Professional Documents
Culture Documents
015-Ih-1001-Pipeline Construction PDF
015-Ih-1001-Pipeline Construction PDF
&
Engineering Group
Specification Number
Pipeline Construction
Specification Number Rev Date Sheet
Engihedng Grwp
015-IH-1001 1 9-7-94 2 of 28
CONTENTS
@ KoC E n g M n g Grwp
SpecJfication 015-IH-1001 1 9-7-94 3 of 28
1.0 SCOPE
1.I This document covers the minimum requirements the Contractor shall
consider in supply of materials and the construction of the pipelines and
ancillary facilities for installation at the Facility in Kuwait.
1.2 The construction of the pipelines shall fully comply with all relevant
contractual requirements specified in the Scope of Work and the
Technical Specification of the Contract.
2.1 The construction of pipelines and ancillary shall conform, except where
specified otherwise, with the current issue and amendments of the
following prevailing on the effective date of the Contract:
IInternational Standards
2. I.
Buttwelding Ends
2.5 Where conflicts exist between this specification and other Drawings,
standards, codes or specifications, the most stringent shall be applied.
3.1 The construction of the pipelines and ancillary shall be suitable for
continuous operations at the desert location under high ambient
temperatures and humidity. The atmosphere at the Facility is generally
dusty and corrosive and may contain traces of hydrogen sulphide.
3.2 The installed pipelines shall in all respects be suitable for continuous
operation in service conditions stated in the Engineering Group
Specification entitled "Basic Design Criteria" (Number 015-AH-1001).
The Contractor shall establish a chainage marking survey for the Crude
Oil Transit System, low-pressure (LP) gas lines, high-pressure (HP) gas
lines and Fuel Gas System.
The survey shall locate all buried services, which shall then be shown on
the alignment sheets. This survey shall also establish the depth of the
services.
5.1 The Contractor shall not start any construction work on the ROW until
control staking has been approved by the Company.
5.2 The Contractor shall clear and level the construction ROW to the degree
required to support all work scope activities.
6.1 The Contractor shall perform such grading of the ROW as is required to
properly perform the pipeline construction, and to provide access to the
pipeline during the construction period.
6.2 The Contractor shall grade the ROW to eliminate sharp high points,
minimise bending and maximise laying within the limits permissible for
elastic bending. In rocky sections, the Contractor shall excavate rock
or other material that cannot be graded with normal grading equipment
in order to build an adequate working space along the pipeline route
Specification Number Rev Date Sheet
01 5-IH-1001 1 9-7-94 7 of 28
The Contractor shall perform all necessary grading at road crossings and
at any other location required to permit the passage of construction
equipment.
Great care shall be taken of any cultivated ground. For these areas the
topsoil shall be carefully removed and protected against erosion and
contamination by blown sand and kept for reinstatement by the
Contractor after the pipeline is constructed.
6.12 When any existing line is located and/or when the berm is removed from
any existing line, the Contractor shall clearly indicate its buried route by
pegs and warning signs.
6.13 The Contractor shall protect the existing line from vehicle wheel loads
by suitable barriers or the placement of protective slabs. Berms of
existing lines so removed shall be replaced or left at the discretion of the
Company.
The Contractor shall unload, stockpile, load, haul and string all materials
and shall make all the necessary arrangements and agreements.
The Contractor shall use a Pipe Traceability System that shall enable
control and tracing of all pipe from source through to its as-built
position.
Pipe stringing in rock ditch areas shall not be permitted until ditching is
complete. Pipe ends may be placed on wooden skids to prevent ground
contact during stringing.
The Contractor shall be fully responsible for providing and paying for all
storage areas, except as may be made available by the Company.
8.1 The Contractor shall stake the centre line of the pipeline and flag the
limits of the working area of the ROW in accordance with Construction
Drawings approved by the Company. The Contractor shall dig the
pipeline trench on the staked centre line of the pipeline.
8.2 The Contractor shall employ equipment and methods to keep the ditch
to the line established regardless of the type of soil and rock
encountered and regardless of the depth of excavation necessary.
8.3 The Contractor shall furnish all equipment, materials and supplies
necessary for the completion and maintenance of the ditch, including
shoring, sheet piling, dewatering and any other incidentals for the
completion of the work.
Specification Number Rev Date Sheet
QKK-
E n g l m Gnwp
~
0 1 5-IH-1001 1 9-7-94 10 of 28
The Contractor shall dig the pipeline trenches in accordance with the
approved Construction Drawings.
Minimum depth of cover shall be measured from the top of the pipe to
the level of the graded surface of the soil.
8.18 Prior to exposure of any existing pipelines, the Contractor shall erect a
suitable, substantial barrier to prevent any damage to those pipelines,
particularly where removal of the berm for trenching operations opens
up a gap which could be used by vehicles as an unauthorised crossing.
