Professional Documents
Culture Documents
Solar Focus Interconnection Process Improvement
Solar Focus Interconnection Process Improvement
D.C.
20 installers
13 states and Washington DC
30,088 applications in 2013 (33 utility territories)
57,482 applications in 2014 (34 utility territories)
120
100
80
# of Days
Median
Lowest Reported
60
Highest Reported
40
20
0
2013 2014
55
45
35
Number of Days
25
15
-5
Average # of Days
0 5 10 15 20
CL&P (CT)
NYSEG (NY)
PG&E (CA)
BGE (MD)
MECO (HI)
PacifiCorp (UT)
ORU (NY)
2013
PSE&G (NJ)
SDG&E (CA)
2014
SRP (AZ)
TEP (AZ)
NV Power (NV)
SCE (CA)
MID (CA)
NSTAR (MA)
PGE (OR)
Con Ed (NY)
SMUD (CA)
ACE (NJ)
Delmarva (DE)
HECO (HI)
LIPA (NY)
HELCO (HI)
APS (AZ)
PacifiCorp (OR)
WMECO (MA)
Xcel (CO)
LADWP (CA)
Pepco (DC)
Pepco (MD)
• Paper process it
outdated
D.C.
• Survey data:
• 50 utility service territories with the most net-
metered residential customers
• 2013 and 2014
• # of applications submitted
• # average PTO waiting period
• # of applications denied due to grid reliability
concerns
PHI
Applications have nearly
doubled in 2015 compared to
2014
• We expect them to double again
in 2016
– End of federal tax credit
– Aggregated and community net
metering programs
– Leasing programs and grants
– Association forecasts
o MDV-SEIA, SEPA
Call volumes substantial but
leveling off
• 1,625 in October, down from
1,915 in September and up from
average of 1,436 / month
January-June
As of September 30, 2015
• Inquiries shifting from
application status to billing
questions
November 17, 2015 3
Regulatory Requirements – Guidelines to all PHI Processes
Interconnection requirements differ substantially state to state,
region to region
Regulatory requirements PHI follows are similar but different
state to state
• DC – Title 15, Chapter 40 of the D.C. Code of Municipal Regulations for
Small Generator Interconnection Rules (SGIR) and the D.C. Customer Net
Energy Metering Contract (NEM Contract) define Pepco’s application
process
• MD – Code of Maryland Regulations (COMAR) 20.50.09 for Small
Generation Interconnection Standards (SGIS) defines the application
process Pepco follows. COMAR 20.50.10 for Net Metering Authority defines
the qualifications for net energy metering in Maryland
• DE – Title 26 of the Delaware Code, Chapter 10 and corresponding
regulations adopted by the Delaware Public Service Commission define the
net energy metering and interconnection application processes Delmarva
Power follows
• NJ – New Jersey Administrative Code Title 14, Chapter 8, Subchapter 4
defines net energy metering and Subchapter 5 defines the interconnection
application processes Atlantic City Electric follows
All PHI processes follow these regulatory guidelines very closely
Responsible
Steps Actions To Take
Party
1. Research • Research the various types of renewable energy systems available and decide which system • Customer
best fits consumption needs. Renewable energy-generating systems can be sized up to 200%
in Maryland, up to 110% in Delaware, and up to 100% in New Jersey and the District of
Columbia
• Customers should understand their electrical load and energy consumption
2. Select • Interview and select a licensed and reputable installing contractor • Customer
3. Apply • The customer should understand the documentation needed with the interconnection • Customer
agreement (e.g., rebate forms, permit applications, inspection forms)
• The customer applies and submits Part I of our interconnection application and agreement Apply for
along with the application fee and supporting documentation Building Permit
• Applications without supporting documentation will be delayed. The customer can resubmit a
corrected application and documentation
4. Approval • The customer waits for our Approval to Install before installing any renewable generator • Customer
equipment • PHI Utility
• We will provide the customer a written screening result or Approval to Install
5. Install • Begin constructing and installing the renewable generator facility • Customer
6. Inspect • After installation, submit Part II of our interconnection agreement, including a copy of the • Customer
certificate of completion and the inspection certificate
• We will review the customer’s documentation to verify the interconnection application meets • PHI Utility
regulatory requirements
