STF PALONG TIMUR REV.05 ALL RUN BS 10.03.

2018 - Overall Classic Schedule Layout 05-May-18 08:56 PM


Activity ID Activity Name Original Remaining Total Start Finish Schedule % Units %
Duration Duration Float Complete Complete

332.0d
STF PALONG TIMUR REV.05 ALL RUN BS 10.03.2018 - Overall Update - Drag172.0d -60.0dDate
To Actual 02-Oct-17 08:00 30-Aug-18 08:00 51.53% 43.25%
AM A AM
Milestone 280.0d 0.0d -52.0d 02-Oct-17 08:00 AM A
30-Aug-18 08:00 AM 0% 0%
STF1000 Milestone Start STF 0.0d 0.0d 02-Oct-17 08:00 AM A
02-Oct-17 08:00 AM A 100% 100%
STF1010 Milestone Finish STF 0.0d 0.0d -52.0d 30-Aug-18 08:00 AM*30-Aug-18 08:00 AM 0% 0%
General & Preliminaries 32.0d 0.0d 02-Oct-17 08:00 AM A
07-Nov-17 05:00 PM A 100% 100%

Documentation 32.0d 0.0d 02-Oct-17 08:00 AM A


07-Nov-17 05:00 PM A 100% 100%
Preparation & Submission 32.0d 0.0d 02-Oct-17 08:00 AM A
07-Nov-17 05:00 PM A 100% 100%
STF1020 Preparation of Performance Bond 14.0d 0.0d 02-Oct-17 08:00 AM A
17-Oct-17 05:00 PM A 100% 100%
STF1030 Preparation of Insurances Policies / Public Liability / Workmen's Compensation
14.0d 0.0d 02-Oct-17 08:00 AM A
17-Oct-17 05:00 PM A 100% 100%
STF1040 Preparation & Submission of Levy of CIDB 14.0d 0.0d 02-Oct-17 08:00 AM A
17-Oct-17 05:00 PM A 100% 100%
STF1050 Site Registration of JKKP (DOSH) 14.0d 0.0d 02-Oct-17 08:00 AM A
17-Oct-17 05:00 PM A 100% 100%
STF1060 Submission Copy of SPAN Certificate 14.0d 0.0d 02-Oct-17 08:00 AM A
17-Oct-17 05:00 PM A 100% 100%
STF1070 Preparation & Submission of Lithography Expenses 14.0d 0.0d 02-Oct-17 08:00 AM A
17-Oct-17 05:00 PM A 100% 100%
STF1080 Preparation & Submission of PQP / Method Statements 14.0d 0.0d 02-Oct-17 08:00 AM A
17-Oct-17 05:00 PM A 100% 100%
STF1090 Preparation of Works (Contractor Requirements) 18.0d 0.0d 18-Oct-17 08:00 AM A
07-Nov-17 05:00 PM A 100% 100%
STF1100 Preparation of Works (Engineers / S.O / PD's Requirements) 18.0d 0.0d 18-Oct-17 08:00 AM A
07-Nov-17 05:00 PM A 100% 100%
STF1110 Preparation of Works (General Obligation, Project Requirements) 18.0d 0.0d 18-Oct-17 08:00 AM A
07-Nov-17 05:00 PM A 100% 100%
STF1120 Preparation of Works (Authorities Requirements) 18.0d 0.0d 18-Oct-17 08:00 AM A
07-Nov-17 05:00 PM A 100% 100%
STF1130 Preparation of Works (Environmental Protection & Enhancement) 18.0d 0.0d 18-Oct-17 08:00 AM A
07-Nov-17 05:00 PM A 100% 100%
Civil & Structures 197.9d 107.9d 4.1d 11-Dec-17 08:00 AM26-Jun-18
A 03:00 PM 27.6% 29.7%

Underground Tank & Building 197.9d 107.9d 4.1d 11-Dec-17 08:00 AM26-Jun-18
A 03:00 PM 27.6% 29.7%
Wash Water Collection & Sludge Balancing Tank 155.0d 65.0d 46.0d 11-Dec-17 08:00 AM14-May-18
A 05:00 PM 57.3% 51.15%
Site Measurement & Site Preparation 55.0d 0.0d 11-Dec-17 08:00 AM03-Feb-18
A 05:00 PM A 100% 100%
STF1140 Site survey 11.0d 0.0d 11-Dec-17 08:00 AM21-Dec-17
A 05:00 PM A 100% 100%
STF1150 Site clearance 14.0d 0.0d 22-Dec-17 08:00 AM04-Jan-18
A 05:00 PM A 100% 100%
STF1160 Excavation, levelling & compaction works 26.0d 0.0d 05-Jan-18 08:00 AM 3
A0-Jan-18 05:00 PM A 100% 100%
STF1170 Install formwork 3.0d 0.0d 31-Jan-18 08:00 AM 0
A2-Feb-18 05:00 PM A 100% 100%
STF1180 Lay of 75mm thick lean concrete 1.0d 0.0d 03-Feb-18 08:00 AM 03-Feb-18
A 05:00 PM A 100% 100%
Slab for All excluding Drywells 19.0d 0.0d 04-Feb-18 08:00 AM 22-Feb-18
A 05:00 PM A 100% 100%
STF1190 Erect formwork, install reinforcement, kicker & waterstop 15.0d 0.0d 04-Feb-18 08:00 AM 19-Feb-18
A 05:00 PM A 100% 100%
STF1200 Inspection 1.0d 0.0d 19-Feb-18 08:00 AM 19-Feb-18
A 05:00 PM A 100% 100%
STF1210 Concreting & curing works 2.0d 0.0d 20-Feb-18 08:00 AM 21-Feb-18
A 05:00 PM A 100% 100%

Page 1 of 10 TASK filter: All Activities


© Oracle Corporation
STF PALONG TIMUR REV.05 ALL RUN BS 10.03.2018 - Overall Classic Schedule Layout 05-May-18 08:56 PM
Activity ID Activity Name Original Remaining Total Start Finish Schedule % Units %
Duration Duration Float Complete Complete

