Anggaran Perbaikan Tie in Hydrant

No Keterangan Quantity Unit Harga Satuan Total Harga Keterangan

1 Man Power include 1 welder & 1 Fitter 26 Titik Rp 270.000 Rp 7.020.000 Payment DP 30 %, 20%,50%

2 Consumable
Tabung Argon 3 Tabung Rp 225.000 Rp 675.000 Pembelian by logistik project
Kawat Las Argon TGN 3 Dus Rp 300.000 Rp 900.000 Pembelian by logistik project
Kawat Las LB 2,6 @ 5 Kg 3 Kg Rp 185.000 Rp 555.000 Pembelian by logistik project
Cutting disc 7" WD 30 Pcs Rp 14.500 Rp 435.000 Pembelian by logistik project
Sarung Tangan Argon 4 Pcs Rp 35.000 Rp 140.000 Pembelian by logistik project

Total Pengajuan Rp 9.725.000