Professional Documents
Culture Documents
18FL0069 Scurve
18FL0069 Scurve
SANGAT, GUBAT, SORSOGON
PART A – FACILTIES FOR THE ENGINEER
PART B – OTHER GENERAL REQUIREMENTS
B.5 Project Billboard / Signboard each 2 7,184.00
B.7 Occupational Safety and Health Program month 2.4 33,320.00
B.9 Mobilization / Demobilization l.s. 1 39,984.00
PART C – EARTHWORKS
100(1) Clearing and Grubbing ha 0.8 56,411.00
102(2) Surplus Common Excavation cu.m. 198.91 187.00
104(1)a Embankment (from Borrow) cu.m. 119.35 1,006.00
105(1)a Subgrade Preparation (Common Material) sq.m. 3,978.20 95.00
PART D – SUBBASE COURSE
200(1) Aggregate Subbase Course cu.m. 397.82 1,704.00
PART E – SURFACE COURSE
311(1)b PCC Pavement (Unreinforced) 0.23m thk. 14 days sq.m. 3,978.20 1,107.00
TOTAL (1) 5,
1. CONCRETING OF PURO - MATACLA FMR, BRGY. PURO AND BRGY. MATACLA, STA. MAGDALENA, SORSOGON
TOTAL (2) 4,
3. CONSTRUCTION OF M. ROXAS – BICAL ROAD, STA. 0+000 – STA. 2+000 WITH EXCEPTION, BRGY. M ROXAS AND BRGY. B
PART A – FACILITIES FOR THE ENGINEER
Provision of Field Office for the Engineer
A.1.1(8) month 4.1 7,170.73
(Rental Basis)
PART B – OTHER GENERAL REQUIREMENTS
B.5 Project Billboard / Signboard each 2 4,651.50
B.7 Occupational Safety and Health Program month 4.1 31,948.17
B.9 Mobilization / Demobilization l.s. 1 52,500.00
PART C – EARTHWORKS
100(1) Clearing and Grubbing ha 0.83 87,744.58
101(3)b1 Removal of Actual Structure (0.15m thk. PCCP) sq.m. 264 132.68
102(2) Surplus Common Excavation cu.m. 7,161.00 141.19
104(1a) Embankment from Borrow cu.m. 1,976.00 491.39
105(1) Subgrade Preparation (Common Excavation) sq.m. 8,263.00 21.89
PART D – SUBBASE COURSE
200(1) Aggregate Subbase Course cu.m. 752 639.68
PART E – SURFACE COURSE
311(1) PCC Pavement (Unreinforced) 0.20m thk. sq.m. 6,784.50 1,403.93
500(1)c Pipe Culvert, 910mm dia. (36”Ø”) ln.m. 8 6,427.42
505(1)a Grouted Riprap, Class A cu.m. 354.98 3,357.58
505(2)a Grouted Riprap, Class A (Lined Canal) cu.m. 108.28 3,426.03
45,128.80
37,196.17
120,066.10
377,929.00
677,885.28
4,403,867.40
5,796,392.75
14,368.00
55,644.40
115,954.00
46,448.22
122,187.00
314,746.00
591,307.50
549,219.00
2,920,335.00
100,487.00
4,830,696.12
29,399.99
9,303.00
130,987.50
52,500.00
72,828.00
35,027.52
1,011,061.59
970,986.64
180,877.07
481,039.36
9,524,963.09
51,419.36
1,191,873.75
370,970.53
14,113,237.40
37,635,893.40
B.9 1 100(1) 7 102(1)
0 1 1 8 8
0 1 1 8 8
B.5 1
PROJECT BILLBOARD
0 1
0 1
200(1) 54
-54
AGGREGATE SUBBASE COURSE
16 70
16 70
311(1)b 61
PCC PAVEMENT
-46 16 77
16 77
31
TABLE EXCAVATION
39
-23 105(1)a 46
39
SUBGRADE PREPARATION
(COMMON MATERIAL)
16 62
16 62
-31
104(1)b1 31
31 62
31 62
B.7 80
OCCUPATIONAL SAFETY AND HEALTH
PROGRAM
0 80
0 80
B.9 3
DEMOBILIZATION
77 80
77 80
Contract I.D.: 18FL0068
Contract Name: Concreting of Farm-to-Market Road (Cluster I) Start Date: July 16, 2018
Completion Date: October 3, 2018
Location: Bulan, Sorsogon Duration: 80 C.D.