STF1220 Dismantle formwork 1.0d 0.0d 22-Feb-18 08:00 AM 22-Feb-18


A 05:00 PM A 100% 100%
Slab for Drywells 11.0d 3.0d -5.1d 03-Mar-18 08:00 AM13-Mar-18
A 05:00 PM 100% 77.78%
STF1230 To excavate, level & compact 1.0d 0.0d 03-Mar-18 08:00 AM03-Mar-18
A 05:00 PM A 100% 100%
STF1240 Lay of 75mm thick lean concrete 1.0d 0.0d 03-Mar-18 08:00 AM03-Mar-18
A 05:00 PM A 100% 100%
STF1250 Erect formwork, install reinforcement, kicker & waterstop 3.0d 0.0d 04-Mar-18 08:00 AM06-Mar-18
A 05:00 PM A 100% 100%
STF1260 Inspection 1.0d 0.0d 06-Mar-18 08:00 AM08-Mar-18
A 05:00 PM A 100% 100%
STF1270 Concreting & curing works 2.0d 2.0d -5.1d 10-Mar-18 08:00 AM12-Mar-18
A 05:00 PM 100% 50%
STF1280 Dismantle formwork 1.0d 1.0d -5.1d 13-Mar-18 08:00 AM*
13-Mar-18 05:00 PM 100% 0%
Wall '1' - 1st Lift (1.5m) 31.0d 11.0d -5.1d 22-Feb-18 08:00 AM 24-Mar-18
A 05:00 PM 69.23% 5.68%
STF1290 Erect scaffold & stagging 1.0d 1.0d -5.1d 28-Feb-18 08:00 AM 14-Mar-18
A 05:00 PM 100% 12.5%
STF1300 Erect formwork, install reinforcement, kicker & waterstop 4.0d 4.0d -5.1d 22-Feb-18 08:00 AM 18-Mar-18
A 05:00 PM 100% 12.5%
STF1310 Inspection 1.0d 1.0d -5.1d 19-Mar-18 08:00 AM*
19-Mar-18 05:00 PM 100% 0%
STF1320 Concreting works 1.0d 1.0d -5.1d 20-Mar-18 08:00 AM*
20-Mar-18 05:00 PM 100% 0%
STF1330 Curing works 3.0d 3.0d -5.1d 21-Mar-18 08:00 AM*
23-Mar-18 05:00 PM 0% 0%
STF1340 Dismantle formwork, scaffold & stagging 1.0d 1.0d -5.1d 24-Mar-18 08:00 AM*
24-Mar-18 05:00 PM 0% 0%
Wall '2' - 1st Lift (1.5m & 2.4m) 39.0d 13.0d -5.1d 27-Feb-18 08:00 AM 06-Apr-18
A 05:00 PM 0% 4.81%
STF1350 Erect scaffold & stagging 1.0d 1.0d -5.1d 01-Mar-18 08:00 AM25-Mar-18
A 05:00 PM 0% 12.5%
STF1360 Erect formwork, install reinforcement, kicker & waterstop 4.0d 4.0d -5.1d 27-Feb-18 08:00 AM 29-Mar-18
A 05:00 PM 0% 12.5%
STF1370 Install 4 units of 100mm dia. Pipes 2.0d 2.0d -5.1d 30-Mar-18 08:00 AM*
31-Mar-18 05:00 PM 0% 0%
STF1380 Inspection 1.0d 1.0d -5.1d 01-Apr-18 08:00 AM*01-Apr-18 05:00 PM 0% 0%
STF1390 Concreting works 1.0d 1.0d -5.1d 02-Apr-18 08:00 AM*02-Apr-18 05:00 PM 0% 0%
STF1400 Curing works 3.0d 3.0d -5.1d 03-Apr-18 08:00 AM*05-Apr-18 05:00 PM 0% 0%
STF1410 Dismantle formwork, scaffold & stagging 1.0d 1.0d -5.1d 06-Apr-18 08:00 AM*06-Apr-18 05:00 PM 0% 0%
Wall '1' - 2nd Lift (2.1m) 49.0d 12.0d -5.1d 01-Mar-18 08:00 AM18-Apr-18
A 05:00 PM 0% 4.17%
STF1420 Erect scaffold & stagging 1.0d 1.0d -5.1d 07-Apr-18 08:00 AM*07-Apr-18 05:00 PM 0% 0%
STF1430 Erect formwork, install reinforcement 4.0d 4.0d -5.1d 01-Mar-18 08:00 AM11-Apr-18
A 05:00 PM 0% 12.5%
STF1440 Install 2 units of 300mm dia. of pipes (level - 22.50) 1.0d 1.0d -5.1d 12-Apr-18 08:00 AM*12-Apr-18 05:00 PM 0% 0%
STF1450 Inspection 1.0d 1.0d -5.1d 13-Apr-18 08:00 AM*13-Apr-18 05:00 PM 0% 0%
STF1460 Concreting works 1.0d 1.0d -5.1d 14-Apr-18 08:00 AM*14-Apr-18 05:00 PM 0% 0%
STF1470 Curing works 3.0d 3.0d -5.1d 15-Apr-18 08:00 AM*17-Apr-18 05:00 PM 0% 0%
STF1480 Dismantle formwork, scaffold & stagging 1.0d 1.0d -5.1d 18-Apr-18 08:00 AM*18-Apr-18 05:00 PM 0% 0%
Wall '2' - 2nd Lift (2.1m, 1.45m, 2.15m) 57.0d 12.0d -5.1d 05-Mar-18 08:00 AM30-Apr-18
A 05:00 PM 0% 5.21%
STF1490 Erect scaffold & stagging 1.0d 1.0d -5.1d 19-Apr-18 08:00 AM*19-Apr-18 05:00 PM 0% 0%

Page 2 of 10 TASK filter: All Activities


© Oracle Corporation
STF PALONG TIMUR REV.05 ALL RUN BS 10.03.2018 - Overall Classic Schedule Layout 05-May-18 08:56 PM
Activity ID Activity Name Original Remaining Total Start Finish Schedule % Units %
Duration Duration Float Complete Complete

