LANJUTAN PEKERJAAN FINISHING RUMAH TINGGAL

BAPAK GUSTI NGURAH DAMENA


Jln.Mina Utama Pesanggaran

NO URAIAN PEKERJAAN VOLUME SATUAN HARGA JUMLAH


SATUAN(RP) HARGA(RP)
I PEKERJAAN GARASE
1 GALIAN TELAPAK 5 M3 135.000 675.000
2 GALIAN PONDASI MENERUS 23 M1 35.000 805.000
3 PASANG PONDASI 6.75 M3 165.000 1.113.750
4 URUGAN/PEMERETAAN TANAH 36.4 M2 20.000 728.000
5 GALIAN PONDASI PELINGGIH 1 M3 125.000 125.000
6 PASANG PONDASI PELINGGIH 1 M3 135.000 135.000
JUMLAH 3.581.750
II PEKERJAAN BETON
1 BETON TELAPAK 1.2 M3 800.000 960.000
2 BETON SLOOP 1.38 M3 900.000 1.242.000
3 BETON KOLOM 1.35 M3 975.000 1.316.250
4 BETON BALOK 2 M3 1.050.000 2.100.000
5 BETON DAK/PLAT 3 M3 1.200.000 3.600.000
6 BETON BALOK TUMPUAN ATAP 14 M1 80.000 1.120.000
7 BETON TOPIAN 12 M1 80.000 960.000
8 BETON BALOK PRAKTIS 7.5 M1 70.000 625.000
9 KOLOM PRAKTIS 6.5 M1 65.000 422.500
10 BOBOK BETON PLAT LAMA LS LS - 750.000
11 BETON RABATAN 32.2 M2 40.000 1.288.000
12 BETON PENUTUP PIPA 6.5 M1 50.000 325.000
JUMLAH 14.708.750
III PEK.TEMBOK/PLESTER/ACI
1 PASANG BATA MERAH 25 M2 40.000 1.000.000
2 PEKERJAAN PLESTER 38.7 M2 27.500 1.064.250
3 ACIAN 15 M2 20.000 300.000
4 ACIAN TOPIAN 12 M2 30.000 240.000
5 BENANG TOPIAN 32 M1 12.500 400.000
6 PLESTER TALANG DAK 19 M2 35.000 660.000
7 ACIAN TALANG DAK 19 M2 17.500 332.500
8 ACIAN BETON BALOK 16 M2 40.000 640.000
9 ACIAN BENANGAN 60.4 M1 12.500 755.000
10 PASANG KERAMIK DINDING 19.3 M2 85.000 1.640.500
11 PASANG KERAMIK LANTAI 29.9 M2 60.000 1.794.000
12 PEKERJAAN GOT SAMPING GRSE 7 M1 50.000 350.000
JUMLAH 9.176.250
TOTAL 27.446.750

1
NO URAIAN PEKERJAAN VOLUME SATUAN HARGA JUMLAH
SATUAN(RP) HARGA(RP)
IV PEKERJAAN TERAS DEPAN
1 GALIAN TELAPAK 6.25 M3 125.000 781.250
2 GALIAN PONDASI 7 M1 35.000 245.000
3 PASANG PONDASI 5 M3 175.000 875.000
JUMLAH 1.901.250
V PEKERJAAN BETON
1 BETON TELAPAK 1.56 M3 800.000 1.248.000
2 BETON SLOOP 0.45 M3 900.000 405.000
3 BETO KOLOM 1.2 M3 1.200.000 1.440.000
4 BETON BALOK 0.64 M3 1.200.000 768.000
5 BETON PLAT/DAK 1.08 M3 1.200.000 1.296.000
6 BETON BALOK NGAMBANG 0.8 M3 1.200.000 960.000
7 BETON KOLOM ATAS 0.7875 M3 1.200.000 945.000
8 BETON RING+ KOLOM PRAKTIS 11.8 M1 70.000 826.000
9 BETON TOPIAN 4 M3 80.000 320.000
10 BETON RABATAN 9 M2 40.000 360.000
JUMLAH 8.568.000
VI PEKERJAAN TEMBOK/PLESTER/ACI
1 PASANG BATA LANTAI 2 13.12 M2 45.000 590.000
2 PEKERJAAN PLESTER 26.24 M2 30.000 787.200
3 ACIAN 34 M2 20.000 524.000
4 ACIAN BENANGAN 63.6 M1 12.500 795.000
5 PLESTER KOLOM ATAS 10.8 M2 90.000 972.000
6 ACIAN KOLOM ATAS 10.8 M2 30.000 324.000
7 ACIAN TOPIAN 5.6 M2 30.000 168.000
8 PASANG BATA SAMPING PINTU 4.2 M2 45.000 189.000
9 PLESTER BATA SAMPING PINTU 8.4 M2 30.000 252.000
10 ACIAN SAMPING PINTU 8.4 M2 20.000 168.000
11 BOBOKAN PENYAMBUNG BETON LS LS 300.000 300.000
12 KERAMIK LANTAI 1 8.5 M2 60.000 510.000
13 KERAMIK LANTAI 2 8.5 M2 60.000 510.000
JUMLAH 6.089.200
TOTAL 16.558.450

