Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 18

2.     CONCRETING OF SANGAT FMR, BRGY.

 SANGAT, GUBAT, SORSOGON
PART A – FACILTIES FOR THE ENGINEER
PART B – OTHER GENERAL REQUIREMENTS
B.5 Project Billboard / Signboard each 2 7,184.00
B.7 Occupational Safety and Health Program month 2.4 33,320.00
B.9 Mobilization / Demobilization l.s. 1 39,984.00
PART C – EARTHWORKS
100(1) Clearing and Grubbing ha 0.8 56,411.00
102(2) Surplus Common Excavation cu.m. 198.91 187.00
104(1)a Embankment (from Borrow) cu.m. 119.35 1,006.00
105(1)a Subgrade Preparation (Common Material) sq.m. 3,978.20 95.00
PART D – SUBBASE COURSE
200(1) Aggregate Subbase Course cu.m. 397.82 1,704.00
PART E – SURFACE COURSE
311(1)b PCC Pavement (Unreinforced) 0.23m thk. 14 days sq.m. 3,978.20 1,107.00

TOTAL (1) 5,

1.     CONCRETING OF PURO - MATACLA FMR, BRGY. PURO AND BRGY. MATACLA, STA. MAGDALENA, SORSOGON

PART B – OTHER GENERAL REQUIREMENTS


B.5 Project Billboard / Signboard each 2 7,184.00
B.7 Occupational Safety and Health Program month 1.67 33,320.00
B.9 Mobilization / Demobilization l.s. 1 115,954.00
PART C – EARTHWORKS
100(1) Clearing and Grubbing ha 0.26 178,647.00
102(1) Unsuitable Excavation cu.m. 241.00 507.00
104(1)b1 Embankment from borrow cu.m. 241.00 1,306.00
105(1)a Subgrade Preparation sq.m. 2,413.50 245.00
PART D – SUBBASE COURSE AND BASE COURSE
200(1) Aggregate Subbase Course cu.m. 121.00 4,539.00
PART E – SURFACE COURSE
311(1)b PCC Pavement (Unreinforced) 0.23m thk. sq.m. 2,413.50 1,210.00
506(1) Stone Masonry cu.m. 23 4,369.000

TOTAL (2) 4,

3.      CONSTRUCTION OF M. ROXAS – BICAL ROAD, STA. 0+000 – STA. 2+000 WITH EXCEPTION, BRGY. M ROXAS AND BRGY. B
PART A – FACILITIES FOR THE ENGINEER
Provision of Field Office for the Engineer
A.1.1(8) month 4.1 7,170.73
(Rental Basis)
PART B – OTHER GENERAL REQUIREMENTS
B.5 Project Billboard / Signboard each 2 4,651.50
B.7 Occupational Safety and Health Program month 4.1 31,948.17
B.9 Mobilization / Demobilization l.s. 1 52,500.00
PART C – EARTHWORKS
100(1) Clearing and Grubbing ha 0.83 87,744.58
101(3)b1 Removal of Actual Structure (0.15m thk. PCCP) sq.m. 264 132.68
102(2) Surplus Common Excavation cu.m. 7,161.00 141.19
104(1a) Embankment from Borrow cu.m. 1,976.00 491.39
105(1) Subgrade Preparation (Common Excavation) sq.m. 8,263.00 21.89
PART D – SUBBASE COURSE
200(1) Aggregate Subbase Course cu.m. 752 639.68
PART E – SURFACE COURSE
311(1) PCC Pavement (Unreinforced) 0.20m thk. sq.m. 6,784.50 1,403.93
500(1)c Pipe Culvert, 910mm dia. (36”Ø”) ln.m. 8 6,427.42
505(1)a Grouted Riprap, Class A cu.m. 354.98 3,357.58
505(2)a Grouted Riprap, Class A (Lined Canal) cu.m. 108.28 3,426.03

TOTAL (3) 14,

GRAND TOTAL 37,


14,368.00
79,968.00
39,984.00

45,128.80
37,196.17
120,066.10
377,929.00

677,885.28

4,403,867.40

5,796,392.75

14,368.00
55,644.40
115,954.00

46,448.22
122,187.00
314,746.00
591,307.50

549,219.00

2,920,335.00
100,487.00

4,830,696.12

BRGY. M ROXAS AND BRGY. BICAL, BULAN, SORSOGON

29,399.99

9,303.00
130,987.50
52,500.00

72,828.00
35,027.52
1,011,061.59
970,986.64
180,877.07

481,039.36

9,524,963.09
51,419.36
1,191,873.75
370,970.53

14,113,237.40

37,635,893.40
B.9 1 100(1) 7 102(1)

