Professional Documents
Culture Documents
Body of Requisition - ROW Work Package PDF
Body of Requisition - ROW Work Package PDF
A All -
B All -
1.1 Scope
This requisition covers the technical requirements for All Construction Work in ROW Area (hereinafter
called the WORK), consist of:
• Site Preparation and Civil Work
• Pipeline Work
• Electrical and Instrument Work
• Precommisioning Work
The WORK shall be performed and completed by the SUBCONTRACTOR for Jambaran Tiung Biru
Unitization Gas Project in Bojonegoro, East Java, Indonesia (hereinafter referred as PROJECT) managed
by Consortium of PT. Rekayasa Industri, JGC Corp.,and JGC Indonesia, hereinafter referred as
CONTRACTOR for PT. Pertamina EP Cepu, hereinafter refered as COMPANY.
The SUBCONTRACOR shall perform and complete the Work in strict accordance with the requirements
contained in this Requisition.
1.2 Definition
COMPANY
PT. Pertamina EP Cepu is defined as COMPANY, the party that owned the PROJECT
CONTRACTOR
PT. Rekayasa Industri, JGC Corp., and PT. JGC Indonesia are defined as CONTRACTOR, the party that
carries out the design, engineering, procurement, construction, commissioning and management of the
Project.
SUBCONTRACTOR
SUBCONTRACTOR is the successful BIDDER(s) awarded by CONTRACTOR to be the Construction
SUBCONTRACTOR(s) who has(ve) responsibility for executing the Work of the Project at the above
mentioned location.
BIDDER(s)
BIDDER(s) are the companies who have passed the prequalification performed by the CONTRACTOR
which intended to bid or submit the quotation for this Work.
1.3 Location
The WORK will be located in Bojonegoro, East Java, Indonesia. Location of the WORK can be seen in
drawings in Attachment 2. BIDDERs are requested to develop detail layout as per their execution plan,
wich shall be written in the Bid Form, Form 14 “Construction Method” (shown in Attachment 1 of this
document).
Total WORK duration shall be maximum 18 month. BIDDERs are requested to develop detail schedule as
per their execution plan, wich shall be written in the Bid Form, Form 9 “Detail for Construction Schedule
and Productivity” (shown in Attachment 1 of this document).
If there is any discrepancy between the documents forming this Requisition, the order of precedence shall
be as indicated bellow:
1. In the event of any discrepancy between the local laws/regulations and the documents listed
here, the stringent shall govern.
2. If the event of any discrepancy between the documents of the same category, the SUB-
CONTRACTOR shall consult with CONTRACTOR for clarification.
2. SCOPE OF WORK
2.1 General
The SUBCONTRACTOR shall, in the shortest practicable time, commencing after the avaibility of letter of
award or contract, conduction of kick of meeting, and completion of premobilization checklist; procure
material and deliver it to site, furnish labour and personnel, mobilize construction equipments and tools,
construct temporary facilities and supplies, and do other things necessary for completion of the Work in
accordance with schedule, drawing, specifications, and the terms and conditions of the contract.
The SUBCONTRACTOR shall follow local regulation regarding to the optimization of local labor utilization,
especially Peraturan Daerah No. 23 Bojonegoro 2011.
The SUBCONTRACTOR shall be responsible for the following engineering and procurement work:
a. Engineering for SUBCONTRACTOR’s temporary facilities such as but not limited to, site office,
storage room, work shop, water distribution pipe line, power distribution line and lighting,
temporary roads and drainage, septic tank, etc.
b. Engineering for SUBCONTRACTOR’s permanent work such as but not limited to working
drawings, construction procedures, method statement, etc.
c. Procurement for all temporary and consumable materials.
CONTRACTOR will not provide space/area for housing or camp facilities to SUBCONTRACTOR.
SUBCONTRACTOR shall provide the housing or camp facilities for their staff/employees by themselves in
the number and condition as necessary.
The brief Scope of Work that is separated into work disciplines an d working area can be seen in the
following table:
Picture-1
AREA SEPARATION
The SUB-CONTRACTOR shall be responsible for all direct work required to be carried out and completed.
The work included, but not limited to, the items defined in Table-2 up to Table-6 “Scope of Direct Work” for
each discipline.
Table-2
SCOPE OF DIRECT WORK FOR SITE PREPARATION AND CIVIL WORK
RESPONSIBILITY BY
NO. WORK ITEM REMARKS
CONT. SUBCNT.