Contractor: RMH CONSTRUCTION AND SUPPLY
1. CONCRETING OF PURO - MATACLA FMR, BRGY. PURO AND BRGY. MATACLA, STA. MAGDALENA, SORSOGON
CONSTRUCTION SCHEDULE AND BAR CHART
Y 2018
ITEM NO. DESCRIPTION UNIT QTY UNIT COST TOTAL COST WTD % M JULY AGUST SEPTEMBER OCT
D 16-23 24-31 1-7 8-15 16-23 24-31 1-7 8-15 16-23 24-30 1-3
8 8 7 8 8 8 7 8 8 7 3
PART B – OTHER GENERAL REQUIREMENTS
Planned 0.297
B.5 Project Billboard / Signboard each 2.00 7,184.00 14,368.00 0.297
% Actual
Occupational Safety and Health Planned 0.115 0.115 0.101 0.115 0.115 0.115 0.101 0.115 0.115 0.101 0.043
B.7 month 1.67 33,320.00 55,644.40 1.152
Program % Actual
Planned 1.200 1.200
B.9 Mobilization / Demobilization l.s. 1.00 115,954.00 115,954.00 2.400
% Actual
PART C – EARTHWORKS
Planned 0.962
100(1) Clearing and Grubbing ha 0.26 178,647.00 46,448.22 0.962
% Actual
Planned 0.571 0.653 0.653 0.653
102(1) Unsuitable Excavation cu.m. 241.00 507.00 122,187.00 2.529
% Actual
Planned 1.681 1.681 1.471 1.681
104(1)b1 Embankment from borrow cu.m. 241.00 1,306.00 314,746.00 6.516
% Actual
Planned 1.863 2.129 2.129 2.129 1.863 2.129
105(1)a Subgrade Preparation sq.m. 2,413.50 245.00 591,307.50 12.241
% Actual
PART D – SUBBASE COURSE
Planned 1.474 1.684 1.684 1.684 1.474 1.684 1.684
200(1) Aggregate Subbase Course cu.m. 121.00 4,539.00 549,219.00 11.369
% Actual
PART E – SURFACE COURSE
Planned
311(1)b PCC Pavement (Unreinforced) 0.23m sq.m. 6.937 7.928 7.928 7.928 6.937 7.928 7.928 6.937
2,413.50 1,210.00 2,920,335.00 60.454
thk. % Actual
Planned 0.537 0.470 0.537 0.537
506(1) Stone Masonry cu.m. 23.00 4,369.00 100,487.00 2.080
% Actual
WEEKLY TARGET ACCOMPLISHMENT 1.61 1.65 11.03 12.51 14.19 14.07 12.32 14.07 10.26 7.04 1.24
%
CUMM. TARGET ACCOMPLISHMENT 1.61 3.26 14.29 26.80 40.99 55.06 67.38 81.45 91.72 98.76 100.00
RMH CONSTRUCTION AND SUPPLY JESALOU R. ALMILLA WILFREDO D. FLORES EFREN C. MANALO, MPA
CONTRACTOR PROJECT ENGINEER OIC, ASST. DISTRICT ENGINEER DISTRICT ENGINEER
Contract I.D.: 18FL0069
Contract Name: Concreting of Farm-to-Market Road (Cluster II) Start Date: July 16, 2018
Completion Date: September 25, 2018
Location: Sta. Magdalena and Gubat, Sorsogon Duration: 72 C.D.
Contractor: RMH CONSTRUCTION AND SUPPLY
8 8 7 8 8 8 7 8 8 7 3
PART B – OTHER GENERAL REQUIREMENTS
Planned 0.248
B.5 Project Billboard / Signboard each 2.00 7,184.00 14,368.00 0.248
% Actual
Occupational Safety and Health Planned 0.138 0.138 0.121 0.138 0.138 0.138 0.121 0.138 0.138 0.121 0.052
B.7 Program month 2.40 33,320.00 79,968.00 1.380
% Actual
Planned 0.345 0.345
B.9 Mobilization / Demobilization l.s. 1.00 39,984.00 39,984.00 0.690
% Actual
PART C – EARTHWORKS
Planned 0.779
100(1) Clearing and Grubbing ha 0.80 56,411.00 45,128.80 0.779
% Actual
Planned 0.145 0.166 0.166 0.166
102(2) Surplus Common Excavation cu.m. 198.91 187.00 37,196.17 0.642
% Actual
Planned 0.483 0.552 0.552 0.483
104(1)a Embankment (from Borrow) cu.m. 119.35 1,006.00 120,066.10 2.071
% Actual
Subgrade Preparation (Common Planned 0.992 1.134 1.134 1.134 0.992 1.134
105(1)a sq.m. 3,978.20 95.00 377,929.00 6.520
Material) % Actual
PART D – SUBBASE COURSE
Planned 1.516 1.733 1.733 1.733 1.516 1.733 1.733
200(1) Aggregate Subbase Course cu.m. 397.82 1,704.00 677,885.28 11.695
% Actual
PART E – SURFACE COURSE
Planned
311(1)b PCC Pavement (Unreinforced) 0.23m sq.m.