MOBILIZATION CLEARING AND GRUBBING UNSUITABLE EXCAV

0 1 1 8 8
0 1 1 8 8

B.5 1

PROJECT BILLBOARD

0 1
0 1
200(1) 54
-54
AGGREGATE SUBBASE COURSE

16 70
16 70

311(1)b 61

PCC PAVEMENT

-46 16 77
16 77
31

TABLE EXCAVATION

39
-23 105(1)a 46
39
SUBGRADE PREPARATION
(COMMON MATERIAL)

16 62
16 62

-31

104(1)b1 31

EMBANKMENT FROM BORROW

31 62
31 62
B.7 80
OCCUPATIONAL SAFETY AND HEALTH
PROGRAM

0 80
0 80

B.9 3

DEMOBILIZATION

77 80
77 80
Contract I.D.: 18FL0068
Contract Name: Concreting of Farm-to-Market Road (Cluster I) Start Date: July 16, 2018
Completion Date: October 3, 2018
Location: Bulan, Sorsogon Duration: 80 C.D.
Contractor: RMH CONSTRUCTION AND SUPPLY

1. CONCRETING OF PURO - MATACLA FMR, BRGY. PURO AND BRGY. MATACLA, STA. MAGDALENA, SORSOGON
CONSTRUCTION SCHEDULE AND BAR CHART
Y 2018
ITEM NO. DESCRIPTION UNIT QTY UNIT COST TOTAL COST WTD % M JULY AGUST SEPTEMBER OCT
D 16-23 24-31 1-7 8-15 16-23 24-31 1-7 8-15 16-23 24-30 1-3

8 8 7 8 8 8 7 8 8 7 3
PART B – OTHER GENERAL REQUIREMENTS
Planned 0.297
B.5 Project Billboard / Signboard each 2.00 7,184.00 14,368.00 0.297
% Actual
Occupational Safety and Health Planned 0.115 0.115 0.101 0.115 0.115 0.115 0.101 0.115 0.115 0.101 0.043
B.7 month 1.67 33,320.00 55,644.40 1.152
Program % Actual
Planned 1.200 1.200
B.9 Mobilization / Demobilization l.s. 1.00 115,954.00 115,954.00 2.400
% Actual
PART C – EARTHWORKS
Planned 0.962
100(1) Clearing and Grubbing ha 0.26 178,647.00 46,448.22 0.962
% Actual
Planned 0.571 0.653 0.653 0.653
102(1) Unsuitable Excavation cu.m. 241.00 507.00 122,187.00 2.529
% Actual
Planned 1.681 1.681 1.471 1.681
104(1)b1 Embankment from borrow cu.m. 241.00 1,306.00 314,746.00 6.516
% Actual
Planned 1.863 2.129 2.129 2.129 1.863 2.129
105(1)a Subgrade Preparation sq.m. 2,413.50 245.00 591,307.50 12.241
% Actual
PART D – SUBBASE COURSE
Planned 1.474 1.684 1.684 1.684 1.474 1.684 1.684
200(1) Aggregate Subbase Course cu.m. 121.00 4,539.00 549,219.00 11.369
% Actual
PART E – SURFACE COURSE
Planned
311(1)b PCC Pavement (Unreinforced) 0.23m sq.m. 6.937 7.928 7.928 7.928 6.937 7.928 7.928 6.937
2,413.50 1,210.00 2,920,335.00 60.454
thk. % Actual
Planned 0.537 0.470 0.537 0.537
506(1) Stone Masonry cu.m. 23.00 4,369.00 100,487.00 2.080
% Actual

TOTAL 4,830,696.12 100 %


16-23 24-31 1-7 8-15 16-23 24-31 1-7 8-15 16-23 24-30 1-3

WEEKLY TARGET ACCOMPLISHMENT 1.61 1.65 11.03 12.51 14.19 14.07 12.32 14.07 10.26 7.04 1.24
%
CUMM. TARGET ACCOMPLISHMENT 1.61 3.26 14.29 26.80 40.99 55.06 67.38 81.45 91.72 98.76 100.00

SUBMITTED BY: CHECKED BY: RECOMMENDING APPROVAL: APPROVED BY:

