The document outlines the progress and remaining work for an underground cable project with the following details:
- 3,150 meters of underground cable still need to be installed, which at the installation rate of 250 meters per week will take approximately 12.6 weeks.
- Other tasks like digging and land acquisition are in progress.
- Procurement of poles, accessories, cable, and other equipment is mostly complete with fabrication and shipment ongoing or completed.
- Construction activities like pole erection, cable laying, and cubicle installation are upcoming or in progress.
- Commissioning, testing and documentation will occur after construction is finished.
The document outlines the progress and remaining work for an underground cable project with the following details:
- 3,150 meters of underground cable still need to be installed, which at the installation rate of 250 meters per week will take approximately 12.6 weeks.
- Other tasks like digging and land acquisition are in progress.
- Procurement of poles, accessories, cable, and other equipment is mostly complete with fabrication and shipment ongoing or completed.
- Construction activities like pole erection, cable laying, and cubicle installation are upcoming or in progress.
- Commissioning, testing and documentation will occur after construction is finished.
The document outlines the progress and remaining work for an underground cable project with the following details:
- 3,150 meters of underground cable still need to be installed, which at the installation rate of 250 meters per week will take approximately 12.6 weeks.
- Other tasks like digging and land acquisition are in progress.
- Procurement of poles, accessories, cable, and other equipment is mostly complete with fabrication and shipment ongoing or completed.
- Construction activities like pole erection, cable laying, and cubicle installation are upcoming or in progress.
- Commissioning, testing and documentation will occur after construction is finished.
total qty cum progressQty Remaining dikerjakan per minggu [minggu]
Underground cable 3900 750 3150 250 12.6 Digging 20 Qty Remaining [hari] asumsi 1 minggu= 7 hari 88.2 54 142.2 Task Name Contract Drawing Approval ok Technical Presentation With PLN Area Gorontalo ok Drawing Approval Sign Of ok Owner Drawing Approval ok Land Acqusition ok Socialization and Price Negotiation ok - Molowahu Village ok - Dunggala Village ok - Isimu Utara Village ok Transaction ok -Payment For Span, Trees and Compensation ok -Payment Document Signing ok Procurement Poles (Steel and Concrete) ok PO ok Fabrication ok FAT ok Shipment ok From Surabaya To Anggrek Port ok From Anggrek Port To Gorontalo ok Accessories ok PO ok Fabrication ok Shipment ok From Surabaya To Anggrek Port ok From Anggrek Port To Gorontalo ok Cable, Conductor and Insulator ok PO ok Fabrication ok FAT ok Shipment ok From Bogor To Tanjung Priok Port ok From Tanjung Priok Port To Anggrek Port ok From Anggrek Port To Gorontalo ok Cubicle PO Fabrication FAT Shipment From Bogor To Tanjung Priok Port From Tanjung Priok Port To Anggrek Port From Anggrek Port To Gorontalo Constrution Poles (Steel and Concrete) Digging Pole Erection Accessories Installation Conductor Stringing Cable Underground NA2XSEYBY 3 X 300 mm2 Soil Excavation Cable Laying Soil Covering Terminating and Jointing Cubicle Civil Modification 6 10 14 8.4 Cable Laying 2 10 14 2.8 Installation 1 10 14 1.4 Terminating 1 10 14 1.4 Commisioning and SLO Megger Test Hivolt Test Ground Earth Test Documentation Document SLO As Built Drawing Document COD