificate 14.0d 14.0d 3.0d 02-Oct-17 08:00 AM 17-Oct-17 05:00 PM
STF1070 Preparation & Submission of Lithography Expenses 14.0d 14.0d 3.0d 02-Oct-17 08:00 AM 17-Oct-17 05:00 PM
STF1080 Preparation & Submission of PQP / Method Statements 14.0d 14.0d 3.0d 02-Oct-17 08:00 AM 17-Oct-17 05:00 PM
STF1090 Preparation of Works (Contractor Requirements) 18.0d 18.0d 3.0d 18-Oct-17 08:00 AM 07-Nov-17 05:00 PM
STF1100 Preparation of Works (Engineers / S.O / PD's Requirements) 18.0d 18.0d 3.0d 18-Oct-17 08:00 AM 07-Nov-17 05:00 PM
STF1110 Preparation of Works (General Obligation, Project Requirements) 18.0d 18.0d 3.0d 18-Oct-17 08:00 AM 07-Nov-17 05:00 PM
STF1120 Preparation of Works (Authorities Requirements) 18.0d 18.0d 3.0d 18-Oct-17 08:00 AM 07-Nov-17 05:00 PM
STF1130 Preparation of Works (Environmental Protection & Enhancement)18.0d 18.0d 3.0d 18-Oct-17 08:00 AM 07-Nov-17 05:00 PM
177.9d 177.9d 3.1d 11-Dec-17 08:00 AM 06-Jun-18 03:00 PM 06-Jun-18 03:00 PM, Civil & Structures
Civil & Structures
Underground Tank & Building 177.9d 177.9d 3.1d 11-Dec-17 08:00 AM 06-Jun-18 03:00 PM 06-Jun-18 03:00 PM, Underground Tank & Building

Wash Water Collection & Sludge Balancing Tank 137.0d 137.0d 3.0d 11-Dec-17 08:00 AM 26-Apr-18 05:00 PM 26-Apr-18 05:00 PM, Wash Water Collection & Sludge Balancing Tank