RMH CONSTRUCTION AND SUPPLY JESALOU R. ALMILLA WILFREDO D. FLORES EFREN C. MANALO, MPA
CONTRACTOR PROJECT ENGINEER OIC, ASST. DISTRICT ENGINEER DISTRICT ENGINEER
Contract I.D.: 18FL0069
Contract Name: Concreting of Farm-to-Market Road (Cluster II) Start Date: July 16, 2018
Completion Date: September 25, 2018
Location: Sta. Magdalena and Gubat, Sorsogon Duration: 72 C.D.
Contractor: RMH CONSTRUCTION AND SUPPLY

2. CONCRETING OF SANGAT FMR, BRGY. SANGAT, GUBAT, SORSOGON


CONSTRUCTION SCHEDULE AND BAR CHART
Y 2018
ITEM NO. DESCRIPTION UNIT QTY UNIT COST TOTAL COST WTD % M JULY AGUST SEPTEMBER OCT
D 16-23 24-31 1-7 8-15 16-23 24-31 1-7 8-15 16-23 24-30 1-3

8 8 7 8 8 8 7 8 8 7 3
PART B – OTHER GENERAL REQUIREMENTS
Planned 0.248
B.5 Project Billboard / Signboard each 2.00 7,184.00 14,368.00 0.248
% Actual
Occupational Safety and Health Planned 0.138 0.138 0.121 0.138 0.138 0.138 0.121 0.138 0.138 0.121 0.052
B.7 Program month 2.40 33,320.00 79,968.00 1.380
% Actual
Planned 0.345 0.345
B.9 Mobilization / Demobilization l.s. 1.00 39,984.00 39,984.00 0.690
% Actual
PART C – EARTHWORKS
Planned 0.779
100(1) Clearing and Grubbing ha 0.80 56,411.00 45,128.80 0.779
% Actual
Planned 0.145 0.166 0.166 0.166
102(2) Surplus Common Excavation cu.m. 198.91 187.00 37,196.17 0.642
% Actual
Planned 0.483 0.552 0.552 0.483
104(1)a Embankment (from Borrow) cu.m. 119.35 1,006.00 120,066.10 2.071
% Actual
Subgrade Preparation (Common Planned 0.992 1.134 1.134 1.134 0.992 1.134
105(1)a sq.m. 3,978.20 95.00 377,929.00 6.520
Material) % Actual
PART D – SUBBASE COURSE
Planned 1.516 1.733 1.733 1.733 1.516 1.733 1.733
200(1) Aggregate Subbase Course cu.m. 397.82 1,704.00 677,885.28 11.695
% Actual
PART E – SURFACE COURSE
Planned
311(1)b PCC Pavement (Unreinforced) 0.23m sq.m.
8.719 9.964 9.964 9.964 8.719 9.964 9.964 8.719
3,978.20 1,107.00 4,403,867.40 75.976
thk. 14 days % Actual

TOTAL 5,796,392.75 100 %


23 24-30 1-7 8-15 16-23 24-31 1-7 8-15 16-23 24-30 1-7

WEEKLY TARGET ACCOMPLISHMENT 0.73 1.06 11.51 13.13 13.13 12.97 11.83 13.52 12.39 9.32 0.40
%
CUMM. TARGET ACCOMPLISHMENT 0.73 1.79 13.31 26.44 39.57 52.54 64.37 77.89 90.28 99.60 100.00

SUBMITTED BY: CHECKED BY: RECOMMENDING APPROVAL: APPROVED BY:

RMH CONSTRUCTION AND SUPPLY JESALOU R. ALMILLA WILFREDO D. FLORES EFREN C. MANALO, MPA
CONTRACTOR PROJECT ENGINEER OIC, ASST. DISTRICT ENGINEER DISTRICT ENGINEER
Contract I.D.: 18FL0069
Contract Name: Concreting of Farm-to-Market Road (Cluster II) Start Date: July 16, 2018
Location: Sta. Magdalena and Gubat, Sorsogon Completion Date: October 3, 2018
Contractor: RMH CONSTRUCTION AND SUPPLY Duration: 80 CD
MANPOWER UTILIZATION SCHEDULE
MONTH JULY AUGUST SEPTEMBER OCTOBER
PROJECT MNGR. 1 1 1 1
PROJECT ENGR. 1 1 1 1
MATERIALS ENGR. 1 1 1 1
SAFETY OFFICER 1 1 1 1
FOREMAN 1 1 1 1
SKILLED WORKERS 17 17 17 17
COMMON LABORERS 25 25 25 25