4. SUPPLY OF MANPOWER
4.1 Indirect manpower
a. Managerial manpower X
b. Finance and adiminstrations personnel X
c. Human resources X
5. CONSTRUCTION
5.1 General
a. Preparation work; measurement of X
coordinates & elevations, marking, etc.
b. Protection of existing facilities during the X
execution of the work
c. Additional access road work for X
SUBCONTRACTOR’s purpose
d. Store and transport all materials supplied by X
SUBCONTRACTOR
e. Transportation of materials from X
CONTRACTOR’s lay down to
SUBCONTRACTOR’s working area (if any)
f. Move soil to designated area X
g. Controll, repair, and maintenance existing X
access road during site preparation activities
h. Inspection and testing X
i. Conduct maintenance/repair for construction X
equipment and tools, including its spare parts
j. Disposal of packing materials and waste X
material base on CONTRACTOR’s instruction
Table-3
SCOPE OF DIRECT WORK FOR PIPELINE WORK
RESPONSIBILITY BY
NO. WORK ITEM REMARKS
CONT. SUBCNT.
3. SUPPLY OF EQUIPMENT
3.1 All direct and indirect construction equipment, X
crane, trailer long bed, TMC, forklift, welding
engine, welding machine, compressor, generator
set, etc.
3.2 All related construction tools, chain block, beveling X
machine, plasma cutting machine, automatic
welding machine, threading machine, tripod and
lifting gear, baking and holding oven, portable
drier (ink dryer), hammer, wrench, scaffolding,
torque wrench, non-spark tools, preheat and
PWHT equipment, coil and burner, etc.
3.3 Inspection and Testing Tools
a. All related welding and fabrication inspection X
tools i.e. welding gauge, mirror, light,
temperature stick, temperature gauge, clamp
ampere meter, welding gauges, vernier
caliper, etc.
b. All related pipe testing inspection tools, i.e. X
light, pressure gauge, temperature stick,
temperature gauge, pressure recorder set,
etc.
c. All related material inspection tools, i.e. PMI X
test equipment. PMI test equipment shall
capable to check material element in
accordance with document no (TBN), Positive
Material Identification Procedure, i.e. Cr, Mo,
V, Ni, C, Ti, Nb, Cb, P, S
5. PIPELINE WORK
5.1 Fabrication and installation of pipe spool and other X 4) Accessories such as
accessories according to specification for piping valves, strainers, filters,
work (including connection to tie-in)4) etc. according to drawing
5.2 Demolish unused existing piping X
material/connection
5.3 Cleaning pipe and pickling based on project X
specification
5.4 Fabrication and installation of pipe support X 5) Raw material is
including column high adjustment, painting, and supplied by
grouting (if any)5) CONTRACTOR
7. EARTH WORK
7.1 Site preparation (setting out, survey) X
7.2. Earth work (excavation, stripping) X
Table-4
SCOPE OF DIRECT WORK FOR INSTRUMENT WORK
RESPONSIBILITY BY
NO. WORK ITEM REMARKS
CONT. SUBCNT.
3. FABRICATION
3.1 Fabrication and/or modification of material for all X
necessary installation (such as: fabrication Steel
Channel, Angel, etc) for completing the
construction/installation.
3.2 Demolish unused existing instrument X
material/connection
6. WIRING
6.1 The secondary electrical power supply wiring from X
the power distribution boards in control rooms to
the control panel boards & DCS System
6.2 Wiring including system cables for the equipment X
in control room/sub-station building room.
6.3 The electrical power supply wiring from power X
distribution boards in control room/field to field
instruments, analyzer and sampling pumps.
6.4 Wiring from electronic instruments, Transmitters, X
instrument switch type, solenoid valves, limit
switches, etc. to control/ESB room through field
junction boxes, remote scanner, local panels.
Table-5
SCOPE OF DIRECT WORK FOR ELECTRICAL WORK
RESPONSIBILITY BY
NO. WORK ITEM REMARKS
CONT. SUBCNT.
2. MATERIALS
2.1 Main Equipment (Panel,Transformer, etc.) X
2.2 Electrical Cables X
2.3 Cable Tray X
2.4 Lighting and accessories X
2.5 Grounding, Lightning and accessories X
2.6 Wiring Accessories X
2.7 Bulk Materials X
4. CONSTRUCTION (ALL) X
4. SUPPLY OF MANPOWER
4.1 Indirect manpower
a. Precommissioning Engineer X
b. Other related indirectmanpower which is X
required for the WORK.
4.2 Direct Manpower
a. Supervisor X
b. Foreman X
c. Pipe Fitter X
d. Safety man X
e. Equipments operator required (heavy X
equipment, hydrauliq torque, air compressor,
electrical generator, etc.)
f. Technician X
g. Helper X
h. Other related directmanpower which is X
required for the WORK.
