Professional Documents
Culture Documents
Garis Panduan Hakisan
Garis Panduan Hakisan
Garis Panduan Hakisan
JKR 20401-0062-15
A GUIDE FOR
ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS
A GUIDE FOR
ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS
In line with the environmental policy of Jabatan Kerja Raya Malaysia which is committed
to ensure the implementation of government projects with emphasis on the importance of
environmental protection as well as legal and regulatory compliance, efforts to improve
environmental management during project implementation is prioritized. Environmental
management during project implementation for Jabatan Kerja Raya Malaysia is
standardized by adopting this Arahan Teknik (Jalan) 16/03 Pindaan 2015: A Guide for
Environmental Protection & Enhancement Works.
The enhancements from the previous edition have resulted in a more comprehensive
environmental management and protection technical document.
As a summary, this revised Arahan Teknik Jalan has been formulated and is to be
implemented by various government agencies and parties involved, in line with the
nation’s aspirations in protecting the environment thus to ensure better quality of life
through sustainable development for future generations.
i
ACKNOWLEDGEMENT
This revised Arahan Teknik (Jalan) 16/03; (Pindaan 2015) was prepared by a sub-
committee comprising fifty (50) multi-disciplinary personnel as listed below:-
ii
(39) En. Razmann bin Abdul Rashid JKR
(40) En. Mohd Shahir bin Mokhtar JKR
(41) Cik Hasnaliza Aini binti Abd Talib JKR
(42) En. Lim Chi Chon JKR
(43) Pn. Wan Yusnira binti Wan Jusoh JKR
(44) Pn. Nik Nor Shyzleen binti Mohd Azizi JKR
(45) Pn. Fadini binti Mohd Razali JKR
(46) Pn. Salkiah binti Mohamad Salleh Tan JKR
(47) Cik Ayu Shahiza binti Shahidan JKR
(48) En. Mahadir bin Masihat JKR
(49) En. Ahmad Afzan Bin Mohamad Bakri JKR
(50) Cik Noor Maziana Binti Mazlam JKR
Finally, the publisher wishes to express its gratitude to the above committee members for
their valuable contributions in preparing this guide.
Published by:-
Reproduction of any part from this publication may be made subject to due
acknowledgement of the source. However, the publisher does not accept any responsibility
for any consequences arising from the use of the information within this guide.
iii
List Of Acronyms
A
ATJ - ARAHAN TEKNIK JALAN
B
BMP - BEST MANAGEMENT PRACTICES
BOD - BIOCHEMICAL OXYGEN DEMAND
BQ - BILL OF QUANTITIES
C
CBR TEST - CALIFORNIA BEARING RATIO TEST
CFS - CENTRAL FOREST SPINE
COD - CHEMICAL OXYGEN DEMAND
CPC - CERTIFICATE OF PRACTICAL COMPLETION
D
DEIA - DETAILED ENVIRONMENTAL IMPACT ASSESSMENT
DO - DISSOLVED OXYGEN
DOE - DEPARTMENT OF ENVIRONMENT (JABATAN ALAM
SEKITAR (JAS)
E
EAR - ENVIRONMENTAL AUDIT REPORT
ECAR - ENVIRONMENTAL CLOSURE AUDIT REPORT
E-COLI - ESCHERICHIA COLI
EIA - ENVIRONMENTAL IMPACT ASSESSMENT
EMP - ENVIRONMENTAL MANAGEMENT PLAN
EMR - ENVIRONMENTAL MONITORING REPORT
EMS - ENVIRONMENT MANAGEMENT SYSTEM
EO - ENVIRONMENTAL OFFICER
EQA - ENVIRONMENTAL QUALITY ACT
ESA - ENVIRONMENTAL SENSITIVE AREA
ESCP - EROSION AND SEDIMENT CONTROL PLAN
I
IMS - INTEGRATED MANAGEMENT SYSTEM
J
JKR - JABATAN KERJA RAYA
JPBD - JABATAN PERANCANGAN BANDAR DAN DESA
(FEDERAL DEPARTMENT OF TOWN AND COUNTRY
PLANNING)
JPS - JABATAN PENGAIRAN DAN SALIRAN
JPAS - JABATAN PERLINDUNGAN ALAM SEKITAR SABAH
iv
K
KPKT - KEMENTERIAN PERUMAHAN DAN KERAJAAN
TEMPATAN
L
LOA - LETTER OF ACCEPTANCE
M
MOM - METHOD OF MEASUREMENT
MSMA - MANUAL SALIRAN MESRA ALAM (URBAN
STORMWATER MANAGEMENT MANUAL)
MyCESMM - MALAYSIAN CIVIL ENGINEERING STANDARD METHOD
OF MEASUREMENT
N
NPP 2 - NATIONAL PHYSICAL PLAN 2
NREB - NATURAL RESOURCES AND ENVIRONMENT BOARD
SARAWAK
NTU - NEPHELOMETRIC TURBIDITY UNITS
NWQS - NATIONAL WATER QUALITY STANDARDS
P
P.D - PROJECT DIRECTOR
PAT - PENILAIAN AWAL TAPAK (PRELIMINARY SITE
ASSESSMENT)
PEIA - PRELIMINARY ENVIRONMENTAL IMPACT ASSESSMENT
PERHILITAN- JABATAN PERLINDUNGAN HIDUPAN LIAR DAN TAMAN
NEGARA
PM - PARTICULATE MATTER
S
S.O - SUPERINTENDENT OFFICER
SPAS - SISTEM PENGURUSAN ALAM SEKITAR
T
TSP - TOTAL SUSPENDED PARTICULATES
TSS - TOTAL SUSPENDED SOLIDS
v
A GUIDE FOR ENVIRONMENTAL PROTECTION & ENHANCEMENT WORKS
CONTENTS PAGE
CHAPTERS
1.0 Introduction 1
4.0 Specifications 23
REFERENCES
vi
CHAPTER 1
INTRODUCTION
1
CHAPTER 1 : INTRODUCTION
NPP 2 outlines strategic policies for the purpose of determining the general direction and
trends of the physical development of the nation. The main goal of NPP 2 is to establish
an efficient, equitable and sustainable national spatial framework to guide the overall
development of the country towards achieving developed and high-income nation status
by 2020. NPP 2 is also strengthened by Theme 6 : Conserving Natural Resources,
Biodiversity & the Environmental in the National Spatial Framework for 2020. Six areas
has been identified for conservation and they comprised of Environmental Sensitive Areas
(ESA), Central Forest Spine, Coastal & Marine Ecosystems, Highland Development,
Water Resources and Climate Change.
2
Central Forest Spine
(CFS)
Coastal & Marine
Environmental
Ecosystem
Sensitive Area
NPP2
(Theme 6)
Climate Change Highland Development
Water Resources
1.1 Objectives
This Revised Arahan Teknik aims to attain the following objectives:
1.1.1 To ensure that the JKR’s Integrated Management System (IMS) related to
MS ISO 14001 requirements in terms of environmental protection
measures are identified and incorporated in the preparation of the tender
document and subsequently implemented during the planning, design,
procurement and construction stages of the project.
1.1.2 To provide a guide for users in the form of a more comprehensive document
in accordance to technical requirements incorporating the latest
environmental protection, mitigation and enhancement measures in the
preparation of tender document.
3
1.2.2 Produce a comprehensive guide on environmental management that covers
the planning, design and construction phases of projects as elaborated in
Table 1.1:-
Table 1.1: General Issues and their Requirements
1.2.3 Introduce pictorial guidance and standard drawings for best management
practices based on current needs.
This document is applicable for both conventional and design and build projects. A
typical example of the process flow for both types of projects can be referred to the JKR
Integrated Management System (IMS).
1.4 Limitation
This document may have limited use for costing and environmental protection measures
purposes in the preparation of Bill of Quantities (BQ) for projects that are subjected to the
following:
4
Projects located within areas identified as Environmentally Sensitive Areas (ESAs)
such as wildlife sanctuary, wetlands, marine parks and national parks.
This Revised Arahan Teknik (Jalan) 16/03 has been divided into eight chapters addressing
the various components which form part and parcel of the tender document preparation
process. Specifications relating to environmental matters in the execution of JKR projects
in line with JKR EMS: MS ISO 14001 and shall be read in conjunction with the latest
Standard Specification for Buildings Works and Standard Specification for Road Works.
In addition, Method of Measurement and Bill of Quantities (BQ) shall also be read in
conjunction with the Malaysian Civil Engineering Standard Method of Measurement
(MyCESMM).
Chapter 7.0 Best Management Practices (BMP)– samples of BMPS that have
been implemented successfully at JKR sites are shown.
5
Appendix 2 Government Requirements (Need Statement) (Terms of Reference)
(For Design and Build Projects Only)
6
CHAPTER 2
ENVIRONMENTAL REQUIREMENTS
7
CHAPTER 2: ENVIRONMENTAL REQUIREMENTS
The Environmental Quality (Amendment) Act 2012 has outlined compliance with relevant
environmental protection legislation respectively. To date, 38 sets of Regulations and
Orders have been enforced. Under this Act, an Environmental Impact Assessment (EIA) is
required to be prepared and approved for any activities prescribed under the
Environmental Quality (Prescribed Activities) (Environmental Impact Assessment)
Order 1987. Those activities that are not subjected to the mandatory EIA requirement are
nevertheless subjected to various other regulations under the Act. One of the latest
requirements is submission of a Preliminary Site Assessment (PAT) that is required by the
Department of Environment Malaysia (DOE) for any new proposed project in order to
evaluate the project development in a compatible land use zones.
For the states of Sabah and Sarawak, the environmental requirements are clearly stipulated
in the Environment Protection (Amendment) Enactment 2002 and Natural Resources
and Environment Ordinance, 1993 – Chapter 84, Laws of Sarawak 1958 respectively.
Apart from the Environmental Quality (Amendment) Act 2012, there are other related
environmental legislations that should be complied by the project proponent such as:
Meanwhile, in Sabah there are other environmental legislations that should be complied
such as the following;
Since April 2011, an Integrated Management System (IMS) has been implemented in JKR
Malaysia. IMS is comprised of Quality Management System (QMS) 9001:2008,
Environmental Management System (EMS) 14001:2004 and Occupational Safety and
Health System (OSHA): 18001:2007.
8
The Environmental Management System (EMS) is also known as Sistem Pengurusan
Alam Sekitar (SPAS) 14001:2004. SPAS includes organizational structure, planning
activities, responsibilities, practices , procedures, processes and resources for developing,
implementing, achieving, reviewing and maintaining the environmental policy. For project
management, its processes will include environmental requirements in planning, design,
procurement, construction and handing over stages.
The planning stage is crucial to ensure that projects comply with the relevant environmental
requirements. If the said project has been classified as a “prescribed activity” according to
the Environmental Quality (Prescribed Activities) (Environmental Impact Assessment)
Order 1987 under Section 34A of the Environmental Quality(Amendment) Act 2012,
an Environmental Impact Assessment (EIA) study needs to be carried out and submitted to
Department of Environment (DOE) for approval prior to project implementation.
The EIA screening process is included in the SPAS and shall be carried out for every project
at its planning stage. By undergoing this process, the need for compliance to EIA and/or JKR
EMS 14001 requirements can be identified earlier. The project proponent shall submit the
PAT form to DOE within the planning stage. The PAT submission ensures that any new
project to be developed is in accordance with the specified land use zone for the site. The
flowchart of the PAT process is shown in Figure 2.1.1.
For projects that located in the Central Forest Spine (CFS), the project proponent shall
make reference to the Central Forest Spine Management Plan and Species Management
Plan.
9
Figure 2.1.1: Flowchart for Preliminary Site Assessment (PAT) for Any Proposed
Development Project
PAT Application
10
Under the Environmental Quality (Prescribed Activities)(Environmental Impact
Assessment) Order 1987, there are a total of nineteen (19) categories of prescribed
activities which includes agriculture, airport, drainage and irrigation, land reclamation,
fisheries, forestry, housing, industry, railways, transportation, resort and recreation
development, waste treatment and disposal, and water supply projects. Additionally, a
Detailed Environmental Impact Assessment (DEIA) study is required for seventeen (17)
different types of projects. Projects of which are relevant to JKR Malaysia are:
i. Cement plant
ii. Construction of dams for water supply and hydroelectric power schemes
iii. Land reclamation
iv. Incineration plant (scheduled waste & solid wastes)
v. Construction of municipal solid waste land fill facility (including municipal solid
waste transfer station)
vi. Project involving land clearing where 50% of the area or more having slopes
exceeding 25 degrees (except quarry)
vii. Logging covering an area exceeding 500 hectares or more
viii. Development of tourist or recreational facilities on islands in surrounding waters
which are gazetted as national marine parks
ix. Prescribed activities using radioactive materials(s) and generating radioactive
waste(s)
It is important to note that for projects in Sabah and Sarawak, specific local legislations
pertaining to EIA requirements need to be adhered to.
For the state of Sabah, lists of prescribed activities are contained in the First Schedule
and the Second Schedule of the Environment Protection (Prescribed Activities)
(Environment Impact Assessment) Order 2005. For projects in Sabah, an
environmental impact assessment report is required for any prescribed activities specified
in the Second Schedule of the Environment Protection (Prescribed Activities)
(Environment Impact Assessment) Order 2005 whilst , a proposal for mitigation measures
(PMM) is required for any prescribed activities specified in the First Schedule.
For projects in Sarawak, an environmental impact assessment report is required for any
prescribed activities specified in the First Schedule of the Natural Resources and
Environment (Prescribed Activities) Order 1994.
11
Figure 2.1.2: Flowchart for Preliminary EIA Process in Malaysia
12
Figure 2.1.3: Flowchart for Detailed EIA Process in Malaysia
13
Figure 2.1.4: Flowchart for EIA Process in Sarawak
14
Figure 2.1.5: Flowchart for Preliminary EIA Process in Sabah
15
2.2 Design Stage
For conventional projects, an EMP report should be submitted by Contractor to S.O for
approval within 14 days of site possession prior to commencement of any works on site.
The contractor shall comply with all requirements of the conditions of approval of the EIA
report and/or the EMP.
For design and build project, within fourteen (14) days of site possession, the Contractor shall
submit for the P.D approval a detailed EMP based on the Arahan Teknik (Jalan) 16/03 –
Pindaan 2015.