8.19 Trenches shall be approximately 4.5 m from the agreed-to edge of the
ROW.
9.0 CROSSINGS
Where the pipeline crosses roads, other pipelines, sewers, water lines,
cables, conduits or other underground structures of any kind, the
Contractor shall dig and grade the trench to a depth and in the manner
specified on the Project Drawings.
The Contractor shall provide adequate supports for all existing services
during the construction operations including concrete slabslbeams as
required by the Company.
01 5-IH-1001 1 9-7-94 12 of 28
The Contractor shall place danger signs visible during dry light and red
lanterns of flame visible during night 100 m from excavated road
crossing in both direction of traffic. Danger signs are to be in English
and Arabic and must be recognisable at 50 m.
Breaks in the berm for a vehicle crossing at every kilometre post shall be
constructed as a track crossing. This provision does not apply to
pipelines in existing corridors where no corresponding crossing is
provided over the existing pipelines. In existing corridors, the Company
shall instruct the Contractor as to the correct location for such
crossings.
The sections of pipeline route crossing overhead power line way leaves
shall be buried without bunds and constructed as a track crossing.
10.1 The Contractor shall make all necessary pipe bends reqjuired in the
. . .
The Contractor shall bend the pipe t o conform to the grade and
horizontal alignment of the trench. Field bends shall be required at all
points where the change in grade or horizontal alignment is such that
the pipe will not conform to such changes by elastic bending.
The Contractor shall develop a procedure for field bending for Company
approval.
In no case shall the radius of a field bend be less than 40 times the
outside diameter (OD) of the pipe being bent.
10.9.2 For bending the longitudinal weld of the pipe shall be on the
neutral axis of the pipe. Bending of spirally welded pipe shall
not be made.
10.12 The Contractor shall cut out and remove any bends which do not meet
the specification and replace them at its own cost.
The Contractor shall align and weld together the joints of pipe into a
continuous pipeline, and all welds in the pipeline made by the Contractor
shall be of strength equal to that of the pipe and of the quality set forth
in this specification. Permitted weld hardness and other parameters
shall be in accordance with the applicable weld qualification procedure.
All welding procedures shall conform to the Engineering Group
Specification entitled "Field Welding" (Number 01 5-IH-1008) and API
1 104 (latest edition).
Each pipe joint shall be thoroughly swabbed to remove all dirt and
foreign matter from the inside of the pipe before the joints are lined up
and welded. The swabbing operation shall not be carried out on more
than six pipe joints ahead of the stringer bead welders.
The open end of the line shall be securely closed at the end of each
day's work to prevent entrance of small animals or the introduction of
foreign matter of any nature and shall not be reopened until work is
resumed. The Contractor shall remove all obstructions in the line after
the completion thereof.
The Contractor shall use approved line-up clamps and shall ensure during
the line-up operation that longitudinal or spiral welds are offset at 90°
or 10 in., whichever is larger. Internal line-up clamps shall be used for
16-in. and larger size pipes.
11.8 All welding procedures, welder and NDT personnel shall be qualified as
specified in the Engineering Group Specification entitled "Field Welding"
(Number 01 5-IH-1008).
12.2 The Contractor shall furnish all materials, equipment, labour and
supervision and shall be responsible for cleaning, priming and coating the
line pipe, field joints, valves, fittings, connections and appurtenances,
together with recleaning, repriming and recoating to meet the
specification.
12.3 The coating of pipeline field joints, tie-ins and fittings shall be made in
accordance with the Engineering Group Specification entitled "Pipeline
Field Joint Coating" (Number 01 5-IH-1012).
12.5 The Contractor shall make a detailed inspection of the coating for
holidays and imperfections, with a holiday detector, immediately
preceding the lowering in of the pipe. The Contractor shall furnish high
voltage electric holiday detectors set to the Approved Manufacturer's
recommendations.
12.6 All holidays and damaged places in the coating shall be repaired by the
Contractor until the detector is passed over the entire joint without
disclosing any holiday or imperfections in the coating.
12.8 Coated pipe shall be handled at all times with equipment designed to
prevent damage to the coating.
Specification Number Rev Date Sheet
01 5-IH-1001 1 9-7-94 16 of 28
13.0 LOWERING-IN
The Contractor shall lower in the pipe into the trench after the coating
and wrapping of field joints.
Pipe shall not be lowered into the trench until the bottom of the trench
has been cleared of all debris and the bedding has been graded so that
the pipe has a uniform bearing. The Contractor shall request and receive
approval from the Company prior to lowering in any pipe.
The handling of the pipe shall be done in such a manner that the pipe in
its final position in the trench shall be free from abraded spots or
holidays.
When lowered in, the pipeline shall have a clearance of 0.1 5 m on either
side of the trench wall.