4.3 General Worker (general affairs, driver, etc.) X
Notes:
The approved Inspection Report will be one of mandatory attachments of Work Progress Report. The
Work Progress Report will not be approved when the approved Inspection Report is not attached.
The major of Indirect Work and Services required to be carried out and completed are listed in Table-2
“Scope of Indirect Work”. All services, utilities, materials, equipment, etc. other than those stated in Table-
5, if any, shall be supplied by SUB-CONTRACTOR at his cost and expense.
Table-7
SCOPE OF INDIRECT WORK
RESPONSIBILITY BY
NO. WORK ITEM REMARKS
CONT. SUBCNT.
4. UTILITIES
4.1 Water
a. Water Supplies
• Potable water at SUBCONTRACTOR’s X
office
• Construction water at job site, including X
for testing
• Sewage water system
b. Distribution Piping X
4.2 Electrical
a. Supplies generator set X
b. Distribution system and wiring X
8. INSURANCE
8.1 SUBCONTRACTOR’s All Risk Installation X
Insurance
8.2 Comprehensive General Liability X
Insurance (CGL), Bodily Injury and Property
Damage
8.3 Workman’s Compensation Insurance (WCI)6) X 6) For SUBCONT’s
8.4 Employer’s Liability Insurance (ELI) 6) X worker
8.5 Comprehensive Automobile liability Insurance X 7) For SUBCONT’s
(ALI) 7) automobile
8.6 SUBCONTRACTOR’s “All Risk” Equipment X
Insurance
8.7 All Risk Marine Cargo Insurance for materials and X
Equipment supplied by the SUBCONTRACTOR’s
8.8 Other Insurance for SUBCONTRACTOR’s (if any) X
SUBCONTRACTOR shall supply all the required tools and consumable required for the work as specified
in Table-1 “Scope of Direct Works”. SUBCONTRACTOR shall anticipate and procure tools and
consumable which are going to be needed for at least the next two months to prevent shortage of
tools/consumable which can affect construction progress. SUBCONTRACTOR shall also submit list
enumerating suppliers of tools and consumable used in the PROJECT.
All equipment, tools and materials supplied by SUBCONTRACTOR for execution of the work shall be
subject to CONTRACTOR’s prior review, inspection and test. If SUBCONTRACTOR fail to comply with the
The critical construction equipment supplied by SUBCONTRACTOR shall be inspected and approved by
CONTRACTOR and witnessed by COMPANY if necessary at the present location before its mobilization
to site. All those inspected and approved construction equipment shall be available on the site from the
starting date of the relevant work up to the completion date thereof. Equipment certificate from
government should be prepared by SUBCONTRACTOR.The approval by CONTRACTOR shall not in any
way relieve the SUB-CONTRACTOR of its responsibility for the proper construction and functioning of the
equipments.
The layout drawings contained in this requisition are preliminary drawings for quotation purpose only.After
the contract is awarded, CONTRACTOR will supply the engineering drawings, for the Work.Beside the
above Engineering drawings, SUBCONTRACTOR shall provide the construction method for
CONTRACTOR’s approval.
The SUBCONTRACTOR shall furnish the working drawings necessary for the Work, and approved by
CONTRACTOR before execution of the Work. SUBCONTRACTOR shall develop Mark-up drawing based
on the approved survey results, after performing the Work.
The SUBCONTRACTOR shall keep all portions of the Work properly and efficiently drained and or
pumped at all times during the construction and until completion of the Work. Drainage and pumping
facilities shall be maintained operable and manned at all times as required.
SUBCONTRACTOR shall design and construct silt trap/sedimentation pondin any temporary drainage
before it comes to Glonggong river. SUBCONTRACTOR shall take all other precautions to ensure the
efficient protection of all streamsand waterways against pollution arising by the execution of the Works.
SUBCONTRACTOR shall be responsible for all damage which may be caused by or result from water
collecting or flowing overfromany part of the Work.
SUBCONTRACTOR shall carry out the Works in such manner to cause as little as inconvenience and
nuisance to persons living in neighboring properties and to the public. SUBCONTRACTOR will take
responsibility and accountability for social, environmental, and security impact during the Work execution
The SUB-CONTRACTOR shall not obstruct, as far as possible, the public roads and where this is
necessary and unavoidable, SUBCONTRACTOR shall provide barriers, warning lights, etc. required for
proper traffic control including getting the necessary permits from the relevant authorities and paying all
fees in connection therewith. SUBCONTRACTOR shall be responsible for clearing and cleaning all roads,
drains, etc. when these are fouled as a result of the Works at regular intervals or when directed by the
CONTRACTOR.