No site clearing and earthworks shall be carried out prior to EMP approval by relevant
parties/authorities. EMP should be revised throughout the construction period for on-site
suitability.
Upon submission and acceptance of the closing audit at the end of the construction period,
monitoring of operational activities in compliance to the necessary laws and regulations is
encouraged to be continued during the post construction stage in order to ensure that the
operational stage of the project does not cause any environmental damage. The impact of
generated wastewater has been deemed to be a significant residual impact that requires
further monitoring. The quality of any wastewater discharged must comply with the limits
as stipulated by the Environmental Quality (Sewage) Regulations 2009.
In order to identify the environmental requirement subjected to the proposed project, there
are two stages of undertaking which are environmental classification followed by project
classification. The details as shown in Table 2.5.1: Environmental Classification and its
Documents Compliance and Table 2.5.2: Project Classification and its Documents
Compliance.
16
Table 2.5.1: ENVIRONMENTAL CLASSIFICATION AND ITS DOCUMENTS COMPLIANCE
ONCE DURING PLANNING STAGE FILL IN FORM PENILAIAN AWAL TAPAK (PAT)
1 PENILAIAN AWAL TAPAK
(PAT) (FOR THE DETERMINATION OF ENVIROMENTAL CLASSIFICATION)
ONCE √ √
3 ESCP DRAWINGS
JPS APPROVAL APPLICABLE HODT
MONTHLY √ √
5 EMR
ONCE IN 3 MONTHS √ √
6 EAR
FULLTIME AT SITE √ √
8 EO
Note: *1 = The determination of projects categorized under 19 Prescribed Activities as in the Schedule in ‘Environmental Quality (Prescribed
Activities)(Environmental Impact Assessment) Order 1987’.
*2 =The determination of projects categorized under Environmental Sensitive Areas with reference made from Rancangan Fizikal
Negara, Rancangan Struktur Negeri and Rancangan Tempatan by JPBD / Local Authority.
17
Table 2.5.2 PROJECT CLASSIFICATION AND ITS DOCUMENTS COMPLIANCE
NO CRITERIA FREQUENCY PROJECT COST > RM 20 MILLION PROJECT COST < RM 20 MILLION
WITH EARTHWORK WITH EARTHWORK
MONTHLY √ X
4 EMR
ONCE IN 3 MONTHS X X
5 EAR
Note: If a project does not fall in any category above (Table 2.5.1), then the Project Classification will be based on the project cost as below.
18
2.6 Applicable Guidelines
Area to be
developed Applicable Guidelines Publisher
A Handbook of EIA Guidelines DOE
EIA Procedure and Requirements in DOE
Malaysia
Environmental Impact Assessment DOE
Guidelines for Housing and New
Township Development Project
Guidance Document for Addressing DOE
Soil Erosion and Sediment Control
Aspects in the Environmental Impact
Assessment (EIA) Report
Guidelines of Siting and Zoning for DOE
Industry and Residential Areas
Environmental Audit Guidance Manual DOE
The Planning Guidelines for DOE
General Sites
Environmental Noise Limits and
Control
The Guidelines for Noise Labelling and DOE
Emission Limits of Outdoor Sources
The Planning Guidelines for Vibration DOE
Limits and Control
Guidelines for Erosion and Sediment JPS
Control in Malaysia
Latest Edition of Manual Saliran Mesra JPS
Alam(MSMA) (Urban Stormwater
Management Manual for Malaysia)
Guidelines for the Environmental
Impact Assessment of Highway/Road JKR
Projects
19
Area to be
developed Applicable Guidelines Publisher
Planning Standards for Coastal Areas, JPBD
JPBD
Planning Standards for the Physical JPBD
Development of Islands
Islands and Marine Park Physical JPBD
Development Planning
The National Coastal Zone Physical JPBD
Plan (Volume 1 & 2)
EIA Guidelines for Coastal Resort DOE
Coastal Sites Development Projects
EIA Guidelines for Tourist and DOE
Recreational Island in Marine Parks
EIA Guidelines for Coastal and Land DOE
Reclamation
Guidelines for Preparation of Coastal JPS
Engineering Hydraulic Study and
Impact Evaluation
Sabah Shoreline Management Plan JPS
20
CHAPTER 3
CONTRACTUAL REQUIREMENTS
21
CHAPTER 3: CONTRACTUAL REQUIREMENTS
Environmental protection and enhancement works for conventional contract projects are to
be specified in the Instructions to Tenderer (ITT) and Conditions of Contracts. These
shall form part of the pre bid document to be prepared for Conventional Contract projects.
For conventional projects, an EMP report should be submitted by the Contractor to the
S.O for approval within fourteen (14) days of site possession prior to commencement of
any works on site. The contractor shall comply with all the requirements of the
conditional approval of the EIA report and/or the recommendations in the EMP.
No site clearing and earthworks shall be carried out prior to EMP approval by relevant
parties/authorities. EMP should be revised throughout the construction period for onsite
suitability. In the event if the contractor fails to submit such a plan, then the government
deserves the right to prepare such a plan and the costs incurred shall be deducted from the
contract sum. The cost of preparing the EMP shall include the cost involved in obtaining
the services of a DOE-registered environmental consultant and is deemed to be borne by
the Contractor.
The Environmental Impact Assessment (EIA) Report and the Conditions of Approval
given by the Department of Environment (DOE), NREB (Sarawak) or EPD (Sabah) shall
be made available to assist the Contractor and the environmental consultant in preparing
the EMP or any other applicable reports.
For design and build contract, reference shall be made to the need statement pertaining to
environmental protection and enhancement requirements. The need statement is as
attached in Appendix 2 of this document.
22
CHAPTER 4
SPECIFICATIONS
23
CHAPTER 4: SPECIFICATIONS
This section contains the specification relating to environmental matters in the execution
of JKR projects in line with JKR EMS: MS ISO 14001 and shall be read in conjunction
with the latest JKR Standard Specification for Buildings and Standard Specification for
Road Works. However where these matters appear also in other sections of the Contract
Document, this specification shall take precedence.
The Contractor shall at all times adhere to all existing statutes regarding the protection
of the Environment.
Prior to the execution of the project, the Contractor shall comply with all related
environmental legislations, such as following:
The Contractor shall be liable for and shall indemnify the Government against any
damages, expenses, liability, losses, claims, prosecution, proceedings, fines and penalties
caused by any non-compliances or contraventions of the above legislations and
regulations.
The Contractor shall submit a report on project’s impact on the environment if the project
is listed as prescribed activities as indicated in Table 4.2.1.
24
Table 4.2.1: EIA Legislation
4.3.1 Definition
4.3.2 Objectives
The main objective of the Environmental Management Plan (EMP) is to set out a
comprehensive programme which will form the basis for implementing
environmental mitigation measures, environmental monitoring and environmental
auditing of the construction works by the Contractor as listed below:-
(ii) To ensure that the Contractor complies with all applicable environmental
standards and guidelines, legislative requirements and other relevant
conditions related to the environment;
25
(iii) To specify a detailed environmental monitoring and auditing programmes to
ensure that the Contractor and all his Sub-contractors comply with all
stipulated requirements throughout the duration of the project; and
Any project that falls under one of these following categories shall prepare
an EMP:-
(iii) Projects that cost RM20 million and above including earthworks.
The Contractor shall submit an EMP and the EMP shall be approved prior to
commencement of any works on site. The EMP shall be submitted to the S.O for
endorsement within fourteen (14) days of Site Possession in compliance with the
Conditions of Contract and/or in compliance with the requirements of the
conditions of approval of the EIA report by the Department of Environment. For
design and build projects, the Need Statement shall prevail.
The EMP shall make reference to the following but not limited to:-
The EMP is a document for practical use on site by nominated personnel, thus it
shall be concise, up to date and site specific.
The execution of the EMP is a joint responsibility of the contractor, consultant and
appointed Environmental Officer (EO) for the project.
26
4.3.5 Environmental Officer
4.3.7 Deliverables
27
(a) The Contractor shall provide and maintain on site, suitable and sufficient
offices for the S.O, his representatives and the Contractor’s own use.
(b) The Contractor shall provide and maintain on site, suitable workshops and
stores with impervious flooring including grease traps.
(c) The Contractor is prohibited from discharging oil and grease to any
watercourses. Any spilled oil and grease shall be promptly removed and
this contaminated waste shall be kept in proper containers. Used oil and
grease shall be kept in separate containers for recycling. All containers
shall be stored in secured areas prior to disposal by a licensed contractor as
per the Environmental Quality (Scheduled Wastes) Regulations 2005.
The accommodation for workmen shall comply with the requirements mentioned
in Section A –Preliminaries and General Conditions in the latest JKR Standard
Specification for Building Works and Standard Specification for Road Works.
4.4.3 Utilities
(i) The water supply shall comply with the requirements mentioned in
Section A –Preliminaries and General Conditions in the latest JKR
Standard Specification for Building Works and Standard Specification for
Road Works.
(b) Sanitation
No site clearing and earthworks shall be carried out prior to EMP approval by
relevant parties/authorities.
(a) Site clearing shall be done in stages and within construction limit. No
burning of cleared vegetation and debris shall be allowed.
28
‘work in stages’ and also plans for diverting as much as possible surface
runoff from the work areas into these structures.
(c) For road projects, site clearing should be from the center of the road
outwards towards the construction limit to enable escape of wildlife into
neighbouring jungles.
(f) Trees and vegetation identified for conservation must be protected by the
Contractor at all costs.
(g) Other clearing activities such as access road construction, site office and
work-camp construction, etc shall be carried out with minimal cutting of
trees and site clearing. The intended area shall be marked out for the
S.O.’s inspection and approval prior to any site clearing works.
(h) Holes and cavities resulting from clearing, grubbing, de-stumping and de-
rooting shall be backfilled with acceptable materials and compacted to
approximate densities of adjacent areas.
(i) The Contractor shall provide all necessary temporary drainage for keeping
the site and other areas free of standing water. Efforts must be made to
channel the surface runoff as much as possible away from the work areas.
(k) Should the Contractor fail to ensure compliance with any of the above, the
S.O. without prejudice to any other rights or remedies available to the
Government under this Contract may employ and pay other persons to
execute the work and all costs incurred in connection with such
employment shall be recoverable from the Contractor as stipulated in the
Conditions of Contract.
4.5.2 Earthworks
(a) All silt traps, sedimentation basins, erosion control measures and drainage
system as shown in drawings must be constructed in stages and maintained
by the Contractor. The location of these mitigating measures shall be
detailed and shown on plan in the EMP for the approval of the S.O.
29
(b) The Contractor shall provide all necessary temporary drainage for keeping
the site and other areas free of standing water before the commencement
of any earthworks. Effort must be made to channel the surface runoff as
much as possible away from the work areas.
(c) All temporary drainage, mitigation measures (e.g. silt traps and silt fence)
must be constructed before the commencement of any earthworks and
shall be maintained throughout the construction period to ensure their
effectiveness.
(d) Unsuitable materials and surplus earth shall be disposed off in designated
spoil tips, within the site or off site. Unless otherwise stated, the
Contractor shall be responsible for identifying these disposal areas. The
dump site/ disposal areas shall be identified and approved by the S.O.
before commencement of any earthworks. In the event additional disposal
areas (spoil tips) are required, the Contractor shall also be responsible for
identifying these disposal areas which shall be approved by the S.O.
(e) The method of depositing the unsuitable materials and surplus earth to the
spoil tips must be properly engineered, designed and must be sufficiently
graded, leveled, compacted, properly drained, revegetated and approved
by the S.O. End-tipping shall not be allowed.
(f) The Contractor shall schedule for earthworks to be carried out as much as
possible during dry weather periods. This is to ensure that the earthwork
activities being carried out are done in a systematic/orderly manner in
order to minimize earth surfaces from being exposed for long periods
during wet weather periods. The turfing or hydro seeding must be carried
out immediately after earthworks and before work on other beam/lift
commences. If due to unforeseen circumstances turfing cannot be carried
out immediately, temporary protection/cover (e.g. plastic sheets or
equivalent) shall be applied to the exposed slopes.
(g) Should the Contractor fail to ensure compliance with any of the above, the
S.O. without prejudice to any other rights or remedies available to the
Government under this Contract may employ and pay other persons to
execute the work and all costs incurred in connection with such
employment shall be recoverable from the Contractor as stipulated in the
Conditions of Contract.
(a) All access roads to the site shall be built away from the existing
watercourses, streams and rivers with proper drainage system and be
paved for a distance of at least 10 meters from where these access roads
join existing roads.
30
(b) The Contractor shall maintain all access roads including the drainage
system throughout the construction period to the satisfaction of the S.O.
(c) Where the Contractor uses existing/private roads as his access, he shall be
responsible for any damage to the existing roads, bridges, drains, culverts,
roadside furniture, and all other appurtenances and services on such roads
caused by any work carried out by him throughout the construction period.
The Contractor shall repair any damages and reinstate the same to their
original condition or the condition satisfying the current
standards/guidelines/requirements to the satisfaction of the S.O.
(a) All silt fence, silt traps, sedimentation basins and other erosion and
sediment control measures as shown in ESCP drawings must be
constructed and maintained by the Contractor.
(b) The water used for cleaning vehicle tires in wash troughs should be
distributed through any sediment settling sump overflow and directed into
the trap tilt. The used water should not be allowed to discharge directly
into existing drainage system.
(c) Water quality standards and monitoring schedule from the silt traps/
sedimentation basin/rivers/stream/water bodies shall comply as specified
in Table 4.7.1 or as directed by the S.O. Silt traps and sediment basin
discharges shall be monitored monthly and shall be collected within 30
minutes after a rainfall event of more than 20mm.
(d) The Contractor is prohibited from discharging oil and grease to any
watercourse. Oil drums must be placed within a sheltered, paved bunded
area and the drainage outlet must be provided with an oil sump or oil
interceptor. Any spilled oil and grease shall be promptly removed by the
Contractor.
(e) The Contractor shall carry out water quality monitoring at locations on
existing water bodies as indicated in the EMP. Parameters to be tested are
as specified in Table 4.7.1.
(a) The Contractor is prohibited from carrying out open burning of cleared
vegetation, debris and construction waste etc.