STF1500 Erect formwork, install reinforcement 5.0d 5.0d -5.1d 05-Mar-18 08:00 AM24-Apr-18
A 05:00 PM 0% 12.5%
STF1510 Inspection 1.0d 1.0d -5.1d 25-Apr-18 08:00 AM*25-Apr-18 05:00 PM 0% 0%
STF1520 Concreting works 1.0d 1.0d -5.1d 26-Apr-18 08:00 AM*26-Apr-18 05:00 PM 0% 0%
STF1530 Curing works 3.0d 3.0d -5.1d 27-Apr-18 08:00 AM*29-Apr-18 05:00 PM 0% 0%
STF1540 Dismantle formwork, scaffold & stagging 1.0d 1.0d -5.1d 30-Apr-18 08:00 AM*30-Apr-18 05:00 PM 0% 0%
Cantilever Beam, Walkway Slab & Overflow Slab/Wall 12.0d 12.0d -5.1d 19-Apr-18 08:00 AM 30-Apr-18 05:00 PM 0% 0%
STF1550 Erect scaffold & stagging 1.0d 1.0d -5.1d 19-Apr-18 08:00 AM*19-Apr-18 05:00 PM 0% 0%
STF1560 Erect & install formwork, t-props, soffit and reinforcement 4.0d 4.0d -5.1d 20-Apr-18 08:00 AM*23-Apr-18 05:00 PM 0% 0%
STF1570 Install 2 units of 200mm dia. of pipes at Overflow Wall A & C 1.0d 1.0d -5.1d 24-Apr-18 08:00 AM*24-Apr-18 05:00 PM 0% 0%
STF1580 Inspection 1.0d 1.0d -5.1d 25-Apr-18 08:00 AM*25-Apr-18 05:00 PM 0% 0%
STF1590 Concreting works 1.0d 1.0d -5.1d 26-Apr-18 08:00 AM*26-Apr-18 05:00 PM 0% 0%
STF1600 Curing works 3.0d 3.0d -5.1d 27-Apr-18 08:00 AM*29-Apr-18 05:00 PM 0% 0%
STF1610 Dismantle formwork, t-props, soffit, scaffold & stagging 1.0d 1.0d -5.1d 30-Apr-18 08:00 AM*30-Apr-18 05:00 PM 0% 0%
Partial Backfilling (Drywells Area) 6.0d 6.0d -5.1d 01-May-18 08:00 AM06-May-18 05:00 PM 0% 0%
STF1620 Repair of cold joints & honeycomb at affected area 1.0d 1.0d -5.1d 01-May-18 08:00 AM*
01-May-18 05:00 PM 0% 0%
STF1630 Partial backfilling & compaction (1st stage) 1.0d 1.0d -5.1d 02-May-18 08:00 AM*
02-May-18 05:00 PM 0% 0%
STF1640 Reinstate existing sump 2.0d 2.0d -5.1d 03-May-18 08:00 AM*
04-May-18 05:00 PM 0% 0%
STF1650 Reinstate existing sewer pipes 1.0d 1.0d -5.1d 05-May-18 08:00 AM*
05-May-18 05:00 PM 0% 0%
STF1660 Partial backfilling & compaction (2nd stage) 1.0d 1.0d -5.1d 06-May-18 08:00 AM*
06-May-18 05:00 PM 0% 0%
Repair of Cold Joints, Waterproofing & Painting 4.0d 4.0d 46.0d 02-May-18 08:00 AM05-May-18 05:00 PM 0% 0%
STF1670 Repair of cold joints & honeycomb 2.0d 2.0d 46.0d 02-May-18 08:00 AM*
03-May-18 05:00 PM 0% 0%
STF1680 Waterproofing of internal wall 1.0d 1.0d 46.0d 04-May-18 08:00 AM*
04-May-18 05:00 PM 0% 0%
STF1690 Painting (1 coat resistant primer & 2 coats anti-fungus) 1.0d 1.0d 46.0d 04-May-18 08:00 AM*
04-May-18 05:00 PM 0% 0%
STF1700 Cleanup site 1.0d 1.0d 46.0d 05-May-18 08:00 AM*
05-May-18 05:00 PM 0% 0%
Water Tighness Testing & Backfilling 9.0d 9.0d 46.0d 06-May-18 08:00 AM14-May-18 05:00 PM 0% 0%
STF1710 To fill up WWCT & SBT with water 1.0d 1.0d 46.0d 06-May-18 08:00 AM*
06-May-18 05:00 PM 0% 0%
STF1720 Monitoring 3.0d 3.0d 46.0d 07-May-18 08:00 AM*
09-May-18 05:00 PM 0% 0%
STF1730 To backfill & compact outer perimeter of WWCT & SBT 5.0d 5.0d 46.0d 10-May-18 08:00 AM*
14-May-18 05:00 PM 0% 0%
Dewatering Platform (Geotube) 155.5d 48.5d 3.5d 15-Jan-18 08:00 AM 1
A9-Jun-18 12:00 PM 0% 15.44%
Excavation Works & Hardcore 112.0d 5.0d 4.0d 15-Jan-18 08:00 AM 0
A6-May-18 05:00 PM 0% 18%
STF1740 Site measurement & marking 1.0d 1.0d 4.0d 02-May-18 08:00 AM*
02-May-18 05:00 PM 0% 0%
STF1750 To excavate, level & compact ground 3.0d 3.0d 4.0d 15-Jan-18 08:00 AM 0
A5-May-18 05:00 PM 0% 30%
STF1760 To lay, spread & compact Crusher-run as hardcore (0.3m Thk) 1.0d 1.0d 4.0d 06-May-18 08:00 AM*
06-May-18 05:00 PM 0% 0%

Page 3 of 10 TASK filter: All Activities


© Oracle Corporation
STF PALONG TIMUR REV.05 ALL RUN BS 10.03.2018 - Overall Classic Schedule Layout 05-May-18 08:56 PM
Activity ID Activity Name Original Remaining Total Start Finish Schedule % Units %
Duration Duration Float Complete Complete

Drain (Base) 105.1d 10.1d 3.9d 01-Feb-18 08:00 AM 17-May-18


A 09:00 AM 0% 17.5%
STF1770 Install formwork, lay of 50mm thick lean concrete 2.0d 2.0d 4.0d 01-Feb-18 08:00 AM 08-May-18
A 05:00 PM 0% 30%
STF1780 Erect formwork, install reinforcement 5.0d 5.0d 5.9d 01-Feb-18 07:00 PM12-May-18
A 09:00 AM 0% 30%
STF1790 Inspection 1.0d 1.0d 3.9d 12-May-18 09:00 AM*
13-May-18 09:00 AM 0% 0%
STF1800 Concreting works 2.0d 2.0d 3.9d 13-May-18 09:00 AM*
15-May-18 09:00 AM 0% 0%
STF1810 Curing works 1.0d 1.0d 3.9d 15-May-18 09:00 AM*
16-May-18 09:00 AM 0% 0%
STF1820 Dismantle formwork 1.0d 1.0d 3.9d 16-May-18 09:00 AM*
17-May-18 09:00 AM 0% 0%
Drain (Wall - 2 sides) 115.0d 10.9d 3.5d 01-Feb-18 07:00 PM27-May-18
A 05:00 PM 0% 16.15%
STF1830 Erect formwork, install reinforcement 7.0d 7.0d 5.3d 01-Feb-18 07:00 PM21-May-18
A 09:00 PM 0% 30%
STF1840 Inspection 1.0d 1.0d 3.5d 22-May-18 08:00 AM*
22-May-18 05:00 PM 0% 0%
STF1850 Concreting works 2.0d 2.0d 3.5d 23-May-18 08:00 AM*
24-May-18 05:00 PM 0% 0%
STF1860 Curing works 1.0d 1.0d 3.5d 25-May-18 08:00 AM*
25-May-18 05:00 PM 0% 0%
STF1870 Dismantle formwork & backfilling works 2.0d 2.0d 3.5d 26-May-18 08:00 AM*
27-May-18 05:00 PM 0% 0%
Ground Slab 127.1d 11.8d 4.3d 01-Feb-18 01:00 PM08-Jun-18
A 02:00 PM 0% 19.29%
STF1880 Install formwork, lay of 50mm thick lean concrete 2.0d 2.0d 4.5d 01-Feb-18 01:00 PM29-May-18
A 05:00 PM 0% 30%
STF1890 Erect formwork, install reinforcement 7.0d 7.0d 6.9d 01-Feb-18 01:00 PM03-Jun-18
A 02:00 PM 0% 30%
STF1900 Inspection 1.0d 1.0d 4.4d 03-Jun-18 02:00 PM*04-Jun-18 02:00 PM 0% 0%
STF1910 Concreting works 2.0d 2.0d 4.4d 04-Jun-18 02:00 PM*06-Jun-18 02:00 PM 0% 0%
STF1920 Curing works 1.0d 1.0d 4.4d 06-Jun-18 02:00 PM*07-Jun-18 02:00 PM 0% 0%
STF1930 Dismantle formwork 1.0d 1.0d 4.4d 07-Jun-18 02:00 PM*08-Jun-18 02:00 PM 0% 0%
Ramp 127.9d 12.5d 3.5d 01-Feb-18 01:00 PM09-Jun-18
A 12:00 PM 0% 12.86%
STF1940 Install formwork, lay of 50mm thick lean concrete 2.0d 2.0d 3.5d 01-Feb-18 01:00 PM29-May-18
A 05:00 PM 0% 30%
STF1950 Erect formwork, install reinforcement 4.0d 4.0d 5.4d 01-Feb-18 01:00 PM01-Jun-18
A 12:00 PM 0% 30%
STF1960 Inspection 1.0d 1.0d 3.5d 01-Jun-18 01:00 PM*02-Jun-18 12:00 PM 0% 0%
STF1970 Concreting works 2.0d 2.0d 3.5d 02-Jun-18 01:00 PM*04-Jun-18 12:00 PM 0% 0%
STF1980 Curing works 1.0d 1.0d 3.5d 04-Jun-18 01:00 PM*05-Jun-18 12:00 PM 0% 0%
STF1990 Dismantle formwork 1.0d 1.0d 3.5d 05-Jun-18 01:00 PM*06-Jun-18 12:00 PM 0% 0%
STF2000 Install cheuque plate covers 1.0d 1.0d 3.5d 06-Jun-18 01:00 PM*07-Jun-18 12:00 PM 0% 0%
STF2010 To clean up site condition including levelling & compaction 2.0d 2.0d 3.5d 07-Jun-18 01:00 PM*09-Jun-18 12:00 PM 0% 0%
Geotube 110.5d 10.0d 3.5d 01-Mar-18 08:00 AM19-Jun-18
A 12:00 PM 0% 9%
STF2020 Delivery of 30 units of geotube to site 3.0d 3.0d 3.5d 01-Mar-18 08:00 AM12-Jun-18
A 12:00 PM 0% 30%
STF2030 Setting of site ready for installation works 1.0d 1.0d 3.5d 12-Jun-18 01:00 PM*13-Jun-18 12:00 PM 0% 0%
STF2040 Installation of geotube and necessarry works 5.0d 5.0d 3.5d 13-Jun-18 01:00 PM*18-Jun-18 12:00 PM 0% 0%