2
NO URAIAN PEKERJAAN VOLUME SATUAN SATUAN JUMLAH
HARGA(RP) HARGA(RP)
VII FINISHING LANTAI 1
1 PS. GRANIT KAMAR MANDI UTAMA 55 M2 85.000 4.675.000
2 ACI+PLESTER LUBANG PINTU/JENDELA 29.2 M1 20.000 580.000
3 BENANGAN 54.6 M1 12.500 682.500
4 PS.GRANIT LANTAI R.TIDUR 53.25 M2 60.000 3.195.000
5 KERAMIK PLIN LANTAI RUANG TIDUR 31.3 M1 27.500 860.750
6 BOBOKAN PLIN 31 M1 10.000 310.000
7 BENANGAN TOPIAN 2.4 M1 12.500 30.000
8 BETON TOPIAN 1 M1 175.000 175.000
9 ACIAN TOPIAN 1.5 M2 30.000 45.000
10 PEKERJAAN GRANIT DAPUR 72.54 M2 70.000 5.077.800
11 PEKERJAAN GRANIT R. KELUARGA+TIDUR P 95.64 M2 60.000 5.738.400
12 BOBOK LUBANG JENDELA DAPUR LS LS 350.000 350.000
13 PLESTER+ACI LUBANG JENDELA 8.40 M1 45.000 378.000
14 BENANGAN 16.8 M1 12.500 210.000
15 JENDELA SAMPING DAPUR 4.6 M1 20.000 92.000
16 BENANGAN 12.8 M1 12.500 160.000
17 BETON PEKERJAAN BALOK RUANG 6 M1 90.000 540.000
18 BETON KOLOM 32 M1 80.000 256.000
19 PLESTER LUBANG PINTU 98 M1 20.000 196.000
20 BENANGAN 19.6 M1 12.500 245.000
21 BETON TOPIAN 4 M1 90.000 360.000
22 ACIAN TOPIAN 9.2 M2 30.000 276.000
23 BENANGAN 20 M1 12.500 125.000
24 JENDELA PLESTER ACI 6 M1 20.000 120.000
25 BENANGAN 12 M1 12.500 150.000
26 PEKERJAAN KERAMIK PLIN LANTAI 87.05 M1 27.500 2.448.875
27 BETON MEJA DAPUR 4.4 M1 125.000 550.000
28 PASANG BATA KAKI MEJA DAPUR 1.56 M2 40.000 62.400
29 PLESTER KAKI MEJA 3.12 M2 40.000 124.800
30 ACI KAKI MEJA 3.12 M2 30.000 93.600
31 BENANGAN MEJA DAPUR 4.8 M1 12.500 60.000
32 TEMBOK PINTU DAPUR 1.5 M2 40.000 60.000
33 PLESTER 3 M2 27.500 82.500
34 ACIAN 3 M2 20.000 60.000
35 ACIAN LUBANG PINTU 5.7 M1 20.000 114.000
36 BETON RING PRAKTIS 1.5 M1 60.000 90.000
JUMLAH 28.573.625
TOTAL 28.573.625

