LIMESTONE – PROJECT SUMMARY

TYPICAL LIMESTONE MINING INFRASTRUCTURE


TYPICAL LIMESTONE CRUSHING PLANT
TYPICAL LIMESTONE CRUSHING PLANT
TYPICAL LIMESTONE CRUSHING PLANT
ESTIMATED MINING COST vs SELLING PRICE

Proyek : CV. ARTHAGAMA MINERALINDO


USD 1.0 13,550
Asumsi - Asumsi
Asumsi Operasional : Keterangan
Mining live (within 5Ha) 2 Years
Mining commercial commencement Year - 1st
Stripping Ratio 0 :1
Total Cadangan 1,200,000 100%
Total Production 100% 1,200,000 MT Rock Resources (measured)
Produksi Bulan ke-1 50,000 MT
Produksi Bulan ke-2 50,000 MT
Produksi Bulan ke-3 50,000 MT
Produksi Bulan ke-4 dst 50,000 MT

Quality Basis (CaCO3) > 95%

Harga Jual (FOT) $ 19.56 Rp 265,000.00 / MT

Biaya Pokok $ 6.20 Rp 84,028.50 / MT exclude ppn, overhead & depreciation


Drill and Blast $ 0.50 Rp 6,775.00 / BCM
Mining incl Dig, Break & Load $ 1.50 Rp 20,325.00 / MT Include Land / top soil clearing
ROM & Stockpiling $ 0.20 Rp 2,710.00 / MT ROM and End Product stockpile handling
Crushing incl Power $ 0.55 Rp 7,452.50 / MT
Hauling 10 KM $ 1.50 Rp 20,325.00 / MT
LV Rental incl fuel $ 0.01 Rp 142.50 / MT
Security incl Local Police & Army $ 0.07 Rp 1,000.00 / MT
Road Maintenance 10 KM $ 0.50 Rp 6,775.00 / MT
CSR to local villagers nearby $ 0.07 Rp 1,000.00 / MT
Admin & salary incl overhead $ 0.14 Rp 1,845.00 / MT
Royalty to government 4% $ 0.78 Rp 10,600.00 / MT provision
Local office & messing $ 0.02 Rp 336.00 / MT provision
Reclamation $ 0.15 Rp 2,032.50 / MT provision
Exploration $ - Rp - / MT provision
Installment payment to Crushing Coy $ 0.20 Rp 2,710.00 / MT Payment to Crushing Plant LEASING Company
Depr. / Amort. $ - / MT
Total Investasi 100% Rp - Milyar
ESTIMATED MINING PERMIT / LEGAL COST

RENCANA / PERKIRAAN ANGGARAN BELANJA PERIZINAN IUP OPERASI-PRODUKSI


No Pekerjaan / Kegiatan Instansi / Dinas Jenis Laporan / Anggaran Belanja
/ Lembaga Izin (Rupiah)
1 Penyusunan AMDAL UKL-UPL Konsultan AMDAL Dokumen UKL-UPL Rp50,000,000
Koordinasi dg Dinas Lingkungan Hidup
Kab. Sukabumi
2 Rapat Pembahasan UKL-UPL Kab. Sukabumi Izin Lingkungan Rp10,000,000
3 Penyusunan Dokumen Studi Kelayakan (FS) Dinas ESDM Prov Jawa Barat Laporan Studi Kelayakan Rp20,000,000
4 Rapat Pembahasan Studi Kelayakan Dinas ESDM Prov Jawa Barat Persetujuan Studi Kelayakan Rp10,000,000
5 Penyusunan dokumen RKAB Dinas ESDM Prov Jawa Barat Laporan RKAB Tahun 2018 Rp20,000,000
6 Rapat Pembahasan RKAB Dinas ESDM Prov Jawa Barat Persetujuan RKAB Tahun 2018 Rp10,000,000
7 Penyusunan Dokumen Rencana Reklamasi Dinas ESDM Prov Jawa Barat Laporan Rencana Reklamasi Rp20,000,000
8 Rapat Pembahasan Dok Rencana Reklamasi Dinas ESDM Prov Jawa Barat Persetujuan Rencana Reklamasi Rp10,000,000
9 Pengukuran / survei topografi Konsultan Surveyor Laporan Topografi Rp25,000,000
10 Pemasangan patok batas wilayah IUP Dinas ESDM Prov Jawa Barat Persetujuan batas wilayah IUP Rp15,000,000
11 Penyusunan Dokumen Eksplorasi & Konsultan Eksplorasi Laporan Cadangan & Rp15,000,000
Perencanaan Tambang Rencana Tambang
12 Rapat Pembahasan Dokumen Eksplorasi Dinas ESDM Prov Jawa Barat Persetujuan Eksplorasi Rp10,000,000
13 Pembayaran Jaminan Reklamasi Dinas ESDM Prov Jawa Barat Deposit Jamrek Bank Pemerintah Rp50,000,000
Via Bank yang ditunjuk Prov Jawa Barat Bank Jawa Barat Banten (BJB)
TOTAL: Rp265,000,000
ESTIMATED MINING INVESTMENT COST / CAPEX