Page 4 of 10 TASK filter: All Activities


© Oracle Corporation
STF PALONG TIMUR REV.05 ALL RUN BS 10.03.2018 - Overall Classic Schedule Layout 05-May-18 08:56 PM
Activity ID Activity Name Original Remaining Total Start Finish Schedule % Units %
Duration Duration Float Complete Complete

STF2050 Cleanup site 1.0d 1.0d 3.5d 18-Jun-18 01:00 PM*19-Jun-18 12:00 PM 0% 0%
Polymer Building 162.9d 50.9d 4.1d 15-Jan-18 08:00 AM 2
A6-Jun-18 03:00 PM 0% 7.93%
Footing (1m x 1m - 0.3m Thk) & Stump (0.3m x 0.3m - 0.45m Thk) 120.0d 8.0d -5.0d 15-Jan-18 08:00 AM 1
A4-May-18 05:00 PM 0% 15.45%
STF2060 To excavate, level & compact ground to receive foundation 1.0d 1.0d -5.1d 15-Jan-18 08:00 AM 0
A7-May-18 05:00 PM 0% 50%
STF2070 Install formwork, lay of 50mm thick lean concrete 1.0d 1.0d -5.1d 01-Feb-18 08:00 AM 08-May-18
A 05:00 PM 0% 30%
STF2080 Erect formwork & install reinforcement 3.0d 3.0d -7.5d 01-Feb-18 07:00 PM10-May-18
A 05:00 PM 0% 30%
STF2090 Inspection 1.0d 1.0d -5.0d 10-May-18 08:00 AM*
10-May-18 05:00 PM 0% 0%
STF2100 Concreting works 1.0d 1.0d -5.0d 11-May-18 08:00 AM*
11-May-18 05:00 PM 0% 0%
STF2110 Curing works 2.0d 2.0d -5.0d 12-May-18 08:00 AM*
13-May-18 05:00 PM 0% 0%
STF2120 Dismantle formwork 1.0d 1.0d -5.0d 13-May-18 08:00 AM*
13-May-18 05:00 PM 0% 0%
STF2130 Backfilling & compaction works to the level of top stump 1.0d 1.0d -5.0d 14-May-18 08:00 AM*
14-May-18 05:00 PM 0% 0%
Ground Beam (0.3m x 0.6m) & Ground Slab (0.2m Thk) 112.0d 9.0d -5.0d 01-Feb-18 08:00 AM 23-May-18
A 05:00 PM 0% 12.5%
STF2140 Erect formwork surround the outer of stump 1.0d 1.0d -5.0d 01-Feb-18 08:00 AM 15-May-18
A 05:00 PM 0% 30%
STF2150 Backfilling & compaction works to the level of bottom slab 2.0d 2.0d -5.0d 16-May-18 08:00 AM*
17-May-18 05:00 PM 0% 0%
STF2160 Install formwork, lay of 50mm thick lean concrete 1.0d 1.0d -5.0d 01-Feb-18 08:00 AM 18-May-18
A 05:00 PM 0% 30%
STF2170 Install reinforcement both ground beam & slab 3.0d 3.0d -7.4d 01-Feb-18 07:00 PM20-May-18
A 05:00 PM 0% 30%
STF2180 Inspection 1.0d 1.0d -5.0d 20-May-18 08:00 AM*
20-May-18 05:00 PM 0% 0%
STF2190 Concreting works 1.0d 1.0d -5.0d 21-May-18 08:00 AM*
21-May-18 05:00 PM 0% 0%
STF2200 Curing works 2.0d 2.0d -5.0d 22-May-18 08:00 AM*
23-May-18 05:00 PM 0% 0%
STF2210 Dismantle formwork 1.0d 1.0d -5.0d 23-May-18 08:00 AM*
23-May-18 05:00 PM 0% 0%
Column - 5.5m (0.25mm x 0.25mm) 119.0d 8.0d 31.0d 01-Feb-18 08:00 AM 30-May-18
A 05:00 PM 0% 9%
STF2220 Install reinforcement 2.0d 2.0d -7.5d 01-Feb-18 08:00 AM 24-May-18
A 12:00 PM 0% 30%
STF2230 Erect formwork & bracing 1.0d 1.0d -7.5d 01-Feb-18 01:00 PM24-May-18
A 11:00 PM 0% 30%
STF2240 Inspection 1.0d 1.0d 31.0d 24-May-18 08:00 AM*
25-May-18 08:00 AM 0% 0%
STF2250 Concreting works 2.0d 2.0d 31.0d 25-May-18 08:00 AM*
26-May-18 05:00 PM 0% 0%
STF2260 Curing works 3.0d 3.0d 31.0d 27-May-18 08:00 AM*
29-May-18 05:00 PM 0% 0%
STF2270 Dismantle formwork & bracing 1.0d 1.0d 31.0d 30-May-18 08:00 AM*
30-May-18 05:00 PM 0% 0%
Intermediate Beam (0.25mm x 0.5mm) 121.0d 8.0d -5.0d 01-Feb-18 08:00 AM 01-Jun-18
A 05:00 PM 0% 12%
STF2350 Erect scaffold, stagging, t-prox & soffit 1.0d 1.0d -7.5d 01-Mar-18 08:00 AM25-May-18
A 08:00 PM 0% 30%
STF2360 Install reinforcement 2.0d 2.0d -7.5d 01-Feb-18 07:00 PM27-May-18
A 09:00 AM 0% 30%
STF2370 Erect formwork 1.0d 1.0d -7.5d 01-Feb-18 08:00 AM 27-May-18
A 08:00 PM 0% 30%
STF2380 Inspection 1.0d 1.0d -5.0d 27-May-18 08:00 AM*
28-May-18 08:00 AM 0% 0%
STF2390 Concreting works 1.0d 1.0d -5.0d 28-May-18 08:00 AM*
28-May-18 05:00 PM 0% 0%

