SCHEDULE KERJA GALIAN DAN TIMBUNAN

Kap. Alat Jumlah Kap. DT Kap. Produksi Durasi


URAIAN Sta Volume (M3) Jam Kerja Jumlah DT
M3/Jam Alat M3/Jam (M3/Hari) (Hari)
GALIAN 00+925 - 01+300 19,427.69 45.21 2 8 13.27 4 723.36 27
TIMBUNAN 01+300 - 01+500 3,109.98 45.21 2 8 13.27 4 723.36 4

Agustus 2018 September 2018


URAIAN
21 22 23 24 25 26 27 28 29 30 31 32 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
Rencana
Clearing
Realisasi
Rencana
Galian
Realisasi
Rencana
Sloping
Realisasi
Rencana
Timbun
Realisasi
Hampar Rencana
& Padat Realisasi

Disetujui Diperiksa Dibuat

Miftah Ardiyansah Agus Irianto Almutahir


Project Engineering Manager Supervisor Project Planning