EQUIPMENT UTILIZATION SCHEDULE


MONTH JULY AUGUST SEPTEMBER OCTOBER

BULLDOZER, D6H SERIES II 1 1 1 1


TRANSIT MIXER (5 CU.M.) - - - 4
BATCHING PLANT 1 1 1 1
PAYLOADER (1.50 CU.M.) 1 1 1 1
DUMP TRUCK 1 1 1 1
BAR CUTTER - - 1 1
ONE BAGGER MIXER - - 1 1
WATER TRUCK (1000 GAL.) - - 1 1
PUMP - - 1 1
MOTORIZED ROAD GRADER - - 1 1
CONCRETE VIBRATOR - - 1 1
PLATE COMPACTOR 1 1 1 1
CONCRETE SAW - - 1 1
CONCRETE SCREEDER - - 1 1
BACKHOE (0.80 CU.M.) 1 1 1 1
VIBRATORY ROLLER - - 1 1
HANDTOOLS enough enough enough enough

2. CONCRETING OF SANGAT FMR, BRGY. SANGAT, GUBAT, SORSOGON


CASH FLOW PER MONTH AND PAYMENT
SCHEDULE
JULY AUGUST SEPTEMBER OCTOBER

PLANNED ACCOMPLISHMENT (%) 1.79% 50.75% 47.06% 0.40%


CUM. PLANNED ACCOMPLISHMENT (%) 1.79% 52.54% 99.60% 100%
CASH FLOW (PHP) 103,881.54 2,941,663.26 2,727,857.16 22,990.80
CUMULATIVE CASH FLOW (PHP) 103,881.54 3,045,544.79 5,773,401.95 5,796,392.75

1. CONCRETING OF PURO - MATACLA FMR, BRGY. PURO AND BRGY. MATACLA, STA. MAGDALENA, SORSOGON

CASH FLOW PER MONTH AND PAYMENT


SCHEDULE

JULY AUGUST SEPTEMBER OCTOBER

PLANNED ACCOMPLISHMENT (%) 3.26% 51.80% 43.69% 1.24%


CUM. PLANNED ACCOMPLISHMENT (%) 3.26% 55.06% 98.76% 100%
CASH FLOW (PHP) 157,512.71 2,502,427.17 2,110,692.57 60,063.67
CUMULATIVE CASH FLOW (PHP) 157,512.71 2,659,939.88 4,770,632.46 4,830,696.12
Contract I.D.: 18FL0069
Contract Name: Concreting of Farm-to-Market Road (Cluster II) Start Date: July 16, 2018
Completion Date: September 25, 2018
Location: Sta. Magdalena and Gubat, Sorsogon Duration: 72 C.D.
Contractor: RMH CONSTRUCTION AND SUPPLY

PRECEDENCE DIAGRAM METHOD

2. CONCRETING OF SANGAT FMR, BRGY. SANGAT, GUBAT, SORSOGON

1. CONCRETING OF PURO - MATACLA FMR, BRGY. PURO AND BRGY. MATACLA, STA. MAGDALENA, SORSOGON

SUBMITTED BY: CHECKED BY: RECOMMENDING APPROVAL: APPROVED BYL:

RMH CONSTRUCTION AND SUPPLY JESALOU R. ALMILLA WILFREDO D. FLORES EFREN C. MANALO, MPA
CONTRACTOR PROJECT ENGINEER OIC, ASST. DISTRICT ENGINEER DISTRICT ENGINEER
Contract I.D.: 18FL0058
Contract Name: Construction of Concrete Road – Cluster XVIII Start Date: April 23, 2018
Completion Date: September 1, 2018
Location: Bulan, Sorsogon Duration: 132 C.D.
Contractor: C.T. LEONCIO CONSTRUCTION AND TRADING

1. CONCRETING OF PURO - MATACLA FMR, BRGY. PURO AND BRGY. MATACLA, STA. MAGDALENA, SORSOGON
CONSTRUCTION SCHEDULE AND BAR CHART
Y 2018
ITEM NO. DESCRIPTION UNIT QTY UNIT COST TOTAL COST WTD % M APRIL MAY JUNE JULY AUGUST SEPTEMBER
D 23 24-30 1-7 8-15 16-23 24-31 1-7 8-15 16-23 24-30 1-7 8-15 16-23 24-31 1-7 8-15 16-23 24-31 1

