Professional Documents
Culture Documents
CL-E134 Overvoltage Protection: Commissioning Check List E
CL-E134 Overvoltage Protection: Commissioning Check List E
CL-E134 Overvoltage Protection: Commissioning Check List E
Restricted
ANSI 59
CL-E134 Overvoltage Protection
Primary Injection Tests
Panama Colon PP BB001062
Power Plant Plant Code
Page: 1 of 1 Appendices:
2. Primary tests
UL1-E [V]
UL2-E [V]
UL3-E [V]
UL1-L2 [V]
UL1-L3 [V]
UL2-L3 [V]
3. Evaluation
4. Remarks:
......................................................................................................................................................................................... 1
......................................................................................................................................................................................... 2