Site Measurement & Site Preparation 55.0d 55.0d 3.0d 11-Dec-17 08:00 AM 03-Feb-18 05:00 PM 03-Feb-18 05:00 PM, Site Measurement & Site Preparation
STF1140 Site survey 11.0d 11.0d 3.0d 11-Dec-17 08:00 AM* 21-Dec-17 05:00 PM
STF1150 Site clearance 14.0d 14.0d 3.0d 22-Dec-17 08:00 AM* 04-Jan-18 05:00 PM
STF1160 Excavation, levelling & compaction works 26.0d 26.0d 3.0d 05-Jan-18 08:00 AM* 30-Jan-18 05:00 PM
STF1170 Install formwork 3.0d 3.0d 3.0d 31-Jan-18 08:00 AM* 02-Feb-18 05:00 PM
STF1180 Lay of 75mm thick lean concrete 1.0d 1.0d 3.0d 03-Feb-18 08:00 AM* 03-Feb-18 05:00 PM
Slab for All excluding Drywells 19.0d 19.0d 3.0d 04-Feb-18 08:00 AM 22-Feb-18 05:00 PM 22-Feb-18 05:00 PM, Slab for All excluding Drywells
STF1190 Erect formwork, install reinforcement, kicker & waterstop 15.0d 15.0d 3.0d 04-Feb-18 08:00 AM* 18-Feb-18 05:00 PM
STF1200 Inspection 1.0d 1.0d 3.0d 19-Feb-18 08:00 AM* 19-Feb-18 05:00 PM
STF1210 Concreting & curing works 2.0d 2.0d 3.0d 20-Feb-18 08:00 AM* 21-Feb-18 05:00 PM
STF1220 Dismantle formwork 1.0d 1.0d 3.0d 22-Feb-18 08:00 AM* 22-Feb-18 05:00 PM
Slab for Drywells 9.0d 9.0d 3.0d 23-Feb-18 08:00 AM 03-Mar-18 05:00 PM 03-Mar-18 05:00 PM, Slab for Drywells
STF1230 To excavate, level & compact 1.0d 1.0d 3.0d 23-Feb-18 08:00 AM* 23-Feb-18 05:00 PM
STF1240 Lay of 75mm thick lean concrete 1.0d 1.0d 3.0d 24-Feb-18 08:00 AM* 24-Feb-18 05:00 PM
STF1250 Erect formwork, install reinforcement, kicker & waterstop 3.0d 3.0d 3.0d 25-Feb-18 08:00 AM* 27-Feb-18 05:00 PM
STF1260 Inspection 1.0d 1.0d 3.0d 28-Feb-18 08:00 AM* 28-Feb-18 05:00 PM
STF1270 Concreting & curing works 2.0d 2.0d 3.0d 01-Mar-18 08:00 AM* 02-Mar-18 05:00 PM
STF1280 Dismantle formwork 1.0d 1.0d 3.0d 03-Mar-18 08:00 AM* 03-Mar-18 05:00 PM
Wall '1' - 1st Lift (1.5m) 11.0d 11.0d 3.0d 04-Mar-18 08:00 AM 14-Mar-18 05:00 PM 14-Mar-18 05:00 PM, Wall '1' - 1st Lift (1.5m)
STF1290 Erect scaffold & stagging 1.0d 1.0d 3.0d 04-Mar-18 08:00 AM* 04-Mar-18 05:00 PM
STF1300 Erect formwork, install reinforcement, kicker & waterstop 4.0d 4.0d 3.0d 05-Mar-18 08:00 AM* 08-Mar-18 05:00 PM
STF1310 Inspection 1.0d 1.0d 3.0d 09-Mar-18 08:00 AM* 09-Mar-18 05:00 PM
STF1320 Concreting works 1.0d 1.0d 3.0d 10-Mar-18 08:00 AM* 10-Mar-18 05:00 PM
