ILUBA SWIP

Tabuk City, Kalinga


VOLUMETRIC COMPUTATION

A. DAM/ RESERVOIR WORKS:


101 Mobilization & Demobilization = Lump sum

102 CLEARING & GRUBBING


a.) Area
a-1) Creek Bed Considering L= 120 m., ave. w = 6m
Area = ( L X W
= ( 100 X 6
Area = 600 sq.m
600 sq.m
a-2) Right abbutment facing down stream considering L=120m., Ave. W= 90m.
Area = ( Ave.W X L
= ( 90 X 100
Area = 9,000 sq.m
9,000 sq.m
a-3) left abbutment facing down stream considering L=120m., Ave W= 80m.
Area = ( Ave.W X L
= ( 80 X 100
Area = 8,000 sq.m
8,000 sq.m
a-4) Along Spillway Channel considering L=150m, Ave w = 15m.
Area = ( Ave.W X L
= ( 15 X 130
Area = 1,950 sq.m
1950 sq.m
Total Area for Clearing and Grubbing
Area = 19,550.00 sq.m

103 DIVERSION AND CARE OF RIVER DURING CONSTRUCTION = Lumpsum

104 EXCAVATION AND FOUNDATION PREPARATION


a.) Common Excavation
A. SPILLWAY:
A-1) (by end Area) Using Authocad
@ Sta. 0-020 to 0-010
Volume = [( A1+ A2) / 2.00 X
Volume = [( 27.1300 + 30.2500 ) /
Volume ................................... =

@ Sta. 0-010 - 0+000


Volume = [( A1+ A2) / 2.00 X
Volume = [( 30.2500 + 34.0700 ) /
Volume ................................... =

@ Sta. 0+000 - 0+010


Volume = [( A1+ A2) / 2.00 X
Volume = [( 34.0700 + 34.0400 ) /
Volume ................................... =

@ Sta. 0+010 - 0+020


Volume = [( A1+ A2) / 2.00 X
Volume = [( 34.0400 + 42.0500 ) /
Volume ................................... =

@ Sta. 0+020 - 0+030


Volume = [( A1+ A2) / 2.00 X
Volume = [( 42.0500 + 37.7200 ) /
Volume ................................... =

@ Sta. 0+030 - 0+040


Volume = [( A2+ A3) / 2.00 X
Volume= [( 37.7200 + 33.5700 ) /
Volume ................................... =

@ Sta. 0+040 - 0+050


Volume = [( A3+ A4) / 2.00 X
Volume= [( 33.5700 + 52.1500 ) /
Volume ................................... =

@ Sta. 0+050 - 0+060


Volume = [( A3+ A4) / 2.00 X
Volume= [( 52.1500 + 77.7500 ) /
Volume ................................... =

@ Sta. 0+060 - 0+070


Volume = [( A3+ A4) / 2.00 X
Volume= [( 77.7500 + 36.8400 ) /
Volume ................................... =

@ Sta. 0+070 - 0+080


Volume = [( A3+ A4) / 2.00 X
Volume= [( 36.8400 + 55.3600 ) /
Volume ................................... =

@ Sta. 0+080 - 0+090


Volume = [( A3+ A4) / 2.00 X
Volume= [( 55.3600 + 50.7000 ) /
Volume ................................... =

@ Sta. 0+090 - 0+100


Volume = [( A3+ A4) / 2.00 X
Volume= [( 50.7000 + 56.9900 ) /
Volume ................................... =

@ Sta. 0+100 - 0+110


Volume = [( A3+ A4) / 2.00 X
Volume= [( 56.9900 + 51.8600 ) /
Volume ................................... =

@ Sta. 0+110 - 0+120


Volume = [( A3+ A4) / 2.00 X
Volume= [( 51.8600 + 27.1100 ) /
Volume ................................... =

@ Sta. 0+120 - 0+130


Volume = [( A3+ A4) / 2.00 X
Volume= [( 27.1100 + 15.8300 ) /
Volume ................................... =

Total Volume of Common Excavation Along Spillway ……………………. =

B.) ALONG DAM AXIS:


B-1) (by end Area) Using Autocad
@ Sta. 0+000 - 0+020
Volume = [( A1+ A2) / 2.00 X
Volume = [( 12.9300 + 27.6000 ) /
Volume ................................... =

@ Sta. 0+020 - 0+040


Volume = [( A1+ A2) / 2.00 X
Volume = [( 27.6000 + 24.0500 ) /
Volume ................................... =

@ Sta. 0+040 - 0+060


Volume = [( A1+ A2) / 2.00 X
Volume = [( 24.0500 + 36.9200 ) /
Volume ................................... =

@ Sta. 0+060 - 0+080


Volume = [( A2+ A3) / 2.00 X
Volume= [( 36.9200 + 27.3400 ) /
Volume ................................... =

@ Sta. 0+080 - 0+100


Volume = [( A3+ A4) / 2.00 X
Volume= [( 27.3400 + 51.5700 ) /
Volume ................................... =