The lowering operation shall be carried out by the Contractor when pipe
temperatures are within the limits and in accordance with the lowering-
in temperatures.
13.10 The Contractor shall at all the times make good and repair or replace
all effects as directed by the Company.
Specification Number Rev Date Sheet
E n g / d n g Grwp
01 5-IH-1001 1 9-7-94 1 7 0 f 28
-n
13.11 All equipment used for lifting and handling the pipelines and
components shall be tested, inspected and certified by an Approved
Authority. The test certificates showing safe working loads, safety
systems, etc. shall be submitted to the Company for approval.
14.1 The Contractor shall do all work necessary to tie-in separate welded
sections of the pipeline into a continuous system.
14.2 All bevelling, aligning and welding shall be done in accordance with the
Engineering Group Specifica,tion entitled "Pipeline Field Welding Non-
Sour Service" (Number 01 5-IH-1008).
14.3 Welding after the pipe has been lowered into the ditch (bell-hole
welding) shall be done only where sufficient clearance has been provided
to enable the welder to exercise normal welding skill and ability and to
ensure against trench collapse.
14.4 The protective coating of tie-in welds shall be done in accordance with
the Engineering Group Specification entitled "Pipeline Field Joint
Coating" (Number 015-IH-1012).
14.5 All pipe 2 m or more in length cut off at tie-in points shall not be allowed
to accumulate but shall be moved ahead daily as the Work progresses
and welded into the line as directed by the Company.
14.6 The Contractor shall observe the maximum and minimum tie-in
temperature to be used based on the prevailing temperature conditions
and the calculations developed during detail design.
14.7 The Contractor shall perform tie-ins as soon as practicable after lower-in
of the strings. Extended periods between lower-in and tie-in shall only
be allowed when specified tie-in temperatures cannot be reached.
14.8 The maximum length of exposed unsupported pipeline must not exceed
7 m. When it exceeds five 5 m, a central substantial wooden support
shall be installed with a minimum 10-mm-thick rubber "shoe" or
equivalent contacting the pipe.
15.1 Pipeline fittings shall include but not be limited to insulating joints,
temporary scraper traps, valves and fittings and branch connections,
cathodic protection test stations, anchor flanges, line markers and
miscellaneous supports and concrete foundations for the above and for
the specified related facilities as needed.
GTOUD
I Specification Number I Rev I Date 1 Sheet
15.2 The Contractor shall install all such fittings as specified herein and as
shown on the approved construction Drawings. Welding shall be in
accordance with the Engineering Group Specification entitled "Field
Welding Non-Sour Service" (Number 01 5-IH- 1008).
15.3 All scale, dirt and debris shall be removed from the inside of the piping
fittings before installation.
Wherever the possibility exists of soil erosion due to surface water runoff as
in wadis, underground water or wind, the Contractor shall provide protection
for the pipeline and install drainage, barrier wind breaks or other installations,
as required.
The Contractor shall pad and backfill the trench after the pipe is in place
as set forth in the approved construction Drawings.
The Contractor shall grade the trench bedding material to give the
maximum amount of support to the pipeline when it is lowered into
place. The material shall be compacted to the degree specified by the
approved detail design calculations.
The depth of padding shall be such as to give the pipe in place the
specified clearance from the hard material.
The Contractor shall not commence the padding operation until the
Company has inspected and approved the lowered-in pipe. If any
backfilling is done without Company approval, the Company shall have
the right to require removal of the backfill for examination, and the cost
Specification Number Rev Date Sheet
Eng/1)001jngGrwp
01 5-IH-1001 1 9-7-94 19 of 28
m n
17.9 The padding material to shade the pipe shall be applied immediately after
the trench is approved for backfilling.
17.10 All lowered-in pipe shall be shaded with padding material at the end of
each working day or otherwise restrained by spot backfilling.
17.13 Berm material shall be selected from desert fill or excavated material
in rock areas. Berm material shall be free from organic material and
course graded. Fines shall be placed at the bottom of the berm with
greater particle sizes on the top. The berm angle shall be less than the
normal angle or repose of the berm material. Crude oil for berm
stabilisation will be made available to the Contractor by the Company.
20.2 All surplus and defective materials supplied by the Contractor for the
construction of the pipelines and all trash, refuse and unusable spoil
materials shall be collected and disposed of by the Contractor to the
satisfaction of the Company.
20.3 The construction ROW shall be graded smooth, and surface soil shall be
carefully replaced in a manner acceptable to the Company.
-N43-0160 -
d-r flu.a r
I Specification Number 1 Rev 1 Date 1 Sheet
The Contractor shall supply all the gravel or gatch required to cover
areas as shown on approved Drawings. The Contractor shall dress-up
areas disturbed during construction and shall rework surfaced areas as
required for acceptable finish condition.
The final ROW shall be graded smooth enough to provide for access to
light four-wheel-driven units.