Page 5 of 10 TASK filter: All Activities


© Oracle Corporation
STF PALONG TIMUR REV.05 ALL RUN BS 10.03.2018 - Overall Classic Schedule Layout 05-May-18 08:56 PM
Activity ID Activity Name Original Remaining Total Start Finish Schedule % Units %
Duration Duration Float Complete Complete

STF2400 Curing works 3.0d 3.0d -5.0d 29-May-18 08:00 AM*


31-May-18 05:00 PM 0% 0%
STF2410 Dismantle scaffold, stagging, t-prox, soffit & formwork 1.0d 1.0d -5.0d 01-Jun-18 08:00 AM*01-Jun-18 05:00 PM 0% 0%
Roof Beam (0.25mm x 0.5mm) 121.4d 8.0d -5.0d 01-Feb-18 01:00 PM02-Jun-18
A 05:00 PM 0% 12%
STF2280 Erect scaffold, stagging, t-prox & soffit 1.0d 1.0d -7.0d 01-Mar-18 07:00 PM26-May-18
A 02:00 PM 0% 30%
STF2290 Install reinforcement including L-Plates for roof truss 2.0d 2.0d -7.0d 01-Feb-18 01:00 PM27-May-18
A 08:00 PM 0% 30%
STF2300 Erect formwork 1.0d 1.0d -7.0d 01-Feb-18 07:00 PM28-May-18
A 02:00 PM 0% 30%
STF2310 Inspection 1.0d 1.0d -4.6d 27-May-18 02:00 PM*
28-May-18 02:00 PM 0% 0%
STF2320 Concreting works 1.0d 1.0d -4.6d 28-May-18 02:00 PM*
29-May-18 02:00 PM 0% 0%
STF2330 Curing works 3.0d 3.0d -4.6d 29-May-18 02:00 PM*
01-Jun-18 02:00 PM 0% 0%
STF2340 Dismantle scaffold, stagging, t-prox, soffit & formwork 1.0d 1.0d -5.0d 02-Jun-18 08:00 AM*02-Jun-18 05:00 PM 0% 0%
Roof Truss, Covering & Accessories 10.0d 10.0d 17.0d 02-Jun-18 08:00 AM 11-Jun-18 05:00 PM 0% 0%
STF2420 Deliver material for light gauge MS roof trusses on-site 1.0d 1.0d 3.0d 02-Jun-18 08:00 AM*02-Jun-18 05:00 PM 0% 0%
STF2430 Install prefabricated light gauge MS roof truss & bracing 2.0d 2.0d 3.0d 03-Jun-18 08:00 AM*04-Jun-18 05:00 PM 0% 0%
STF2440 Install purlins 2.0d 2.0d 3.0d 05-Jun-18 08:00 AM*06-Jun-18 05:00 PM 0% 0%
STF2450 Inspection 1.0d 1.0d 3.0d 06-Jun-18 08:00 AM*06-Jun-18 05:00 PM 0% 0%
STF2460 Install concrete roof tiles & ridge cap 4.0d 4.0d 3.0d 07-Jun-18 08:00 AM*10-Jun-18 05:00 PM 0% 0%
STF2470 Install fascia board & bracket for gutter 1.0d 1.0d 3.0d 11-Jun-18 08:00 AM*11-Jun-18 05:00 PM 0% 0%
STF2480 Inspection 1.0d 1.0d 17.0d 11-Jun-18 08:00 AM*11-Jun-18 05:00 PM 0% 0%
Floor, Wall, Ceiling & Accessories 19.0d 19.0d 21.1d 02-Jun-18 07:00 PM 15-Jun-18 03:00 PM 0% 0%
STF2490 Install 225mm thk. brickwall, tie with mortar - Team A & B 3.0d 3.0d -7.0d 02-Jun-18 07:00 PM*04-Jun-18 05:00 PM 0% 0%
STF2500 Install roller shutter & frame for door and window 2.0d 2.0d -7.0d 04-Jun-18 07:00 PM*05-Jun-18 11:00 PM 0% 0%
STF2510 Electrical wiring works - carry out by specialist team 4.0d 4.0d -7.0d 04-Jun-18 07:00 PM*07-Jun-18 12:00 PM 0% 0%
STF2520 External plastering - Team A 3.0d 3.0d -7.0d 07-Jun-18 01:00 PM*09-Jun-18 02:00 PM 0% 0%
STF2530 Internal plastering - Team B 3.0d 3.0d -7.0d 07-Jun-18 01:00 PM*09-Jun-18 02:00 PM 0% 0%
STF2540 Install frame & ceiling (external) - Team A 2.0d 2.0d -7.0d 09-Jun-18 02:00 PM*10-Jun-18 08:00 PM 0% 0%
STF2550 Install frame & ceiling (internal) - Team B 2.0d 2.0d -7.0d 09-Jun-18 02:00 PM*10-Jun-18 08:00 PM 0% 0%
STF2560 Install gutter & UPVC downpipes 1.0d 1.0d 21.1d 10-Jun-18 08:00 PM*11-Jun-18 02:00 PM 0% 0%
STF2570 Rendering of floor, install tiles & skirting 4.0d 4.0d 21.1d 10-Jun-18 08:00 PM*13-Jun-18 02:00 PM 0% 0%
STF2580 Painting of wall (external & internal) & ceiling - undercoat - Team A 3.0d 3.0d 21.1d 13-Jun-18 02:00 PM*15-Jun-18 03:00 PM 0% 0%
STF2590 Painting of wall (external & internal) & ceiling - finish coat - Team B 3.0d 3.0d 21.1d 13-Jun-18 02:00 PM*15-Jun-18 03:00 PM 0% 0%
STF2600 Install door & windows 1.0d 1.0d 21.1d 13-Jun-18 02:00 PM*14-Jun-18 09:00 AM 0% 0%
STF2610 Install GI tray / condiut 1.0d 1.0d 21.1d 14-Jun-18 09:00 AM*14-Jun-18 08:00 PM 0% 0%
U-Shaped Drain - Team C 156.8d 8.8d 3.3d 15-Jan-18 08:00 AM 2
A0-Jun-18 02:00 PM 0% 16.36%

Page 6 of 10 TASK filter: All Activities


© Oracle Corporation
STF PALONG TIMUR REV.05 ALL RUN BS 10.03.2018 - Overall Classic Schedule Layout 05-May-18 08:56 PM
Activity ID Activity Name Original Remaining Total Start Finish Schedule % Units %
Duration Duration Float Complete Complete