The excavation in rock is applicable only for solid boulders or detached pieces of rock exceeding 1.0 cu.m
in size.No blasting shall be permitted in the area. Rock encountered in such areas shall be excavated by
the use of one of the following methods:
All cost for work including excavation, removal and disposal of rock by all means shall
beSUBCONTRACTOR’s responsibility.
3.7 Survey, Base Point and Bench Mark (Refer to Engineering Specification)
SUBCONTRACTOR shall set out the Works from the Bench Marks and check all the Works.
SUBCONTRACTOR is responsible in securing and maintaining the Bench Marks and executing other
survey required for performing the Work. In case the survey work is required, SUBCONTRACTOR shall
prepare the survey drawings.
Whether or not indicated or provided in the Contract and any other document and data provided by
CONTRACTOR, but considered necessary from technical or commonly accepted standpoint,
SUBCONTRACTOR shall have the responsibility to provide, execute, and complete all the Works, in order
to meet technical, statutory, safety, or security requirements. These works shall be informed and under
CONTRACTOR supervision.
If any of the materials after acquisition from CONTRACTOR are lost or damaged by the SUB-
CONTRACTOR, replacement or refurnishment of such materials shall beSUBCONTRACTOR’s
responsibility.
SUBCONTRACTOR shall conduct all quality inspection and testing for the work to provide warranty to
CONTRACTOR. All equipments and material for test requirement shall be provided by
SUBCONTRACTOR.
If testing shall be conducted outside project location and needs specific facilities like laboratorium or other
institutions, all necessary cost and resource shall be SUBCONTRACTOR’s responsibility.
SUBCONTRACTOR shall coordinate and report the testing result to CONTRACTOR, and if the testing
result doesn’t fulfill the specification required by CONTRACTOR, SUBCONTRACTOR responsible to
improve and re-test until the result is approved by CONTRACTOR. Approval from CONTRACTOR shall
not relieve the SUBCONTRACTOR from the responsibility to repair their work result if any discrepancy is
found in the next days until working handover.
SUBCONTRACTOR shall conduct treatment activities until the work finish and handed over to
CONTRACTOR.
CONTRACTOR can give instruction change in writing and orally about the ongoing work.
SUBCONTRACTOR shall follow up the instruction change and report the change to be calculated in the
end of the project.
Revision of design, drawings, and specification or other documents that is required by CONTRACTOR
shall not always be change order and shall not always make enhancement of contract value as in change
in scope of work.
When CONTRACTOR judges that the SUBCONTRACTOR is not capable of continuing the Works
in respect of volume, quality or schedule of the Works, CONTRACTOR may in its sole discretion take over
from the SUBCONTRACTOR and execute certain portion of the Works. In this event, unit price adjustment
in the manner specified in Para12 shall be applied for calculation of the price to be paid for the Works
accomplished by the SUBCONTRACTOR.
The following scenario shall be considered by SUBCONTRACTOR in planning their construction execution
strategy:
Picture-2
PRIORITY AREA SEPARATION
4. Clearing, stripping, and top soil removal shall be conducted in whole area mentioned above for
minimum thickness of 45 cm. Material from clearing, stripping, and top soil removal shall be
disposed to Perhutani’s area (under coordination of SUBCONTRACTOR) around project site
location (< 5 km) as per picture below:
SUBCONTRACTOR is required to inform their execution plan in importing material from outside project
location (included in bid document Form 13 “Construction Execution Strategy”). The execution plan for this
concern shall explain following items:
Control and maintenance existing road access that will be used for material and equipment mobilization
activities shall be SUBCONTRACTOR’s responsibility. SUBCONTRACTOR shall explain the related
program for this concern in bid document Form 13 “Construction Execution Strategy”. Any interfacing
matter with local community/government shall be SUBCONTRACTOR’s responsibility.
SUBCONTRACTOR shall take all necessary precautions to preserve all earth slopes both existing (slopes
already exist on the site at the time of the site being handed over to the SUBCONTRACTOR) and new
(slopes formed and constructed by the SUBCONTRACTOR under the contract).SUBCONTRACTOR shall
construct adequate temporary drains, and take all necessary steps to prevent slips from occurring.
In the event of slips occurring or may possibly occur, the SUBCONTRACTOR shall immediately report to
theCONTRACTOR who shall give the necessary instructions to the SUBCONTRACTOR.