STF1330 Curing works 3.0d 3.0d 3.0d 11-Mar-18 08:00 AM* 13-Mar-18 05:00 PM
STF1340 Dismantle formwork, scaffold & stagging 1.0d 1.0d 3.0d 14-Mar-18 08:00 AM* 14-Mar-18 05:00 PM
Wall '2' - 1st Lift (1.5m & 2.4m) 13.0d 13.0d 3.0d 15-Mar-18 08:00 AM 27-Mar-18 05:00 PM 27-Mar-18 05:00 PM, Wall '2' - 1st Lift (1.5m & 2.4m)
STF1350 Erect scaffold & stagging 1.0d 1.0d 3.0d 15-Mar-18 08:00 AM* 15-Mar-18 05:00 PM
STF1360 Erect formwork, install reinforcement, kicker & waterstop 4.0d 4.0d 3.0d 16-Mar-18 08:00 AM* 19-Mar-18 05:00 PM
STF1370 Install 4 units of 100mm dia. Pipes 2.0d 2.0d 3.0d 20-Mar-18 08:00 AM* 21-Mar-18 05:00 PM
STF1380 Inspection 1.0d 1.0d 3.0d 22-Mar-18 08:00 AM* 22-Mar-18 05:00 PM
STF1390 Concreting works 1.0d 1.0d 3.0d 23-Mar-18 08:00 AM* 23-Mar-18 05:00 PM
STF1400 Curing works 3.0d 3.0d 3.0d 24-Mar-18 08:00 AM* 26-Mar-18 05:00 PM
STF1410 Dismantle formwork, scaffold & stagging 1.0d 1.0d 3.0d 27-Mar-18 08:00 AM* 27-Mar-18 05:00 PM
Wall '1' - 2nd Lift (2.1m) 12.0d 12.0d 3.0d 28-Mar-18 08:00 AM 08-Apr-18 05:00 PM 08-Apr-18 05:00 PM, Wall '1' - 2nd Lift (2.1m)
STF1420 Erect scaffold & stagging 1.0d 1.0d 3.0d 28-Mar-18 08:00 AM* 28-Mar-18 05:00 PM
STF1430 Erect formwork, install reinforcement 4.0d 4.0d 3.0d 29-Mar-18 08:00 AM* 01-Apr-18 05:00 PM
STF1440 Install 2 units of 300mm dia. of pipes (level - 22.50) 1.0d 1.0d 3.0d 02-Apr-18 08:00 AM* 02-Apr-18 05:00 PM
STF1450 Inspection 1.0d 1.0d 3.0d 03-Apr-18 08:00 AM* 03-Apr-18 05:00 PM
STF1460 Concreting works 1.0d 1.0d 3.0d 04-Apr-18 08:00 AM* 04-Apr-18 05:00 PM
STF1470 Curing works 3.0d 3.0d 3.0d 05-Apr-18 08:00 AM* 07-Apr-18 05:00 PM
STF1480 Dismantle formwork, scaffold & stagging 1.0d 1.0d 3.0d 08-Apr-18 08:00 AM* 08-Apr-18 05:00 PM
Wall '2' - 2nd Lift (2.1m, 1.45m, 2.15m) 12.0d 12.0d 3.0d 09-Apr-18 08:00 AM 20-Apr-18 05:00 PM 20-Apr-18 05:00 PM, Wall '2' - 2nd Lift (2.1m, 1.45m, 2.15m)
STF1490 Erect scaffold & stagging 1.0d 1.0d 3.0d 09-Apr-18 08:00 AM* 09-Apr-18 05:00 PM
STF1500 Erect formwork, install reinforcement 5.0d 5.0d 3.0d 10-Apr-18 08:00 AM* 14-Apr-18 05:00 PM
STF1510 Inspection 1.0d 1.0d 3.0d 15-Apr-18 08:00 AM* 15-Apr-18 05:00 PM