@ Sta. 0+100 - 0+120


Volume = [( A3+ A4) / 2.00 X
Volume= [( 51.5700 + 17.2900 ) /
Volume ................................... =

@ Sta. 0+120 - 0+140


Volume = [( A3+ A4) / 2.00 X
Volume= [( 17.2900 + 3.9600 ) /
Volume ................................... =

Total Volume of Common Excavation Along Dam Axis ……………………. =

104-A OVERHOUL/DISPOSAL OF WASTE MATERIALS


a. Total area for clearing & grubbing x 0.30 mtrs min stripping depth =
Volume ................................... =

105 STRUCTURE BACKFILL


a) ALONG SPILLWAY WORKS: (by end Area) Using Authocad
@ Sta. 0-020 to 0-010
Volume = [( A1+ A2) / 2.00 X
Volume = [( 3.2800 + 3.2800 ) /
Volume ................................... =

@ Sta. 0-010 - 0+000


Volume = [( A1+ A2) / 2.00 X
Volume = [( 3.2800 + 3.2800 ) /
Volume ................................... =

@ Sta. 0+000 - 0+010


Volume = [( A1+ A2) / 2.00 X
Volume = [( 3.2800 + 3.2800 ) /
Volume ................................... =

@ Sta. 0+010 - 0+020


Volume = [( A1+ A2) / 2.00 X
Volume = [( 3.2800 + 3.2800 ) /
Volume ................................... =

@ Sta. 0+020 - 0+030


Volume = [( A1+ A2) / 2.00 X
Volume = [( 3.2800 + 3.2800 ) /
Volume ................................... =
@ Sta. 0+030 - 0+040
Volume = [( A2+ A3) / 2.00 X
Volume= [( 3.2800 + 3.2800 ) /
Volume ................................... =

@ Sta. 0+040 - 0+050


Volume = [( A3+ A4) / 2.00 X
Volume= [( 3.2800 + 2.1800 ) /
Volume ................................... =

@ Sta. 0+050 - 0+060


Volume = [( A3+ A4) / 2.00 X
Volume= [( 2.1800 + 2.1800 ) /
Volume ................................... =

@ Sta. 0+060 - 0+070


Volume = [( A3+ A4) / 2.00 X
Volume= [( 2.1800 + 2.1800 ) /
Volume ................................... =

@ Sta. 0+070 - 0+080


Volume = [( A3+ A4) / 2.00 X
Volume= [( 2.1800 + 2.1800 ) /
Volume ................................... =

@ Sta. 0+080 - 0+090


Volume = [( A3+ A4) / 2.00 X
Volume= [( 2.1800 + 2.1800 ) /
Volume ................................... =

@ Sta. 0+090 - 0+100


Volume = [( A3+ A4) / 2.00 X
Volume= [( 2.1800 + 2.1800 ) /
Volume ................................... =

@ Sta. 0+100 - 0+110


Volume = [( A3+ A4) / 2.00 X
Volume= [( 2.1800 + 2.6400 ) /
Volume ................................... =

@ Sta. 0+110 - 0+120


Volume = [( A3+ A4) / 2.00 X
Volume= [( 2.6400 + 2.6400 ) /
Volume ................................... =

@ Sta. 0+120 - 0+130


Volume = [( A3+ A4) / 2.00 X
Volume= [( 2.6400 + 2.6400 ) /
Volume ................................... =

Grand Total Vol. for Common Material Backfill ................................... =

a.4.2) FILTER DRAIN


Clean Gravel
Volume = Area X L x
Volume = 0.1771 X 146.4 x
Volume = .......................... 51.87 cu.m
51.870 cu.m

Coarse Filter
Volume = Area X L x
Volume = 0.0523 X 146.4 x
Volume = .......................... 15.32 cu.m
15.32 cu.m

Find Filter
Volume = Area X L x
Volume = 2.3200 X 146.4 x
Volume = .......................... 679.48 cu.m
679.480 cu.m

106 DAM EMBANKMENT


a.) IMPERVIOUS MATERIALS (CLAY)
(by end Area) Using Authocad
@ Sta. 0+000 - 0+020
Volume = [( A1+ A2) / 2.00 X
Volume = [( 31.2800 + 12.6900 ) /
Volume ................................... =

@ Sta. 0+020 - 0+040


Volume = [( A1+ A2) / 2.00 X
Volume = [( 12.6900 + 12.6900 ) /
Volume ................................... =

@ Sta. 0+040 - 0+060


Volume = [( A1+ A2) / 2.00 X
Volume = [( 12.6900 + 259.0000 ) /
Volume ................................... =

@ Sta. 0+060 - 0+080


Volume = [( A2+ A3) / 2.00 X
Volume= [( 259.0000 + 200.8600 ) /
Volume ................................... =

@ Sta. 0+080 - 0+100


Volume = [( A3+ A4) / 2.00 X
Volume= [( 200.8600 + 108.9500 ) /
Volume ................................... =

@ Sta. 0+100 - 0+120


Volume = [( A3+ A4) / 2.00 X
Volume= [( 108.9500 + 18.7900 ) /
Volume ................................... =