SUBCONTRACTOR shall, at their own expense, make good steps to the entire earth slopes and shall
indemnify the CONTRACTOR in respect of any claims or proceedings arising out of SUBCONTRACTOR’s
negligence of this clause.
All soil disposal activities shall be SUBCONTRACTOR’s responsibility. The SUBCONTRACTOR is not
allowed to store the excavated unsuitable soil in the battery limit area. The excavated soil shall be
removed from the point of work to the specified disposal area outside ROW boundary site.
SUBCONTRACTOR shall propose the disposal area for CONTRACTOR and COMPANY approval.
• 20” gathering gas pipeline from Wellpad East to GPF (1.55 km)
• 18” gathering gas pipeline from Wellpad Central to Wellpad East (5 km)
• 20” sales gas pipeline from GPF to metering station (10.98 km)
• 6” filtered water pipeline from Banyu Urip CPF to GPF (9,02 km)
• 4” condensate pipeline from GPF to Banyu Urip CPF (8.35 km)
• 4” produced water pipeline from GPF to Banyu Urip CPF (8.36 km)
• Piping at Wellpad East, Wellpad Central, and metering facilities
• Tie-in works at Banyu Urip facilities
• Auger boring for crossing area (± 37.5 m; list will be detailed).
Pipe to be installed by SUBCONTRACTOR shall be requested and aligned with CONTRACTOR’s plan.
After taking material from CONTRACTOR’s warehouse, material preservation shall be
SUBCONTRACTOR’s responsibility. All pipe transported from warehouse to site must be handled
properly.
After stringing, pipe shall be placed at safe area, prevented from direct contact with soil.
SUBCONTRACTOR shall prepare wooden block to support pipe. Pipe end shall be capped to protect from
dust, dirt, mud, soil, and other foreign materials.
SUBCONTRACTOR shall follow the requirement of pipe installation based on alignment sheet issued by
CONTRACTOR.
After completion of installation, SUBCONTRACTOR shall clean the interior of pipe, cover both ends with
vinyl sheet, and protect face flanges by means of plywood (or similar) to protect from rust or coat material
(or similar). Marking shall be made showing line number and spool piece number, referring to the
respective procedures or specification during installation and the marks shall be matched with material
received from warehouse.
SUBCONTRACTOR shall adopt normal fabrication procedure and perform based on CONTRACTOR’s
guidance as minimum. SUBCONTRACTOR shall adopt the actual condition at site and final inspection.
Picture-4
DISPOSAL AREA FOR ROW SITE PREPARATION
SUBCONTRACTOR shall conduct coating works in accordance with the Specification for Pipeline Anti-
Corrosion Coating (JTB-SF-Y-SPE-600-00010). SUBCONTRACTOR shall perform field joint coating and
field coating straight pipe as necessary (see detail Bill of Quantity).
Prior to any coating work, SUBCONTRACTOR shall conduct necessary coating test in accordance with
the specification to get COMPANY’s approval. SUBCONTRACTOR shall comply with the requirement of
coating applicator personnel, supervisor, coating inspector, advisor, and environmental regulation
regarding the emission and disposal of coat and other local Health and Safety regulation.
In case there are wrapping works, SUBCONTRACTOR should meet CONTRACTOR’s criteria and
specification.
If flange faces are scratched/damaged during transportation or during installation at site, then,
SUBCONTRACTOR shall perform re-facing (machining) at their cost and expense.
SUBCONTRACTOR shall arrange his pipe-cutting schedule to minimize pipe wastage/scrap pipe. The
remaining pieces of cut-off pipe is defined as follows:
All surplus materials and cut-off pipe, including scrap of pipe, shall be transported by SUBCONTRACTOR
to CONTRACTOR warehouse or conforming to local regulation by SUBCONTRACTOR’s expense if
requested by CONTRACTOR.
Due to high consequence of risk resulting from any damage/loss of special materials, SUBCONTRACTOR
shall give extra care when receiving, handling, transporting, storing, controlling, and working on these
special materials:
• Duplex
• Incoloy 825
SUBCONTRACTOR shall take special measures, including, but not limited to, practices listed below:
• Receiving from warehouse. Check for any damage or deviation from the PROJECT’s technical
specification. Do NOT accept the materials if any damage/deviation is found.
Any damage or loss of special material shall be replaced by SUBCONTRACTOR. If not feasible, then
CONTRACTOR will repurchase the material (all cost incurred will be back-charged to
SUBCONTRACTOR).
Each pipe will be supplied with or without bevels as described in the piping specification.
SUBCONTRACTOR shall be responsible to perform beveling.