STF1520 Concreting works 1.0d 1.0d 3.0d 16-Apr-18 08:00 AM* 16-Apr-18 05:00 PM
STF1530 Curing works 3.0d 3.0d 3.0d 17-Apr-18 08:00 AM* 19-Apr-18 05:00 PM
STF1540 Dismantle formwork, scaffold & stagging 1.0d 1.0d 3.0d 20-Apr-18 08:00 AM* 20-Apr-18 05:00 PM
Cantilever Beam, Walkway Slab & Overflow Slab/Wall 12.0d 12.0d 3.0d 09-Apr-18 08:00 AM 20-Apr-18 05:00 PM 20-Apr-18 05:00 PM, Cantilever Beam, Walkway Slab & Overflow Slab/Wall
STF1550 Erect scaffold & stagging 1.0d 1.0d 3.0d 09-Apr-18 08:00 AM* 09-Apr-18 05:00 PM
STF1560 Erect & install formwork, t-props, soffit and reinforcement 4.0d 4.0d 3.0d 10-Apr-18 08:00 AM* 13-Apr-18 05:00 PM
STF1570 Install 2 units of 200mm dia. of pipes at Overflow Wall A & C 1.0d 1.0d 3.0d 14-Apr-18 08:00 AM* 14-Apr-18 05:00 PM
STF1580 Inspection 1.0d 1.0d 3.0d 15-Apr-18 08:00 AM* 15-Apr-18 05:00 PM
STF1590 Concreting works 1.0d 1.0d 3.0d 16-Apr-18 08:00 AM* 16-Apr-18 05:00 PM
STF1600 Curing works 3.0d 3.0d 3.0d 17-Apr-18 08:00 AM* 19-Apr-18 05:00 PM
STF1610 Dismantle formwork, t-props, soffit, scaffold & stagging 1.0d 1.0d 3.0d 20-Apr-18 08:00 AM* 20-Apr-18 05:00 PM
Partial Backfilling (Drywells Area) 6.0d 6.0d 3.0d 21-Apr-18 08:00 AM 26-Apr-18 05:00 PM 26-Apr-18 05:00 PM, Partial Backfilling (Drywells Area)
STF1620 Repair of cold joints & honeycomb at affected area 1.0d 1.0d 3.0d 21-Apr-18 08:00 AM* 21-Apr-18 05:00 PM
STF1630 Partial backfilling & compaction (1st stage) 1.0d 1.0d 3.0d 22-Apr-18 08:00 AM* 22-Apr-18 05:00 PM
STF1640 Reinstate existing sump 2.0d 2.0d 3.0d 23-Apr-18 08:00 AM* 24-Apr-18 05:00 PM
STF1650 Reinstate existing sewer pipes 1.0d 1.0d 3.0d 25-Apr-18 08:00 AM* 25-Apr-18 05:00 PM
STF1660 Partial backfilling & compaction (2nd stage) 1.0d 1.0d 3.0d 26-Apr-18 08:00 AM* 26-Apr-18 05:00 PM
Repair of Cold Joints, Waterproofing & Painting 0.0d 0.0d 0.0d
Water Tighness Testing & Backfilling 0.0d 0.0d 0.0d
Dewatering Platform (Geotube) 0.0d 0.0d 0.0d
Excavation Works & Hardcore 0.0d 0.0d 0.0d
Drain (Base) 0.0d 0.0d 0.0d
Drain (Wall - 2 sides) 0.0d 0.0d 0.0d
Ground Slab 0.0d 0.0d 0.0d
Ramp 0.0d 0.0d 0.0d
Geotube 0.0d 0.0d 0.0d
Polymer Building 40.9d 40.9d 3.1d 27-Apr-18 08:00 AM 06-Jun-18 03:00 PM 06-Jun-18 03:00 PM, Polymer Building