@ Sta. 0+120 - 0+140


Volume = [( A3+ A4) / 2.00 X
Volume= [( 18.7900 + 0.0000 ) /
Volume ................................... =

Grand Total Vol. for Impervious Material Fill ................................... =

b.) RANDOM FILL (COMMON)


(by end Area) Using Authocad
@ Sta. 0+000 - 0+020
Volume = [( A1+ A2) / 2.00 X
Volume = [( 9.8700 + 9.8700 ) /
Volume ................................... =

@ Sta. 0+020 - 0+040


Volume = [( A1+ A2) / 2.00 X
Volume = [( 9.8700 + 78.9200 ) /
Volume ................................... =

@ Sta. 0+040 - 0+060


Volume = [( A1+ A2) / 2.00 X
Volume = [( 78.9200 + 299.4700 ) /
Volume ................................... =

@ Sta. 0+060 - 0+080


Volume = [( A2+ A3) / 2.00 X
Volume= [( 299.4700 + 313.6100 ) /
Volume ................................... =

@ Sta. 0+080 - 0+100


Volume = [( A3+ A4) / 2.00 X
Volume= [( 313.6100 + 76.4300 ) /
Volume ................................... =

@ Sta. 0+100 - 0+120


Volume = [( A3+ A4) / 2.00 X
Volume= [( 76.4300 + 4.2000 ) /
Volume ................................... =

@ Sta. 0+120 - 0+140


Volume = [( A3+ A4) / 2.00 X
Volume= [( 4.2000 + 12.9300 ) /
Volume ................................... =

Grand Total Vol. for Common Material Fill ................................... =

c)BOULDER RIPRAP
(by end Area) Using Authocad
@ Sta. 0+000 - 0+020
Volume = [( A1+ A2) / 2.00 X
Volume = [( 2.6200 + 1.2700 ) /
Volume ................................... =

@ Sta. 0+020 - 0+040


Volume = [( A1+ A2) / 2.00 X
Volume = [( 1.2700 + 8.7800 ) /
Volume ................................... =

@ Sta. 0+040 - 0+060


Volume = [( A1+ A2) / 2.00 X
Volume = [( 8.7800 + 10.5400 ) /
Volume ................................... =

@ Sta. 0+060 - 0+080


Volume = [( A2+ A3) / 2.00 X
Volume= [( 10.5400 + 10.5400 ) /
Volume ................................... =

@ Sta. 0+080 - 0+100


Volume = [( A3+ A4) / 2.00 X
Volume= [( 10.5400 + 10.2600 ) /
Volume ................................... =

@ Sta. 0+100 - 0+120


Volume = [( A3+ A4) / 2.00 X
Volume= [( 10.2600 + 1.5800 ) /
Volume ................................... =
@ Sta. 0+120 - 0+140
Volume = [( A3+ A4) / 2.00 X
Volume= [( 1.5800 + 0.0000 ) /
Volume ................................... =

Grand Total Vol. for Boulder riprap @ upper stream ................................... =

d) GRAVEL BEDDING
(by end Area) Using Authocad
d-1) @ dam embankment
@ Sta. 0+000 - 0+020
Volume = [( A1+ A2) / 2.00 X
Volume = [( 0.5300 + 0.2700 ) /
Volume ................................... =

@ Sta. 0+020 - 0+040


Volume = [( A1+ A2) / 2.00 X
Volume = [( 0.2700 + 1.9800 ) /
Volume ................................... =

@ Sta. 0+040 - 0+060


Volume = [( A1+ A2) / 2.00 X
Volume = [( 1.9800 + 2.5700 ) /
Volume ................................... =

@ Sta. 0+060 - 0+080


Volume = [( A2+ A3) / 2.00 X
Volume= [( 2.5700 + 2.5700 ) /
Volume ................................... =

@ Sta. 0+080 - 0+100


Volume = [( A3+ A4) / 2.00 X
Volume= [( 2.5700 + 2.4000 ) /
Volume ................................... =

@ Sta. 0+100 - 0+120


Volume = [( A3+ A4) / 2.00 X
Volume= [( 2.4000 + 0.3400 ) /
Volume ................................... =

@ Sta. 0+120 - 0+140


Volume = [( A3+ A4) / 2.00 X
Volume= [( 0.3400 + 0.0000 ) /
Volume ................................... =

Grand Total Vol. for Surface Gravel ................................... =

d-2) @ out let works


at Outlet stilling basin
Volume = thickness x width x
= 0.6 x 1.5 x
Volume = 3.81 cu.m

e) SAND BEDDING (Dam Crest)


@ Sta. 0+000 - 0+140 L = 86.00 m.
Volume = w x h x
6 x 0.1 x
Volume = 51.60 cu.m

f) Gravel Surfacing (Dam Crest)