5.9. Cleaning
SUBCONTRACTOR is fully responsible to daily remove and transport waste or rubbish after finishing work
based on EPC CONTRACTOR’s instruction directly without any back charge to CONTRACTOR.
SUBCONTRACTOR shall be responsible for quality control and inspection activities. CONTRACTOR shall
control directly and will instruct to SUBCONTRACTOR for necessary repair if any welding defect is found.
SUBCONTRACTOR shall execute all test and inspection of quality of the Work in order to guarantee the
quality to CONTRACTOR. All materials and equipment required to complete the Work shall be under
SUBCONTRACTOR’s responsibility. Content of this inspection and test shall include but not limited to:
SUBCONTRACTOR shall operate software for controlling piping progress named “WMS” (Welding
Management System). This software will be provided by CONTRACTOR as a main tool to control Piping
Work. SUBCONTRACTOR shall provide operators, personal computer and maintain piping progress using
this system
SUBCONTRACTOR shall prepare working area (stack out, joint survey, marking, etc.).
SUBCONTRACTOR shall excavate soil and haul the disposal to the dedicated area. SUBCONTRACTOR
shall coordinate with CONTRACTOR’s Supervisor before start working to prevent clash with other
discipline (e.g. electrical cables, instrument cables, civil drainage, etc.). Slope and width of trench shall
follow CONTRACTOR’s drawing. SUBCONTRACTOR shall prepare trench collapse protection. Sand for
bedding and sand filling shall meet CONTRACTOR’s quality. In case of rainy season, SUBCONTRACTOR
shall provide dewatering pumps to manage flood or water inside trench. Backfilling and sand filling shall
follow CONTRACTOR’s specification (JTB-SF-C-SPE-900-00018).
5.13. HSE
Radiographic work
SUBCONTRACTOR shall provide isotope bunker (bump-it). At any time, isotope shall not be stored in the
worker camp and it must be approved by COMPANY.
Electrical safety
• Plug connector on a welding machine must be 3 connector type and water tight.
• Welding machine and electricity generator must be properly grounded.
• At any time, fire extinguisher must be available in the vicinity of welding machine and electricity
generator.
A. PROJECT MANAGER
• Ten years working experience in EPC projects for S1 degree or 15 years working experience in
EPC projects for D3 diploma
• Has working experience as Project Manager on 2 previous EPC projects
• Has thorough and broad knowledge of project management, HSE management, business
administration principles, contracts management, construction equipment management and
personnel management
• Has strong communication, coordination and team building skills, customer-focused and fluent in
spoken and written English.
B. CONSTRUCTION MANAGER
• Ten years working experience in EPC projects for S1 degree or 12 years working experience in
EPC projects for D3 diploma
• Has working experience as Construction Manager on 3 previous EPC projects
• Has strong HSE leadership, strong managerial, facilitation and coordination skill, understand
business administration principles and contract law and principles
• Has experience in construction of pipeline/piping systems and able to address any construction
progress shortcomings
• Has strong communication and interpersonal skills, customer-focused and fluent in spoken and
written English.
C. PROJECT CONTROL
• Five years working experience in EPC projects for S1 degree or 7 years working experience in
EPC projects for D3 diploma
• Has good communication and interpersonal skills, customer-focused, fluent in spoken and written
English.
D. COMDEV COORDINATOR
• Five years working experience in EPC projects for S1 degree or 7 years working experience in
EPC projects for D3 diploma
• Has thorough understanding of engineering and construction methods regarding onshore oil &
gas pipeline/piping systems.
F. SUPERINTENDENT
G. SUPERVISOR
• Five years working experience in EPC projects for S1 degree or 8 years working experience in
EPC projects for D3 diploma
• Has thorough understanding of pipeline/piping systems.
I. HSE COORDINATOR
K. QA/QC COORDINATOR
• Five years working experience related to QA/QC of piping/pipeline systems construction on oil &
gas, geothermal or petrochemical projects
• Has valid CSWIP 3.0 certification
• Has thorough and broad knowledge of quality assurance and quality control methods.
• Five years working experience in oil & gas, geothermal or petrochemical projects
• Has strong knowledge regarding quality assurance and quality control methods in pipeline/piping
construction.
• Five years working experience in oil & gas, geothermal or petrochemical projects
• Has valid WI certification
• Has strong knowledge regarding welding quality assurance and quality control methods.
All key personnel shall be dedicated full-time for this project. All key personnel shall also have certificate in
accordance with the requirements.
7. TEMPORARY WORK
SUBCONTRACTOR shall build their temporary facilities area in designated area instructed by CONTRACTOR.