31
(b) The Contractor shall provide suitable spraying equipment for regular
spraying of water over the existing roads, tracks and access roads, near
settlements, completed as well as incomplete road and other barren areas
of the site used by the contractor especially during the dry season or as and
when directed by the S.O.
(d) The Contractor shall provide for the prompt removal of all dirt and other
materials spilled from his or his sub-contractor’s vehicles on public or
private roadways.
(e) The Contractor’s trucks carrying sand, aggregates, earth and other loose
construction materials liable to spillage, tarpaulin must be used to cover
such open trucks when passing through villages and settlements or on all
roadways.
(f) The Contractor shall also ensure dust control at quarry / batching plant (if
any) complies with environmental requirement as stipulated in the
Environmental Quality (Clean Air) Regulations, 2014.
(g) The Contractor shall carry out air quality monitoring at locations as
indicated in the EMP. The parameters to be tested are as specified in Table
4.7.1.
(a) All work shall be carried out with least disturbance and noise. The
Contractor shall ensure all his equipment and machineries are in proper
working condition so as to minimize the amount of noise generated. The
S.O. may require the Contractor to replace any machinery that to his
discretion is emitting excessive noise.
(b) The location of the noise monitoring station shall be placed to the nearest
sensitive receptor such as hospital, school, and housing scheme as
identified and directed by the S.O. The Contractor shall comply with the
general recommendations set out in Planning Guidelines for
Environmental Noise Limits & Control, (Department of Environment)
together with any specific requirements described in the Contract.
(c) The Contractor shall indemnify and keep indemnified the Government,
S.O. and the S.O. representatives against any liability for damages on
account of noise or other disturbances created while or in carrying out of
the works and from and against all claims, demands, proceedings,
32
damages, costs charges and expenses whatever in regard or in relation to
such liability.
(d) The Contractor shall carry out noise quality monitoring at locations as
indicated in the EMP. The parameters to be tested are as specified in Table
4.7.1.
(a) The Contractor shall ensure that at any time, the vibration levels resulting
from his works at or across real property boundary should not exceed the
Recommended Limits as Specified in Table 4.7.1. No person unless duly
authorized by law or carrying our legitimate duties shall use explosives or
results in explosions which create a vibration disturbance across a real
property boundary or on a public space or right of way.
(b) The Contractor shall comply with the general recommendations set out in
The Planning Guidelines for Environmental Noise Limits and Control and
The Planning Guidelines for Vibration Limits and Control in the
Environment together with any specific requirements described in the
Contract.
(c) The Contractor shall indemnify and keep indemnified the Government,
S.O. and the S.O.’s Representatives against any liability for damages on
account of vibration disturbance created while or in carrying out of the
works and from and against all claims, demands, proceedings, damages,
costs charges and expenses whatever in regard or in relation to such
liability.
33
Table 4.7.1: Environmental Quality Standards to be complied with by the Contractor
Environment Quality National
(Sewage) Regulations, Water Quality
2009 Standards
Parameter JKR Set (NWQS)
Aspects Target
Standard Standard Class Class
A B IIA IIB
34
Nitrogen mg/l mg/l
(river)
Silt trap Turbidity ≤250 NTU - - - -
and Total ≤50 mg/l - - - -
Sediment Suspended
Basin Solids
Discharge
Total Suspended ≤260 µg/m3/day
Particulates(TSP) (24hr)
Air3 Particulate Matter (PM10) ≤150 µg/m3/day
(24hr)
Coral Live coral cover according to Maintain live coral cover of fair category
Reef Reef Check Procedure (26% to 50% live coral cover).
Health
*Note: Refer Appendix 4 for Malaysia National Water Quality Standards (NWQS)
35
Table 4.7.2: Water Quality Monitoring Parameters to be Monitored (Projects at Marine
Parks)
Reference:
(1) 2nd Schedule (Regulation 7), Environmental Quality (Sewage) Regulations 2009,
Environmental Quality Act 1974.
Standard A: For the areas upstream of surface or above subsurface water supply
intakes
Standard B: Applicable to any other inland waters or Malaysian waters
(4) Schedule 1 & Schedule 6 of the Planning Guidelines for Environmental Noise
Limits & Control, (Department of Environment)
(5) Planning Guidelines for Vibration Limits and Control of the Environment
(Department of Environment)
36
4.11 Waste Management
(a) Definition
(iii) Any other materials that according to this Act or any other written law is
required by the authority to be disposed of, Solid Waste and Public
Cleansing Management 15 but does not include scheduled wastes as
prescribed under the Environmental Quality Act 1974 [Act 127], sewage as
defined in the Water Services Industry Act 2006 [Act 655] or radioactive
waste as defined in the Atomic Energy Licensing Act 1984 [Act 304].
(i) The Contractor shall undertake the collection and disposal of solid waste
Such as litter, kitchen and canteen refuse, non-hazardous solid waste
including office, workshop and accommodation waste. Solid waste
collection shall be made at least twice a week or as and when directed by
the S.O.
(ii) Solid waste shall be stored in proper bins and containers, collected and
disposed of at designated site(s) approved by the S.O. or to a locally
available landfill by a licensed contractor.
(iv) The Contractor should adopt ways to minimize waste such as reduce, reuse
and recycle of waste. Example of waste minimizations is to reduce the
amount of waste from concrete usage, first is by ordering the correct
quantity and batch or by using concrete panels. Excess concrete can then
be recycled as concrete blocks and bench or reused as hardcore materials.
37
4.11.2 Scheduled Waste
(a) Definition
Scheduled waste means any waste falling within the categories of waste listed
in the First Schedule, Environmental Quality (Scheduled Wastes) Regulations
2005.
Examples of scheduled waste in the construction site are rags, plastics, papers
or oil filters that is contaminated with scheduled wastes, used engine oil, used
paint and spent lubricant oil.
(i) Contractor shall submit the notification to the DOE once only, unless there
is a change in the category of waste produced within 30 days after being
generated.
(ii) Storage for scheduled waste must be in compatible and durable container,
scheduled waste container shall always be closed and provide proper
scheduled waste storage area to prevent spillage into the environment.
(i) The Contractor shall undertake the collection and disposal of scheduled
waste at site. Scheduled waste collection shall be made within 180 days or
as and when directed by the S.O.
(iii) The contractor must ensure that all details including forms, documents,
receipts and other related to management of construction scheduled waste
must be kept at site and recorded for auditing purposes.
38
4.12 Preservation of Flora and Fauna
4.12.1 Flora
(a) Prior to site clearing, the forester and/or botanist engaged by JKR or Contractor
shall assist the surveyor to identify any trees of rare, endemic or endangered
species which need to be conserved or relocated. The Contractor shall produce
a survey report as specified by Jabatan Perhutanan or other relevant
authorities. Trees which are classified as rare, endemic and endangered shall be
conserved and marked (crossed) red. Similarly, trees having girth of 800mm
and above shall be conserved and marked (crossed) red. Trees which are rare,
endemic or endangered and required to be relocated shall be marked (crossed)
white.
(b) The Contractor shall be responsible for the transportation of trees to nearby
sites, arboretum or other alternatives, which is among from any roads so as not
to cause interruption to traffic flow and become hazardous to road users, as
advised by the forester. The Contractor shall ensure all relocated trees are well
kept.
(d) The falling of trees during cutting or logging activities shall be confined within
the construction boundary.
(e) The Contractor shall be prohibited from destroying, removing or clearing trees,
timber, shrub and other flora to any extent greater than that approved by the
S.O. as being necessary for the execution of the contract.
(a) The Contractor shall comply with the Wildlife Conservation Act, 2010
(Act 716) and other related environmental legislations.
39
(c) Fauna survey is to identify the fauna species and their habitat, in particular
those of rare, endangered, and endemic fauna species that require protection
and rehabilitation, which may include possible relocation to other designated
sites.
(d) The contractor shall produce a wildlife inventory report and Wildlife
Management Plan as specified by Jabatan Perlindungan Hidupan Liar dan
Taman Negara (PERHILITAN) or other relevant authorities.
(f) The contractor shall be responsible for handling and transporting of wildlife in
well-kept condition including safety during relocation and transportation. It
shall also include trapping, transportation and protection and treatment required
for the well-being of the fauna at the rehabilitation centers and before their
release at the final place of relocation / rehabilitation.
(a) Prior to site clearing, a marine biologist engaged by JKR or Contractor and a
marine park officer shall assist the surveyor to identify any boulder or
encrusted coral colony or immotile endangered species such as giant clams
which need to be conserved. Coral colonies and immotile species which have
been identified shall be conserved and marked accordingly in construction
plan. Surveyor shall also identify coral colonies for translocation. Contractor
shall bear all costs of translocation.
(b) The Contractor should ensure that all coral reefs and immotile marine
organisms such as giant clams identified to be conserved in the construction
area are transplanted to an approved location and in accordance with the
transitional rules set by the Department of Marine Parks Malaysia, Ministry of
Natural Resources and Environment.
(c) Transplantation of identified coral colonies has to be carried out before any
earth works. For non-transplantable coral colonies (boulder corals, encrusting
coral), design of piling location shall be changed accordingly including
redesigning of the structures for avoidance.
40
(d) The contractor must obtain the approval of the Director General of the
Department of Marine Parks Malaysia at least three weeks before the transplant
operation of coral reefs and immotile marine organisms.
(e) The contractor should ensure coral and immotile marine organisms relocation
work is monitored by the Department of Marine Parks Malaysia.
(f) The contractor and his employees are prohibited from collecting or possessing
of any coral and marine organisms, dredging or extracting any sand or gravel,
discharging or depositing any pollutant, altering or destroying the natural
breeding grounds or habitat of aquatic life, or destroying any aquatic life.
(g) The contractor and his employees are prohibited from anchoring any vessel by
dropping any kind of weights, or by attaching any type of rope or chain to any
coral, rock or other submerged object.
(h) Coral relocation - Sites for translocation of coral has to be 200m from project
site with similar depth profile as original coral population location.
b. Method to be used:
Reef Check (20m permanent transect)
1m x 1m permanent quadrate for seagrass bed (3 quadrate on
each 20m transect – start point, middle point and end point
Number of sites: 5 sites
Critical observation: coral bleaching and physical damage
(breakage)
Type of report to be submitted: written report, photos and
video of survey site)
(a) The contractor and his employees are prohibited from fishing or attempts to
fish capturing, disturbing, removing or possessing any aquatic animal or
aquatic plant or part thereof, whether alive or dead;
(a) The contractor and his employees are prohibited from constructing or erecting
any building on or over any land or waters within a marine park or marine
reserve without specific written permission from the Director General of the
Department of Marine Parks Malaysia.
(b) The contractor and his employees are prohibited from destroying or removing
anything in Marine Parks or marine reserve.
41
4.14 Requirements In Relation To Waterways
(a) The Contractor and/or JKR shall seek approval from Jabatan Pengaliran &
Saliran (JPS) for any works related to natural waterways including diversions,
modifications replacements and/or relocation of rivers, watercourses and
related structures during execution of the works.
(b) The Contractor shall coordinate all operations and make adjustments to his
programme resulting from JPS requirements pertaining to changes made to the
natural waterways.
(c) The Contractor shall ensure that temporary diversions of rivers and/or
waterways shall be capable of sustaining flows throughout the year as specified
by the JPS.
(i) Bioengineering
Creepers
(ii) Mulching
Mulch is a protective cover placed over the soil to protect soil from
rain, preserve moisture and slows runoff velocity. A variety of
materials can be used as mulch such as grass clippings, leaves, hay,
straw, shredded bark, sawdust, wood chips, shredded newspaper,
cardboard and wool.
42
(b) Proprietary products
The Contractor may also use proprietary or any man-made products available
in the market to control erosion on slopes such as plastic sheet, etc. subject to
JKR’s approval. The suitability of the products used shall follow the
manufacturer’s specifications including method of installation and
maintenance. Others examples of propriety products are geotubes, ENKA mat,
geocells/geoweb, fibromat and coir logs.
The specification as described under this Section shall be read together with
other related sections of the Standard Specification for Road Works or
Standard Specification for Buildings and the drawings shall refer to the Chapter
8 - Standard Drawings of this document.
Silt fence shall consist of geotextile supported by poles at regular interval. The
geotextile shall be made of non-woven materials with minimum properties of
200 g/m² or tensile strength 15 kN/m shall be constructed as close as possible,
parallel to the contours of the site with a setback of at least 0.9 m (3 ft) from
the toe of the slope.
The silt fence shall be inspected after every rain event. The silt accumulated
behind the fence shall be removed when it has reached 2/3 of the fence filter
height and disposed at designated site. The geotextile shall be checked for rips,
tears and other types of deterioration and replaced as needed. Any failures shall
be repaired immediately and the silt fence shall be re-installed after repairing
the damage.
43
the silt traps/sediment basins shall be removed when it has reached 2/3 of its
depth and disposed at designated site.
The check dams shall be inspected regularly after rain and any damages shall
be rectified. The sediment accumulated behind the check dams shall be
removed when it has reached 2/3 of its height and disposed at designated site.
The height of the check dam shall be maintained to be the same at all time.
Additional check must be performed after each runoff events, as well as after
heavy winds or current. Accumulated sediment shall be removed as per
manufacturers’ instruction. The suspended sediments trapped behind silt
curtain shall be allowed to settle for a minimum of 24 hours, prior to removal
of the silt curtain. For fine particle, longer time for settlement shall be
expected. The curtain shall be removed during calm weather and low flows.
44
Marine parks
Note: Skirt length to be adjusted 10% longer than the water depth
Sand bag barrier shall be checked regularly before and after rain events, In
addition, sandbags exposed to sunlight will cause degradation and need to be
replaced immediately. Sediment should be removed when the sediment
accumulation reaches one-third of the barrier height and disposed at designated
site.
Note: Other items not specified above shall be referred to the latest JKR
Standard Specification for Buildings Works and Standard Specification
for Road Works
45
CHAPTER 5
METHOD OF MEASUREMENT
46
CHAPTER 5: METHOD OF MEASUREMENT
Non-Physical Work
Unit
The unit of measurement for preparation of EIA Report shall be Lump Sum (sum).
Measurement
The measurement for payment shall be the preparation and approval of the EIA
report in accordance to the format in the EIA guidelines for specific activities and
A Handbook of EIA Guidelines prepared by Department of Environment (DOE).