3
NO URAIAN PEKERJAAN VOLUME SATUAN SATUAN JUMLAH
HARGA(RP) HARGA(RP)
VIII PEKERJAAN 2 BUAH KAMAR MANDI LT I
1 GALIAN SLOOP 7.4 M1 30.000 222.000
2 BETON SLOOP PRAKTIS 7.4 M1 60.000 444.000
3 BETON KOLOM PRAKTIS 19.2 M1 60.000 1.152.000
4 PEKERJAAN TEMBOK 28.68 M2 40.000 1.147.500
5 PEKERJAAN PLESTER 53.36 M2 27.500 1.467.400
6 LUBANG PLESTER PINTU+ACI 22.6 M1 20.000 452.000
7 BENANGAN 45.2 M1 12.500 565.500
8 PEKERJAAN KERAMIK KAMAR MANDI 43.5 M2 85.000 3.697.500
9 PLESTER KOLOM STRUKTUR 21 M2 40.000 840.000
10 ACIAN 17 M2 20.000 340.000
11 BENANGAN 72 M1 12.500 900.000
JUMLAH 11.227.900
TOTAL 11.227.900

4
NO URAIAN PEKERJAAN VOLUME SATUAN HARGA JUMLAH
SATUAN(RP) HARGA(RP)
IX RUANG SAUNA+TANGGA LANTAI II
1 PASANG KERAMIK LANTAI 30.88 M2 70.000 2.161.600
2 KERAMIK PLIN 13 M1 22.500 292.500
3 PLESTER LUBANG PINTU+ACI 8.80 M1 20.000 176.000
4 ACIAN BENAGAN 17.60 12.500 220.000
5 BETON BALOK AMBANG 4 M1 90.000 360.000
6 BETON SAMPING KUSEN 6 M1 55.000 330.000
JUMLAH 3.540.100
X KAMAR MANDI SAUNA
1 KERAMIK DINDING 28.8 M2 85.00 2.448.000
2 KERAMIK LANTAI KM MANDI 5.75 M2 85.000 488.750
3 BETON MEJA WASHTAFEL 1.10 M1 175.000
4 PLESTER LUBANG PINTU 5.8 M1 20.000 116.000
5 BENANGAN 9.2 M1 12.500 115.000
JUMLAH 3.342.750
XI TAMBAHAN RUANG SAUNA
1 BETON TOPIAN 6.50 M1 90.000 585.000
2 ACIAN TOPIAN 9.1 M2 25.000 277.500
3 BENANGAN TOPIAN 14.20 M1 12.500 177.500
JUMLAH 1.040.000
XII PK.KOLOM+BALOK SAMPNG T.BESI
1 PK.BETON KOLOM+BALOK PRAKTIS 25 M1 70.000 1.750.000
2 PEKERJAAN PLESTER 15 M2 40.000 600.000
3 PEKERJAAN ACIAN 17.85 M2 30.000 535.500
4 BENANGAN 122 M1 12.500 1.400.000
5 KOLOM STRUKTUR ACI 2.88 M2 30.000 86.400
6 BENANGAN 12.8 M1 12.500 160.000
7 BUNGKUS PIPA/COR 12.5 M1 30.000 375.000
8 PLESTER+ACI 12.5 M1 25.000 312.500
9 BENANGAN 12.5 M1 12.500 156.250
JUMLAH 5.375.650
TOTAL 13.298.500

5
NO URAIAN PEKERJAAN VOLUME SATUAN HARGA JUMLAH
SATUAN(RP) HARGA(RP)
XIII RUANG TIDUR BARAT LANTAI II
1 UBAH RUANG PINTU/BOBOK LS LS 75.000 75.000
2 PS.TEMBOK 2.5 M2 40.000 100.000
3 PLESTER 5 M2 30.000 150.000
4 ACIAN 5 M2 17.500 87.500
5 ACI+PLESTER LUBANG PINTU 5.8 M1 20.000 116.000
6 BENANGAN 116 M1 12.500 145.000
7 BETON BALOK TOPIAN 5 M1 90.000 450.000
8 BETON TOPIAN 3 M1 90.000 270.000
9 ACIAN TOPIAN 4.2 M2 25.000 105.000
10 BENANGAN TOPIAN 9 M1 12.500 112.500
11 PLESTER LUBANG JENDELA 6.8 M1 20.000 136.000
12 BENANGAN 13.2 12.500 165.000
13 PS.KERAMIK DINDING KM MANDI 30 M2 85.000 2.550.000
14 PS KERAMIK LANTAI KM MANDI 6.6 M2 85.000 561.000
15 BOBOK TEMBOK PLIN 10 M1 10.000 100.000
16 KALI AIR+PS. PLIN KERAMIK 25 M1 27.500 687.500
JUMLAH 5.810.500
XIV PS.KERAMIK LANTAI II
1 RUANGAN KELUARGA 61.31 M2 60.000 3.678.600
2 BETON KOLOM L.II TAMBAHAN T.KAP 6.5 M1 70.000 455.000
3 BETON BALOK TAMBAHAN TOPIAN 3.6 M1 90.000 324.000
4 PLESTER KOLOM 3.25 M2 30.000 97.500
5 PLESTER+ACI LUBANG PINTU 3 M1 20.000 600.000
6 BENANGAN 18.6 M1 12.500 232.500
7 KERAMIK PLIN 24 M1 22.500 540.000
JUMLAH 5.927.600
TOTAL 11.738.100