@ Sta. 0+000 - 0+140 L = 140.00 m.
Volume = w x h x
6 x 0.3 x
Volume = 252.00 cu.m

g.) TOE DRAIN (by end area using autocad)


g-1) Boulders
Volume = Area X L
Volume = 17.08 X 90.0
Volume = .......................... 1537.20 cu.m
1,537.20 cu.m

g-2) Coarse Filter


Volume = Area X L
Volume = 6.00 X 90.0
Volume = .......................... 540.00 cu.m
540.00 cu.m

g-3) Fine Filter


Volume = Area X L
Volume = 2.38 X 90.0
Volume = .......................... 214.20 cu.m
214.200 cu.m

107 CONCRETE STRUCTURES


a. SPILL WAY CLASS "A" (3000 psi) "see schedule of dimensions"
a.1) Side Walls

STATION LENGTH DESIGNATION


sta. 0-020.00 A= 2.000
B= 0.350
C= 0.200 (( C + F )/2) x A + (( B+ C )/2)
TO 60.00
D= 0.150 x E + (D x B) =
E= 0.050
sta. 0+040.00 F= 0.150
STATION SLOPE DESIGNATION
sta. 0+040.00 LENGTH A 1.500
B= 0.350
C= 0.200 (( C + F )/2) x A + (( B+ C )/2)
TO
65.77 D= 0.150 x E + (D x B) =
E= 0.050
sta. 0+100.00 F= 0.150

STATION SLOPE DESIGNATION


sta. 0+100.00 LENGTH Ave. A= 1.750
B= 0.350
C= 0.200 (( C + F )/2) x A + (( B+ C )/2)
TO
10.69 D= 0.150 x E + (D x B) =
E= 0.050
sta. 0+110.00 F= 0.150

STATION LENGTH DESIGNATION


sta. 0+110.00 A= 2.000
B= 0.400
C= 0.250 (( C + F )/2) x A + (( B+ C )/2)
TO 10.00
D= 0.250 x E + (D x B) =
E= 0.100
sta. 0+120.00 F= 0.200

a.2) Flooring

STATION LENGTH DESIGNATION


sta. 0-000.00 a= 0.200
b= 1.000
TO 60.00 (( a * b ) * 2) + (c * d) =
c= 0.150
sta. 0+040.00 d= 2.000

STATION SLOPE DESIGNATION


sta. 0+040.00 LENGTH a= 0.200
b= 1.000
TO (( a * b ) * 2) + (c * d) =
76.44 c= 0.150
sta. 0+110.00 d= 2.000

STATION SLOPE DESIGNATION


sta. 0+110.00 LENGTH a= 0.350
b= 1.000
TO (( a * b ) * 2) + (c * d) =
10.00 c= 0.300
sta. 0+120.00 d= 2.000

a.2) Wing Wall


STATION LENGTH DESIGNATION
both sides A= 2.000
B= 0.350
C= 0.200
D= 0.150 (( C + F )/2) x A + ((( B+ C )/2)
sta. 0-000.00
6.00 E= 0.050 x E) + (D x B)+(axb) =
F= 0.150
(( C + F )/2) x A + ((( B+ C )/2)
sta. 0-000.00
6.00 x E) + (D x B)+(axb) =

a= 0.200
b= 1.000

STATION LENGTH DESIGNATION


both sides A= 2.000
B= 0.400
C= 0.250
D= 0.250 (( C + F )/2) x A + ((( B+ C )/2)
sta. 0+120.00
4.00 E= 0.100 x E) + (D x B)+(axb) =
F= 0.200
a= 0.350
b= 1.000

a.3) Cut of Wall


STATION LENGTH DESIGNATION
A= 0.200
sta. 0-000.00 12.00 a= 0.100 (A+a)/2 x h =
h= 1.500

STATION LENGTH DESIGNATION


A= 0.200
sta. 0+040.00 6.00 a= 0.100 (A+a)/2 x h =
h= 0.800

STATION LENGTH END AREA BY AUTO CAD

sta. 0+110.00 6.00 1.8851

STATION LENGTH DESIGNATION


A= 0.200
sta. 0+120.00 6.00 a= 0.100 (A+a)/2 x h =
h= 2.000

a.4) Chute Blocks

STATION no. of Blocks DESIGNATION


H= 0.600
sta. 0+110.00 3.00 L= 1.380 HxLxW=
W= 0.600

a.5) End Sill

STATION LENGTH DESIGNATION


A= 0.200
sta. 0+120.00 6.00 B= 0.100 (A+B)/2 x C =
C= 0.600

Total Vol. for Class A Concrete (Spillway): ................................... =

b. OUTLET WORKS CLASS "A" (3000 psi) "see details of OUTLET WORKS for the dimensions"
b.1) Inlet
b.1-1) Flooring
Volume = Thickness x Surface area of flooring
= 0.30 x ( 2.06 + 1.26 ) x 1.50
2
Volume = 0.75 cu.m.

b.1-2) Side Walls "Both Sides"


Volume = Thickness x Surface area of side wall x no. of sides
= 0.13 x ( 3.00 x 2.40 ) x 2.00
2
Volume = 0.94 cu.m.

b.1-3) Cut of wall


Volume = Thickness x Surface area of cut of wall
= 0.13 x 0.450 x 2.40
Volume = 0.14 cu.m.