Pricing Factors
The item for preparation of the EIA Report shall be in accordance with the
Preambles to Bill of Quantities:-
(c) Submission of twenty one (21) hard copies and one (1) digital copy of the
approved and accepted report to S.O. The copyright of the said documents
shall be transferred and become the absolute property of the Government
Unit
The unit of measurement for preparation and acceptance of EMP shall be Lump
Sum (sum) and include:
Pricing Factor
The item for preparation of ESCP shall be in accordance with the Preambles to Bill
of Quantities:-
47
(a) All cost associated in the preparation of a complete report on drainage
system, erosion control plan and course of action to be taken;
(b) Additional cost for the engagement of a professional engineer required for
the preparation of the ESCP;
(c) Submission of five (5) copies of ESCP for endorsement by the S.O.
(f) Coral Reef Management Plan for translocation of coral colonies and
immotile marine organisms; if applicable
Measurement
The measurement for payment shall be made upon submission and acceptance of
the EMP prepared in accordance to the format as stipulated in the DOE General
Checklist for Preparing EMP as follows:-
Unit
Measurement
The measurement for payment shall be the man-month basis throughout the
contract period (excluding Defects Liability Period).
48
Pricing Factors
(c) The Contractor, with the approval of the S.O., shall employ a competent
E.O. (A Graduate in science and/or engineering field with a minimum of
one year experience in the environmental sector);
(d) Costs and expenses incurred consequent upon the employment or hiring of
a competent full time E.O. throughout the contract period including
payment of Employee Provident Fund, insurance, medical and
hospitalization;
(e) Costs and expenses incurred for the training/awareness briefing by the E.O.
to site personnel whose activities have impact on the environment;
(g) Any substitution when the appointed E.O. is absent or on leave for more
than three (3) consecutive days.
Unit
The unit for measurement to conduct the above monitoring shall be Lump Sum
(sum) for the whole duration of the contract.
49
Measurement
The measurement for payment shall be the number of samples taken for
monitoring, tested and accepted by the S.O.
Pricing Factor
The item to conduct environmental monitoring (water, air, noise and vibration)
shall be in accordance with the Preambles to Bill of Quantities:-
(c) Taking samples according to the intervals, parameters and for the duration
specified at approved sampling locations by trained laboratory personnel;
Unit
The unit for measurement to conduct the above monitoring shall be Lump Sum
(sum) for the whole duration of the contract.
Measurement
Pricing Factor
The item to conduct Reef Check (20m permanent transect) and 1m x 1m permanent
quadrate for seagrass bed (3 quadrate on each 20m transect – start point, middle
point and end point for at least 5 sites).
50
5.4.2 Environmental Monitoring Report
Unit
Measurement
The measurement for payment shall be the number of reports prepared based on
monitoring carried out and accepted by the S.O.
Pricing Factor
The item for preparation of the monitoring report shall be in accordance with the
Preambles to Bill of Quantities:-
(b) Submission of five (5) copies of report (submitted with photos) to S.O.
Unit
Measurement
The measurement for payment shall be the number of reports prepared based on
audits carried out and accepted by the S.O.
Pricing Factor
The item to conduct environmental audit and preparation of report including the
Closure Audit Report shall be in accordance with the Preambles to Bill of
Quantities:-
(b) Cost of carrying out 3rd party audit once every four months or at any other
intervals deemed necessary due to legal requirement or nature of works on
site, evaluation of monitoring data and verifying implementation of
corrective and preventive actions;
51
(c) Cost associated in the preparation of a comprehensive report including
recommendations for improvement in accordance with the Standard Report
Format as specified in Appendix 2 of this Document;
(d) Submission of five (5) copies of report (per audit) with colour photographs
to S.O.
5.4.4 Training
Unit
Measurement
The measurement for payment shall be the number of training sessions carried out
for the duration of the contract.
Pricing Factor
The item for training JKR personnel shall be in accordance with the Preambles to
Bill of Quantities:-
Physical Work
Unit
Measurement
The measurement for payment shall be the number of water bowser truck provided
on site and shall be made as follows:-
52
(b) 40% for operation and maintenance which shall be made in each interim
payment in proportion of the total period lapsed to the Contract Period
(excluding Defects Liability Period).
Pricing Factor
The item for provision, operation and maintenance of bowser truck shall be in
accordance with the Preambles to Bill of Quantities:-
(a) All costs associated with the provision and operation of trucks including
operators, water supply, pumping of water, water tank and all other
necessary equipments needed to carryout water spraying;
(b) Carrying out water spraying minimum 3 times a day along haul/access
roads, existing road and nearby settlement zone or other affected areas or as
directed by S.O.;
(e) Removal of truck and equipments from site on completion of the works to
the satisfaction of the S.O including reinstatement of the site.
Unit
Measurement
The measurement for payment shall be the number of portable water jet provided
on site and shall be made as follows:-
(b) 40% for operation and maintenance which shall be made in each interim
payment in proportion of the total period lapsed to the Contract Period
(excluding Defects Liability Period).
53
Pricing Factor
The item for provision, operation and maintenance of portable water jet shall be in
accordance with the Preambles to the Bill of Quantities:-
(a) cost of construction and maintenance of the structure for the elevated water
tank and the supply of the water tank;
(b) cost for the construction of the tyre washing concrete platform;
(c) provision for portable water jet including operator and other necessary
equipments deemed required for the successful washing operation;
(d) carrying out of cleaning of all vehicle tyres at various exits of worksites;
(g) demolition, and disposal of all rubbish, debris and surplus materials
including removal of all equipments from site on completion of the works to
the satisfaction of the S.O. including reinstatement of the site.
Unit
The unit of measurement for construction and maintenance of wash trough shall be
in number (nr).
Measurement
The measurement for payment shall be the number of wash trough constructed on
site as shown in Drawing and shall be made as follows:-
(b) 20% for maintenance which shall be made in each interim payment in
proportion of the total period lapsed to the Contract Period (excluding
Defects Liability Period).
Pricing Factor
The item for construction and maintenance of wash trough shall be in accordance
with the Preambles to Bill of Quantities:-
54
(b) Construction of wash trough including concrete, formwork, reinforcement,
hardcore complete as shown in Drawing;
(c) Filling and regular maintaining of water during the course of the works;
(e) Demolition and disposal of all rubbish, debris and surplus materials from
the site to the satisfaction of the S.O. including reinstatement of the site.
Unit
The unit of measurement for provision and maintenance of water sprinkler shall be
in number (nr)
Measurement
The measurement for payment shall be the number of water sprinkler installed at
quarry/batching plant and shall be made as follows:-
(b) 60% for operation and maintenance which shall be made in each interim
payment in proportion of the total period lapsed to the Contract Period
(excluding Defects Liability Period).
Pricing Factor
The item for provision and maintenance of water sprinkler shall be in accordance
with the Preambles to Bill of Quantities:-
(a) Supply and installation of water sprinkler system including all other
necessary equipments and facilities;
5.6.1 Creepers
Unit
55
Measurement
The measurement for payment shall be made of the plan area placed to the lines,
level grades and dimensions shown in Drawing or as directed by the S.O.
Pricing Factor
The item for planting and maintenance of creepers shall be in accordance with the
Preambles to Bill of Quantities:-
(c) The details and results of investigations to determine which types of grass
and legumes are compatible with the soil in the areas to be turfed;
(d) The types of grass and legumes (if any) and strains of seeds to be used, and
the function, root and growth characteristics of each type;
(f) The type of mulch to be used and its method and rate of application;
(g) The amount of lime or other chemicals (if any) to be applied to improve the
soil before, during and after turfing;
(h) The equipments and methods to be used in preparing and placing the turf
mix and other materials;
(i) The cultivation and after – care of the turfed areas, including rates and
frequencies of watering, fertilising, grass cutting and general maintenance
for 1 year after turfing;
Unit
56
Measurement
The measurement for payment shall be made of the plan area placed to the lines,
level grades and dimensions shown in Drawing or as directed by the S.O.
Pricing Factor
(b) The preparation of the areas to be controlled including (if any) the amount
of topsoil to be used and its method of application;
(d) The types of artificial erosion control items (if any) and strains of
proprietary products to be used, and the function, root and growth
characteristics of each type;
(e) The type of proprietary products to be used and its method and rate of
application including equipment and maintenance required.
Unit
The unit of measurement for construction of silt fence shall be in linear metre (m).
Measurement
The measurement for payment shall be the length of complete fence constructed as
shown in Drawing and shall be made as follows:-
Pricing Factor
The item for construction of silt fence shall be in accordance with the Preambles to
Bill of Quantities:-
57
(b) Construction of silt fence as shown in the detailed drawing;
(c) Removal and disposal of all rubbish, debris and surplus materials from the
site
Unit
The unit of measurement for maintenance of silt fence shall be in linear metre (m).
Measurement
Pricing Factor
The item for maintenance of silt fence shall be in accordance with the Preambles to
Bill of Quantities:-
(a) Inspections at regular interval and after heavy rain of geotextile and other
components for rips, tears and other types of deteriorations and
replacements if required;
Unit
The unit of measurement for Installation of sand bag barrier shall be in number
(nr).
Measurement
The measurement for payment shall be the number of sand bag barrier constructed
as shown in Drawing and approved by the S.O. and made as follows:-
58
Pricing Factor
The item for construction of installation of sand bag barrier shall be in accordance
with the Preambles to Bill of Quantities:-
Unit
The unit of measurement for maintenance of sand bag barrier shall be in number
(nr).
Measurement
The measurement for payment shall be the maintenance of the completed sand bag
barrier and shall be made in each interim payment in proportion of the total period
lapsed to the Contract Period (excluding Defects Liability Period).
Pricing Factor
The item for maintenance of sand bag barrier shall be in accordance with the
Preambles to Bill of Quantities:-
(a) Sand bag barrier shall be checked daily before and after rain events, weekly
during the rainy season, and at two-week intervals during the non-rainy
season.
(i) Gabion
Unit
The unit of measurement for construction of gabion units in silt traps or sediment
basins shall be in number (no).
Measurement
The measurement for payment shall be the number of specified size gabion unit
constructed as shown in Drawing and approved by the S.O. and made as follows:-
59
(b) 20% on removal
Pricing Factor
The item for construction of gabion units in silt traps and sediment basins shall be
in accordance with the Preambles to Bill of Quantities:-
(a) Excavation for preparation of the silt trap and disposal of surplus excavated
materials;
(b) Construction of gabion overflow including cage, geotextile and rock fill as
shown in detailed drawings;
(c) Assembling, tying and staking for the positioning of the gabion units ;
(d) Removal and disposal of all rubbish, debris and surplus materials from the
site to the satisfaction of the S.O. including reinstatement of the site
Unit
The unit of measurement for sand bedding in silt traps or sediment basins shall be
in cubic meter (m3).
Measurement
The measurement for payment shall be the volume of sand bedding constructed as
shown in Drawing and approved by the S.O. and made as follows:-
Pricing Factor
The item for construction of sand bedding in silt traps and sediment basins shall be
in accordance with the Preambles to Bill of Quantities:-
(a) Excavation for construction of the sand bedding and disposal of surplus
excavated materials;
60
(iii) Stone Filling
Unit
The unit of measurement for construction of stone filling in silt traps or sediment
basins shall be in cubic meter (m3).
Measurement
The measurement for payment shall be the volume of stone filling constructed as
shown in the detailed drawings and approved by the S.O. and made as follows:-
Pricing Factor
The item for construction of stone filling in silt traps and sediment basins shall be
in accordance with the Preambles to Bill of Quantities:-
Unit
The unit of measurement for construction of mortared rip rap in silt traps or
sediment basins shall be in cubic meter (m3).
Measurement
The measurement for payment shall be the volume of mortared rip rap constructed
as shown in Drawing and approved by the S.O. and made as follows:-
Pricing Factor
The item for construction of mortared rip rap in silt traps and sediment basins shall
be in accordance with the Preambles to Bill of Quantities:-
(a) Excavation for construction of the mortared rip rap and disposal of surplus
excavated materials;
61
(b) Maintenance of the mortared rip rap to effectively control siltation and
sedimentation.
Unit
The unit of measurement for excavation of earth for silt traps or sediment basin
shall be in cubic meter (m3).
Measurement
The measurement for payment shall be the volume of earth excavated as shown in
Drawing and approved by the S.O. and made as follows:-
Pricing Factor
The item for excavation of earth for silt traps or sediment basin shall be in
accordance with the Preambles to Bill of Quantities:-
(a) Excavation for preparation of the silt trap and disposal of surplus excavated
materials;
Unit
The unit of measurement for maintenance of silt trap or sediment basin shall be
lump sum (sum).
Measurement
The measurement for payment shall be the maintenance of the completed silt trap
or sediment basin and shall be made in each interim payment in proportion of the
total period lapsed to the Contract Period (excluding Defects Liability Period).
Pricing Factor
The item for maintenance of silt trap or sediment basin shall be in accordance with
the Preambles to Bill of Quantities:-
62
(b) Removal of silt and sediment accumulated to approximately 2/3 of filter
height including disposal;
(c) Inspections at regular interval and after heavy rain for damage and other
types of deteriorations and replacements if required
Unit
The unit of measurement for construction of gabion wall shall be in number (nr).
Measurement
The measurement for payment shall be the number of specified size gabion
constructed as shown in Drawing and approved by the S.O. and made as follows:-
Pricing Factor
The item for construction of gabion wall shall be in accordance with the Preambles
to Bill of Quantities:-
(b) Construction of gabion overflow including cage, geotextile and rock fill as
shown in the detailed drawings;
(c) Assembling, tying and staking for the positioning of the gabion units;
(d) Removal and disposal of all rubbish, debris and surplus materials from the
site to the satisfaction of the S.O. including reinstatement of the site.
Unit
Measurement
63
Pricing Factor
The item for maintenance of gabion wall shall be in accordance with the Preambles
to Bill of Quantities:-
(b) Removal of accumulated silt and sediment when full including disposal.
Unit
The unit of measurement for construction of check dam shall be in cubic metre
(m3).
Measurement
The measurement for payment shall be the volume of rock constructed as shown in
the detailed drawings and approved by the S.O. and made as follows:-
Pricing Factor
The item for construction of check dam shall be in accordance with the Preambles
to Bill of Quantities:-
(c) Removal and disposal of check dam, all rubbish, to the satisfaction of the
S.O. including reinstatement of the site.