6
PEKERJAAN KERAMIK LANTAI II
NO URAIAN PEKERJAAN VOLUME SATUAN HARGA JUMLAH
SATUAN(RP) HARGA(RP)
XV PK.KERAMIK RUANG TIDUR BARAT DAYA
1 PK. KERAMIK DINDING 30 M2 85.000 2.550.000
2 PK.KERAMIK LANTAI KM 7.59 M2 60.000 637.500
3 PK. KERAMIK LANTAI 32.4 M2 60.000 1.944.000
4 KERAMIK PLIN 24.5 M1 22.500 551.250
JUMLAH 5.682.750
XVI PK.JENDELA+PINTU. KERAMIK PLIN
1 PLESTER LUBANG JENDELA+ACI 8.34 M1 20.000 166.800
2 ACIAN BENANGAN 16.68 M1 12.500 208.500
JUMLAH 375.300
XVII UBAH TEMPAT PINTU KAMAR
1 BONGKAR/BOBOK LUBANG LS LS 125.000 125.000
2 PS. TEMBOK KEMBALI 3.9 M2 40.000 156.000
3 PLESTER 7.8 M2 30.000 234.000
4 ACIAN 7.8 M2 17.500 136.500
5 PK.PLESTER LUBANG PINTU+ACI 5.8 M1 85.000 116.000
6 ACIAN BENANGAN 11.6 M1 12.500 145.000
7 PINTU KM PLESTER 5.8 M1 20.000 116.000
8 ACIAN BENANGAN 5.8 M1 12.500 72.500
9 BOBOK LUBANG JENDELA LS LS 200.000 200.00O
10 BETON TOPIAN 1.5 M1 90.000 135.000
11 ACIAN TOPIAN 1.2 M2 30.000 36.000
12 BENANGAN TOPIAN 4.6 M1 12.500 57.000
13 PLESTER SAMPING LUBANG JENDELA +ACI 4.2 M1 15.000 63.000
14 BENANGAN JENDELA 5.4 M1 12.500 67.000
JUMLAH 1.459.000
NO URAIAN PEKERJAAN VOLUME SATUAN HARGA JUMLAH
SATUAN(RP) HARGA(RP)
1 BOBOK PLESTER BETON DAK ATAS DAPUR 7.5 M2 35.000 262.500
2 WATER PROPING 7.5 M2 15.000 112.500
JUMLAH 375.000
XVIII KAMAR TIDUR TIMUR LANTAI II
1 KRAMIK DINDING KM 28.5 M2 85.000 2.422.500
2 KRAMIK LANTAI KM 6 M2 85.000 510.000
3 BOBOK LUBANG JENDELA LS LS 125.000 125.000
4 PLESTER+ACI LUBANG JENDELA 3.6 M1 20.000 72.000