INVESTMENT COST in Million (1,000,000) Rupiahs


INVESTMENT COST Remarks - (per UNIT COST)
Main Equipment M Rups 3,350.00
Crushing Plant M Rups 3,000.00 LEASING (Brand New) WITH 30% DP Incl Construction
Complete Accessories, Incl. Genset 300 KVA M Rups 350.00 Incl. Panel System
Civil Work (Mining Infrastructures) M Rups 500.00
Permits M Rups 265.00
Facility M Rups 250.00
Camp & Workshop M Rups 100.00 Incl. Spare parts
Excavators (2) M Rups - Rental
Breaker (1) M Rups - Rental
Hand Drill & Compressor M Rups 150.00
Working Capital M Rups 3,361.14
Production for 1 Month M Rups 3,361.14 Production 40,000 Metric Ton in the 1st Month
Total Investment Cost M Rups 7,726.14
Tangible Cost M Rups 4,100.00
Intangible Cost M Rups 3,626.14
SCOPE OF WORK
LOADING
DEVELOP CRUSHING & SALES
DRILLING BLASTING & CONVEYING LOADING
MENT HAULING
-
• Pengupasan tanah • Kegiatan • Loading & Hauling • Operasi Crusher • Penyediaan alat
dan vegetasi • Fasilitas gudang, batu andesit hasil muat (wheel
pemboran untuk & Belt Conveyor.
• Persiapan lokasi pengadaan peledakan menuju loader untuk
membuat lubang
pemboran. explosive dan crusher. kegiatan sales)
tembak sesuai
• Pembuatan dan perijinan • Memecahkan • Pemuatan
dengan mining
perawatan jalan. • Charging material boulder hasil material dari
plan
explosive ke dalam blasting agar sesuai stock-pile di
lubang tembak. ukurannya masuk quarry ke hopper
• pelaksanaan crusher long conveyor.
peledakan oleh • Pemuatan mate-
Dahana. rial dari stockpile
ke truck
Keterangan :

: Fasilitas gudang Explosive, perijinan & Operasional oleh


Operator
: Penyediaan alat berat, Operasional & Perawatan oleh
Operator
: Mesin, Operasional & Perawatan

: Operator menyediakan alat muat untuk kegiatan sales


Estimation of Equipment Requirement :
• Drilling Machine : 1 Unit
• Excavator : 2 Unit 20t Class + 1 Unit Breaker (20t Class)
• Dump Truck : 5 Unit (25t - 30t Class)
• Wheel Loader : 1 Unit (WA 350 / Cat 960 Class)
• Bulldozer : 1 Unit
• Grader : 1 Unit (Optional)
• Compactor : 1 Unit (Optional)
• Water Truck : 1 Unit
• Fuel & Lubricant Truck : 1 Unit