Unit
The unit of measurement for maintenance of check dam shall be in cubic metre
(m3).
64
Measurement
The measurement for payment shall be the maintenance of the completed check
dam and shall be made in each interim payment in proportion of the total period
lapsed to the Contract Period (excluding Defects Liability Period).
Pricing Factor
The item for maintenance of check dam shall be in accordance with the Preambles
to Bill of Quantities:-
Unit
The unit of measurement for installation of silt curtain shall be in square metre
(m2).
Measurement
The measurement for payment shall be the area of curtain constructed as shown in
the detailed drawings and approved by the S.O. and made as follows:-
Pricing Factor
The item for installation of silt curtain shall be in accordance with the Preambles to
Bill of Quantities:-
(b) Removal including of all rubbish, debris and surplus materials from the site
to the satisfaction of the S.O.
Unit
The unit of measurement for maintenance of silt curtain shall be in square metre
(m2).
65
Measurement
The measurement for payment shall be the maintenance of the completed silt
curtain and shall be made in each interim payment in proportion of the total period
lapsed to the Contract Period (excluding Defects Liability Period).
Pricing Factor
The item for maintenance of silt curtain shall be in accordance with the Preambles
to Bill of Quantities:-
(a) Inspections at regular interval and after heavy rain for rips, tears and other
types of deteriorations and replacements if required.
Unit
The unit of measurement for plastic sheeting to temporarily cover topsoil and
finished slope shall be in square metre (m2).
Measurement
The measurement for payment shall be the area of sheeting laid (laps shall not be
measured for payment) as approved by the S.O. and made as follows:-
Pricing Factor
The item for installation of plastic sheeting shall be in accordance with the
Preambles to Bill of Quantities:-
Unit
The unit of measurement for construction of silt fence shall be in linear metre (m).
66
Measurement
The measurement for payment shall be the length of complete fence constructed as
shown in the detailed drawings and shall be made as follows:-
Pricing Factor
The item for construction of silt fence shall be in accordance with the Preambles to
Bill of Quantities:-
(c) Removal and disposal of all rubbish, debris and surplus materials from the
site;
Unit
The unit of measurement for skid tank bund shall be in Lump sum (sum).
Measurement
Pricing Factor
The item for construction of containment bund shall be in accordance with the
Preambles to Bill of Quantities:-
67
(a) Excavation for preparation of base and disposal of surplus excavated
materials;
(b) Construction of concrete base, brick wall, roof including grease trap with
oil and grease separator overflow complete as shown in the detailed
drawings. The bund wall around the storage tanks should have the capacity
to contain the worst spillage condition (110% of the capacity of the
container).
(c) Regular cleaning and maintenance of grease trap, bund and surrounding
areas to prevent surface corrosion;
(e) Demolition, removal and disposal of bund and all rubbish, debris and
surplus materials from the site to the satisfaction of the S.O. including
reinstatement of the site.
Unit
The unit of measurement for construction of storage shed shall be Lump Sum
(sum).
Measurement
The measurement for payment shall be the shed constructed as shown in Drawing
and approved by the S.O. and made as follows:-
Pricing Factor
The item for construction of containment bund shall be in accordance with the
Preambles to the Bill of Quantities:-
(a) All costs associated with the construction, maintenance and removal of
suitable storage shed for the purpose of housing scheduled wastes.
68
(ii) Scheduled Wastes
Unit
The unit of measurement for disposal of scheduled wastes shall be in Lump Sum
(sum).
Measurement
Pricing Factor
The item for disposal of scheduled waste shall be in accordance with the Preambles
to Bill of Quantities:-
(a) Identifying the category of scheduled waste generated from the project site
as per the 1st Schedule;
Unit
Measurement
The measurement for payment shall be the number of grease trap constructed as
shown in the detailed drawings.
Pricing Factor
The item for construction of grease trap shall be in accordance with the Preambles
to Bill of Quantities:-
69
(a) Construction and maintenance of grease trap at kitchen areas, sharing and
workshop;
(b) Skimming of oil and grease from the trap for disposal as scheduled waste;
5.11.1 Earthworks
(iii) Vertiver Z
Unit
Measurement
The measurement for payment shall be made of the plan area placed to the lines,
level grades and dimensions shown in Drawing or as directed by the S.O.
Pricing Factor
The item for planting and maintenance of vertizer Z shall be in accordance with the
Preambles to Bill of Quantities:-
(c) The details and results of investigations to determine which types of grass
and legumes are compatible with the soil in the areas to be turfed;
(d) The types of grass and legumes (if any) and strains of seeds to be used, and
the function, root and growth characteristics of each type;
(f) The type of mulch to be used and its method and rate of application;
70
(g) The amount of lime or other chemicals (if any) to be applied to improve the
soil before, during and after turfing;
(h) The equipments and methods to be used in preparing and placing the turf
mix and other materials;
(i) The cultivation and after – care of the turfed areas, including rates and
frequencies of watering, fertilising, grass cutting and general maintenance
for 1 year after turfing;
(iv) Creepers
Unit
Measurement
The measurement for payment shall be made of the plan area placed to the lines,
level grades and dimensions shown in Drawing or as directed by the S.O.
Pricing Factor
The item for planting and maintenance of creepers shall be in accordance with the
Preambles to Bill of Quantities:-
(c) The details and results of investigations to determine which types of grass
and legumes are compatible with the soil in the areas to be turfed;
(d) The types of grass and legumes (if any) and strains of seeds to be used, and
the function, root and growth characteristics of each type;
(f) The type of mulch to be used and its method and rate of application;
(g) The amount of lime or other chemicals (if any) to be applied to improve the
soil before, during and after turfing;
(h) The equipments and methods to be used in preparing and placing the turf
mix and other materials;
71
(i) The cultivation and after – care of the turfed areas, including rates and
frequencies of watering, fertilising, grass cutting and general maintenance
for 1 year after turfing;
5.11.2 Drainage
Unit
The unit of measurement for surface drain shall be in linear metre (m).
Measurement
The measurement for payment shall be the length measured along the centre line of
the drain as shown on the drawings or as directed by the S.O between any of the
following:
(a) The external faces of manholes, sump, chambers, and the like;
(b) The external faces of headwalls, inlet and outlet structures and the like;
In the case of cascade drains, the length shall be measured along the centre line of
the projected horizontal plane. No allowance shall be made for laps.
The depth of drains shall be the vertical measurement between the invert and the
lowest of the following:
(c) At slopes, for the lower finished earthwork level at sides prior to top soiling
measured perpendicular to the invert;
72
The average depth to invert shall be calculated by arithmetic means of the depths
taken at intervals of 10 metres along the drains starting from the outfall end. For
terminal lengths of drains less than 10 metres long, the measurement of depths
shall be taken at their ends.
Where the depth of drains are not stated, the Contractor shall establish the depth of
excavation required from the information provided in the Contract and allow their
costs in the rates.
Item Coverage
The item for the drain shall be in accordance with the Preambles to the Bill of
Quantities General Directions and shall include:
(b) Breaking into existing drains, chambers and the like, dealing with existing
flow and making connections unless otherwise measured separately;
(e) Excavation and filling of soft spot with granular backfilling materials and
compaction;
(m) Double handling and disposal of materials to dumping site which is off site
provided by the Contractor;
73
(p) Taking precautions to prevent siltation and desalting prior to handing over;
(r) R.C struts for blocks to drain with brick sides, precast concrete covers
(where specified, mild steel gratings, frame and bedding);
(s) Additional excavation the contractor may require for working space and its
subsequent backfilling; and
(t) Transport, unload, storage and multiple handling of precast concrete drain
sections.
4.10 Sumps
Unit
Measurement
The measurement shall be the number of the completed sump (walls and base) as
shown on the Drawing or as directed by the S.O. The depth shall be the distance
between the top surface or the structure and the invert if the main channel or upper
most surface of the base slab.
Item Coverage
The item of the sump shall be in accordance with the Preambles to the Bill of
Quantities General Directions and shall include:
(a) Excavation in any materials except rock, upholding the sides, keeping
excavation free of water, backfilling with approved materials from any
source and compaction, double handling and disposal of materials;
(d) Excavation and filling of soft spots with granular backfilling materials and
compaction;
74
(i) Steps iron, safety chains, ladders, handholds, anchor irons, bearers support
and the like;
(m) Additional excavation for working space and its subsequent backfilling;
Unit
The unit of measurement for construction and maintenance of retaining wall shall
be in number (nr).
Measurement
The measurement for payment shall be the number of specified size of the
retaining wall as shown in the detailed drawings and approved by the S.O. and
made as follows:-
Pricing Factor
The item for construction and maintenance of retaining wall shall be in accordance
with the Preambles to Bill of Quantities:-
(c) Assembling, tying and staking for the positioning of the gabion units;
(d) Removal and disposal of all rubbish, debris and surplus materials from the
site to the satisfaction of the S.O. including reinstatement of the site.
75
(e) Regular inspections and maintenance throughout the construction period as
directed by the S.O. and make good and replace any damaged components;
(f) Removal of accumulated silt and sediment when full including disposal.
Unit
The unit of measurement to conduct Flora Survey shall be Lump Sum (sum).
Measurement
The measurement for payment shall be the submission and acceptance of the report
by the S.O.
Pricing Factor
The item for conducting flora survey shall be in accordance with the Preambles to
Bill of Quantities:-
(a) The costs of literatures, references and consultation in the production of the
floral survey report.
Unit
Measurement
The measurement for payment shall be upon the completion of the relocation
process and acceptance by the S.O.
Pricing Factor
76
(c) Watering;
(d) Fertiliser required and nurturing until the flora is established at the
temporary nursery and at the final place of relocation.
Unit
The unit of measurement to conduct fauna survey shall be in Lump Sum (sum).
Measurement
The measurement for payment shall be based on surveys and report conducted for
the project.
Pricing Factor
The item to conduct fauna survey shall be in accordance with the Preambles to Bill
of Quantities:-
(a) Fauna survey prior to site clearing, during the middle and end of
construction period;
Unit
Measurement
The measurement for payment shall be based on the preparation and submission of
a Wildlife Management Plan conducted for the project.
Pricing Factor
The item to prepare, submit and to get approval for Wildlife Management Plan
shall be in accordance with the Preambles to Bill of Quantities:-
77
(c) Submission of five (5) hard copies and one (1) digital copy of the approved
and accepted report to the S.O. The copyright of the said documents shall
be transferred and become the absolute property of the Government.
Unit
Measurement
The measurement for payment shall be based on the cost for relocation of wildlife.
Pricing Factor
The cost for relocation of wildlife shall be in accordance with the Preambles to the
Bill of Quantities:-
Unit
The unit of measurement to conduct Coral and Marine Ecosystem survey shall be
Lump Sum (sum).
Measurement
The measurement for payment shall be based on surveys and report conducted for
the project.
Pricing Factor
The item to conduct Coral and Marine Ecosystem survey shall be in accordance
with the Preambles to Bill of Quantities:-
78
(a) Coral and Marine Ecosystem survey prior to site clearing, during and at the
end of the construction period;
Unit
The unit of measurement for preparation and submission of Coral and Marine
Ecosystem Management Plan shall be in Lump Sum (sum).
Measurement
The measurement for payment shall be based on the preparation and submission of
Coral and Marine Ecosystem Management Plan conducted for the project.
Pricing Factor
The item to prepare, submit and to get approval for Coral and Marine Ecosystem
Management Plan shall be in accordance with the Preambles to Bill of Quantities:-
(c) Submission of ten (10) hard copies and one (1) digital copy of the approved
and accepted report to the S.O. The copyright of the said documents shall
be transferred and become the absolute property of the Government.
Unit
The unit of measurement for relocation of Coral and Immotile Marine Organisms
to an approved location shall be provisional sum.
Measurement
The measurement for payment shall be based on the cost for relocation of Coral
and Immotile Marine Organisms.
Pricing Factor
The cost for relocation of Coral and Immotile Marine Organisms shall be in
accordance with the Preambles to the Bill of Quantities:-
79
(a) Coral relocation to an approved location as required by Jabatan Taman
Laut or other relevant authorities;
80
CHAPTER 6
BILL OF QUANTITIES
(Select only applicable items for the project)
81
BILL OF QUANTITIES
BILL NO 10: ENVIRONMENTAL PROTECTION WORKS
Carried to Collection
82
ITEM DESCRIPTION OF WORKS UNIT QTY RATE AMOUNT
NO RM SEN
NON – PHYSICAL WORKS (cont’d)
Carried to Collection
83
ITEM DESCRIPTION OF WORKS UNIT QTY RATE AMOUNT
NO RM SEN
NON – PHYSICAL WORKS (cont’d)
Carried to Collection
84
ITEM DESCRIPTION OF WORKS unit QTY RATE AMOUNT
NO RM SEN
NON – PHYSICAL WORKS (cont’d)
Vibration Measurement
Carried to Collection
85
ITEM DESCRIPTION OF WORKS UNIT QTY RATE AMOUNT
NO RM SEN
NON – PHYSICAL WORKS (cont’d)
Carried to Collection
86
ITEM DESCRIPTION OF WORKS UNIT QTY RATE AMOUNT
NO RM SEN
NON – PHYSICAL WORKS (cont’d)
10.4.4 Training
PHYSICAL WORKS
Carried to Collection
87
ITEM DESCRIPTION OF WORKS UNIT QTY RATE AMOUNT
NO RM SEN
PHYSICAL WORKS (cont’d)
ii)Wash trough
Water Sprinkler
10.5.3
Item for water sprinkler shall be deemed
to include provision and maintenance of
water sprinkler
EROSION CONTROL
10.6
Natural Control
10.6.1
Creepers
I) CentrusemoPubscens
II) FicusPumila m2
III)ParthenocissusHimalayana m2
IV) ……………… (any other suitable m2
species) m2
Carried to Collection
88
ITEM DESCRIPTION OF WORKS UNIT QTY RATE AMOUNT
NO RM SEN
PHYSICAL WORK (cont'd)
89
ITEM DESCRIPTION OF WORKS UNIT QTY RATE AMOUNT
NO RM SEN
PHYSICAL WORK (cont'd)
Maintenance
Silt fence. m
Sand bags nr
Gabion wall nr
Check dam. nr
Silt curtain. m2
Carried to Collection
90
ITEM DESCRIPTION OF WORKS UNIT QTY RATE AMOUNT
NO RM SEN
PHYSICAL WORK (cont'd)
Carried to Collection
91
ITEM DESCRIPTION OF WORKS UNIT QTY RATE AMOUNT
NO RM SEN
PHYSICAL WORK (cont'd)
10.11.1 Earthworks
i) Closed turfing m2
ii) Hydroseeding with fibromat or m2
equivalent
iii) Vertiver Z m2
iv) Creepers m2
10.11.2 Drainage
ii)Drains
Reinforced in situ concrete class 25/20 in nr
drains at any inclination including
excavation, junction, reinforcement,
formworks where necessary, joints,
stepping, backfilling and disposal of
surplus materials and all incidental
necessary as specified and as shown in the
drawings or as directed by the S.O./P.D.