STF2620 Excavation & levelling works 2.0d 2.0d 3.0d 15-Jan-18 08:00 AM 1
A3-Jun-18 05:00 PM 0% 30%
STF2630 Erect formwork 1.0d 1.0d 4.9d 01-Feb-18 07:00 PM14-Jun-18
A 12:00 PM 0% 30%
STF2640 Install reinforcement 3.0d 3.0d 4.9d 01-Feb-18 01:00 PM16-Jun-18
A 02:00 PM 0% 30%
STF2650 Inspection 1.0d 1.0d 3.4d 15-Jun-18 02:00 PM*16-Jun-18 02:00 PM 0% 0%
STF2660 Concreting works 1.0d 1.0d 3.4d 16-Jun-18 02:00 PM*17-Jun-18 02:00 PM 0% 0%
STF2670 Curing works 2.0d 2.0d 3.4d 17-Jun-18 02:00 PM*19-Jun-18 02:00 PM 0% 0%
STF2680 Dismantle formwork 1.0d 1.0d 3.4d 19-Jun-18 02:00 PM*20-Jun-18 02:00 PM 0% 0%
Apron & Ramp - Team C 145.3d 6.1d 3.1d 01-Feb-18 01:00 PM26-Jun-18
A 03:00 PM 0% 11.25%
STF2690 Backfilling, levelling & compaction works 1.0d 1.0d 3.4d 20-Jun-18 02:00 PM*21-Jun-18 02:00 PM 0% 0%
STF2700 Erect formwork, install reinforcement 3.0d 3.0d 4.8d 01-Feb-18 01:00 PM23-Jun-18
A 03:00 PM 0% 30%
STF2710 Inspection 1.0d 1.0d 3.3d 22-Jun-18 03:00 PM*23-Jun-18 03:00 PM 0% 0%
STF2720 Concreting works 1.0d 1.0d 3.3d 23-Jun-18 03:00 PM*24-Jun-18 03:00 PM 0% 0%
STF2730 Curing works 1.0d 1.0d 3.3d 24-Jun-18 03:00 PM*25-Jun-18 03:00 PM 0% 0%
STF2740 Dismantle formwork & cleanup site 1.0d 1.0d 3.3d 25-Jun-18 03:00 PM*26-Jun-18 03:00 PM 0% 0%
Pipeworks (200mm & 300mm Dia. Pipe) 136.0d 88.0d 8.0d 22-Jan-18 08:00 AM 0
A6-Jun-18 05:00 PM 53.33% 10%

Procurement & Installation Works 136.0d 88.0d 8.0d 22-Jan-18 08:00 AM 0


A6-Jun-18 05:00 PM 53.33% 10%
STF2750 To procure & deliver 100mm & 300mm Pipes to site 24.0d 24.0d 8.0d 22-Jan-18 08:00 AM 0
A7-Apr-18 05:00 PM 100% 50%
STF2760 Excavation & backfilling works 24.0d 24.0d 9.0d 08-Apr-18 08:00 AM 01-May-18 05:00 PM 75% 0%
STF2770 Pipe laying & jointing 24.0d 24.0d 9.0d 08-Apr-18 08:00 AM 01-May-18 05:00 PM 75% 0%
STF2780 Connection to existing Chamber / Pipes 24.0d 24.0d 9.0d 02-May-18 08:00 AM25-May-18 05:00 PM 0% 0%
STF2790 Miscellaneous works 18.0d 18.0d 20.0d 02-May-18 08:00 AM19-May-18 05:00 PM 0% 0%
STF2800 Cleaning & testing works 6.0d 6.0d 7.0d 31-May-18 08:00 AM06-Jun-18 05:00 PM 0% 0%
Mechanical Works 232.0d 154.0d -42.0d 23-Dec-17 08:00 AM11-Aug-18
A 05:00 PM 52.03% 40.48%

Drawing & Material Approval 24.0d 0.0d 23-Dec-17 08:00 AM21-Jan-18


A 05:00 PM A 100% 100%
STF2810 Submission of Drawing / Material for approval 12.0d 0.0d 23-Dec-17 08:00 AM07-Jan-18
A 05:00 PM A 100% 100%
STF2820 Review & approval for Drawing / Material 12.0d 0.0d 08-Jan-18 08:00 AM 2
A1-Jan-18 05:00 PM A 100% 100%
Tank & Plant 216.0d 154.0d -42.0d 08-Jan-18 08:00 AM 1
A1-Aug-18 05:00 PM 50.57% 38.76%
Wash Water Collection & Sludge Balancing Tank 216.0d 154.0d -46.0d 08-Jan-18 08:00 AM 1
A1-Aug-18 05:00 PM 23.5% 36.76%
Procurement & Delivery 79.0d 125.0d -49.0d 08-Jan-18 08:00 AM 0
A4-Aug-18 05:00 PM 29.14% 50%
STF2830 Horizontal Screw Pump & Subermisble Supernatant Pump 79.0d 79.0d -49.0d 08-Jan-18 08:00 AM 1
A1-Jun-18 05:00 PM 64.56% 50%
STF2840 FAT Wash Water Recovery Pumpset 6.0d 6.0d -49.0d 08-Jan-18 08:00 AM 1
A8-Jun-18 05:00 PM 0% 50%
STF2850 Pipes, Fittings & Valves 30.0d 30.0d -49.0d 08-Jan-18 08:00 AM 0
A4-Aug-18 05:00 PM 0% 50%

Page 7 of 10 TASK filter: All Activities


© Oracle Corporation
STF PALONG TIMUR REV.05 ALL RUN BS 10.03.2018 - Overall Classic Schedule Layout 05-May-18 08:56 PM
Activity ID Activity Name Original Remaining Total Start Finish Schedule % Units %
Duration Duration Float Complete Complete

