Professional Documents
Culture Documents
10.03.2018-P6 (Mip Rev.01)
10.03.2018-P6 (Mip Rev.01)
332.0d
STF PALONG TIMUR REV.05 ALL RUN BS 10.03.2018 - Overall Update - Drag172.0d -60.0dDate
To Actual 02-Oct-17 08:00 30-Aug-18 08:00 51.53% 43.25%
AM A AM
Milestone 280.0d 0.0d -52.0d 02-Oct-17 08:00 AM A
30-Aug-18 08:00 AM 0% 0%
STF1000 Milestone Start STF 0.0d 0.0d 02-Oct-17 08:00 AM A
02-Oct-17 08:00 AM A 100% 100%
STF1010 Milestone Finish STF 0.0d 0.0d -52.0d 30-Aug-18 08:00 AM*30-Aug-18 08:00 AM 0% 0%
General & Preliminaries 32.0d 0.0d 02-Oct-17 08:00 AM A
07-Nov-17 05:00 PM A 100% 100%
Underground Tank & Building 197.9d 107.9d 4.1d 11-Dec-17 08:00 AM26-Jun-18
A 03:00 PM 27.6% 29.7%
Wash Water Collection & Sludge Balancing Tank 155.0d 65.0d 46.0d 11-Dec-17 08:00 AM14-May-18
A 05:00 PM 57.3% 51.15%
Site Measurement & Site Preparation 55.0d 0.0d 11-Dec-17 08:00 AM03-Feb-18
A 05:00 PM A 100% 100%
STF1140 Site survey 11.0d 0.0d 11-Dec-17 08:00 AM21-Dec-17
A 05:00 PM A 100% 100%
STF1150 Site clearance 14.0d 0.0d 22-Dec-17 08:00 AM04-Jan-18
A 05:00 PM A 100% 100%
STF1160 Excavation, levelling & compaction works 26.0d 0.0d 05-Jan-18 08:00 AM 3
A0-Jan-18 05:00 PM A 100% 100%
STF1170 Install formwork 3.0d 0.0d 31-Jan-18 08:00 AM 0
A2-Feb-18 05:00 PM A 100% 100%
STF1180 Lay of 75mm thick lean concrete 1.0d 0.0d 03-Feb-18 08:00 AM 03-Feb-18
A 05:00 PM A 100% 100%
Slab for All excluding Drywells 19.0d 0.0d 04-Feb-18 08:00 AM 22-Feb-18
A 05:00 PM A 100% 100%
STF1190 Erect formwork, install reinforcement, kicker & waterstop 15.0d 0.0d 04-Feb-18 08:00 AM 19-Feb-18
A 05:00 PM A 100% 100%
STF1200 Inspection 1.0d 0.0d 19-Feb-18 08:00 AM 19-Feb-18
A 05:00 PM A 100% 100%
STF1210 Concreting & curing works 2.0d 0.0d 20-Feb-18 08:00 AM 21-Feb-18
A 05:00 PM A 100% 100%
STF1500 Erect formwork, install reinforcement 5.0d 5.0d -5.1d 05-Mar-18 08:00 AM24-Apr-18
A 05:00 PM 0% 12.5%
STF1510 Inspection 1.0d 1.0d -5.1d 25-Apr-18 08:00 AM*25-Apr-18 05:00 PM 0% 0%
STF1520 Concreting works 1.0d 1.0d -5.1d 26-Apr-18 08:00 AM*26-Apr-18 05:00 PM 0% 0%
STF1530 Curing works 3.0d 3.0d -5.1d 27-Apr-18 08:00 AM*29-Apr-18 05:00 PM 0% 0%
STF1540 Dismantle formwork, scaffold & stagging 1.0d 1.0d -5.1d 30-Apr-18 08:00 AM*30-Apr-18 05:00 PM 0% 0%
Cantilever Beam, Walkway Slab & Overflow Slab/Wall 12.0d 12.0d -5.1d 19-Apr-18 08:00 AM 30-Apr-18 05:00 PM 0% 0%
STF1550 Erect scaffold & stagging 1.0d 1.0d -5.1d 19-Apr-18 08:00 AM*19-Apr-18 05:00 PM 0% 0%
STF1560 Erect & install formwork, t-props, soffit and reinforcement 4.0d 4.0d -5.1d 20-Apr-18 08:00 AM*23-Apr-18 05:00 PM 0% 0%