Carried to Collection
92
ITEM DESCRIPTION OF WORKS UNIT QTY RATE AMOUNT
NO RM SEN
PHYSICAL WORK (cont'd)
Carried to Collection
93
ITEM DESCRIPTION OF WORKS UNIT QTY RATE AMOUNT
NO RM SEN
PHYSICAL WORK (cont'd)
Carried to Collection
94
CHAPTER 7
95
CHAPTER 7: BEST MANAGEMENT PRACTICES
SILT FENCE
96
SOIL EROSION AND SEDIMENTATION CONTROL MEASURES
SILT FENCE
97
SOIL EROSION AND SEDIMENTATION CONTROL MEASURES
SILT TRAP
Courtesy of Europasia Engineering Services Sdn Courtesy of Europasia Engineering Services Sdn
Bhd Bhd
serviceServices ices
SEDIMENT BASIN
98
SOIL EROSION AND SEDIMENTATION CONTROL MEASURES
GABION WALL
99
SOIL EROSION AND SEDIMENTATION CONTROL MEASURES
SILT CURTAIN
Courtesy of Wiranda (M) Sdn. Bhd. Courtesy of Wiranda (M) Sdn. Bhd.
100
SOIL EROSION AND SEDIMENTATION CONTROL MEASURES
TURFING/HYDROSEEDING
101
SCHEDULED WASTES MANAGEMENT
Courtesy of Europasia Engineering Services Sdn Bhd Courtesy of Europasia Engineering Services Sdn
Bhd
102
SCHEDULED WASTES MANAGEMENT
103
SCHEDULED WASTES MANAGEMENT
104
FLORA MANAGEMENT
FAUNA MANAGEMENT
105
FAUNA MANAGEMENT
ANIMAL VIADUCT
106
EXAMPLES OF ENVIRONMENTAL MONITORING
107
2. Examples of Air Quality Monitoring
108
CHAPTER 8
109
110
111
Drawing 1: Containment Bund For Skid Tank
112
Drawing 2: Silt Traps
113
Drawing 3: Wash Trough For Construction Site At Rural Area
114
Drawing 4: Wash Trough For Construction Site At Urban Area
115
Drawing 5: Silt Fence
116
Drawing 6: Check Dam
117
Drawing 7: Scheduled Wastes Storage Shed
118
Drawing 8: Disposal of Suitable Cut Materials
119
WATER LEVEL
JOINT TO SUIT
SITE CONDITION
GEOTEXTILE SEPARATOR
CONCRETE ANCHORAGE
EVERY 6000mm CURTAIN
WIRE ROPE
NOTES :
CURTAIN ARRANGEMENT ALL DIMENSION ARE IN MILIMETRE UNLESS OTHERWISE STATED
120
Drawing 10: Unsuitable Materials Disposal Embankment
121
Drawing 11: Sample of ESCP Drawing and EPW Components for Road Project
122
Drawing 12: Sample of ESCP Drawing and EPW Components for Road Project
123
REFERENCES
124
APPENDIX 1
125
SECTION 2 - EARTHWORKS
2.1.1 Description
This work shall consist of clearing, grubbing and stripping topsoil in areas within
the limits of Works designated hereunder and/or shown on the Drawings and/or
directed by the S.O., and of clearing only in other areas designated hereunder
and/or shown on the Drawings and/or directed by the S.O., all as specified herein
and as required by the S.O. The work shall also include the demolition and
disposal of structures in the said areas, except where otherwise provided for in the
Contract, as specified herein and as required by the S.O.
Clearing shall consist of cutting and/or taking down, removal and disposal of
everything above ground level, including objects overhanging the areas to be
cleared such as tree branches, except such trees, vegetation, structures or parts of
structures, and other things which are designated in the Contract to remain, or be
removed by others, or which the S.O. directs are to be left undisturbed. The
materials to be cleared shall include but not necessarily be limited to trees, stumps
(parts above ground), logs, brushwood, undergrowth, long grasses, crops, loose
vegetable matter and structures (except those structures whose removal or
clearance is otherwise provided for in the Contract). Clearing shall also include
leveling of obsolete dikes, terraces, ditches, etc., unless otherwise directed by the
S.O.
2.1.1.2 Grubbing
2.1.1.4 Dumping
All materials resulted from site clearing shall be dumped to the Contractor’s dump
site as approved by the S.O. Method statement on dumping with particular
emphasis on prevention of environmental pollution shall be submitted to the S.O.
for approval.
126
2.1.2 Construction Methods
The areas where the Works are to be carried out shall be cleared as described in
Sub-Section 2.1.1, unless otherwise shown on the Drawings and/or directed by the
S.O.
Clearing shall be carried out to the extents deemed necessary and approved or
directed by the S.O. in areas outside the road reserve where channel excavation or
other work is required.
In areas which are to be cleared only, and in which grubbing and stripping topsoil
are not required, the methods of work shall be such as that will not unduly damage
the surface vegetation and topsoil, and care shall be taken not to disturb the topsoil
and the root systems of grasses and other surface vegetation. No topsoil shall be
removed from such areas, except as directed by the S.O., and any topsoil, grasses
and other surface vegetation otherwise removed or disturbed shall be replaced and
made good at the Contractor's own expense, with the agreement of the S.O.
Unless otherwise shown on the Drawings and/or directed by the S.O., clearing,
grubbing and stripping topsoil shall be carried out in all areas of roadway
excavation and in all areas where embankment is to be constructed, except that
grubbing and stripping topsoil shall not be carried out in those areas where
embankment is to be constructed on ground identified as swamp or soft ground.
Clearing, grubbing and stripping topsoil shall be carried out to the extents deemed
necessary and approved or directed by the S.O. in areas both inside and outside the
road reserve where channel excavation or other work is required.
Except where further excavation is required, holes and cavities in the ground
surface after clearing, grubbing and stripping topsoil shall be filled with materials
similar to the adjacent ground, and such fill shall be compacted to a dry density
similar to that of the surrounding materials, with the agreement of the S.O.
This work shall be considered incidental to the work of clearing, grubbing and
stripping topsoil, and shall not be measured for payment.
2.1.2.3 Topsoil
Topsoil to be stockpiled for the Works shall be sufficiently fertile to promote and
support the growth of vegetation, and shall be taken from such areas where
clearing, grubbing and stripping topsoil is required as approved or directed by the
S.O. Before stockpiling, topsoil shall be separated from objectionable materials as
defined in Sub-Section 2.1.2.6, with the agreement of the S.O. The Contractor shall
127
arrange for stockpile sites either within or outside the road reserve, at his own
expense, and with the agreement of the S.O. or as required by the relevant laws and
regulations.
2.1.2.4 Timber
Saleable timber shall be trimmed and stacked in accordance with the requirements
of the appropriate Government agency, in accessible places within the road reserve
as approved or directed by the S.O.
The Contractor shall have the right to use unsold timber (or saleable timber when
permission is granted in writing by the appropriate Government agency or
authority) for his own purposes in connection with the Contract, always provided
that he shall comply with the requirements of the S.O.
2.1.2.5 Structures
Major structures are those which cannot practicably be cleared by bulldozer and/or
hydraulic excavator, whose demolition requires pneumatic tools, explosives and/or
other specialised equipment. A brief description of each major structure (if any)
and depth to which extent it shall be demolished is given in the Bill of Quantities.
All fences, buildings, structures, and encumbrances of any character within the
limits of the road reserve, except those to be removed by others or designated to
remain, shall be demolished and removed by the Contractor.
128
2.2 EARTHWORKS
2.2.1 Definitions
(b) Subgrade
Subgrade means that part of the embankment or existing ground in cutting which is
immediately below the sub-base or lower sub-base of the road pavement and
shoulders.
Common excavation shall mean excavation in any materials which are not rock or
hard materials as defined in Sub-Sections 2.2.1 (f) and (g).
i) Running silt, peat, logs, stumps, roots, grass and other vegetable matter,
perishable or toxic materials, slurry or mud, or
- Which has a volumetric change greater than 3% in soaked CBR test (for
top 300mm of subgrade).
Materials that are soft or unstable merely because they are too wet or too dry for
effective compaction are not to be classified as unsuitable, unless otherwise
classified by the S.O.
129
(e) Suitable Materials
Suitable materials shall mean those materials other than the unsuitable materials
defined in Sub-Section 2.2.1 (d) above.
This shall mean any hard materials which can be excavated using an excavator
with minimum weight of 44 tonnes and nett horsepower rating of 321 brake
horsepower with production rate not exceeding 50 m3 / hour. The excavator unit is
to be in good condition and operated by experienced personnel.
Hard materials shall exclude individual masses less than 0.5 cubic meters.
Trial excavation shall be carried out using the above equipment to determine hard
materials. The trial excavation shall be carried out on a flat platform in order to
develop the rated horsepower at maximum efficiency.
(g) Rock
Rock shall mean materials found in ledges or masses which can be excavated
using the following equipment with production rate not exceeding 20 m3 / hour: -
and
ii) Ripping Unit: The ripper to be attached to the above mentioned tractor shall
have a minimum penetration force of 120 kN. The ripper shall have a single
shank in good working condition with sharpened cutting point.
130
Boulders or detached pieces shall only be regarded as rock if they
individually exceed 0.5 cubic meter. For the determination of the volume of
individual boulder, diameters of the boulder in three orthogonal directions
shall be taken. The average of the three diameters shall be used to calculate
the volume of boulder. Records of measurements and photographs shall be
taken and kept to support the calculation of the volume of boulder.
The work shall include the excavation of all types of materials, backfilling,
compaction, forming embankments and slopes, etc., as is necessary for the
completion of the works up to the formation levels, in accordance with the lines,
grades, dimensions, shapes and typical cross-sections shown on the Drawings and
to the approval of the S.O.
The Contractor shall provide where necessary temporary water courses, ditches,
drains, pumping or other means of maintaining the earthworks free from water.
Such provision shall include carrying out the work of forming the cuttings and
embankments in such a manner that their surfaces have at all times a sufficient
gradient to enable them to shed water and prevent water ponding.
In pumping water out from excavation and in the lowering of water table the
Contractor shall pay due regard to the stability and settlement of all structures.
Adequate means for trapping silt shall be provided on all temporary drainage
systems. Similar arrangements shall be made for all earthworks including
excavation whether for pile trenches, foundations or cuttings.
Slopes in cutting shall be trimmed mechanically to neat and even surfaces which
shall have gradients not steeper than that shown on the Drawings. Widths of
excavations shall not exceed the dimensions shown on the Drawings by more than
300 mm with encumbrance free to complete the Work, unless otherwise approved
by the S.O.
131
2.2.3.2 Separation and Stockpiling of Suitable Materials
No excavated materials shall be removed from the Site except on the direction or
with the approval of the S.O. Should the Contractor be permitted to remove
suitable materials from the Site to suit his operational procedure, then he shall
make good any consequent deficit of fill materials arising there from, at his own
expense. Unless designated dump sites have been shown on the Drawings, the
Contractor shall dispose of surplus suitable materials at his own dump areas
outside the Site as approved by the S.O. In doing so, the Contractor shall comply
with statutory requirements such as payment of royalties, environmental
protection, etc. Method statement as per Sub-Section 2.1.1.4 shall be submitted to
the S.O. for his agreement prior to dumping.
Unsuitable materials shall be excavated to such depth and over such area as shown
on the drawings and/or directed by the S.O. and be transported and disposed off in
an approved manner. Unless approval of the S.O. to dump and spread the
unsuitable materials within the Site is obtained, the Contractor shall be responsible
for providing his own dump site for such unsuitable materials. The Contractor shall
comply with statutory requirements such as payment of royalties, environmental
protection, etc. Voids created due to removal of unsuitable materials shall be
backfilled with suitable materials compacted to a dry density not less than that of
the surrounding materials or that specified for the respective part of the earthworks
or as directed by the S.O.
132
shall be backfilled with hard clean crushed rock, natural gravel or sand having
grading within the respective limits specified in Table 2.1.
63.0 mm 100
37.5 mm 85 – 100
20.0 mm 0 – 20
10.0 mm 0–5
Sand
10.0 mm 100
5.0 mm 90 – 100
1.18 mm 45 – 80
300 µm 10 – 30
150 µm 2 - 10
The S.O. may instruct the Contractor or the Contractor himself may elect to obtain
materials for the Works by widening cuts. In the latter case, the Contractor shall
first request permission in writing from the S.O.
Widening of cuts shall not be permitted beyond the limits of the road reserve.
Any additional costs and time incurred that resulted from widening cuts shall be
borne by the Contractor.
Where explosives are used, the Contractor shall provide a method statement and
shall comply fully with requirements of this Specification, or any direction, order,
133
requirement or instruction given by the Police Department or any other authority
competent to do so under any written law.
All materials from rock excavations shall be used as far as is practicable in the
Works.
Where the rock is of satisfactory quality, the Contractor may elect to crush and
screen it to produce aggregates required for concrete, roadbase, sub-base, or other
purposes with the prior approval of the S.O. Excavated rock needed for earthwork
construction which the Contractor elects to be used for producing aggregate
materials shall be replaced at the Contractor's own expense by borrowing materials
of satisfactory quality from alternative locations approved by the S.O.
The Contractor may only waste excavated rock with the approval of the S.O.
Excavated rock needed for earthwork construction which the Contractor elects to
waste shall be replaced at the Contractor's own expense by borrowing materials of
satisfactory quality from alternative locations approved by the S.O.
