Project Code: J048 Package: 1 Contractor: Perdana Bayu Enterprise Eng. Consultant: Perunding Nusajasa SDN BHD Qs Consultant: Hra Juruukur Bahan

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 3

PROJECT CODE: J048

PACKAGE: 1
CONTRACTOR: PERDANA BAYU ENTERPRISE
ENG. CONSULTANT: PERUNDING NUSAJASA SDN BHD
QS CONSULTANT: HRA JURUUKUR BAHAN

1) Summary of Daily Physical Progress (Microsoft Project)


2-
8-Apr-18 9-Apr-18 10-Apr-18 11-Apr-18 12-Apr-18 13-Apr-18
PREVIOUS 5
DESCRIPTION PREVIOUS 7 DAYS PREVIOUS 7 DAYS PREVIOUS 7 DAYS PREVIOUS 6 DAYS PREVIOUS 4 DAYS
DAYS
Schedule (%) 84.00% 84.00% 84.00% 85.00% 86.00% 86.00%
Actual (%) 44.00% 44.00% 44.00% 44.00% 44.00% 44.00%
Ahead / Delay (% / Day) -40.00% -40.00% -40.00% -41.00% -42.00% -42.00%

2) Summary of Daily Physical Progress (Primavera P6)


DATE
8-Apr-18 9-Apr-18 10-Apr-18 11-Apr-18 12-Apr-18 13-Apr-18
PREVIOUS 5
DESCRIPTION PREVIOUS 7 DAYS PREVIOUS 7 DAYS PREVIOUS 7 DAYS PREVIOUS 6 DAYS PREVIOUS 4 DAYS
DAYS
Schedule (%) 86.85% 86.85% 86.85% 87.44% 88.03% 88.03%
Actual (%) 44.15% 44.15% 44.15% 44.15% 44.15% 44.15%
Ahead / Delay (% / Day) -42.70% -42.70% -42.70% -43.29% -43.88% -43.88%

3) Summary of Variance between Microsoft Project & Primavera P6


DATE
8-Apr-18 9-Apr-18 10-Apr-18 11-Apr-18 12-Apr-18 13-Apr-18
PREVIOUS 5
DESCRIPTION PREVIOUS 7 DAYS PREVIOUS 7 DAYS PREVIOUS 7 DAYS PREVIOUS 6 DAYS PREVIOUS 4 DAYS
DAYS
Variance (%) 2.85% 2.85% 2.85% 2.44% 2.03% 2.03%
2-WEEKS SUMMARY OF WORK PROGRESS
14-Apr-18 15-Apr-18 16-Apr-18 17-Apr-18 18-Apr-18 19-Apr-18 20-Apr-18 21-Apr-18

PREVIOUS 3 DAYS PREVIOUS 2 DAYS PREVIOUS 1 DAY YESTERDAY YESTERDAY YESTERDAY YESTERDAY YESTERDAY
87.00% 87.00% 88.00% 88.00% 89.00% 89.00% 89.00% 90.00%
44.00% 44.00% 44.00% 44.00% 44.00% 44.00% 44.00% 44.00%
-43.00% -43.00% -44.00% -44.00% -45.00% -45.00% -45.00% -46.00%

DATE DATE
14-Apr-18 15-Apr-18 16-Apr-18 17-Apr-18 18-Apr-18 19-Apr-18 20-Apr-18 21-Apr-18

PREVIOUS 3 DAYS PREVIOUS 2 DAYS PREVIOUS 1 DAY YESTERDAY YESTERDAY YESTERDAY YESTERDAY YESTERDAY
88.62% 89.21% 89.77% 90.33% 90.88% 91.44% 91.44% 91.99%
44.15% 44.15% 44.15% 44.15% 44.15% 44.15% 44.15% 44.15%
-44.47% -45.06% -45.62% -46.18% -46.73% -47.29% -47.29% -47.84%

DATE DATE
14-Apr-18 15-Apr-18 16-Apr-18 17-Apr-18 18-Apr-18 19-Apr-18 20-Apr-18 21-Apr-18

PREVIOUS 3 DAYS PREVIOUS 2 DAYS PREVIOUS 1 DAY YESTERDAY YESTERDAY YESTERDAY YESTERDAY YESTERDAY
1.62% 2.21% 1.77% 2.33% 1.88% 2.44% 2.44% 1.99%
REMARKS

REMARKS

REMARKS

2.34%