STF2860 Submersible Mixer 30.0d 30.0d -49.0d 08-Jan-18 08:00 AM 0


A4-Aug-18 05:00 PM 0% 50%
STF2870 Crane / Lifting Equipment, High Pressure Rubber Hose 30.0d 30.0d -49.0d 08-Jan-18 08:00 AM 0
A4-Aug-18 05:00 PM 0% 50%
Installation Works 54.0d 54.0d -46.0d 19-Jun-18 08:00 AM 11-Aug-18 05:00 PM 0% 0%
STF2880 Construction of Horizontal Screw Pump Pit 24.0d 24.0d -34.0d 19-Jun-18 08:00 AM 12-Jul-18 05:00 PM 0% 0%
STF2890 Horizontal Screw Pump & Submersible Supernatant Pump 18.0d 18.0d -34.0d 13-Jul-18 08:00 AM 30-Jul-18 05:00 PM 0% 0%
STF2900 Pipes, Fittings & Valves 7.0d 7.0d -57.0d 05-Aug-18 08:00 AM 11-Aug-18 05:00 PM 0% 0%
STF2910 Submersible Mixer 7.0d 7.0d -57.0d 05-Aug-18 08:00 AM 11-Aug-18 05:00 PM 0% 0%
STF2920 Crane / Lifting Equipment, High Pressure Rubber Hose 7.0d 7.0d -57.0d 05-Aug-18 08:00 AM 11-Aug-18 05:00 PM 0% 0%
Existing Sedimentation Tank / Basin 154.0d 92.0d 5.0d 08-Jan-18 08:00 AM 1
A0-Jun-18 05:00 PM 77.64% 40.99%
Procurement & Delivery 61.0d 61.0d 13.0d 08-Jan-18 08:00 AM 2
A1-May-18 05:00 PM 89.01% 50%
STF2930 Submersible Sludge Pump 61.0d 61.0d 4.0d 08-Jan-18 08:00 AM 2
A1-May-18 05:00 PM 83.61% 50%
STF2940 Pipes, Fittings & Valves 30.0d 30.0d 44.0d 08-Jan-18 08:00 AM 1
A4-Apr-18 05:00 PM 100% 50%
Installation Works 20.0d 20.0d 5.0d 22-May-18 08:00 AM10-Jun-18 05:00 PM 0% 0%
STF2950 Submersible Sludge Pump 10.0d 10.0d 5.0d 22-May-18 08:00 AM31-May-18 05:00 PM 0% 0%
STF2960 Pipes, Fittings & Valves 10.0d 10.0d 5.0d 01-Jun-18 08:00 AM 10-Jun-18 05:00 PM 0% 0%
Polymer Plant 164.0d 102.0d 10.0d 08-Jan-18 08:00 AM 2
A0-Jun-18 05:00 PM 55.13% 32.5%
Procurement & Delivery 60.0d 60.0d 35.0d 08-Jan-18 08:00 AM 2
A0-May-18 05:00 PM 93.48% 56.52%
STF2970 Engineering Design for Polymer Plant & Dosing System 18.0d 0.0d 08-Jan-18 08:00 AM 2
A8-Jan-18 05:00 PM A 100% 100%
STF2980 Metering pumps (Diaphragm type) 60.0d 60.0d 35.0d 08-Jan-18 08:00 AM 2
A0-May-18 05:00 PM 85% 50%
STF2990 Crane / Lifting Equipment 30.0d 30.0d 44.0d 08-Jan-18 08:00 AM 1
A4-Apr-18 05:00 PM 100% 50%
STF3000 Static Mixer & Sludge Blender 30.0d 30.0d 44.0d 08-Jan-18 08:00 AM 1
A4-Apr-18 05:00 PM 100% 50%
Fabrication Works 14.0d 14.0d 8.0d 12-May-18 08:00 AM27-May-18 05:00 PM 0% 0%
STF3010 Mixing & Service Tank 14.0d 14.0d 8.0d 12-May-18 08:00 AM27-May-18 05:00 PM 0% 0%
STF3020 Hopper, Feeder & Pump Skid 14.0d 14.0d 8.0d 12-May-18 08:00 AM27-May-18 05:00 PM 0% 0%
STF3030 Local Control Panel 14.0d 14.0d 8.0d 12-May-18 08:00 AM27-May-18 05:00 PM 0% 0%
Installation Works 10.0d 10.0d -5.0d 11-Jun-18 08:00 AM 20-Jun-18 05:00 PM 0% 0%
STF3040 Mixing & Service Tank 10.0d 10.0d -5.0d 11-Jun-18 08:00 AM 20-Jun-18 05:00 PM 0% 0%
STF3050 Hopper, Feeder & Pump Skid 10.0d 10.0d -5.0d 11-Jun-18 08:00 AM 20-Jun-18 05:00 PM 0% 0%
STF3060 Dosing Pipeworks 10.0d 10.0d -5.0d 11-Jun-18 08:00 AM 20-Jun-18 05:00 PM 0% 0%
STF3070 Local Control Panel 10.0d 10.0d -5.0d 11-Jun-18 08:00 AM 20-Jun-18 05:00 PM 0% 0%
STF3080 Crane / Lifting Equipment 10.0d 10.0d -5.0d 11-Jun-18 08:00 AM 20-Jun-18 05:00 PM 0% 0%
STF3090 Static Mixer & Sludge Blender 10.0d 10.0d -5.0d 11-Jun-18 08:00 AM 20-Jun-18 05:00 PM 0% 0%
Pipeworks (100mm Dia. Pipe & Below) 114.0d 66.0d 44.0d 22-Jan-18 08:00 AM 1
A5-May-18 05:00 PM 61.02% 27.27%

Page 8 of 10 TASK filter: All Activities


© Oracle Corporation
STF PALONG TIMUR REV.05 ALL RUN BS 10.03.2018 - Overall Classic Schedule Layout 05-May-18 08:56 PM
Activity ID Activity Name Original Remaining Total Start Finish Schedule % Units %
Duration Duration Float Complete Complete

Procurement & Installation Works 114.0d 66.0d 44.0d 22-Jan-18 08:00 AM 1


A5-May-18 05:00 PM 61.02% 27.27%
STF3100 Procurement & Delivery of Pipes 24.0d 24.0d 58.0d 22-Jan-18 08:00 AM 0
A7-Apr-18 05:00 PM 100% 50%
STF3110 Excavation, Backfilling Works 7.0d 7.0d 45.0d 02-May-18 08:00 AM08-May-18 05:00 PM 0% 0%
STF3120 Pipe Laying, Jointing 7.0d 7.0d 45.0d 02-May-18 08:00 AM08-May-18 05:00 PM 0% 0%
STF3130 Cleaning & Testing works 6.0d 6.0d 38.0d 09-May-18 08:00 AM15-May-18 05:00 PM 0% 0%
Miscellaneous Works 143.0d 81.0d 16.0d 08-Jan-18 08:00 AM 3
A0-May-18 05:00 PM 58.66% 50%
Procurement & Delivery 90.0d 61.0d 11.0d 08-Jan-18 08:00 AM 2
A1-May-18 05:00 PM 62.98% 54.97%
STF3140 Engineering Design for Motive Water System & Air Compressor 18.0d 0.0d 22-Jan-18 08:00 AM 1
A1-Feb-18 05:00 PM A 100% 100%
STF3150 Booster Pump 30.0d 30.0d 11.0d 12-Feb-18 08:00 AM 14-Apr-18
A 05:00 PM 70% 50%
STF3160 Air Compressor Set 30.0d 30.0d 11.0d 12-Feb-18 08:00 AM 14-Apr-18
A 05:00 PM 70% 50%
STF3170 Submersible Pump (Portable & Gasoline Engine) 30.0d 30.0d 11.0d 12-Feb-18 08:00 AM 14-Apr-18
A 05:00 PM 70% 50%
STF3180 Portable Water Jet 12.0d 12.0d 11.0d 12-Feb-18 08:00 AM 24-Mar-18
A 05:00 PM 100% 50%
STF3190 Penstock & Valve 60.0d 60.0d 11.0d 12-Feb-18 08:00 AM 20-May-18
A 05:00 PM 35% 50%
STF3200 FAT Penstock / Valve 1.0d 1.0d 11.0d 08-Jan-18 08:00 AM 2
A1-May-18 05:00 PM 0% 50%
Installation Works 46.0d 46.0d 16.0d 15-Apr-18 08:00 AM 30-May-18 05:00 PM 0% 0%
STF3210 Booster Pump 10.0d 10.0d 52.0d 15-Apr-18 08:00 AM 24-Apr-18 05:00 PM 0% 0%
STF3220 Air Compressor Set 3.0d 3.0d 59.0d 15-Apr-18 08:00 AM 17-Apr-18 05:00 PM 0% 0%
STF3230 Penstock & Valve 5.0d 5.0d 9.0d 26-May-18 08:00 AM30-May-18 05:00 PM 0% 0%
Electrical Works 247.0d 157.0d -60.0d 11-Dec-17 08:00 AM14-Aug-18
A 05:00 PM 32.57% 44.02%

