Professional Documents
Culture Documents
0.1 Pre Test Question Paper Core Tools
0.1 Pre Test Question Paper Core Tools
1
a)
b)
c)
d)
e)
2
a)
b)
c)
d)
3
a)
b)
c)
d)
4
a)
b)
5
a)
b)
c)
d)
e)
6
a)
b)
c)
d)
7
a)
b)
c)
d)
8
a)
b)
c)
d)
9
a)
b)
c)
d)
10
a)
b)
c)
d
11
a)
b)
c)
d)
12
a)
b)
c)
d)
13
a)
b)
c)
d)
e)
14
a)
b)
c)
d)
15
a)
b)
c)
16
a)
b)
c)
d)
17
a)
b)
18
a)
b)
c)
d)
19
a)
b)
20
a)
b)
c)
d)
21
a)
b)
c)
d)
22
a)
b)
c)
d)
23
a)
b)
c)
d)
24
a)
b)
c)
d)
25
a)
b)
c)
d)
e)
Essentials of IATF core tools
Pre Test Question Paper
1. All questions are compulsory Name:
2. No negative markings Organization:
3. Only one answer for each question (more than 1 answer will not be considered)
Which is the default Submission level for PPAP if not asked by the customer?
Level 2
Level 5
Level 4
Level 3
Control charts were first used by
Deming
Juran
Ishikawa
Shewart
Under which of the below circumstances it is not required to notify for PPAP ?
New of modified tools
Operator skill level change
Change of Suppliers for chile parts
All the above
Most effective way to know whether control charts are effectively implemented in an organization is
Get report of Cp and Cpk from supplier
Walk into the shop floor and see whether control charts are available & sincerely followed
Ask supplier to give data and check whether data is stable & capable
None of the above
If the Control limits are same as the tolerance for any dimension, then the value of Cpk will be:
2
1
0.5
3
The major difference between process capability indices (Cpk) and process
performance indices (Ppk) is:
The specification spread must be known for process capability indices
How the standard deviation term is determined for the two indices
The target value must be known for process performance indices
The required failure rate limit must be known for process capability indices
If 100 parts are measured, data is normal, average is 50 and sigma is 0.5, then how much % of parts will be
above 51
(select the nearest answer)
1%
2.30%
5%
0.27%
0.135%
Cpk of a process is equal to 0.9 What should be done to the process?
Reduce the spread
Change the mean
Both
Cant say without Cp value
Process potential (Cp) is always equal to greater than process capability (Cpk)?
1
0
Cant say without data
X bar chart represents time to time variation & R chart represents part to part variation.
1
0
Before we calculate the capability or performance of a process we should ensure stability of the process.
1
0
Which of the below control chart is more suitable to monitor the no of defects in final inspection
IMR chart
P chart
NP chart
Xbar - R chart
Which of the below chart is more suitable for monitoring Gear profile measured on CMM
IMR chart
P chart
NP chart
Xbar - R chart
A Measuring Instrument showing different values on the same part, same characteristics by same
inspecter. Then it can be said there is ?
Equipment variation is high
Appraiser variation is High
Reproducability of equipment is very high
Bias of the equipment is high
For visual inspection (Attribute MSA) which of the below criteria is correct
Effectiveness > 0.9, Probability of false alarm < 0.05 & Probability of Miss rate < 0.02
Effectiveness > 0.9, Probability of false alarm < 0.02 & Probability of Miss rate < 0.05
Effectiveness < 0.8, Probability of false alarm < 0.05 & Probability of Miss rate < 0.02
Effectiveness > 0.9, Probability of false alarm < 0.02 & Probability of Miss rate < 0.02
1
a)
b)
c)
d)
e)
2
a)
b)
c)
d)
3
a)
b)
c)
d)
4
a)
b)
5
a)
b)
c)
d)
e)
6
a)
b)
c)
d)
7
a)
b)
c)
d)
8
a)
b)
c)
d)
9
a)
b)
c)
d)
10
a)
b)
c)
d
11
a)
b)
c)
d)
12
a)
b)
c)
d)
13
a)
b)
c)
d)
e)
14
a)
b)
c)
d)
15
a)
b)
c)
16
a)
b)
c)
d)
17
a)
b)
18
a)
b)
c)
d)
19
a)
b)
20
a)
b)
c)
d)
21
a)
b)
c)
d)
22
a)
b)
c)
d)
23
a)
b)
c)
d)
24
a)
b)
c)
d)
25
a)
b)
c)
d)
e)
Core Tools
Pre Test Question Paper 14.02.2018
1. All questions are compulsory Name:
2. No negative markings Organization:
3. Only one answer for each question (more than 1 answer will not be considered)
Which is the default Submission level for PPAP if not asked by the customer?
Level 2
Level 5
Level 4
Level 3
Control charts were first used by
Deming
Juran
Ishikawa
Shewart
Under which of the below circumstances it is not required to notify for PPAP ?
New of modified tools
Operator skill level change
Change of Suppliers for chile parts
All the above
Most effective way to know whether control charts are effectively implemented in an organization is
Get report of Cp and Cpk from supplier
Walk into the shop floor and see whether control charts are available & sincerely followed
Ask supplier to give data and check whether data is stable & capable
None of the above
If the Control limits are same as the tolerance for any dimension, then the value of Cpk will be:
2
1
0.5
3
The major difference between process capability indices (Cpk) and process
performance indices (Ppk) is:
The specification spread must be known for process capability indices
How the standard deviation term is determined for the two indices
The target value must be known for process performance indices
The required failure rate limit must be known for process capability indices
If 100 parts are measured, data is normal, average is 50 and sigma is 0.5, then how much % of parts will be
above 51
(select the nearest answer)
1%
2.30%
5%
0.27%
0.135%
Cpk of a process is equal to 0.9 What should be done to the process?
Reduce the spread
Change the mean
Both
Cant say without Cp value
Process potential (Cp) is always equal to greater than process capability (Cpk)?
1
0
Cant say without data
X bar chart represents time to time variation & R chart represents part to part variation.
1
0
Before we calculate the capability or performance of a process we should ensure stability of the process.
1
0
Which of the below control chart is more suitable to monitor the no of defects in final inspection
IMR chart
P chart
NP chart
Xbar - R chart
Which of the below chart is more suitable for monitoring Gear profile measured on CMM
IMR chart
P chart
NP chart
Xbar - R chart
A Measuring Instrument showing different values on the same part, same characteristics by same
inspecter. Then it can be said there is ?
Equipment variation is high
Appraiser variation is High
Reproducability of equipment is very high
Bias of the equipment is high
For visual inspection (Attribute MSA) which of the below criteria is correct
Effectiveness > 0.9, Probability of false alarm < 0.05 & Probability of Miss rate < 0.02
Effectiveness > 0.9, Probability of false alarm < 0.02 & Probability of Miss rate < 0.05
Effectiveness < 0.8, Probability of false alarm < 0.05 & Probability of Miss rate < 0.02
Effectiveness > 0.9, Probability of false alarm < 0.02 & Probability of Miss rate < 0.02