PART B – OTHER GENERAL REQUIREMENTS 1 7 7 8 8 8 7 8 8 7 7 8 8 8 7 8 8 8 1


Planned Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
% Actual
PART B – OTHER GENERAL REQUIREMENTS
Planned Err:509
B.5 Project Billboard / Signboard each 2.00 7,184.00 14,368.00 Err:509
% Actual
Occupational Safety and Health Planned Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
B.7 month 1.67 33,320.00 55,644.40 Err:509
Program % Actual
Planned Err:509 Err:509
B.9 Mobilization / Demobilization l.s. 1.00 115,954.00 115,954.00 Err:509
% Actual
PART C – EARTHWORKS
Planned Err:509
100(1) Clearing and Grubbing ha 0.26 178,647.00 46,448.22 Err:509
% Actual
Planned Err:509 Err:509 Err:509 Err:509
104(1)b1 Embankment from borrow cu.m. 241.00 1,306.00 314,746.00 Err:509
% Actual
Planned Err:509 Err:509 Err:509 Err:509
105(1)a Subgrade Preparation sq.m. 2,413.50 245.00 591,307.50 Err:509
% Actual
PART D – SUBBASE COURSE AND BASE COURSE
Planned Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
200(1) Aggregate Subbase Course cu.m. 121.00 4,539.00 549,219.00 Err:509
% Actual
PART E – SURFACE COURSE
Planned
311(1)b PCC Pavement (Unreinforced) 0.23m sq.m. 2,413.50
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
1,210.00 2,920,335.00 Err:509
thk. % Actual
PART G – DRAINAGE AND SLOPE PROTECTION STRUCTURES
Planned Err:509 Err:509 Err:509 Err:509
500(1)c Pipe Culvert, 910mm dia. ln.m. 0.00 0.00 0.00 Err:509
% Actual
Planned Err:509 Err:509 Err:509 Err:509
505(2)a Grouted Riprap, Class A cu.m. 0.00 0.00 0.00 Err:509
% Actual
Planned Err:509 Err:509 Err:509 Err:509
505(2)a Grouted Riprap, Class A cu.m. 0.00 0.00 0.00 Err:509
% Actual
Planned Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
506(1) Stone Masonry cu.m. 23.00 4,369.00 100,487.00 Err:509
% Actual
TOTAL Err:509 Err:509 %
23 24-30 1-7 8-15 16-23 24-31 1-7 8-15 16-23 24-30 1-7 8-15 16-23 24-31 1-7 8-15 16-23 24-31 1

WEEKLY TARGET ACCOMPLISHMENT Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
%
CUMM. TARGET ACCOMPLISHMENT Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
SUBMITTED BY: CHECKED BY: RECOMMENDING APPROVAL: APPROVED BY:

C.T. LEONCIO CONSTRUCTION AND TRADING WILFREDO S. FAJARDO WILFREDO D. FLORES EFREN C. MANALO, MPA
CONTRACTOR PROJECT ENGINEER OIC, ASST. DISTRICT ENGINEER DISTRICT ENGINEER
HEDULE AND BAR CHART
2018
OCT.
Contract I.D.: 18FL0058
Contract Name: Construction of Concrete Road – Cluster XVIII Start Date: April 23, 2018
Completion Date: September 1, 2018
Location: Bulan, Sorsogon Duration: 132 C.D.
Contractor: C.T. LEONCIO CONSTRUCTION AND TRADING

3. CONSTRUCTION OF M. ROXAS – BICAL ROAD, STA. 0+000 – STA. 2+000 WITH EXCEPTION, BRGY. M ROXAS AND BRGY. BICAL, BULAN, SORSOGON
CONSTRUCTION SCHEDULE AND BAR CHART
Y 2018
ITEM NO. DESCRIPTION UNIT QTY UNIT COST TOTAL COST WTD % M APRIL MAY JUNE JULY AUGUST SEPTEMBER
D 23 24-30 1-7 8-15 16-23 24-31 1-7 8-15 16-23 24-30 1-7 8-15 16-23 24-31 1-7 8-15 16-23 24-31 1

