y 16, '16 Jun 6, '16 Jun 27, '16 Jul 18, '16 Aug 8, '16 Aug 29, '16 Sep 19, '16
Mode T W T F S S M T W T F S S M T W T
1 Skidanje sloja humusa 1 day 5/31/16 6/1/16
2 Izrada nanosne skele 1 day 6/1/16 6/2/16
3 Kopanje jama za temelje 2 days 6/2/16 6/4/16
samce
4 postavljanje armature za 2 days 6/3/16 6/7/16
temeljne stope
5 spravljanje I ugradnje 1 day 6/7/16 6/8/16
betona
6 postavljanje oplate za 4 days 6/10/16 6/15/16
temeljne grede
7 postavljanje armature za 8 days 6/13/16 6/24/16
temeljne grede
8 spravljanje I ugradnje 1 day 6/24/16 6/25/16
betona za temeljne grede
Project: Project1 Split External Tasks Inactive Summary Manual Summary Progress
Date: 5/31/16 Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only
Page 1
Sep 19, '16 Oct 10, '16 Oct 31, '16 Nov 21, '16 Dec 12, '16 Jan 2, '17 Jan 23, '17 Feb 13, '17 Mar 6, '17 Mar 27, '17 Apr 17, '17
T F S S M T W T F S S M T W T F S S M T W T F S S M T
Project: Project1 Split External Tasks Inactive Summary Manual Summary Progress
Date: 5/31/16 Milestone External Milestone Manual Task Start-only
Summary Inactive Task Duration-only Finish-only
Page 2