8.719 9.964 9.964 9.964 8.719 9.964 9.964 8.719
3,978.20 1,107.00 4,403,867.40 75.976
thk. 14 days % Actual
WEEKLY TARGET ACCOMPLISHMENT 0.73 1.06 11.51 13.13 13.13 12.97 11.83 13.52 12.39 9.32 0.40
%
CUMM. TARGET ACCOMPLISHMENT 0.73 1.79 13.31 26.44 39.57 52.54 64.37 77.89 90.28 99.60 100.00
RMH CONSTRUCTION AND SUPPLY JESALOU R. ALMILLA WILFREDO D. FLORES EFREN C. MANALO, MPA
CONTRACTOR PROJECT ENGINEER OIC, ASST. DISTRICT ENGINEER DISTRICT ENGINEER
Contract I.D.: 18FL0069
Contract Name: Concreting of Farm-to-Market Road (Cluster II) Start Date: July 16, 2018
Location: Sta. Magdalena and Gubat, Sorsogon Completion Date: October 3, 2018
Contractor: RMH CONSTRUCTION AND SUPPLY Duration: 80 CD
MANPOWER UTILIZATION SCHEDULE
MONTH JULY AUGUST SEPTEMBER OCTOBER
PROJECT MNGR. 1 1 1 1
PROJECT ENGR. 1 1 1 1
MATERIALS ENGR. 1 1 1 1
SAFETY OFFICER 1 1 1 1
FOREMAN 1 1 1 1
SKILLED WORKERS 17 17 17 17
COMMON LABORERS 25 25 25 25
1. CONCRETING OF PURO - MATACLA FMR, BRGY. PURO AND BRGY. MATACLA, STA. MAGDALENA, SORSOGON
1. CONCRETING OF PURO - MATACLA FMR, BRGY. PURO AND BRGY. MATACLA, STA. MAGDALENA, SORSOGON
RMH CONSTRUCTION AND SUPPLY JESALOU R. ALMILLA WILFREDO D. FLORES EFREN C. MANALO, MPA
CONTRACTOR PROJECT ENGINEER OIC, ASST. DISTRICT ENGINEER DISTRICT ENGINEER
Contract I.D.: 18FL0058
Contract Name: Construction of Concrete Road – Cluster XVIII Start Date: April 23, 2018
Completion Date: September 1, 2018
Location: Bulan, Sorsogon Duration: 132 C.D.
Contractor: C.T. LEONCIO CONSTRUCTION AND TRADING
1. CONCRETING OF PURO - MATACLA FMR, BRGY. PURO AND BRGY. MATACLA, STA. MAGDALENA, SORSOGON
CONSTRUCTION SCHEDULE AND BAR CHART
Y 2018
ITEM NO. DESCRIPTION UNIT QTY UNIT COST TOTAL COST WTD % M APRIL MAY JUNE JULY AUGUST SEPTEMBER
D 23 24-30 1-7 8-15 16-23 24-31 1-7 8-15 16-23 24-30 1-7 8-15 16-23 24-31 1-7 8-15 16-23 24-31 1
WEEKLY TARGET ACCOMPLISHMENT Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
%
CUMM. TARGET ACCOMPLISHMENT Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
SUBMITTED BY: CHECKED BY: RECOMMENDING APPROVAL: APPROVED BY:
C.T. LEONCIO CONSTRUCTION AND TRADING WILFREDO S. FAJARDO WILFREDO D. FLORES EFREN C. MANALO, MPA
CONTRACTOR PROJECT ENGINEER OIC, ASST. DISTRICT ENGINEER DISTRICT ENGINEER
HEDULE AND BAR CHART
2018
OCT.
Contract I.D.: 18FL0058
Contract Name: Construction of Concrete Road – Cluster XVIII Start Date: April 23, 2018
Completion Date: September 1, 2018
Location: Bulan, Sorsogon Duration: 132 C.D.
Contractor: C.T. LEONCIO CONSTRUCTION AND TRADING
3. CONSTRUCTION OF M. ROXAS – BICAL ROAD, STA. 0+000 – STA. 2+000 WITH EXCEPTION, BRGY. M ROXAS AND BRGY. BICAL, BULAN, SORSOGON
CONSTRUCTION SCHEDULE AND BAR CHART
Y 2018
ITEM NO. DESCRIPTION UNIT QTY UNIT COST TOTAL COST WTD % M APRIL MAY JUNE JULY AUGUST SEPTEMBER
D 23 24-30 1-7 8-15 16-23 24-31 1-7 8-15 16-23 24-30 1-7 8-15 16-23 24-31 1-7 8-15 16-23 24-31 1
WEEKLY TARGET ACCOMPLISHMENT 0.26 0.58 1.73 1.98 1.98 1.98 3.25 3.71 3.71 3.25 9.41 10.75 10.75 10.75 8.06 9.22 9.22 9.22 0.19
%
CUMM. TARGET ACCOMPLISHMENT 0.26 0.84 2.57 4.55 6.53 8.52 11.76 15.48 19.19 22.44 31.84 42.59 53.34 64.09 72.15 81.37 90.59 99.81 100
SUBMITTED BY: CHECKED BY: RECOMMENDING APPROVAL: APPROVED BY:
C.T. LEONCIO CONSTRUCTION AND TRADING WILFREDO S. FAJARDO WILFREDO D. FLORES EFREN C. MANALO, MPA
CONTRACTOR PROJECT ENGINEER OIC, ASST. DISTRICT ENGINEER DISTRICT ENGINEER
April 23, 2018
September 1, 2018