Drawing & Material Approval 24.0d 0.0d 11-Dec-17 08:00 AM09-Jan-18


A 05:00 PM A 100% 100%
STF3240 Submission Drawing/Material for Approval 12.0d 0.0d 11-Dec-17 08:00 AM24-Dec-17
A 05:00 PM A 100% 100%
STF3250 Review & Approval for Drawing/Material 12.0d 0.0d 26-Dec-17 08:00 AM09-Jan-18
A 05:00 PM A 100% 100%
Panel & Cabling Works 247.0d 157.0d -60.0d 11-Dec-17 08:00 AM14-Aug-18
A 05:00 PM 25.74% 39.17%
Switchboard / MCC Panel 185.0d 110.0d -13.0d 26-Dec-17 08:00 AM28-Jun-18
A 05:00 PM 66.55% 44.74%
STF3260 Procurement & Fabrication of Panel 84.0d 84.0d -51.0d 26-Dec-17 08:00 AM17-Jun-18
A 05:00 PM 72.62% 50%
STF3270 FAT Electrical Control and Switchboards 1.0d 1.0d -11.0d 08-Jan-18 08:00 AM 1
A8-Jun-18 05:00 PM 0% 50%
STF3280 Installation Works 10.0d 10.0d -13.0d 19-Jun-18 08:00 AM 28-Jun-18 05:00 PM 0% 0%
Submain Cabling Works for MCC-SDP-Palong 219.0d 58.0d -60.0d 08-Jan-18 08:00 AM 1
A4-Aug-18 05:00 PM 0% 22.22%
STF3290 Procurement & Delivery of Cable 24.0d 24.0d -51.0d 08-Jan-18 08:00 AM 1
A5-Jul-18 05:00 PM 0% 50%
STF3300 Installation & Cabling Works 30.0d 30.0d -60.0d 16-Jul-18 08:00 AM 14-Aug-18 05:00 PM 0% 0%
Distribution & Earthing System 199.0d 38.0d -40.0d 08-Jan-18 08:00 AM 2
A5-Jul-18 05:00 PM 0% 35.29%
STF3310 Procurement & Delivery of Cable 24.0d 24.0d -51.0d 08-Jan-18 08:00 AM 1
A5-Jul-18 05:00 PM 0% 50%
STF3320 Installation Works 10.0d 10.0d -40.0d 16-Jul-18 08:00 AM 25-Jul-18 05:00 PM 0% 0%

Page 9 of 10 TASK filter: All Activities


© Oracle Corporation
STF PALONG TIMUR REV.05 ALL RUN BS 10.03.2018 - Overall Classic Schedule Layout 05-May-18 08:56 PM
Activity ID Activity Name Original Remaining Total Start Finish Schedule % Units %
Duration Duration Float Complete Complete

Compund Lighting System 199.0d 38.0d -60.0d 08-Jan-18 08:00 AM 2


A5-Jul-18 05:00 PM 0% 35.29%
STF3330 Procurement & Delivery 24.0d 24.0d -51.0d 08-Jan-18 08:00 AM 1
A5-Jul-18 05:00 PM 0% 50%
STF3340 Installation & Cabling Works 10.0d 10.0d -60.0d 16-Jul-18 08:00 AM 25-Jul-18 05:00 PM 0% 0%
Miscellaneous Works 247.0d 30.0d -60.0d 11-Dec-17 08:00 AM14-Aug-18
A 05:00 PM 0% 50%
STF3350 Relocations Existing Cabling Works 30.0d 0.0d 11-Dec-17 08:00 AM09-Jan-18
A 05:00 PM A 0% 100%
STF3360 Miscellaneous Works 30.0d 30.0d -60.0d 16-Jul-18 08:00 AM 14-Aug-18 05:00 PM 0% 0%
Instrumentation Works 200.0d 110.0d -13.0d 11-Dec-17 08:00 AM28-Jun-18
A 05:00 PM 73.49% 56.3%

Drawing & Material Approval 24.0d 0.0d 11-Dec-17 08:00 AM09-Jan-18


A 05:00 PM A 100% 100%
STF3370 Submission Drawing/Material for Approval 12.0d 0.0d 11-Dec-17 08:00 AM24-Dec-17
A 05:00 PM A 100% 100%
STF3380 Review & Approval for Drawing/Material 12.0d 0.0d 26-Dec-17 08:00 AM09-Jan-18
A 05:00 PM A 100% 100%
Panel & Cabling Works 185.0d 110.0d -13.0d 26-Dec-17 08:00 AM28-Jun-18
A 05:00 PM 66.55% 45.26%
Procurement & Installation Works 185.0d 110.0d -13.0d 26-Dec-17 08:00 AM28-Jun-18
A 05:00 PM 66.55% 45.26%
STF3390 Procurement & Fabrication of Instrument Panel 84.0d 84.0d -10.0d 26-Dec-17 08:00 AM17-Jun-18
A 05:00 PM 72.62% 50%
STF3400 FAT 1.0d 0.0d 27-Dec-17 08:00 AM27-Dec-17
A 05:00 PM A 0% 100%
STF3410 Installation & Signal Cabling Works 10.0d 10.0d -13.0d 19-Jun-18 08:00 AM 28-Jun-18 05:00 PM 0% 0%
Infrastructure Works 7.0d 7.0d 3.5d 19-Jun-18 01:00 PM 26-Jun-18 12:00 PM 0% 0%

Reinstatement of Damaged Existing Road 7.0d 7.0d 3.5d 19-Jun-18 01:00 PM 26-Jun-18 12:00 PM 0% 0%
STF3420 Site clearance, levelling & compaction 5.0d 5.0d 3.5d 19-Jun-18 01:00 PM 24-Jun-18 12:00 PM 0% 0%
STF3430 Lay & compact crusher-run & premix (binder and wearing coarse) 7.0d 7.0d 3.5d 19-Jun-18 01:00 PM 26-Jun-18 12:00 PM 0% 0%
Site Handover Works 13.0d 13.0d -52.0d 15-Aug-18 08:00 AM 29-Aug-18 05:00 PM 0% 0%

Project Completions 13.0d 13.0d -52.0d 15-Aug-18 08:00 AM 29-Aug-18 05:00 PM 0% 0%


Training, Testing, Commissioning & Maintenance 13.0d 13.0d -52.0d 15-Aug-18 08:00 AM 29-Aug-18 05:00 PM 0% 0%
STF3440 Preparation of Testing & Report 7.0d 7.0d -52.0d 15-Aug-18 08:00 AM 22-Aug-18 05:00 PM 0% 0%
STF3450 Pre-commissioning 4.0d 4.0d -52.0d 15-Aug-18 08:00 AM 19-Aug-18 05:00 PM 0% 0%
STF3460 Setting to Work 3.0d 3.0d -52.0d 20-Aug-18 08:00 AM 22-Aug-18 05:00 PM 0% 0%
STF3470 Commissioning & Training of Works 5.0d 5.0d -52.0d 23-Aug-18 08:00 AM 28-Aug-18 05:00 PM 0% 0%
STF3480 Handing Over to Client 1.0d 1.0d -52.0d 29-Aug-18 08:00 AM 29-Aug-18 05:00 PM 0% 0%

Page 10 of 10 TASK filter: All Activities


© Oracle Corporation