b.1-4) Head wall


Volume = (Thickness x Surface area of head wall) - (Area of pipe x length)
= ( 0.30 x 1.26 x 1.50 ) - ( 3.14 x 0.15 ^2
Volume = 0.55 cu.m.

b.2) Outlet
b.2-1) Flooring
Volume = Thickness x Surface areas of flooring "3 stages"
= ( 0.13 x 1.70 x 1.33 ) + ( 0.15 x
( 0.10 x 0.66 x 0.87 )
Volume = 1.03 cu.m.

b.2-2) Side walls "Both sides"


Volume = Thickness x Surface areas of side wall x 2 "3 stages, Both sides"
[2 x ( 0.13 x 1.33 x 1.18 )] + {[2 x ( 0.15 x
( 0.15 x 0.50 x 1.38 )} + [2 x ( 0.13 x
Volume = 1.57 cu.m.

b.2-3) Head walls


Volume = Thickness x Surface areas of head wall "3 phases"
= ( 0.13 x 1.44 x 1.18 ) + ( 0.15 x
[( 0.15 x 2.75 x 1.38 ) - ( 0.15 x 0.50 x
Volume = 1.08 cu.m.

b.2-4) Cut of Wall


Volume = Thickness x Surface areas of Cut of wall
= ( 0.13 x 0.70 x 0.66 )
Volume = 0.06 cu.m.

b.2-5) Dissipator
Volume = Thickness x Total Surface area of Dissipator
= 0.13 x [( 0.28 x 1.44 ) + ( 0.64 x
Volume = 0.17 cu.m.

b.2-6) Platforms
Volume = Thickness x Surface areas of platform
= ( 0.13 x 0.56 x 1.44 )
Volume = 0.10 cu.m.

b.3) Waste Way


b.3-1) Flooring
Volume = Thickness x Total Surface area of flooring
= 0.15 x [( 0.20 x 0.76 ) + ( 0.82 x
Volume = 0.12 cu.m.

b.3-2) Side walls "Both sides"


Volume = Thickness x Total Surface area of side wall x 2
= 0.13 x [( 0.20 x 1.38 ) + ( 0.82 x
Volume = 0.37 cu.m.

b.3-3) Cut of Wall


Volume = Thickness x Surface areas of Cut of wall
= ( 0.10 x 0.37 x 1.06 )
Volume = 0.04 cu.m.

b.3-4) Platforms
Volume = Thickness x Surface areas of platform
= ( 0.13 x 0.50 x 0.20 )
Volume = 0.013 cu.m.

Total Vol. for Class A Concrete (Spillway): ................................... = 6.92

Grand Total Vol. for Class A Concrete: ................................... = 254.22

110 CONCRETE JOINTS AND JOINT MATERIALS


a. Joint Filler (Bituminous type) Added to miscellaneous materia
b. Joint Sealant Added to miscellaneous materia
c. PVC Waterstop (23 cm. Dumbell Type) "extended up to the wall of spill
station: Length total in l.m.
0+040 6.00 m.
0+050 6.00 m.
0+060 6.00 m.
0+070 6.00 m.
0+080 6.00 m. 54.00 l.m.
0+090 6.00 m.
0+100 6.00 m.
0+110 6.00 m.
0+120 6.00 m.

111 BOULDER RIPRAP (Spillway)

STATION THICKNESS DESIGNATION


A= 10.000
sta.0+120 - 0.60 a= 6.000 (A+a)/2 x L =
sta.0+130
L= 10.000

113 FILTER DRAIN (Spillway)


a.) @ SIDE WALLS
Clean Gravel
Volume = Area X L
Volume = 0.1771 X 146.4
Volume = .......................... 51.87
51.870
Coarse Filter
Volume = Area X L
Volume = 0.0523 X 146.4
Volume = .......................... 15.32
15.32

Find Filter
Volume = Area X L
Volume = 0.0579 X 146.4
Volume = .......................... 16.96
16.960

b.) @ CHUTE BLOCKS " see end areas at details "


Clean Gravel
Volume = Area X L
Volume = 0.0536 X 6.0
Volume = .......................... 0.32
0.320

Coarse Filter
Volume = Area X L
Volume = 0.0523 X 6.0
Volume = .......................... 0.31
0.31

Find Filter
Volume = Area X L
Volume = 0.0709 X 6.0
Volume = .......................... 0.43
0.430

c.) @ END SILL " see end areas at details "


Clean Gravel
Volume = Area X L
Volume = 0.0390 X 6.0
Volume = .......................... 0.23
0.230

Coarse Filter
Volume = Area X L
Volume = 0.0486 X 6.0
Volume = .......................... 0.29
0.29

Find Filter
Volume = Area X L
Volume = 0.0663 X 6.0
Volume = .......................... 0.40
0.400
Total volume for Clean Gravel……………………………………………… 52.420
Total volume for Coarse Filter……………………………………………… 15.92
Total volume for Fine Filter ……………………………………………… 17.790

117 DRILLING & GROUTING


a. Anchor Bars @ Spillway
no. of bars = {[(total length of spillway / spacing longitudinally) - 2] x no. of anchor bar transversely x leng
= {[(146.44 / 2 ) -2] x 3 x 1.6 } / 6
no. of bars = 57 pcs

b. Drilling (Non-coring):
total length of hole to be drilled = {[(total length of spillway/ spacing longitudinally) - 2) x no. of bars tranversely x height of 1 h
= {[ 146.44 / 2) - 2] x 3 x 1
total length of hole to be drilled = 213.66 l.m.

c. Pressure Grouting:
Volume = (Area of 50mm dia. Drill Hole - Area of 25mm dia. Anchor Bars) x height of drill hole x no. o
= {[3.1416x 0.0250^2) - (3.1416x 0.0125^2)] x 1.0 x 222
Volume = 0.33 cu.m.