SUBCONTRACTOR shall submit complete details of temporary works for CONTRACTOR approval not less
than 14 days before the start of the construction. The work shall be properly designed and constructed and
adequate for the intended purpose.The approval by CONTRACTOR of such work shall not in any way relieve
the SUBCONTRACTOR of its responsibility for the proper construction and functioning of temporary works.
8. QUALITY OF WORKMANSHIP
The Workmanship employed in the Work shall be of highest quality in terms of internationally recognized
standards or practice and shall be subject to the approval of CONTRACTOR.SUBCONTRACTOR shall provide
highly experienced and reliable foremen for the Work and all related works which are to be
SUBCONTRACTOR’s Scope of Work, and equipment operators which are well trained to handle such
equipments.
SUBCONTRACTOR must prepare good management skills and control system in this project. In all stages of
project execution, control and coordination must be good. SUBCONTRACTOR must submit to CONTRACTOR
the management and control system of this project, including job description of key personnel.
Construction supervision:
Delays in the Works which may become the subject or basis of claims for time extensions or changes in
contract price shall be immediately reported to CONTRACTOR as soon as such conditions become apparent.
The SUBCONTRACTOR shall submit and outline the circumstances in written form to CONTRACTOR within 7
working days of their discovery. Any claim not submitted within 7 working days will not be considered.
CONTRACTOR shall be immediately informed of any accident fire or other emergency which may arise on the
site, at temporary work yard or any other area at the Job site where the SUBCONTRACTOR is performing the
Woks.
Damage to existing facilities caused by movement of equipment or other operations, whether accidents or made
necessary by reason of the requirements of the contract, shall be restored or replaced as specified or as
directed by CONTRACTOR at the cost of the SUBCONTRACTOR.Restoration shall be equal to the structural
qualities and performance capabilities of original facility, and finishes shall match as nearly as possible to
existing Work.
12. SAFETY
The SUBCONTRACTOR shall observe and enforce all Safety Regulations on the site and
SUBCONTRACTOR’s construction equipments including but not limited to, the provision of safety wear, fire
fighting, and life saving equipments during construction.
12.1. Equipment
Prior to use, all equipment will be checked by CONTRACTOR’s HSE officer. For excavator and all
operators must have Depnaker certification.Lifting Equipment such as crane, TMC, forklift shall have
MIGAS certification
12.2. PPE
• Helmet must be as per ANSI Z 1989 standard (complete with chin strap for working at height)
• Safety glasses (complete with side shields, or goggles)
• Safety shoes (complete with steel toe capped and non-slip soles)
• Safety belt is forbidden. Working at height of more than 1.5 m, worker must be equipped with full
body harness. This equipment must have manufacturer certificate.
SUBCONTRACTOR shall submit their safety personnel’s CV for review and approval of CONTRACTOR.
Safety personnel must be competent person who holds safety certification or at least have attended
professional safety education.
SUBCONTRACTOR shall allocate a particularbudget as safey rewards for their employee and it shall be
distributed if any safety target is achieved.
SUBCONTRACTOR shall during the progress of the Work maintain all area in a neat, clean and orderly
condition, particularly when working in Existing Plant Area (if any). Coating materials, wrapping, rags, or debris
of any kind shall not be permitted to accumulate or be allowed to remain in the Construction Area. Upon
completion of any part or portion of the Work, SUBCONTRACTOR shall promptly remove all debris that may
have accumulated in the performance of the Work, as well as equipment, tools, temporary structures and
construction material not required in the area for later stages of the Work. Upon Completion of the Work,
SUBCONTRACTOR shall, as directed, satisfactorily remove all its equipment, building, etc., from the facility of
the Work used for construction purpose.
A half day in each week shall be observed as a general cleaning day for the SUBCONTRACTOR. All
supervisors and workers shall make clean the site plant working area under the supervisions of
CONTRACTOR. In addition to this, daily cleaning should be performed by SUBCONTRACTOR using proper
tools and enough manpower. If unsatisfactory action by SUBCONTRACTOR is performed, CONTRACTOR will
take action and all cost will be back charged to SUBCONTRACTOR.
The SUBCONTRACTOR shall carry out and complete the preparatory work, permanent work, and finishing
work in maximum 18 month. The BIDDER shall develop and submit the Construction Schedule (until level 3)
based on above requirement with his quotation:
• For Site Preparation Works, construction shall be undertaken from Month 7 until Month 11
• For Road and Drainage Works, construction shall be undertaken from Month 9 until Month 11
• For Pipeline Works, construction shall be undertaken from Month 10 until Month 22.