STF1570 Install 2 units of 200mm dia. of pipes at Overflow Wall A & C 1.0d 1.0d -5.1d 24-Apr-18 08:00 AM*24-Apr-18 05:00 PM 0% 0%
STF1580 Inspection 1.0d 1.0d -5.1d 25-Apr-18 08:00 AM*25-Apr-18 05:00 PM 0% 0%
STF1590 Concreting works 1.0d 1.0d -5.1d 26-Apr-18 08:00 AM*26-Apr-18 05:00 PM 0% 0%
STF1600 Curing works 3.0d 3.0d -5.1d 27-Apr-18 08:00 AM*29-Apr-18 05:00 PM 0% 0%
STF1610 Dismantle formwork, t-props, soffit, scaffold & stagging 1.0d 1.0d -5.1d 30-Apr-18 08:00 AM*30-Apr-18 05:00 PM 0% 0%
Partial Backfilling (Drywells Area) 6.0d 6.0d -5.1d 01-May-18 08:00 AM06-May-18 05:00 PM 0% 0%
STF1620 Repair of cold joints & honeycomb at affected area 1.0d 1.0d -5.1d 01-May-18 08:00 AM*
01-May-18 05:00 PM 0% 0%
STF1630 Partial backfilling & compaction (1st stage) 1.0d 1.0d -5.1d 02-May-18 08:00 AM*
02-May-18 05:00 PM 0% 0%
STF1640 Reinstate existing sump 2.0d 2.0d -5.1d 03-May-18 08:00 AM*
04-May-18 05:00 PM 0% 0%
STF1650 Reinstate existing sewer pipes 1.0d 1.0d -5.1d 05-May-18 08:00 AM*
05-May-18 05:00 PM 0% 0%
STF1660 Partial backfilling & compaction (2nd stage) 1.0d 1.0d -5.1d 06-May-18 08:00 AM*
06-May-18 05:00 PM 0% 0%
Repair of Cold Joints, Waterproofing & Painting 4.0d 4.0d 46.0d 02-May-18 08:00 AM05-May-18 05:00 PM 0% 0%
STF1670 Repair of cold joints & honeycomb 2.0d 2.0d 46.0d 02-May-18 08:00 AM*
03-May-18 05:00 PM 0% 0%
STF1680 Waterproofing of internal wall 1.0d 1.0d 46.0d 04-May-18 08:00 AM*
04-May-18 05:00 PM 0% 0%
STF1690 Painting (1 coat resistant primer & 2 coats anti-fungus) 1.0d 1.0d 46.0d 04-May-18 08:00 AM*
04-May-18 05:00 PM 0% 0%
STF1700 Cleanup site 1.0d 1.0d 46.0d 05-May-18 08:00 AM*
05-May-18 05:00 PM 0% 0%
Water Tighness Testing & Backfilling 9.0d 9.0d 46.0d 06-May-18 08:00 AM14-May-18 05:00 PM 0% 0%
STF1710 To fill up WWCT & SBT with water 1.0d 1.0d 46.0d 06-May-18 08:00 AM*
06-May-18 05:00 PM 0% 0%
STF1720 Monitoring 3.0d 3.0d 46.0d 07-May-18 08:00 AM*
09-May-18 05:00 PM 0% 0%
STF1730 To backfill & compact outer perimeter of WWCT & SBT 5.0d 5.0d 46.0d 10-May-18 08:00 AM*
14-May-18 05:00 PM 0% 0%
Dewatering Platform (Geotube) 155.5d 48.5d 3.5d 15-Jan-18 08:00 AM 1
A9-Jun-18 12:00 PM 0% 15.44%
Excavation Works & Hardcore 112.0d 5.0d 4.0d 15-Jan-18 08:00 AM 0
A6-May-18 05:00 PM 0% 18%
STF1740 Site measurement & marking 1.0d 1.0d 4.0d 02-May-18 08:00 AM*
02-May-18 05:00 PM 0% 0%
STF1750 To excavate, level & compact ground 3.0d 3.0d 4.0d 15-Jan-18 08:00 AM 0
A5-May-18 05:00 PM 0% 30%
STF1760 To lay, spread & compact Crusher-run as hardcore (0.3m Thk) 1.0d 1.0d 4.0d 06-May-18 08:00 AM*