121 MISCELLANEOUS METAL WORKS & MATERIALS


a. 5 cm. Ø PVC, Perforated Pipe
LOCATION LENGTH OF PIPE "to install" NO. OF PIPE
@ Chute Blocks 1.65 3
@ End Sill 1.1 9
@ Side wall of spill way "both sides" 0.36 120
OVER ALL TOTAL LENGTH ……………………………………………………

b. 10 cm. Ø PVC, Perforated Pipe


LOCATION LENGTH OF PIPE "to install" NO. OF PIPE
@ Chute Blocks 6 1
@ End Sill 6 1
@ Side wall of spill way "both sides" 146.44 2
OVER ALL TOTAL LENGTH ……………………………………………………

c. 16mm Dia. Trashrack ; 1.12mx1.90mx1.92m (Pipe Conduit Inlet)


total length of RSB required= no. of pcs (vert bar) x ave. length of vert bar + no. of pcs (hor bars) x ave length
= 11 pcs x 1.92 + 6 pcs x 1.7
= 63.12 m
RSB req'd in kg= 63.12 x 1.579 kg/m
= 99.67 kgs

d. Dowel Bars, 16 mm dia. Plain Bar with PVC Pipe


Location no. of pcs 1mx16mm dia. Plain Bar w/ PVC Pipe Dowel Bars
sta 0+040 9 pcs
Sta 0+120 9 pcs

e. 300mm Ø HDPE SDR 17 Pipes (Conduit)


STATION: 0+000 - 0+110
Total length ………………………………………………………………………
f. Fab., & Installation of 1.0m x 0.60 m Steel Gate with hand wheel
Quantity …………………………………………….
g. Proc., Delivery & Install'n of 300 mm. Ø Gate Valve w/ Bypass
Quantity …………………………………………….

h. Supply, delivery & install'n of 300 mm. Ø HDPE Mechanical Coupler


Quantity …………………………………………….
LUBA SWIP
uk City, Kalinga
RIC COMPUTATION

)
)

)
)

)
)

)
)

L )]
2.00 X 10.0
286.90 cu.m
286.90 cu.m

L )]
2.00 X 10.0
321.60 cu.m
321.60 cu.m

L )]
2.00 X 10.0
340.55 cu.m
340.55 cu.m

L )]
2.00 X 10.0
380.45 cu.m
380.45 cu.m

L )]
2.00 X 10.0
398.85 cu.m
398.85 cu.m

L )]
2.00 X 10.0
356.45 cu.m
356.45 cu.m

L )]
2.00 X 10.0
428.60 cu.m
428.60 cu.m

L )]
2.00 X 10.0
649.50 cu.m
649.50 cu.m

L )]
2.00 X 10.0
572.95 cu.m
572.95 cu.m

L )]
2.00 X 10.0
461.00 cu.m
461.00 cu.m

L )]
2.00 X 10.0
530.30 cu.m
530.30 cu.m
L )]
2.00 X 10.0
538.45 cu.m
538.45 cu.m

L )]
2.00 X 10.0
544.25 cu.m
544.25 cu.m

L )]
2.00 X 10.0
394.85 cu.m
394.85 cu.m

L )]
2.00 X 10.0
214.70 cu.m
214.70 cu.m

6,419.4000 cu.m

L )]
2.00 X 20.0
405.30 cu.m
405.30 cu.m

L )]
2.00 X 20.0
516.50 cu.m
516.50 cu.m

L )]
2.00 X 20.0
609.70 cu.m
609.70 cu.m

L )]
2.00 X 20.0
642.60 cu.m
642.60 cu.m
L )]
2.00 X 20.0
789.10 cu.m
789.10 cu.m

L )]
2.00 X 20.0
688.60 cu.m
688.60 cu.m

L )]
2.00 X 20.0
212.50 cu.m
212.50 cu.m

3,864.30 cu.m.