7
5 ACI BENANGAN 7.2 25.000 90.000
6 GRANIT KM TIDUR 40 M2 60.000 2.400.000
7 PK GRANIT PLIN+ACI TALI AIR 26 M1 22.500 585.000
8 BOBOK TEMBOK 26 M1 10.000 260.000
9 PK. BETON BALOK PENGUAT TOPIAN 4.5 M1 90.000 405.000
10 BETON TOPIAN 3 M1 90.000 270.000
11 PLESTER+ACIAN TOPIAN 3.9 M2 25.000 97.500
12 BENANGAN JENDELA+BENANGAN TOPIAN 21.4 M1 12.500 267.500
13 ACI+PLESTER LUBANG JENDELA 63.5 M1 20.000 127.000
14 PLESTER+ACI LUBANG PINTU 5.8 M1 20.000 116.000
15 BENANGAN 4.6 M1 12.500 145.000
16 TAMBAHAN BALOK AMBANG TUMPUAN 8 M1 95.000 760.000
17 KOLOM 4.5 M1 95.000 427.500
JUMLAH 9.080.000
XIX PEKERJAAN LANTAI II
1 TEMBOK PEMBATAS TIMUR DAN BARAT 4.5 M2 55.000 247.500
2 KOLOM+RING 8 M2 60.000 480.000
3 PLESTER 4.65 M2 40.000 186.000
4 ACIAN 4.65 M2 30.000 139.500
5 PASANG KERAMIK DINDING 5.2 M2 90.000 468.000
JUMLAH 1.521.000

NO URAIAN PEKERJAAN VOLUME SATUAN HARGA JUMLAH


SATUAN(RP) HARGA(RP)
PK.BETON WASHTAFEL, RABAT, WATER PROPING
1 TOTAL BETON WASHTAFEL LANTAI II 7 M1 125.000 875.000
2 RABAT PENINGGI LANTAI 20.15 M2 40.000 806.000
3 WATER PROPING DINDING KM.MANDI 45 M2 20.000 900.000
4 FLOOR DRIN 8 BUAH 25.000 200.000
JUMLAH 2.781.000
TOTAL 21.274.050

8
PEKERJAAN LANJUTAN LANTAI III

NO URIAN PEKERJAAN VOLUME SATUAN HARGA JUMLAH


SATUAN(RP) HARGA(RP)
1 COR BETON PEPALIHAN DIATAS BATA MERAH 14 M1 95.000 1.330.000
2 PLESTER BETON PEPALIHAN 9.10 M2 40.000 364.000
3 ACIAN BETON PEPALIHAN 9.10 M2 30.000 273.000
4 ACIAN BENANGAN 70 M1 15.000 1.050.000
5 PLESTER TALANG BETON L.III 70.5 M2 40.000 2.820.000
6 WATER PROPING TALANG L.III 99.5 M2 30.000 2.985.000
JUMLAH 8.822.000
XX RUANG JEMUR
1 PK.PASANG TEMBOK 12.15 M2 45.000 546.750
2 PK. PLESTER DINDING 25.84 M2 30.000 775.200
3 ACIAN 25.84 M2 20.000 516.800
4 BENANGAN 21.10 M1 12.500 263.750
5 BETON KOLOM+BALOK PRAKTIS 15 M1 60.000 900.000
6 PK.PASANG BATA TANGGUL TALANG 31.35 M1 25.000 783.750
7 BENANGAN TANGGUL 62.70 M1 12.500 783.750
JUMLAH 4.570.000
XXI PEKERJAAN RUANG SETRIKA L.III
1 BONGKAR TEMBOK PELEBARAN KMR+LUBANG JENDELA LS LS 450.000 450.000
2 TAMBAHAN BALOK+KOLOM 4 M1 70.000 280.000
3 ACIAN BENANGAN 39.55 M1 12.500 494.375
4 RABAT PENINGGI LANTAI 12 M2 50.000 600.000
5 PASANG KERAMIK LANTAI 29 M2 55.000 1.595.000
6 PS. KERAMIK PLIN 24.5 M2 15.000 367.500
7 PK.CAT TEMBOK LUAR LS LS 1.000.000 1.000.000
JUMLAH 4.786.875