06-May-18 05:00 PM 0% 0%
STF2050 Cleanup site 1.0d 1.0d 3.5d 18-Jun-18 01:00 PM*19-Jun-18 12:00 PM 0% 0%
Polymer Building 162.9d 50.9d 4.1d 15-Jan-18 08:00 AM 2
A6-Jun-18 03:00 PM 0% 7.93%
Footing (1m x 1m - 0.3m Thk) & Stump (0.3m x 0.3m - 0.45m Thk) 120.0d 8.0d -5.0d 15-Jan-18 08:00 AM 1
A4-May-18 05:00 PM 0% 15.45%
STF2060 To excavate, level & compact ground to receive foundation 1.0d 1.0d -5.1d 15-Jan-18 08:00 AM 0
A7-May-18 05:00 PM 0% 50%
STF2070 Install formwork, lay of 50mm thick lean concrete 1.0d 1.0d -5.1d 01-Feb-18 08:00 AM 08-May-18
A 05:00 PM 0% 30%
STF2080 Erect formwork & install reinforcement 3.0d 3.0d -7.5d 01-Feb-18 07:00 PM10-May-18
A 05:00 PM 0% 30%
STF2090 Inspection 1.0d 1.0d -5.0d 10-May-18 08:00 AM*
10-May-18 05:00 PM 0% 0%
STF2100 Concreting works 1.0d 1.0d -5.0d 11-May-18 08:00 AM*
11-May-18 05:00 PM 0% 0%
STF2110 Curing works 2.0d 2.0d -5.0d 12-May-18 08:00 AM*
13-May-18 05:00 PM 0% 0%
STF2120 Dismantle formwork 1.0d 1.0d -5.0d 13-May-18 08:00 AM*
13-May-18 05:00 PM 0% 0%
STF2130 Backfilling & compaction works to the level of top stump 1.0d 1.0d -5.0d 14-May-18 08:00 AM*
14-May-18 05:00 PM 0% 0%
Ground Beam (0.3m x 0.6m) & Ground Slab (0.2m Thk) 112.0d 9.0d -5.0d 01-Feb-18 08:00 AM 23-May-18
A 05:00 PM 0% 12.5%
STF2140 Erect formwork surround the outer of stump 1.0d 1.0d -5.0d 01-Feb-18 08:00 AM 15-May-18
A 05:00 PM 0% 30%
STF2150 Backfilling & compaction works to the level of bottom slab 2.0d 2.0d -5.0d 16-May-18 08:00 AM*
17-May-18 05:00 PM 0% 0%
STF2160 Install formwork, lay of 50mm thick lean concrete 1.0d 1.0d -5.0d 01-Feb-18 08:00 AM 18-May-18
A 05:00 PM 0% 30%
STF2170 Install reinforcement both ground beam & slab 3.0d 3.0d -7.4d 01-Feb-18 07:00 PM20-May-18
A 05:00 PM 0% 30%
STF2180 Inspection 1.0d 1.0d -5.0d 20-May-18 08:00 AM*
20-May-18 05:00 PM 0% 0%
STF2190 Concreting works 1.0d 1.0d -5.0d 21-May-18 08:00 AM*
21-May-18 05:00 PM 0% 0%
STF2200 Curing works 2.0d 2.0d -5.0d 22-May-18 08:00 AM*
23-May-18 05:00 PM 0% 0%
STF2210 Dismantle formwork 1.0d 1.0d -5.0d 23-May-18 08:00 AM*
23-May-18 05:00 PM 0% 0%
Column - 5.5m (0.25mm x 0.25mm) 119.0d 8.0d 31.0d 01-Feb-18 08:00 AM 30-May-18
A 05:00 PM 0% 9%
STF2220 Install reinforcement 2.0d 2.0d -7.5d 01-Feb-18 08:00 AM 24-May-18
A 12:00 PM 0% 30%
STF2230 Erect formwork & bracing 1.0d 1.0d -7.5d 01-Feb-18 01:00 PM24-May-18
A 11:00 PM 0% 30%
STF2240 Inspection 1.0d 1.0d 31.0d 24-May-18 08:00 AM*
25-May-18 08:00 AM 0% 0%
STF2250 Concreting works 2.0d 2.0d 31.0d 25-May-18 08:00 AM*