• For Electrical & Instrument Installation Works, construction shall be undertaken from Month 10 until
Month 22
• For Precommissioning Works, construction shall be undertaken from Month 23 until Month 24
The quotation shall be in Indonesian Rupiah currency and prepared in two version (Work Item Wise and Cost
Item Wise) in accordance with the instructions stated below by using the quotation form specified in
Attachment-1, form no 2A, 2B, 3A, and 3B of this requisition.
The price to be quoted in the Cost Item Wise shall consist of direct cost, transportation cost, indirect cost, taxes
and duties other than VAT, overhead and profit. The total price of the Cost Item Wise shall be same as total
price of the Work Item Wise.
Price allocation for Direct Cost and Indirect Cost in Cost Item Wise shall be in accordance with the
definition stated below. If there will be any item other than those stipulated in this Requisition, it shall be
notified to CONTRACTOR who will give appropriate instruction for correct price allocation.
1. Direct Cost
a. Direct materials
Direct materials shall mean the materials procured by SUBCONTRACTOR for the work,
which is to be installed permanently.
The material cost shall include such as but not limited to:
• Packing
• Inspection
• Shop testing
• Procurement fee
• Other charges and duties
b. Direct labour
Direct labour shall be the personnel engaged in direct work at the Job site below supervisor
level such as, but not limited to the following:
• Skilled and unskilled labour and their foremen
• Construction equipment operators and drivers
• Labour for direct temporary work such as:
o Scaffolding
o Position of safety measures
o Clean-up of construction area
The following shall be included in the direct labour cost:
• Salaries
• Burdens
• Allowance
• Commissions
15.2. Escalation
Both unit prices for Direct Work and Indirect Work shall not be adjusted under any circumstances for the
reason of escalation, inflation or fluctuation in currency exchange rates.
The SUBCONTRACTOR shall carry out and complete the work in a manner which assures quality, schedule,
and safety. For this purpose, execution procedure below shall be followed by the SUBCONTRACTOR.
Note:
Above procedure will be issued to the SUBCONTRACTOR within one month after the contract award.
SUBCONTRACTOR shall follow those procedures without any increment of the contract price.
The SUBCONTRACTOR shall, in the course of the execution of the work, prepare and submit the documents
and reports stipulated in Table-3. These documents will become one of the tools for controlling the work and
assure satisfaction execution of the Work.
Table - 8
SUBCONTRACTOR’S DOCUMENT SUBMISSION
FOR APPROVAL
DOCUMENT
(DUE AFTER AWARD)
1.EXECUTION PROCEDURE
a) Organization chart and resumes of key personnel 2 Weeks
b) Manpower mobilization schedule by chart and nationality 2 Weeks
c) Construction equipment mobilization schedule 2 Weeks
d) Layout drawing of temporary facilities and construction access 2 Weeks
e) Premobilization check list compliance 2 Weeks
f) Construction method For each particular Work 2 Weeks
before execution.
2. SCHEDULE CONTROL
a) 3 month look-ahead schedule Monthly
b) Monthly construction schedule Monthly
c) 2 Weeks schedule (present & next) Weekly
d) Consumption schedule of water and electric power Monthly
e) Equipment and materials shipping schedule Monthly
f) Schedule of materials to be supplied by SUB-CONTRACTOR Monthly
3. QUALITY CONTROL
Quality control procedure 1 Month
7. REPORT / OTHERS
a) Daily manpower / Equipment reports and report Daily
b) Weekly report Weekly
c) Accident report Weekly
d) Minutes of meeting Within 3 days
e) Punch list 1 Month prior to Completion
f) Shop / working drawing 1Month (depend onschedule)
g) Mark-up drawing and Final Survey Result Two days after final joint survey
(as attachment of Progress
Report)
h) Close-out report 1 week after the completion
17. BILL OF QUANTITY
The BIDDER shall submit the quotation using the following forms, but not limited to:
FORM NO DESCRIPTION
1 Cover Letter
2A/B Cost Summary / Cost Breakdown-Work Item Wise.
3A/B Cost Summary / Cost Breakdown-Cost Item Wise.
4 Supervision and Labor Rate
5 Construction Equipment and Vehicles Rate
6 Direct Manpower Schedule
7 Indirect Manpower Schedule
8 List and Schedule of Construction Equipment and Vehicles
9 Detail of Construction Schedule and Productivity
10 Project and Site Organization Chart
11 Project Key Personnel Resume
12 List of Proposed Local Vendor/Subcontractor to Joint the Work
13 Construction Execution Strategy
14 Construction Method
15 Construction Productivity and Calculation
16 Company Profile and Experience Statement