2.2.3.9 Blasting
134
blasts, i.e. exceeding 9 kg of explosive, as in seams, drifts, shafts, pits, or large
holes, is prohibited unless authorized in writing by the S.O. Such authorization
shall not in any way relieve the Contractor of his liabilities under the Conditions of
Contract.
All necessary precautions shall be taken to preserve the materials below and
beyond the lines of all excavations in the soundest possible condition. Delayed
blasting to reduce shock waves shall be used to avoid damage to concrete and other
completed works. As the excavation approaches its final lines, blasting with pre-
splitting technique of approved drill hole spacing shall be carried out to reduce
blast damage and create reasonably even finished surface by means of parallel drill
holes perpendicular to the toe of the excavation and parallel to the finally required
face.
When blasting is carried out close to properties or roads, safety rules complying
with authorities’ requirements shall be strictly adhered to. Where necessary or as
directed by the S.O., heavy mesh blasting mats shall be used to ensure that no
damage is caused to persons or properties on or off site. Special care shall be taken
in wet ground to ensure that individual explosions are reduced to such size as to
preclude damage to any buildings or structures. Plaster shooting will not be
permitted within 400 meters of any buildings or structures. If traffic on any road or
railway has to be interrupted for blasting operations, the Contractor shall obtain
approval of his schedule for such interruption from the appropriate authorities and
shall prove to the S.O. that he has obtained it, prior to the interruption.
When blasting is carried out with close proximity to sensitive structures and
environmental sensitive areas, thresholds and criteria of vibration impact shall be
established for monitoring purpose.
The cut slopes shall be cleared of all rock fragments which move when pried with
a crow-bar. Contractor shall excavate any insecure materials to an approved depth
and build up the resulting spaces with grade 15P / 20 concrete or masonry using
rock similar to the adjoining natural rock so as to ensure a solid face.
2.2.4.1 Materials
135
The fill materials shall be free from roots, grass, other vegetable materials, clay
lump or materials of particles size larger than 150 mm.
Sand shall not be used as fill materials at outer edges of the embankment.
The Contractor shall be responsible for locating borrow pits. Designated borrow
pits shown on the Drawings only indicate to the Contractor potential areas for
borrow. Whether the Contractor obtains materials from the designated or his own
borrow pit, it shall be his responsibility to ascertain the suitability of the pit with
respect to the quantity and quality of the materials, which shall be subjected to the
approval of the S.O. The Contractor shall pay all necessary fees, taxes or royalties
to the appropriate authorities and observe all relevant regulations.
The Contractor shall keep the borrow pits free from water ponding and the
excavation neat and tidy. The contractor shall make sure the side-wall of the
borrow pits is stable, protect the slope surface by turfing and shall carry out other
necessary erosion and environmental protection measures following the agreed
method statement or as instructed by the S.O.
The following tests should be carried out for each 1,500 cubic meters of materials
to be placed or more frequent tests as required by the S.O. : -
- Gradation analysis
Additional test only for materials for lower sub-base and top 300 mm of subgrade:
-
All fill materials shall be deposited in layers and brought up at a uniform rate so
that all parts of the Site reach finished level at the same time. The loose depth for
each layer of fill shall be determined from the trial compaction. Each layer shall
extend over the full width of the fill area and shall be compacted in accordance
with the requirements of Sub-Section 2.2.4.4. Each compacted layer shall be
maintained at all times with a sufficiently even surface of longitudinal and cross
slope in order to drain away the surface water.
136
mm, blended with embankment fill materials and compacted as described in Sub-
Section 2.2.4.4.
2.2.4.4 Compaction
a) General
b) Compaction Trials
The latest MS 1056 Compaction Test (4.5 kg rammer method) shall be used
in determining the moisture versus density relation of soil.
The Contractor shall submit to the S.O. for his agreement the proposed
method of compaction for each main type of materials to be used in the
embankment. This shall include the type of compaction plant for each type
of materials and the number of passes in relation to the loose depth of
materials to achieve desired compaction. The maximum loose thickness for
fill shall generally be limited to 400 mm unless trial compaction shows
compliance with larger loose thickness and with the approval from the S.O.
The Contractor shall carry out field compaction trials, supplemented by any
necessary laboratory investigations, as required by the S.O. This shall be
done by using the procedures proposed by the Contractor for earthworks
and shall demonstrate to the S.O. that all the specified requirements
regarding compaction can be achieved. Compaction trials with the main
types of materials likely to be encountered shall be completed before the
137
works with the corresponding materials will be allowed to commence. Each
trial area shall be not smaller than 8 m x 15 m.
For earthwork compaction of less than 100 cubic meters, trial compaction
can be waived with approval from the S.O., but field density testing as per
Sub-Section 2.2.4.4 (d) is still remained necessary as and when instructed
by the S.O.
c) Degree of Compaction
The whole of the embankment below the top 300 mm of the subgrade shall
be compacted to not less than 90% (for cohesive materials) or 95% (for
cohesion less materials) of the maximum dry density determined in the
latest MS 1056 Compaction Test (4.5 kg - rammer method), unless
otherwise specified in the Drawings.
Field density tests on each layer of compacted earth fill shall be carried out
using the sand replacement method in accordance with the latest MS 1056
or by using other means of testing of comparable accuracy approved by the
S.O.
e) Moisture Control
Each layer of earth fill shall be processed as necessary to bring its moisture
content to a uniform level throughout the materials, suitable for
compaction. The optimum moisture content as determined by the latest MS
1056 Compaction Test (4.5 kg rammer method) shall be used as a guide in
determining the proper range of moisture content, preferably on the wet
side, at which each soil type shall be compacted. Water shall be added in
fine spray for consistent moisture absorption in the fill, or the materials
aerated and dried to adjust the soil to the proper range of moisture content
to obtain the required density. A satisfactory method and sufficient
equipment as approved by the S.O. shall be used for the furnishing and
handling of water.
If the natural water content of suitable materials is too high for the proper
compaction to be carried out, the Contractor can either bring down the
moisture content by aeration or drying or alternatively replace it with
suitable materials of compactable moisture range at his own cost.
f) Air Voids
138
controlled to achieve a compacted fill with allowable air void content not
exceeding 5 %.
For each compacted fill material, the frequency of control tests shall be in
accordance with Table 2.2. The control tests shall be evenly allocated to
each compacted layer of the entire compacted fill. Each control test shall
provide moisture content, dry density and air void content.
For California Bearing Ratio (CBR), the frequency of test shall not be less
than one test per 4000 square meters of compacted subgrade surface
completed or otherwise as directed by the S.O.
If certain test methods are used for the reasons of speed and economy,
calibration between such tests and the master test method as per latest MS
1056 shall be carried out at the interval of every 100 tests subjected to the
S.O’s agreement. The calibration is materials specific and shall be
performed for each materials type. The non-master test method with
variation of more than ± 5 % shall be rejected.
There shall be a transition layer between rock fill and earth fill or the top
300 mm of subgrade of at least 300 mm compacted thickness. This shall
139
consist of uniformly graded crushed rock between 6 mm and 150 mm as
approved by the S.O.
Prior to forming embankment over soft ground, the soil over which fill materials
shall be placed shall be given strength improvement treatment as specified and to
the details as shown in the drawings or as directed or approved by the S.O.
Treatment by means of replacement of unsuitable materials shall be as specified in
Sub-Sections 2.2.3.4 and 2.2.3.5.
The first layer of fill materials shall be deposited over the full width of the
embankment and berms in thicknesses not more than 500 mm or as approved by
the S.O. to sufficiently support earthwork machineries.
If fill materials are required to be placed under standing water, hard clean crushed
rock, natural gravel or sand having grading within the respective limits specified in
Table 2.1 shall be used to backfill the embankment not less than 300 mm above
the standing water to receive compacted suitable fill thereafter.
Where indicated in the Contract or directed by the S.O., the embankment shall be
built to different heights in stages with or without surcharge and with allowance for
consolidation time periods in between stages, all in accordance with the Contract.
Where surcharge is specified, the Contractor shall be responsible for the provision
of surcharge materials and the removal and disposal of excess materials on
completion of consolidation or when directed by the S.O.
140
such damage throughout the whole duration of the Works. Necessary visible
barriers shall be installed around each geotechnical instruments wherever required.
For the measurement of the volume that has settled below the original level of the
foundation of the embankment, the measured settlement of each settlement gauge
shall be used for volume computation following the method shown in the
drawings.
2.2.7 Subgrade
Materials for the top 300 mm of subgrade shall have a minimum California
Bearing Ratio (CBR). Specified shear strength or modulus as shown in the
drawings when compacted to 95 % of the maximum dry density determined in the
MS 1056 Compaction Test (4.5 kg rammer method) under 4 days soaked
condition. In the absence of CBR not mentioned in the drawing, a minimum CBR
of 10 % shall be adopted.
Throughout the top 300 mm of subgrade, the materials shall be compacted to not
less than 95 % (for cohesive materials) or 100 % (for cohesionless materials) of the
maximum dry density determined in the MS 1056 Compaction Test (4.5 kg
rammer method).
In cut area, the top 300 mm of the subgrade shall be scarified and re-compacted to
95 % (for cohesive materials) or 100 % (for cohesionless materials) of the
maximum dry density determined in the MS 1056 Compaction Test (4.5 kg
rammer method). If the S.O. agrees that the subgrade in its natural state possesses a
density exceeding the requirements, then the surface of the subgrade shall be
trimmed and rolled to obtain a smooth finish.
Where the materials in cut area is found to be unsuitable for use in the top 300
mm of subgrade it shall be removed and replaced with suitable materials which
shall be compacted as indicated above.
The subgrade shall be finished in a neat and workmanlike manner, and the widths
of embankments and cuts shall be everywhere at least those specified or shown in
the drawings on both sides of the centreline. The top surface of the subgrade shall
have the required shape, superelevation, levels and grades and shall be finished
everywhere to within plus (+) 10 mm and minus (-) 30 mm of the required level.
i) Where rock surface extends over the whole width of the formation: -
141
The rock surface shall be trimmed to a free draining profile, at or below
formation levels. No high spot shall protrude above the formation levels.
Any voids or cavities more than 0.5 m below the formation level shall be
filled up with approved crusher run, gravels or lean concrete having 7 days
cube strength greater than 7 N/mm2. The rock surface shall then be brought
up to the formation levels with approved crushed rock or gravel, regulated
and blinded.
ii) Where rock outcrop occurs over part of the formation only: -
The rock outcrop shall be cut down to a level not less than 300 mm below
the formation level. The surface shall then be brought up to level with
compacted suitable subgrade materials as indicated above.
2.2.8.1 Topsoil
Topsoil stockpiled for the Works in accordance with Sub-Sections 2.1.1.3 and
2.1.2.3 shall be spread and lightly compacted to an even thickness of 50 mm as
directed by the S.O. in areas to be turfed and/or hydroseeded, or used as directed
by the S.O. for tree planting, landscaping and other purposes.
2.2.8.2 Turfing
Turfing shall be carried out immediately after the exposed slope surface exceeds
100 square meters or within two weeks after cutting or one week during monsoon
season, whichever is earlier on all earth slopes and other areas as shown in the
drawings and/or where directed by the S.O. The type of turf shall be as indicated in
the drawings or other alternative type as approved by the S.O. Turf shall be
delivered to Site within 36 hours after removal from the nursery and when stored,
turf shall be stacked grass to grass to a maximum height of one meter. Turf stored
on Site for a period of more than 48 hours shall not be used without prior approval
of the S.O.
Turf shall be obtained in unbroken sods with a substantial amount of topsoil and
shall be approximately 250 mm x 250 mm in size and 50 mm thick topsoil, from an
approved source, and shall be placed in position as stated above.
Turf sods shall be stacked and watered when they cannot be laid immediately after
cutting.
The surfaces to be turfed shall be trimmed and thoroughly wetted. The turf shall
then be carefully laid to form a complete and uniform cover as shown in the
drawings. Turf laid on slopes steeper than 1 (vertical) to 3 (horizontal) shall be
142
anchored down with bamboo/wooden stakes approximately 200 mm in length
where required. Approved fertiliser shall be applied after placing of turf at suitable
times and at rates of application approved by the S.O.
Where close turfing is specified, the turf shall be laid to a well bonded pattern with
no gaps between turves and lightly tamped. When spot turfing is specified, the turf
shall be laid in alternating and staggered diamond pattern with maximum gaps of
not exceeding 100 mm.
All turf shall be regularly watered and fertilised until the vegetation is satisfactorily
established. Any dead turf shall be replaced with new turf at the Contractor's own
expense.
2.2.8.3 Hydroseeding
Hydroseeding shall be carried out after the proposed slope surface exceeds 1000
square meters or within two weeks after cutting or one week during monsoon
season, whichever is earlier on all slopes and other areas as shown in the drawings
and/or directed by the S.O. Every measure should be taken to ensure that the grass
seed properly germinate at the intended location as shown in the drawings at
Contractor’s expense.
The Contractor shall submit to the S.O. for his consideration and approval, at least
four (4) weeks in advance of the proposed work, full details of his proposed
method of hydroseeding. The information submitted shall include, but not
necessarily be limited to, a full description of the following aspects of the work: -
ii) the details and results of investigations to determine which types of grass
and legumes are compatible with the soil in the areas to be seeded;
iii) the types of grass and legumes (if any) and strains of seeds to be used, and
the function, root and growth characteristics of each type;
vii) the type of mulch to be used and its method and rate of application;
viii) the amount of lime or other chemicals (if any) to be applied to improve the
soil before, during and/or after hydroseeding;
143
ix) the type and amount of binding agent to be applied with the seeds, mulch,
fertiliser, etc., as appropriate;
xi) the equipments and methods to be used in preparing and placing the
hydroseeding mix and other materials;
xii) the cultivation and after-care of the seeded areas, including rates and
frequencies of watering, fertilising, grass cutting and general maintenance
for at least 1 year after hydroseeding;
xiii) the time after hydroseeding required for establishing permanent, dense
growth of grasses, which will require minimal maintenance;
xiv) the temporary erosion protection materials used for protecting the seeds;
All grass shall be regularly watered until the vegetation is satisfactorily established
to the requirements of this specification. Any dead grass shall be replaced at the
Contractor's own expense.
