No. Rev. : 0
WORKING METHOD Page No. : 2 of 12
INSTALLATION EQUIPMENT By Chk Appr
Esu Nwa Rph
APPROVAL
NAME POSITION SIGNATURE DATE
Coordinator
Checked
Approved
Rev 00
Date : March 14, 2013
No. Rev. : 0
WORKING METHOD Page No. : 3 of 12
INSTALLATION EQUIPMENT By Chk Appr
Esu Nwa Rph
CONTENT
I. SCOPE
II. APLICABLE DOCUMENT
III. CHIPPING OF FOUNDATION SURFACE.
IV. INSTALLATION OF PAD LINER
V. GROUT OF ANCHOR BOLT
VI. ALLIGNMENT AND LEVELNESS OF EQUIPMENT
Date : March 14, 2013
No. Rev. : 0
WORKING METHOD Page No. : 4 of 12
INSTALLATION EQUIPMENT By Chk Appr
Esu Nwa Rph
I. SCOPE
This technical specification cover for chiping foundations , install pad liners, grouting of anchor bolt and
levelness & alignment for the equipment for the Bluescope project.
b. Water the concrete surface before mounting pad to keep it wet. Use cloth to remove
excessive moisture on the pad right before mounting the pad.
c. Soaking concrete surface with clean water for 24 hours before grouting (minimum 4 hours).
a. Place the dry mortar in the correct position (based on approved drawing).
b. Set the padding plate on top of the dry mix mortar grout, automatic level to set the pad plate
to the correct elevation.
c. After the pad has set, re-check the padding plates as to levelness and elevation by auto level
and others.
d. After mortar grout is dry check the bonding between pad plate and mortar by the place
(knock) with small hammer.
Date : March 14, 2013
No. Rev. : 0
WORKING METHOD Page No. : 6 of 12
INSTALLATION EQUIPMENT By Chk Appr
Esu Nwa Rph
Provide pad on both side of the anchor bolt for equipment as shown bellow.
a.After foundation inspection for installing and centering, measure the dimension from the
centerline with a tape measure to ink the exterior circumference of the equipment.
b.In principle, mount installation seat where concentrated load is expected as well.
c. Provide installation seat where concentrated load is expected as well.
d. When the base frame is deflected at installation, provide installation seats.
e. A : Base liner length x ½ .
B : Interval between anchor hole to end of base liner to be less than 70 mm.
Date : March 14, 2013
No. Rev. : 0
WORKING METHOD Page No. : 7 of 12
INSTALLATION EQUIPMENT By Chk Appr
Esu Nwa Rph
Non shrinking
Cement River sand water / cement
mixed material
Weight
ratio 1 1 1 0.35 - 0.4
a. Pour mortar little and settle it well with a hammer or a bar. Do not settle too much mortar
more than 20 mm at once.
Date : March 14, 2013
No. Rev. : 0
WORKING METHOD Page No. : 8 of 12
INSTALLATION EQUIPMENT By Chk Appr
Esu Nwa Rph
b. There shall no be rust on the surface of base liner. If any, remove the rust with grinder be
use.
c. After setting the mortar, put a base liner into mortar by lightly hitting it with a wooden
hammer.
d. When the hight is too low, do not add mortar on to it. Dig out and remove the mortar to
regain the original condition. Then, place mortar all over again.
time
Important equipment 72 hr
General equipment 48 hr
0
a. The optimum temperature of curing is around 20 C. Therefore, provide heat insulation
when it is too cold, and cover it with a wet linen when it is too hot.
b. Pay attention to avoid foreign matters dropping on the pad while curing.
c. Protect the pad liner from vibration, impact and load while curing.
4.7 Inspection.
Date : March 14, 2013
No. Rev. : 0
WORKING METHOD Page No. : 9 of 12
INSTALLATION EQUIPMENT By Chk Appr
Esu Nwa Rph
a.Check for the abrasion between base liner and mortar, and between mortar and concrete.
b.In case pad liner unaccepted, never give local repair or correction. Always place it all over
again.
c. Set height and levelness.
d.Pad position and quantity.
V. GROUT OF CHEMICAL BOLT.
5.1 Grout the chemical bolt’s hole.
After centering the anchor bolt, fix the anchor bolt as shown below,
a. Preparation.
1. Inside Surface concrete of chemical bolt hole shall be chipping first. At about 20 mm in
depth, then cleaning with air pressure shall be done.
2. Remove foreign matters, water, and cement chips and clean the chemical bolt hole prior
to grout anchor.
3. Make sure that the chemical bolt shaft center and equipment hole center is aligned
better.
b. Preparation of Mortar.
1. Use grouting material as per manufacture technical requirement.
2. Water to be used for mixing grouting material shall be fresh and clean and the
temperature of water not less than 25 0 C (apply ice to control the temperature).
3. Formulation of mixing must be as following,
Every 25 kg of grouting material (non shrink grout) should be mixed with 3,8 liters of
water.
Never used sand for mixing.
Mixing time shall be 3 – 5 minutes long
Date : March 14, 2013
No. Rev. : 0
WORKING METHOD Page No. : 10 of 12
INSTALLATION EQUIPMENT By Chk Appr
Esu Nwa Rph
The curing time depends on the moisture ratio, however, conform to the following curing time,
Time
0
a. The optimum temperature of curing is around 20 C. Therefore, provide heat insulation
when it is cold, and cover it with wet linen when it is too hot. Keep wet as per manufacturer
requirement to protect it.
b. Protect the pad liner from vibration, impact and load while curing.
Levelness of Equipment
a. Use precision level and straight edge
b. Adjust the levelness with a tapper line
c. Securely tighten the anchor bolts. Do not adjust the level by tightening or loosening the
anchor bolt.
d. For installation precision, refer to the installation manual.
When tapper liner is not enough to make necessary adjustment, insert shim plates on the base
liner.Try to use minimum number of shim plates.