Footing (1m x 1m - 0.3m Thk) & Stump (0.3m x 0.3m - 0.45m Thk) 9.0d 9.0d 3.0d 27-Apr-18 08:00 AM 05-May-18 05:00 PM 05-May-18 05:00 PM, Footing (1m x 1m - 0.3m Thk) & Stump (0.3m x 0.3m - 0.45m Thk)
STF2060 To excavate, level & compact ground to receive foundation 1.0d 1.0d 3.0d 27-Apr-18 08:00 AM* 27-Apr-18 05:00 PM
STF2070 Install formwork, lay of 50mm thick lean concrete 1.0d 1.0d 3.0d 28-Apr-18 08:00 AM* 28-Apr-18 05:00 PM
STF2080 Erect formwork & install reinforcement 3.0d 3.0d 4.5d 28-Apr-18 07:00 PM* 30-Apr-18 05:00 PM
STF2090 Inspection 1.0d 1.0d 3.0d 30-Apr-18 08:00 AM* 30-Apr-18 05:00 PM
STF2100 Concreting works 1.0d 1.0d 3.0d 01-May-18 08:00 AM* 01-May-18 05:00 PM
STF2110 Curing works 2.0d 2.0d 3.0d 02-May-18 08:00 AM* 03-May-18 05:00 PM
STF2120 Dismantle formwork 1.0d 1.0d 3.0d 04-May-18 08:00 AM* 04-May-18 05:00 PM
STF2130 Backfilling & compaction works to the level of top stump 1.0d 1.0d 3.0d 05-May-18 08:00 AM* 05-May-18 05:00 PM
Ground Beam (0.3m x 0.6m) & Ground Slab (0.2m Thk) 10.0d 10.0d 3.0d 06-May-18 08:00 AM 15-May-18 05:00 PM 15-May-18 05:00 PM, Ground Beam (0.3m x 0.6m) & Ground Slab (0.2m Thk)
STF2140 Erect formwork surround the outer of stump 1.0d 1.0d 3.0d 06-May-18 08:00 AM* 06-May-18 05:00 PM
STF2150 Backfilling & compaction works to the level of bottom slab 2.0d 2.0d 3.0d 07-May-18 08:00 AM* 08-May-18 05:00 PM
STF2160 Install formwork, lay of 50mm thick lean concrete 1.0d 1.0d 3.0d 09-May-18 08:00 AM* 09-May-18 05:00 PM
STF2170 Install reinforcement both ground beam & slab 3.0d 3.0d 4.4d 09-May-18 07:00 PM* 11-May-18 08:00 PM
STF2180 Inspection 1.0d 1.0d 3.0d 11-May-18 08:00 AM* 12-May-18 08:00 AM
STF2190 Concreting works 1.0d 1.0d 3.0d 12-May-18 08:00 AM* 12-May-18 05:00 PM
STF2200 Curing works 2.0d 2.0d 3.0d 13-May-18 08:00 AM* 14-May-18 05:00 PM
STF2210 Dismantle formwork 1.0d 1.0d 3.0d 15-May-18 08:00 AM* 15-May-18 05:00 PM