PART B – OTHER GENERAL REQUIREMENTS 1 7 7 8 8 8 7 8 8 7 7 8 8 8 7 8 8 8 1


Planned 132
A.1.1(8) Provision of Field Office for the
0.002 0.011 0.011 0.013 0.013 0.013 0.011 0.013 0.013 0.011 0.011 0.013 0.013 0.013 0.011 0.013 0.013 0.013 0.002
month 4.10 7,170.73 29,399.99 0.208
Engineer % Actual
PART B – OTHER GENERAL REQUIREMENTS
Planned 1 0.066
B.5 Project Billboard / Signboard each 2.00 4,651.50 9,303.00 0.066
% Actual
Occupational Safety and Health Planned 132 0.007 0.049 0.049 0.056 0.056 0.056 0.049 0.056 0.056 0.049 0.049 0.056 0.056 0.056 0.049 0.056 0.056 0.056 0.007
B.7 month 4.10 31,948.17 130,987.50 0.928
Program % Actual
Planned 2 0.186 0.186
B.9 Mobilization / Demobilization l.s. 1.00 52,500.00 52,500.00 0.372
% Actual
PART C – EARTHWORKS
Planned 7 0.516
100(1) Clearing and Grubbing ha 0.83 87,744.58 72,828.00 0.516
% Actual
Planned 31
101(3)b1 Removal of Actual Structure (0.15m
0.056 0.064 0.064 0.064
sq.m. 264.00 132.68 35,027.52 0.248
thk. PCCP) % Actual
Planned 31 1.618 1.849 1.849 1.849
102(2) Surplus Common Excavation cu.m. 7,161.00 141.19 1,011,061.59 7.164
% Actual
Planned 30 1.605 1.835 1.835 1.605
104(1a) Embankment from Borrow cu.m. 1,976.00 491.39 970,986.64 6.880
% Actual
Subgrade Preparation (Common Planned 31 0.289 0.331 0.331 0.331
105(1)Excavation) sq.m. 8,263.00 21.89 180,877.07 1.282
% Actual
PART D – SUBBASE COURSE AND BASE COURSE
Planned 62 0.385 0.440 0.440 0.440 0.385 0.440 0.440 0.440
200(1) Aggregate Subbase Course cu.m. 752.00 639.68 481,039.36 3.408
% Actual
PART E – SURFACE COURSE
Planned 62
311(1) PCC Pavement (Unreinforced) 0.20m sq.m. 6,784.50
7.620 8.708 8.708 8.708 7.620 8.708 8.708 8.708
1,403.93 9,524,963.09 67.490
thk. % Actual
PART G – DRAINAGE AND SLOPE PROTECTION STRUCTURES
Planned 31 0.082 0.094 0.094 0.094
500(1)c Pipe Culvert, 910mm dia. (36”Ø”) ln.m. 8.00 6,427.42 51,419.36 0.364
% Actual
Planned 61 0.969 1.108 1.108 0.969 0.969 1.108 1.108 1.108
505(1)a Grouted Riprap, Class A cu.m. 354.98 3,357.58 1,191,873.75 8.445
% Actual
Grouted Riprap, Class A (Lined Planned 30 0.613 0.701 0.701 0.613
505(2)a cu.m. 108.28 3,426.03 370,970.53 2.629
Canal) % Actual
TOTAL 14,113,237.40 100 %
23 24-30 1-7 8-15 16-23 24-31 1-7 8-15 16-23 24-30 1-7 8-15 16-23 24-31 1-7 8-15 16-23 24-31 1

WEEKLY TARGET ACCOMPLISHMENT 0.26 0.58 1.73 1.98 1.98 1.98 3.25 3.71 3.71 3.25 9.41 10.75 10.75 10.75 8.06 9.22 9.22 9.22 0.19
%
CUMM. TARGET ACCOMPLISHMENT 0.26 0.84 2.57 4.55 6.53 8.52 11.76 15.48 19.19 22.44 31.84 42.59 53.34 64.09 72.15 81.37 90.59 99.81 100
SUBMITTED BY: CHECKED BY: RECOMMENDING APPROVAL: APPROVED BY:

C.T. LEONCIO CONSTRUCTION AND TRADING WILFREDO S. FAJARDO WILFREDO D. FLORES EFREN C. MANALO, MPA
CONTRACTOR PROJECT ENGINEER OIC, ASST. DISTRICT ENGINEER DISTRICT ENGINEER
April 23, 2018
September 1, 2018

HEDULE AND BAR CHART


2018
SEPTEMBER OCT.
EFREN C. MANALO, MPA

You might also like