21.1 General
c. Route maps.
d. Profile maps.
i. Cathodic protection.
21 .I
.2 The Contractor shall prepare a Pipe and Weld Book.
Specification Number Rev Date Sheet
E n g J d n g Grwp
015-IH-1001 1 9-7-94 21 of 28
SpeMiw&n
21.2.3 The surveyors shall daily collect and compile all measurements
required such as but not limited to:
m. Location of ROW.
n. Type of soil.
0. Sand padding.
21.3 P i ~ eBook
21.3.1 The Pipe and Welding Book shall contain, but not be limited to:
g. Diameter of pipeline.
j. Wall thickness.
o. Coating.
p. Date of stringing.
q. Date of welding.
r. Direction of working.
s. Welder number.
u. Weld treatment.
21.3.2 In order t o achieve this, the Contractor shall identify all pipe
elements. The Contractor shall track and document all pipes
2 m and greater in length and all condemned pipe for material
accountability.
21.4 Identification
Before a pipe length, pipe end, etc. is cut, the painted serial
number and stamped-in pipe number shall be transferred by the
Contractor in the presence of the Company to either side of
the joint which is to be made by cutting, and the changes shall
be recorded in the above mentioned list stating the new length.
The result shall be such that all pipe pups of diameter greater
than 2 in. bear clear marks painted on.
The Contractor shall explicitly instruct its staff that pipe which
cannot be identified must be removed and condemned.
Specification Number Rev Date Sheet
01 5-IH-1001 1 9-7-94 25 of 28
m n
Sheet 1 of 4
Length KM
Crude Oil Transmission Line Network One No. 20" spur line from GC-5 4.5
to manifold Burgan-1 (GI
One No. 12" spur line from new 3.5
GC-12 t o manifold Burgan-1 (GI
One 20" tie-in from GC-14 t o 1.5
existing line
Low Pressure Gas Transmission Network One No. 18" gas line GC-5 t o 5.0
manifold "S7"
One No. 18" gas line from 2.3
manifold "S7" t o manifold "S6"
One 20" tie-in from GC-12 t o 0.25
existing line
One 20" tie-in from GC-5 t o 2.5
existing 20" gas line
One 20" tie-in from GC-14 t o 2.5
existing line
High Pressure Gas Transmission Network One 12" tie-in from GC-5 t o 2.0
existing line
One 12" tie-in from GC-12 t o 0.25
existing line
One 12" tie-in from GC-14 t o 0.10
existing line
Fuel Gas System One 4" tie-in from GC-5 t o 2.0
existing line
One 4" tie-in from GC-12 t o 0.25
existing line
One 4" tie-in from GC-14 t o 1.5
existing line
Brackish Water GC's t o RinaIMain 0.3
Specification Number Rev Date Sheet
E n g i M n g Gnwp
01 5-IH-1001 1 9-7-94 26 of 28
APPENDIX 1
Sheet 2 of 4
Category Requirement
Material API 5L Grade B
Nominal diameter 1 20" NPS. 18" NPS. 12" NPS and 4" NPS
-- --
APPENDIX 1
GC-29 and 30
Sheet 3 of 4
NetworklSystem Length
Crude Oil Transmission Line Network One 12" crude oil line from GC-30 to
manifold
One 10" crude oil line from GC-29 to
manifold
One 16" from manifold to existing
line
Condensate Transmission Network One 6" condensate line GC-30 to
manifold
One 4" condensate line from GC-29
to manifold
One 6" condensate line from
manifold to existing line
High Pressure Gas Transmission One 10" from GC-30 to manifold
Network
One 8" from GC-299 to manifold
One 10" from manifold to existing
line
Fuel Gas System One 6" from existing line to manifold
One 6" from manifold to GC-30
One 6" from manifold to GC-29
APPENDIX 1
Sheet 4 of 4
Category Requirement
Material API 5L Grade B
Nominal Diameter 16" NPS, 10" NPS, 8" NPS (spiral pipe)
6" NPS and 4" NPS (seamless)
Wall Thickness For all pipe size 9.5 mm
Corrosion Coating 1
I
Polyolefin
I
I
Operating and Design Pressure MAOP
I Design Pressure
lo", 12" 16" NPS Crude Oil Lines 450 psi 1 500 psi
8", 10" HP Gas 930 psi 9 5 0 psi
6", 4" Condensate 1230 psi 75 psi
6" NPS Fuel Gas psi I 400 psi
Flange Rating
Crude Lines ASME Class 300
Fuel Gas ASME Class 300
HP Gas Lines ASME Class 400
Condensate ASME Class 600
Hydrotest Pressure ASME B.31.8 125% of MAOP or 90%
SMYS
Minimum Cover 1.0 m (top of pipe)
Minimum Bending Radius Induction Bend 5D