7. Meter • We will install the net-capable meter • PHI Utility
8. Authorization • We will send the customer an Authorization to Operate letter • PHI Utility
9. Operate • Receipt of the authorization letter means the customer can operate the renewable system • Customer
Responsible
Steps Actions To Take
Party
1. Research • Research the various types of renewable energy systems available and decide which system best fits • Customer
consumption needs. Renewable energy-generating systems can be sized up to 200% in Maryland, up
to 110% in Delaware, and up to 100% in New Jersey and the District of Columbia
Level 1 Applications • Customers should understand their electrical load and energy consumption
Complete application 2. Select • Interview and select a licensed and reputable installing contractor • Customer
Received to
Acknowledgement 3. Apply • The customer should understand the documentation needed with the interconnection agreement (e.g., • Customer
(3-10 days) rebate forms, permit applications, inspection forms)
• The customer applies and submits Part I of our interconnection application and agreement along with
Apply for
the application fee and supporting documentation
Engineering Review to Building Permit
• Applications without supporting documentation will be delayed. The customer can resubmit a corrected
Approval to Install
application and documentation
(10-15 days)
4. Approval • The customer waits for our Approval to Install before installing any renewable generator equipment • Customer
• We will provide the customer a written screening result or Approval to Install • PHI Utility
Customer Installs
and has Inspected 5. Install • Begin constructing and installing the renewable generator facility • Customer
(avg 40 days)
6. Inspect • After installation, submit Part II of our interconnection agreement, including a copy of the certificate of • Customer
completion and the inspection certificate
• We will review the customer’s documentation to verify the interconnection application meets regulatory • PHI Utility
Application Part II requirements
Received,
Meter Exchange, 7. Meter • We will install the net-capable meter • PHI Utility
Authorization to
Operate 8. Authorization • We will send the customer an Authorization to Operate letter • PHI Utility
(20 days)
9. Operate • Receipt of the authorization letter means the customer can operate the renewable system • Customer
Atlantic City
Pepco Delmarva Power
Electric
DC MD DE MD NJ
2011 81% 183 84% 329 54% 183 61% 107 29% 1,673
2012 100% 367 99% 511 97% 227 99% 160 88% 1,314
2013 99% 418 95% 814 99% 385 94% 188 97% 1,629
2014 89% 534 92% 2,143 97% 783 97% 425 97% 2,737
2015
97% 1,110 97% 4,900 80% 1,280 84% 940 81% 6,270
Forecast
Request brochures
from
NEMEducation@
pepcoholdings.com
www.pepco.com/gpc
gpc-south@pepco.com
(202) 872-3419
www.delmarva.com/gpc
www.atlanticcityelectric.com/gpc
gpc-north@pepcoholdings.com
(866) 634-5571
2
MD Installs (MW)
140
120
Maryland
Total MW DC Installed
80
Maryland is experiencing exponential
growth in its solar deployment,
particularly in the residential sector
60
• Summer 2012: 1.1 MW / month
20
0
1/1/2008 1/1/2009 1/1/2010 1/1/2011 1/1/2012 1/1/2013 1/1/2014 1/1/2015
All data from PJM-GATS, retrieved 11/16/15
< 20 kW 20 kW - 2 MW > 2 MW
3
MD Installs (Systems)
18,000
16,000
14,000
Rapid Growth in
Maryland
12,000
2,000
0
1/1/2008 1/1/2009 1/1/2010 1/1/2011 1/1/2012 1/1/2013 1/1/2014 1/1/2015
< 20 kW 20 kW - 2 MW > 2 MW
4
DC Installs (MW)
9
Steady Growth
in DC
6
Total MW DC Installed
5
Consistent growth in both residential
and commercial sectors, with growth
continuing at a linear pace 4
0
1/1/2008 1/1/2009 1/1/2010 1/1/2011 1/1/2012 1/1/2013 1/1/2014 1/1/2015
< 20 kW 20 kW - 2 MW
5
DC Installs (Systems)
1,800
1,600
1,400
in DC
600
200
0
1/1/2008 1/1/2009 1/1/2010 1/1/2011 1/1/2012 1/1/2013 1/1/2014 1/1/2015
< 20 kW 20 kW - 2 MW
6
NJ Installs (MW)
800
700
NJ Scale from
600
Commercial 500
Total MW DC Installed
NJ total installed capacity is much
larger than MD (1,400 MW vs 350 400
0
1/1/2008 1/1/2009 1/1/2010 1/1/2011 1/1/2012 1/1/2013 1/1/2014 1/1/2015
< 20 kW 20 kW - 2 MW > 2 MW
7
NJ Installs (Systems)
35,000
30,000
Commercial
< 20 kW 20 kW - 2 MW > 2 MW
8
MD vs. NJ Residential Installs
1200
1000
800
MD vs. NJ
200
0
1/1/2011 1/1/2012 1/1/2013 1/1/2014 1/1/2015
NJ Res MD Res