2.2.8.4 Creepers
The Contractor shall submit to the S.O for his consideration and approval, at least
(4) weeks in advance of the proposed work, full details of his proposed method of
planting the creepers. The information submitted shall include, but not limited to, a
full description of the following aspects of the work: -
iii) the types of creepers to be used, and the function, root and growth
characteristics of each type;
iv) the composition of fertilizer to be used at the time of planting the creepers
and its rate of application;
144
vi) the amount of lime or other chemicals (if any) to be applied to improve the
soil before, during and/or after planting;
vii) the cultivation and after care of the areas, including rates and frequencies of
watering, fertilizing and general maintenance for at least 1 year after
planting;
viii) the time after planting required for establishing permanent, dense growth of
creepers, which will require minimal maintenance;
Should the Contractor be unable to turf / hydroseed the exposed slopes within two
weeks after cutting or one week during monsoon season, whichever is earlier,
temporary protection measures such as covering with plastic sheeting or artificial
cover to control erosion shall be taken.
Should the Contractor fail to implement the Works as per above Sub-Sections
2.2.8.1, 2.2.8.2, 2.2.8.3, 2.2.8.4 and 2.2.8.5 the Contractor shall bear the time and
cost of turfing / hydroseeding / planting creepers / temporary slope protection
works carried out by others under the S.O’s directive.
145
APPENDIX 2
146
(Please insert this document into the prebid document)
GOVERNMENT REQUIREMENTS
(NEED STATEMENT)
(TERMS OF REFERENCE)
147
Fill in Name of Project
CONTENTS
GENERAL
148
GENERAL
1.1 The works shall cover planning, design, construction, monitoring, auditing,
reporting, training and maintenance of environmental protection and
enhancement works.
1.2 The Contractor is deemed to have visited the site to familiarize himself with
site and local conditions that pertain to the necessary programme, design and
execution of this work. The Contractor shall take all necessary actions and
precautions during construction and maintenance works so as not to affect the
surrounding environment.
2.1 Within Fourteen (14) days from site possession, the Contractor shall submit
for the P.D approval a detailed EMP based on the Arahan Teknik (Jalan)
16/03 – Pindaan 2015. For projects subjected to EIA requirements, the EMP
shall be submitted within 14 days after the approval of the EIA. No site
clearing and earthworks shall be carried out prior to EMP approval by
relevant parties/authorities.
2.2 The Contractor shall need to include the environmental activities in the work
program to be submitted to the P.D. These activities shall contain all the
necessary actions and interactions in detail.
2.3 The onus of obtaining timely approval from each relevant Local Approving
Authority on environment shall be the Contractor’s responsibility. Untimely
receipt of approvals which may affect the Contractor’s design/construction
program shall not in any way be a basis/cause for consideration of time
extension or variation to the contract.
2.4 The Contractor must take serious and urgent actions on all findings and
recommendations toward protecting the environment as in the report or/and as
instructed by the P.D. Failure to do so, the P.D shall appoint other party and
all costs will be borne by the contractor.
Prior to the execution of the project, the Contractor shall comply with all
related environmental legislations, such as following:
149
(a) Environmental Quality (Amendment) Act 2012
(b) Federal Territory (Planning) Act 1982 (Act 267)
(c) Fishery Act 1985 (Act 317)
(d) Forestry Act 1984 (Act 313)
(e) Land Conservation Act 1960 (Act 385)
(f) Local Government Act 1976 (Act 171)
(g) National Land Code 1965 (Act 56)
(h) Occupational Safety and Health Act 1994 (Act 514)
(i) Solid Waste and Public Cleansing Management Act 2007 (Act 672)
(j) Street, Drainage and Building Act, 1974: Act 133 and Amendment,
1978
(k) Town and Country Planning Act 1976(Act 172)
(l) Wildlife Conservation Act 2010 (Act 716)
(m) Workers Minimum Amenities Act 1990 (Act 446)
Where EIA is required by the said Act, the Contractor shall prepare, submit
and obtain approval from the Department of Environment (DOE). The
Contractor shall incorporate in his Works all the abatement and mitigation
measures for environmental protection and enhancement including
monitoring and auditing.
(i) Limit and control site clearing works to construction areas only.
Existing trees of 80cm diameter at breast height are to be retained as
much as possible and only minimum tree cutting is allowed unless
they impose danger to the public and traffic after completion of the
project.
150
(v) Construct berm/bench drains, interceptor drains and other related
drainage works to slopes which have reached the required formation
levels. Provide temporary cover, for example, polythene or plastic
sheet to the exposed slopes.
(vi) Provide and maintain sediment control measures namely silt fences,
silt traps, sediment basins, gabion walls, check dams, silt curtains, etc.
Upon completion, reinstate site including landscaping where sediment
basins were located and remove other measures which are not
required as directed by the P.D.
(vii) Take necessary precautions to ensure that tyres of all vehicles leaving
the site are free of mud.
(viii) Not to carry out open burning on site unless with written approval
from the DOE.
(x) Supply and lay immediately at least to binder course layer on roads
which have reached the required formation levels including the
required drainage system.
The Contractor shall provide and maintain suitable accommodations for workmen by
carrying out the following:
5.1 All types of waste i.e. Solid waste, Liquid waste, Domestic waste (non-
hazardous) and Scheduled wastes are to be segregated, stored and disposed
in accordance with the Ministry of Health requirements , the DOE
151
requirements and other approving Authority requirements (e.g. the Local
Authority).
5.2 Wastes with sharp edges are to be stored in specially designed containers
and specially manufactured for that purpose.
5.3 Scheduled waste shall be kept in labeled containers/ drums and stored in
storage shed which shall both be maintained and removed in accordance
with the DOE requirements. Scheduled wastes shall be disposed by a
licensed contractor to an approved prescribed premises for treatment.
5.4 The disposal of Liquid or Solid waste and scheduled wastes must be
properly designed and programmed to abide with the Authorities’
Requirements.
Stormwater management design and construction works shall comply with the
requirements of Jabatan Kerja Raya ‘Drainage System’, ‘Erosion and Sedimentation
Control Plan (ESCP), Jabatan Pengairan dan Saliran’s latest edition of ‘Urban
Stormwater Management Manual (MSMA)’ and Local Authority requirement.
Stormwater drainage shall be designed for least maintenance cost, effective initial
cost and serves its function. There shall be no flooding, ponding/silting up and
erosion during construction and after completion of the works.
The Contractor shall submit EMP to the P.D. for endorsement within fourteen (14)
days from the Site Possession in compliance with the Conditions of Contract
and/or in compliance with the requirements of the conditions of approval of the
EIA report by the Department of Environment. The earthwork can only be
commenced after EMP is approved by P.D.
The EMP shall make reference to the following but not limited to:
(a) DOE Format for the Preparation of EMPs.
(b) JKR Environmental Management System (EMS).
(c) The approved EIA report.
(d) EIA Approval Conditions from DOE (if any).
It should be clearly noted the EMP is a document for practical use on site by
nominated personnel and thus should be concise, up to date and site specific.
152
7.1 Erosion and Sediment Control Plan (ESCP)
The approved ESCP shall be submitted to the P.D. and JKR Environment
Branch 30 days prior to commencement of any earthwork activity at project
site.
8.1 Monitoring
The Contractor shall monitor water and air quality, noise and vibration, if
required. All samples taken must be tested by an accredited laboratory. The
Contractor shall produce and submit monthly and quarterly environmental
monitoring reports consisting in-situ and laboratory results, sampling
photographs with weather charts and analyses of the monitoring data in terms
of environmental performance. Reference to the contents of the reports can
be made to the Standard Report Format attached in Appendix 3.
8.2 Auditing
153
(iii) To verify effectiveness of corrective and preventive action
implemented.
(iv) To recommend requirement and improvement of mitigating measures.
(v) To produce and submit a comprehensive environmental auditing
report.
8.3 Reports
8.4 Training
The contractor shall provide training for relevant JKR personnel in the field
of environment. This training shall include Environmental Conservation,
Post EIA and Environmental Monitoring, Environmental Management
System in Project Construction, Safety and Health Courses, and Technical
visits. The training shall be conducted and given by an established
organization with reputable track records in environmental protection
during project management and construction with opportunity for transfer
of technology in enhancing such development. The Contractor’s EO shall
also provide training/awareness briefing for site personnel involved in
works that have impact on the environment.
154
APPENDIX 3
155
TITLE OF DOCUMENT: ENVIRONMENTAL MANAGEMENT PLAN (EMP)
STANDARD REPORT FORMAT FOR JKR PROJECTS
The main objective of the Environmental Management Plan (EMP) is to set out a
comprehensive programme which will form the basis for implementing
environmental mitigation measures, environmental monitoring and environmental
auditing of the construction works by the Contractor as listed below:
(b) To ensure that the Contractor comply with all applicable environmental
standards and guidelines, legislative requirements and other relevant
conditions related to the environment;
The following details are needed to help commence the preparation of the EMP:-
156
4.0 Information on EMP
The executive summary must manage to summarise the key elements of the
project:-
157
(iv) Project Description
Concept
Components
Activities
Scheduling
This chapter has to outline the need for the EMP and has to detail the following:-
Chapter 3 has to state in the Policy in relation to the Environment of the Project
Proponent and elaborate on the objectives of the EMP:-
Chapter 4 has to detail the aspects related to the Environmental Management Unit
(EMU) and the allocations provided for Environmental Protection:-
158
(ii) Proposed monitoring programme
This chapter has to detail the auditing programme for the project:-
This chapter has to detail the identified significant aspects, impacts and their
corresponding site specific mitigation measures:-
159
(xvii) Site Abandonment/Closing Plan
This chapter has to detail the analysis used to determine performance of the
environmental Protection Measures and the recommendations for improvement:-
17.0 Appendices
160
18.0 Figures
161
REPORT: ENVIRONMENTAL MONITORINGREPORT (EMR)
TABLE OF CONTENTS
EXECUTIVE SUMMARY
1.0 INTRODUCTION
162
6.0 NOISE QUALITY MONITORING
8.0 CONCLUSION
163
REPORT: ENVIRONMENTAL AUDIT REPORT (EAR)
TABLE OF CONTENTS
EXECUTIVE SUMMARY
1.0 INTRODUCTION
3.0 RECOMMENDATIONS
4.0 CONCLUSION
APPENDIX:
PROJECT PHOTOGRAPHS
164
REPORT: ENVIRONMENTAL CLOSURE AUDIT REPORT (ECAR)
TABLE OF CONTENTS
EXECUTIVE SUMMARY
1.0 INTRODUCTION
APPENDIX:
PROJECT PHOTOGRAPHS
165
APPENDIX 4
166
National Water Quality Standards
Classes
Parameters Unit
I II II II I V
Ammoniac A B I V
mg/l 0.1 0.3 0.3 0.9 2.7 >2.7
al
Nitroge
BOD mg/l 1.0 3.0 3.0 6.0 12.0 >12.0
CODn mg/l 10.0 25.0 25.0 50.0 100.0 >100.0
DO mg/l 7.0 5.0-7.0 5.0-7.0 3.0-5.0 <3. <1.
pH - 6.5-8.5 6.0-9.0 6.0-9.0 5.0-9.0 0
5.0-9.0 0-
Color TCU 15.0 150.0 150.0 - - -
Electrica umho
1,000.0 1,000.0 - - 6,000.0 -
l s/
Conductivit
Floatables c- n n n - - -
y*
Odou m - n n n - - -
r
Salinit % 0.5 1.0 - - 2.0 -
y
Taste - n n n - - -
Total Dissolved mg/l 500.0 1,000.0 - - 4,000.0 -
Solids
Total mg/l 25.0 50.0 50.0 150.0 300.0 300.0
Suspended
Solid Normal Normal
Temperature ° - - - -
+2°C +2°C
C
Turbidity NTU 5.0 50.0 50.0 - - -
counts 5,000.0 5,000.0
FaecalColiform 10.0 100.0 400.0 -
/ (20,000.0 (20,000.0
**
100m
counts )a50,000.0 )a50,000.0 >50,000.
Total Coliform L 100.0 5,000.0 5,000.0
/
0
100m 1.0
Iron Lmg/l 1.0 1.0 1.0 (Leaf)
Natura 5.0
Manganese mg/l 0.1 0.1 0.1 (Other
0.2 Levels
l above
Nitrat mg/l levelso 7.0 7.0 - s)
5.0 IV
e
Phosphorous mg/l r 0.2 0.2 0.1 -
Oil &Grease mg/l absent 0.04; N 0.04; N N -
Notes : No visible floatable materials or debris or No objectionable odour,or No objectionable taste.
* : Related parameters,only one recommended for use
** : Geometric mean.
a : maximum not to be exceeded.
N : Free from visiblesheen,discolouration and deposits.
ClassUses
ClassI : Conservation of natural environment.
Water Supply1 –practical lynotreatment necessary.
Fishery1 –very sensitive aquatic species.
ClassIIA : WaterSupplyII –conventional treatment required.
FisheryII-sensitive aquatic species
ClassIIB : Recreationalusewithbodycontact.
ClassIII : WaterSupplyIII –extensivetreatmentrequired.FisheryIII –
common,ofeconomicvalueandtolerantspecies;livestockdrinking.
ClassIV : Irrigation.ClassV : None of the above.
167
APPENDIX 5
168
Malaysia Marine Water Quality Criteria And Standard
Cyanide (µg/L) 2 7 20 7
Ammonia 35 70 320 70
(unionized)
(µg/L)
Nitrite(NO2) 10 55 1,000 55
(µg/L)
Nitrate (NO3) 10 60 1,000 60
(µg/L)
Phosphate 5 75 670 75
(µg/L)
Phenol (µg/L) 1 10 100 10
Tributyltin(TBT
)(µg/L) 0.001 0.01 0.05 0.01
169
Faecal coliform 70 faecal 100 faecal 200 faecal 100 faecal
(Human health coliform coliform 100mL-1 coliform coliform 100mL-1
protection for 100mL-1 & (70 faecal 100mL-1 & (70 faecal
seafood coliform 100mL- coliform 100mL-
1) 1)
consumption)-
most Probable
Number(MPN)
Polycyclic
Aromatic
Hydrocarbon 100 200 1000 1000
( PAHs)ng/g
*MWQCS in parentheses are for coastal and marine water areas where seafood for human
consumption is applicable
170