Primary Baseline Remaining Work Baseline Milestone Page 1 of 2 TASK filter: Longest Path.
Actual Work Critical Remaining Work Summary © Oracle Corporation
STF PALONG TIMUR REV.04 ALL NON-RUN Classic Schedule Layout 16-Apr-18 05:04 PM
Activity ID Activity Name Original Remaining Total Start Finish October 2017 November 2017 December 2017 January 2018 February 2018 March 2018 April 2018 May 2018 June 2018 July 2018 August 2018
Duration Duration Float 05
01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 04 11 18 25 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15 22 29
Column - 5.5m (0.25mm x 0.25mm) 3.0d 3.0d 4.4d 15-May-18 08:00 AM 16-May-18 11:00 PM 16-May-18 11:00 PM, Column - 5.5m (0.25mm x 0.25mm)
STF2220 Install reinforcement 2.0d 2.0d 4.4d 15-May-18 08:00 AM* 16-May-18 12:00 PM
STF2230 Erect formwork & bracing 1.0d 1.0d 4.4d 16-May-18 01:00 PM* 16-May-18 11:00 PM
Roof Beam (0.25mm x 0.5mm) 8.0d 8.0d 3.0d 17-May-18 08:00 AM 24-May-18 05:00 PM 24-May-18 05:00 PM, Roof Beam (0.25mm x 0.5mm)
STF2280 Erect scaffold, stagging, t-prox & soffit 1.0d 1.0d 4.4d 17-May-18 08:00 AM* 17-May-18 05:00 PM
STF2290 Install reinforcement including L-Plates for roof truss 2.0d 2.0d 4.4d 17-May-18 07:00 PM* 19-May-18 09:00 AM
STF2300 Erect formwork 1.0d 1.0d 4.4d 19-May-18 09:00 AM* 19-May-18 08:00 PM
STF2310 Inspection 1.0d 1.0d 3.0d 19-May-18 08:00 AM* 20-May-18 08:00 AM
STF2320 Concreting works 1.0d 1.0d 3.0d 20-May-18 08:00 AM* 20-May-18 05:00 PM
STF2330 Curing works 3.0d 3.0d 3.0d 21-May-18 08:00 AM* 23-May-18 05:00 PM
STF2340 Dismantle scaffold, stagging, t-prox, soffit & formwork 1.0d 1.0d 3.0d 24-May-18 08:00 AM* 24-May-18 05:00 PM
Intermediate Beam (0.25mm x 0.5mm) 8.0d 8.0d 3.0d 17-May-18 08:00 AM 24-May-18 05:00 PM 24-May-18 05:00 PM, Intermediate Beam (0.25mm x 0.5mm)
STF2350 Erect scaffold, stagging, t-prox & soffit 1.0d 1.0d 4.4d 17-May-18 08:00 AM* 17-May-18 05:00 PM
STF2360 Install reinforcement 2.0d 2.0d 4.4d 17-May-18 07:00 PM* 19-May-18 09:00 AM
STF2370 Erect formwork 1.0d 1.0d 4.4d 19-May-18 09:00 AM* 19-May-18 08:00 PM
STF2380 Inspection 1.0d 1.0d 3.0d 19-May-18 08:00 AM* 20-May-18 08:00 AM
STF2390 Concreting works 1.0d 1.0d 3.0d 20-May-18 08:00 AM* 20-May-18 05:00 PM
STF2400 Curing works 3.0d 3.0d 3.0d 21-May-18 08:00 AM* 23-May-18 05:00 PM
STF2410 Dismantle scaffold, stagging, t-prox, soffit & formwork 1.0d 1.0d 3.0d 24-May-18 08:00 AM* 24-May-18 05:00 PM
Roof Truss, Covering & Accessories 0.0d 0.0d 0.0d
Floor, Wall, Ceiling & Accessories 19.0d 19.0d 4.6d 24-May-18 07:00 PM 06-Jun-18 03:00 PM 06-Jun-18 03:00 PM, Floor, Wall, Ceiling & Accessories
STF2490 Install 225mm thk. brickwall, tie with mortar - Team A & B 3.0d 3.0d 4.6d 24-May-18 07:00 PM* 26-May-18 08:00 PM
STF2500 Install roller shutter & frame for door and window 2.0d 2.0d 4.6d 26-May-18 08:00 PM* 28-May-18 09:00 AM
STF2510 Electrical wiring works - carry out by specialist team 4.0d 4.0d 4.6d 26-May-18 08:00 PM* 29-May-18 02:00 PM
STF2520 External plastering - Team A 3.0d 3.0d 4.6d 29-May-18 02:00 PM* 31-May-18 02:00 PM
STF2530 Internal plastering - Team B 3.0d 3.0d 4.6d 29-May-18 02:00 PM* 31-May-18 02:00 PM
STF2540 Install frame & ceiling (external) - Team A 2.0d 2.0d 4.6d 31-May-18 02:00 PM* 01-Jun-18 09:00 PM
STF2550 Install frame & ceiling (internal) - Team B 2.0d 2.0d 4.6d 31-May-18 02:00 PM* 01-Jun-18 09:00 PM
STF2560 Install gutter & UPVC downpipes 1.0d 1.0d 4.6d 01-Jun-18 09:00 PM* 02-Jun-18 03:00 PM
STF2570 Rendering of floor, install tiles & skirting 4.0d 4.0d 4.6d 01-Jun-18 09:00 PM* 04-Jun-18 03:00 PM
STF2580 Painting of wall (external & internal) & ceiling - undercoat - Team A3.0d 3.0d 4.6d 04-Jun-18 03:00 PM* 06-Jun-18 03:00 PM
STF2590 Painting of wall (external & internal) & ceiling - finish coat - Team B3.0d 3.0d 4.6d 04-Jun-18 03:00 PM* 06-Jun-18 03:00 PM
STF2600 Install door & windows 1.0d 1.0d 4.6d 04-Jun-18 03:00 PM* 05-Jun-18 10:00 AM
STF2610 Install GI tray / condiut 1.0d 1.0d 4.6d 05-Jun-18 10:00 AM* 05-Jun-18 09:00 PM
U-Shaped Drain - Team C 0.0d 0.0d 0.0d
Apron & Ramp - Team C 0.0d 0.0d 0.0d
Pipeworks (200mm & 300mm Dia. Pipe) 0.0d 0.0d 0.0d

