Professional Documents
Culture Documents
GRP General Procedure (EWS)
GRP General Procedure (EWS)
WORKING PROCEDURE
FOR
GRP LINING
Client
TCI-Sanmar
Date : 7-August-2018
0
WORKING PROCEDURE
Content
1. Introduction…………………………………………………...... 1
2. General………………………………………….....…………….4
2.1 Planning…………………...……...……………………………..4
2.2 Equipment protection and clean up …………...…………….…. 4
2.3 Coating materials………………………………………..……....5
2.4 Health, Safety and environment……...…………………………. 5
2.5 Blast cleaning ………………………………………………........ 6
2.6 Final surface condition…………………………………….......... 7
2.7 Inspections and testing………...…………………………...…... 7
2.8 Pre-blasting preparations ………………………………...……... 9
2.9 Working Conditions………………………………………….......10
2.10 Tools………………………………………………………..….. 11
2.11 materials...……………………………………….…………….. 13
1
WORKING PROCEDURE
1. Introduction
2
WORKING PROCEDURE
4. Second layer of glass fibre (CSM) is placed over the first layer
with resin applied over it.
3
WORKING PROCEDURE
2. General
2.1 Planning
All activities shall be fully incorporated in the fabrication plan.
4
WORKING PROCEDURE
7
WORKING PROCEDURE
8
WORKING PROCEDURE
9
WORKING PROCEDURE
Repairs and coating can be carried out both indoors and out
under a variety of circumstances. It is advisable to work under
cover whenever possible so that some control over working
conditions can be exercised particularly protection from rain.
However, one rule must be observed with all repair work. The
surface on which the repair is to be carried out MUST be dry.
Failure to ensure this will result in the repair refusing to stick to
the original laminate and the job will have to be repeated.
11
WORKING PROCEDURE
12
WORKING PROCEDURE
14
WORKING PROCEDURE
15