19,550.00 x 0.30
5,865.00 cu.m
5,865.00 cu.m

L )]
2.00 X 10.0
32.80 cu.m
32.80 cu.m

L )]
2.00 X 10.0
32.80 cu.m
32.80 cu.m

L )]
2.00 X 10.0
32.80 cu.m
32.80 cu.m

L )]
2.00 X 10.0
32.80 cu.m
32.80 cu.m

L )]
2.00 X 10.0
32.80 cu.m
32.80 cu.m
L )]
2.00 X 10.0
32.80 cu.m
32.80 cu.m

L )]
2.00 X 10.0
27.30 cu.m
27.30 cu.m

L )]
2.00 X 10.0
21.80 cu.m
21.80 cu.m

L )]
2.00 X 10.0
21.80 cu.m
21.80 cu.m

L )]
2.00 X 10.0
21.80 cu.m
21.80 cu.m

L )]
2.00 X 10.0
21.80 cu.m
21.80 cu.m

L )]
2.00 X 10.0
21.80 cu.m
21.80 cu.m

L )]
2.00 X 10.0
24.10 cu.m
24.10 cu.m

L )]
2.00 X 10.0
26.40 cu.m
26.40 cu.m

L )]
2.00 X 10.0
26.40 cu.m
26.40 cu.m

410.00 cu.m.

2.00
2.00

2.00
2.00

2.00
2.00

L )]
2.00 X 20.0
439.70 cu.m
439.70 cu.m

L )]
2.00 X 20.0
253.80 cu.m
253.80 cu.m

L )]
2.00 X 20.0
2716.90 cu.m
2716.90 cu.m

L )]
2.00 X 20.0
4598.60 cu.m
4598.60 cu.m

L )]
2.00 X 20.0
3098.10 cu.m
3098.10 cu.m

L )]
2.00 X 20.0
1277.40 cu.m
1277.40 cu.m

L )]
2.00 X 20.0
187.90 cu.m
187.90 cu.m

12,572.40 cu.m
12,572.40 cu.m

L )]
2.00 X 20.0
197.40 cu.m
197.40 cu.m

L )]
2.00 X 20.0
887.90 cu.m
887.90 cu.m

L )]
2.00 X 20.0
3783.90 cu.m
3783.90 cu.m

L )]
2.00 X 20.0
6130.80 cu.m
6130.80 cu.m

L )]
2.00 X 20.0
3900.40 cu.m
3900.40 cu.m

L )]
2.00 X 20.0
806.30 cu.m
806.30 cu.m

L )]
2.00 X 20.0
171.30 cu.m
171.30 cu.m

15,878.00 cu.m
15,878.00 cu.m

L )]
2.00 X 20.0
38.90 cu.m
38.90 cu.m

L )]
2.00 X 20.0
100.50 cu.m
100.50 cu.m

L )]
2.00 X 20.0
193.20 cu.m
193.20 cu.m

L )]
2.00 X 20.0
210.80 cu.m
210.80 cu.m

L )]
2.00 X 20.0
208.00 cu.m
208.00 cu.m

L )]
2.00 X 20.0
118.40 cu.m
118.40 cu.m

L )]
2.00 X 20.0
15.80 cu.m
15.80 cu.m

885.60 cu.m
885.60 cu.m

L )]
2.00 X 20.0
8.00 cu.m
8.00 cu.m

L )]
2.00 X 20.0
22.50 cu.m
22.50 cu.m

L )]
2.00 X 20.0
45.50 cu.m
45.50 cu.m

L )]
2.00 X 20.0
51.40 cu.m
51.40 cu.m

L )]
2.00 X 20.0
49.70 cu.m
49.70 cu.m

L )]
2.00 X 20.0
27.40 cu.m
27.40 cu.m

L )]
2.00 X 20.0
3.40 cu.m
3.40 cu.m

207.90 cu.m
207.90 cu.m

length
4.23

L
86

L
140

AREA BOTH SIDE VOLUME

0.42 49.95
AREA BOTH SIDE VOLUME

0.33 43.24

AREA BOTH SIDE VOLUME

0.37 7.96

AREA BOTH SIDE VOLUME

0.58 11.65

AREA VOLUME

0.70 42.00

AREA VOLUME

0.70 53.51

AREA VOLUME

1.30 13.00

AREA VOLUME

0.62 3.70
0.62 3.70

AREA VOLUME

0.93 3.73

AREA VOLUME

0.23 2.70

AREA VOLUME

0.12 0.72

VOLUME

11.31

AREA VOLUME

0.30 1.80

VOLUME TOTAL VOLUME

0.50 1.49

AREA VOLUME

0.09 0.54

247.30 cu.m
(Area of pipe x length)
x 0.30 )

1.74 x 2.60 ) +

"3 stages, Both sides"


2.75 x 1.38 )] -
1.00 x 0.50 )]

1.53 x 1.70 ) +
1.38 )]

1.44 )]
0.76 )]

0.14 )] x

cu.m

cu.m

Added to miscellaneous materials


Added to miscellaneous materials
"extended up to the wall of spillway"

AREA VOLUME

80.00 48.00
x 2.00
x 2.00
cu.m
cu.m

x 2.00
x 2.00
cu.m
cu.m

x 2.00
x 2.00
cu.m
cu.m

cu.m
cu.m

cu.m
cu.m

cu.m
cu.m

cu.m
cu.m

cu.m
cu.m

cu.m
cu.m
cu.m.
cu.m
cu.m

ngitudinally) - 2] x no. of anchor bar transversely x length of 1 anchor bar} 6

gitudinally) - 2) x no. of bars tranversely x height of 1 hole to be drilled}

of 25mm dia. Anchor Bars) x height of drill hole x no. of anchor bars

NO. OF PIPE TOTAL LENGTH


3 4.95 l.m.
9 9.90 l.m.
120 43.20 l.m.
58.05 l.m.