26-May-18 05:00 PM 0% 0%
STF2260 Curing works 3.0d 3.0d 31.0d 27-May-18 08:00 AM*
29-May-18 05:00 PM 0% 0%
STF2270 Dismantle formwork & bracing 1.0d 1.0d 31.0d 30-May-18 08:00 AM*
30-May-18 05:00 PM 0% 0%
Intermediate Beam (0.25mm x 0.5mm) 121.0d 8.0d -5.0d 01-Feb-18 08:00 AM 01-Jun-18
A 05:00 PM 0% 12%
STF2350 Erect scaffold, stagging, t-prox & soffit 1.0d 1.0d -7.5d 01-Mar-18 08:00 AM25-May-18
A 08:00 PM 0% 30%
STF2360 Install reinforcement 2.0d 2.0d -7.5d 01-Feb-18 07:00 PM27-May-18
A 09:00 AM 0% 30%
STF2370 Erect formwork 1.0d 1.0d -7.5d 01-Feb-18 08:00 AM 27-May-18
A 08:00 PM 0% 30%
STF2380 Inspection 1.0d 1.0d -5.0d 27-May-18 08:00 AM*
28-May-18 08:00 AM 0% 0%
STF2390 Concreting works 1.0d 1.0d -5.0d 28-May-18 08:00 AM*
28-May-18 05:00 PM 0% 0%
STF2620 Excavation & levelling works 2.0d 2.0d 3.0d 15-Jan-18 08:00 AM 1
A3-Jun-18 05:00 PM 0% 30%
STF2630 Erect formwork 1.0d 1.0d 4.9d 01-Feb-18 07:00 PM14-Jun-18
A 12:00 PM 0% 30%
STF2640 Install reinforcement 3.0d 3.0d 4.9d 01-Feb-18 01:00 PM16-Jun-18
A 02:00 PM 0% 30%
STF2650 Inspection 1.0d 1.0d 3.4d 15-Jun-18 02:00 PM*16-Jun-18 02:00 PM 0% 0%
STF2660 Concreting works 1.0d 1.0d 3.4d 16-Jun-18 02:00 PM*17-Jun-18 02:00 PM 0% 0%
STF2670 Curing works 2.0d 2.0d 3.4d 17-Jun-18 02:00 PM*19-Jun-18 02:00 PM 0% 0%
STF2680 Dismantle formwork 1.0d 1.0d 3.4d 19-Jun-18 02:00 PM*20-Jun-18 02:00 PM 0% 0%
Apron & Ramp - Team C 145.3d 6.1d 3.1d 01-Feb-18 01:00 PM26-Jun-18
A 03:00 PM 0% 11.25%
STF2690 Backfilling, levelling & compaction works 1.0d 1.0d 3.4d 20-Jun-18 02:00 PM*21-Jun-18 02:00 PM 0% 0%
STF2700 Erect formwork, install reinforcement 3.0d 3.0d 4.8d 01-Feb-18 01:00 PM23-Jun-18
A 03:00 PM 0% 30%
STF2710 Inspection 1.0d 1.0d 3.3d 22-Jun-18 03:00 PM*23-Jun-18 03:00 PM 0% 0%
STF2720 Concreting works 1.0d 1.0d 3.3d 23-Jun-18 03:00 PM*24-Jun-18 03:00 PM 0% 0%
STF2730 Curing works 1.0d 1.0d 3.3d 24-Jun-18 03:00 PM*25-Jun-18 03:00 PM 0% 0%
STF2740 Dismantle formwork & cleanup site 1.0d 1.0d 3.3d 25-Jun-18 03:00 PM*26-Jun-18 03:00 PM 0% 0%
Pipeworks (200mm & 300mm Dia. Pipe) 136.0d 88.0d 8.0d 22-Jan-18 08:00 AM 0
A6-Jun-18 05:00 PM 53.33% 10%
Reinstatement of Damaged Existing Road 7.0d 7.0d 3.5d 19-Jun-18 01:00 PM 26-Jun-18 12:00 PM 0% 0%
STF3420 Site clearance, levelling & compaction 5.0d 5.0d 3.5d 19-Jun-18 01:00 PM 24-Jun-18 12:00 PM 0% 0%
STF3430 Lay & compact crusher-run & premix (binder and wearing coarse) 7.0d 7.0d 3.5d 19-Jun-18 01:00 PM 26-Jun-18 12:00 PM 0% 0%
Site Handover Works 13.0d 13.0d -52.0d 15-Aug-18 08:00 AM 29-Aug-18 05:00 PM 0% 0%