Procurement & Installation Works 0.0d 0.0d 0.0d


7.0d 7.0d 3.0d 06-Jun-18 08:00 AM 12-Jun-18 05:00 PM 12-Jun-18 05:00 PM, Mechanical Works
Mechanical Works
Drawing & Material Approval 0.0d 0.0d 0.0d
Tank & Plant 7.0d 7.0d 3.0d 06-Jun-18 08:00 AM 12-Jun-18 05:00 PM 12-Jun-18 05:00 PM, Tank & Plant

Wash Water Collection & Sludge Balancing Tank 0.0d 0.0d 0.0d
Procurement & Delivery 0.0d 0.0d 0.0d
Installation Works 0.0d 0.0d 0.0d
Existing Sedimentation Tank / Basin 0.0d 0.0d 0.0d
Procurement & Delivery 0.0d 0.0d 0.0d
Installation Works 0.0d 0.0d 0.0d
Polymer Plant 7.0d 7.0d 3.0d 06-Jun-18 08:00 AM 12-Jun-18 05:00 PM 12-Jun-18 05:00 PM, Polymer Plant

Procurement & Delivery 0.0d 0.0d 0.0d


Fabrication Works 0.0d 0.0d 0.0d
Installation Works 7.0d 7.0d 3.0d 06-Jun-18 08:00 AM 12-Jun-18 05:00 PM 12-Jun-18 05:00 PM, Installation Works
STF3040 Mixing & Service Tank 7.0d 7.0d 3.0d 06-Jun-18 08:00 AM 12-Jun-18 05:00 PM
STF3050 Hopper, Feeder & Pump Skid 7.0d 7.0d 3.0d 06-Jun-18 08:00 AM 12-Jun-18 05:00 PM
STF3060 Dosing Pipeworks 7.0d 7.0d 3.0d 06-Jun-18 08:00 AM 12-Jun-18 05:00 PM
STF3070 Local Control Panel 7.0d 7.0d 3.0d 06-Jun-18 08:00 AM 12-Jun-18 05:00 PM
STF3080 Crane / Lifting Equipment 7.0d 7.0d 3.0d 06-Jun-18 08:00 AM 12-Jun-18 05:00 PM
STF3090 Static Mixer & Sludge Blender 7.0d 7.0d 3.0d 06-Jun-18 08:00 AM 12-Jun-18 05:00 PM
Pipeworks (100mm Dia. Pipe & Below) 0.0d 0.0d 0.0d
Procurement & Installation Works 0.0d 0.0d 0.0d
Miscellaneous Works 0.0d 0.0d 0.0d
Procurement & Delivery 0.0d 0.0d 0.0d
Installation Works 0.0d 0.0d 0.0d
Electrical Works 0.0d 0.0d 0.0d

Drawing & Material Approval 0.0d 0.0d 0.0d


Panel & Cabling Works 0.0d 0.0d 0.0d
Switchboard / MCC Panel 0.0d 0.0d 0.0d
Submain Cabling Works for MCC-SDP-Palong 0.0d 0.0d 0.0d
Distribution & Earthing System 0.0d 0.0d 0.0d
Compund Lighting System 0.0d 0.0d 0.0d
Miscellaneous Works 0.0d 0.0d 0.0d
Instrumentation Works 0.0d 0.0d 0.0d

Drawing & Material Approval 0.0d 0.0d 0.0d


Panel & Cabling Works 0.0d 0.0d 0.0d
Procurement & Installation Works 0.0d 0.0d 0.0d
Infrastructure Works 0.0d 0.0d 0.0d

Reinstatement of Damaged Existing Road 0.0d 0.0d 0.0d


14.5d 14.5d 3.5d 13-Jun-18 08:00 AM 27-Jun-18 12:00 PM 27-Jun-18 12:00 PM, Site Handover Works
Site Handover Works
Project Completions 14.5d 14.5d 3.5d 13-Jun-18 08:00 AM 27-Jun-18 12:00 PM 27-Jun-18 12:00 PM, Project Completions

Training, Testing, Commissioning & Maintenance 14.5d 14.5d 3.5d 13-Jun-18 08:00 AM 27-Jun-18 12:00 PM 27-Jun-18 12:00 PM, Training, Testing, Commissioning & Maintenance
STF3440 Preparation of Testing & Report 8.0d 8.0d 2.0d 13-Jun-18 08:00 AM 21-Jun-18 05:00 PM
STF3450 Pre-commissioning 4.0d 4.0d 2.0d 13-Jun-18 08:00 AM 17-Jun-18 05:00 PM
STF3460 Setting to Work 3.0d 3.0d 2.0d 18-Jun-18 08:00 AM 20-Jun-18 05:00 PM
STF3470 Commissioning & Training of Works 5.0d 5.0d 2.0d 21-Jun-18 08:00 AM 26-Jun-18 05:00 PM
STF3480 Handing Over to Client 1.0d 1.0d 4.9d 26-Jun-18 07:00 PM 27-Jun-18 12:00 PM

Primary Baseline Remaining Work Baseline Milestone Page 2 of 2 TASK filter: Longest Path.
Actual Work Critical Remaining Work Summary © Oracle Corporation