NO. OF PIPE TOTAL LENGTH


1 6.00 l.m.
1 6.00 l.m.
2 292.88 l.m.
304.88 l.m.

of vert bar + no. of pcs (hor bars) x ave length

Total
18 pcs

110.00 l.m.
110.00 l.m.

1 Assy

1 Assy

37 pcs
ILUBA SWIP
Tabuk City, Kalinga

BILL OF QUANTITIES (UPDATED)

ITEMS OF WORKS QUANTITY


A. DIVERSION AND RESERVOIR/DAM WORKS
101 Mobilization and Demobilization 1.00
102 Clearing and Grubbing 19,550.00
103 Diversion and Care of River During Construction 1.00
104 Excavation and Foundation Preparation
Common Excavation
a. Spillway 6,419.40
b. Along Dam Axis 3,864.30
104-A Overhaul/Disposal of Waste Materials 5,865.00
105 Structure Backfill
a. Spillway 410.00
106 Dam Embankment
a. Impervious Materials (Clay) 12,572.40
b. Random Fill (Common) 15,878.00
c. Boulder Riprap 885.60
d. Gravel Bedding
d-1 At Dam Embankment 207.90
d-2 At Outlet Works 3.81
e. Sand Bedding (Dam Crest) 51.60
f. Gravel Surfacing (Dam Crest) 252.00
g. Toe Drain
g-1 Boulders 1,537.20
g-2 Coarse Filter 540.00
g-3 Fine Filter 214.20
107 Concrete Structures
a. Spillway Class "A" (3000 psi) 247.30
b. Outlet Works Class "A" (3000 psi) 6.92
110 Concrete Joints And Joint Materials
a. Joint Filler (Bituminous type) (added to miscellaneous materials)
b. Joint Sealant (added to miscellaneous materials)
c. PVC Waterstop (23 cm. Dumbell Type) 54.00
113 Filter Drain (Spillway)
a. Clean Gravel 51.87
b. Coarse Filter 15.32
c. Fine Filter 16.96
117 Drilling and Grouting
a. Anchor Bars at Spillway 57.00
b. Drilling (non-coring) 213.66
c. Pressure Grouting 0.33
121 Miscellaneous Metal Works and Materials
a. 5 cm. Ø PVC, Perforated Pipe 58.05
b. 10 cm. Ø PVC, Perforated Pipe 304.88
c. 16 mm. dia Trashrack 1.12m x 1.9m x 1.92m (Diversion Inlet) 99.67
d. Dowel Bars, 16mm dia. Plain bar with PVC Pipe 18.00
e. 300mm dia. HDPE SDR 17 Pipes 110.00
f. 1m x 0.60m Steel Gate with hand wheel 1.00
g. 300mm dia. Gate Valve w/ Bypass 1.00
h. 300 mm dia. HDPE Pipe Mechanical Coupler 37.00
UNITS

l.s.
sq.m.
l.s.

cu.m.
cu.m.
cu.m.

cu.m.

cu.m.
cu.m.
cu.m.

cu.m.
cu.m.
cu.m.
cu.m.

cu.m.
cu.m.
cu.m.

cu.m.
cu.m.

l.m.

cu.m.
cu.m.
cu.m.

pcs.
l.m.
cu.m.
l.m.
l.m.
kg.
pcs.
l.m.
Assy
Assy
pcs.
VOLUME

50,000.00 50,000.00
10,865.00 12.00 234,600.00
50,000.00 50,000.00
-
-
10,773.5475 75.00 481,455.00
28,553.0015 75.00 289,822.50
125.00 733,125.00
-
210.76 150.00 61,500.00
-
21,197.54 300.00 3,771,720.00
20,106.61 300.00 4,763,400.00
2,656.52 800.00 708,480.00
-
1,297.17 800.00 166,320.00
13.80 800.00 3,045.60
86.10 800.00 41,280.00
258.30 800.00 201,600.00
-
224.13 800.00 1,229,760.00
105.00 800.00 432,000.00
119.00 800.00 171,360.00
-
208.40 8,000.00 1,978,400.00
6.92 8,000.00 55,364.61
-
100,000.00 -
50,000.00 -
30.00 150.00 8,100.00
-
25.34 800.00 41,496.00
7.92 800.00 12,256.00
8.94 800.00 13,568.00
-
247.00 150.00 8,550.00
922.90 150.00 32,049.00
1.36 150.00 49.50
-
63.00 150.00 8,707.50
152.00 200.00 60,976.00
49.45 50.00 4,983.50
18.00 200.00 3,600.00
110.00 3,000.00 330,000.00
1.00 50,000.00 50,000.00
1.00 300,000.00 300,000.00
5,000.00 185,000.00
-
-
16,482,568.21