TOTAL 18.178.875

9
NO URAIAN PEKERJAAN VOLUME SATUAN HARGA JUMLAH
SATUAN(RP) HARGA(Rp)
XXI PK.TEMPAT KEBUN+PS.KERAMIK DINDING BELAKANG
1 GALIAN 8 M1 35.000 280.000
2 PASANG TEMBOK BAK 16 M1 45.000 720.000
3 BETON KEBUN ATAS 15 M1 115.000 1.725.000
4 PASANG KERAMIK DINDING 86 M2 85.000 7.310.000
5 PASANG BETAKO GOT/PLESTER ACI 12 M1 75.000 840.000
JUMLAH 10.875.000
XXII PEKERJAAN GRONTENG
1 PASANG BATAKO 13.12 M2 40.000 524.800
2 PEKERJAAN BETON GRONTENG 3.12 M3 1.050.000 3.276.000
3 PEKERJAAN KERAMIK 16.8 M2 85.000 1.428.000
4 WATER PROPING 16.8 M2 25.000 420.000
JUMLAH 5.648.800
XXII PEKERJAAN HALAMAN DEPAN
1 PLANSIR+KERUK TANAH PEMERTAAN LANTAI 50 M2 50.000 2.500.000
2 PASANG KERAMIK LANTAI 50.5 M2 60.000 3.030.000
JUMLAH 5.530.000
XXIII PEKERJAAN BANGUNAN SUCI/MERAJAN
1 BETON RABAT LANTAI II 9 M2 50.000 450.000
2 PEKERJAAN KERMIK LANTAI I + LANTAI II 47.3 M2 60.000 2.838.000
3 PEKERJAAN KERAMIK DINDING 12.7 M2 85.000 1.079.500
4 PEKERJAAN KERAMIK TANGGA 5.25 M2 95.000 498.500
5 KERAMIK PLIN GIDAT 16 M1 15.000 240.000
6 PLESTER LEHER TANGGA +ACI 16 M1 10.000 160.000
7 ACIAN BAWAH TANGGA 7.25 M2 30.000 217.500
8 PLESTER BETON TANGGA 7.25 M2 50.000 362.500
9 BENANGAN 20 M1 12.500 250.000
JUMLAH 6.096.000
XXIV PEKERJAAN SEPITENG
1 GALIAN 10 M3 150.000 1.500.000
2 PASANG BATAKO 18 M2 40.000 720.000
3 PLESTER 12 M2 30.000 360.000
4 ACIAN 16 M2 20.000 320.000
5 RABAT 4 M2 50.000 200.000
6 ANGKUT TANAH BEKAS GALIAN LS LS 600.000 600.000
7 COR/BETON PENUTUP SEPITENG 0.9 M2 80.000 720.000
JUMLAH 4.420.000
XXV PEKERJAAN GOT PINGGIR JALAN
1 GALI GOT BOBOK BETON 17 M1 50.000 850.000
2 SERVIS GOT+COR TUTUP 17 M1 85.000 1.445.000
3 PLESTER TEMPAT UKIRAN PAGAR 6 M2 30.000 180.000
JUMLAH 2.475.000
TOTAL 35.044.800

10
NO URAIAN PEKERJAAN VOLUME SATUAN HARGA JUMLAH
SATUAN(RP) HARGA(Rp)
XXVI PK.GRANIT MEJA DAPUR/GRANIT MEJA KM.MANDI
1 GRANIT MEJ A DAPUR 6 M1 175.000 1.050.000
2 GRANIT DINDING DAPUR 7.5 M1 175.000 1.312.500
3 GRANIT MEJA KAMAR MANDI(TOTAL 5 KM.MANDI) 7 M1 175.000 1.225.000
4 PEKERJAAN TEMPAT SABUN KM.MANDI 7 M1 60.000 420.000
JUMLAH 4.007.500

NO URAIAN PEKERJAAN VOLUME SATUAN HARGA JUMLAH


SATUAN(RP) HARGA(Rp)
PEKERJAAN TAMBAHAN
1 SERVIS ATAP BUGBUGAN+BOCORAN LS LS 6.000.000 6.000.000
2 SERVIS PIPA+CAT DI PENCUCIAN TUAK ILANG LS LS 900.000 900.000
JUMLAH 6.900.000
TOTAL 10.907.500

11
GRAND TOTAL
LAMPIRAN JUMLAH TOTAL(RP)
LAMPIRAN 1 27.466.750
LAMPIRAN 2 16.558.450
LAMPIRAN 3 28.573.625
LAMPIRAN 4 11.227.900
LAMPIRAN 5 13.298.500
LAMPIRAN 6 11.738.100
LAMPIRAN 8 21.274.050
LAMPIRAN 9 18.178.875
LAMPIRAN 10 35.044.800
LAMPIRAN 11 10.907.500
TOTAL 194.268.550

TABANAN,05 JUNI 2017

( I MADE SUANDI )