Professional Documents
Culture Documents
(G.R. No. 140047. July 13, 2004) : Decision DAVIDE, JR., C.J.
(G.R. No. 140047. July 13, 2004) : Decision DAVIDE, JR., C.J.
DECISION
DAVIDE, JR., C.J.:
1
The SOB required the contractors to submit (1) a performance bond of
ID271,808/610 representing 5% of the total contract price and (2) an advance
payment bond of ID541,608/901 representing 10% of the advance payment to be
released upon signing of the contract.[6] To comply with these requirements,
respondents 3-Plex and VPECI applied for the issuance of a guarantee with
petitioner Philguarantee, a government financial institution empowered to issue
guarantees for qualified Filipino contractors to secure the performance of approved
service contracts abroad.[7]
Petitioner Philguarantee approved respondents application. Subsequently,
letters of guarantee[8] were issued by Philguarantee to the Rafidain Bank
of Baghdad covering 100% of the performance and advance payment bonds, but
they were not accepted by SOB. What SOB required was a letter-guarantee from
Rafidain Bank, the government bank of Iraq. Rafidain Bank then issued a
performance bond in favor of SOB on the condition that another foreign bank, not
Philguarantee, would issue a counter-guarantee to cover its exposure. Al Ahli Bank
of Kuwait was, therefore, engaged to provide a counter-guarantee to Rafidain Bank,
but it required a similar counter-guarantee in its favor from the petitioner. Thus, three
layers of guarantees had to be arranged.[9]
Upon the application of respondents 3-Plex and VPECI, petitioner Philguarantee
issued in favor of Al Ahli Bank of Kuwait Letter of Guarantee No. 81-194-
F [10] (Performance Bond Guarantee) in the amount of ID271,808/610 and Letter of
Guarantee No. 81-195-F[11] (Advance Payment Guarantee) in the amount
of ID541,608/901, both for a term of eighteen months from 25 May 1981. These
letters of guarantee were secured by (1) a Deed of Undertaking[12] executed by
respondents VPECI, Spouses Vicente P. Eusebio and Soledad C. Eusebio, 3-Plex,
and Spouses Eduardo E. Santos and Iluminada Santos; and (2) a surety
bond[13] issued by respondent First Integrated Bonding and Insurance Company, Inc.
(FIBICI). The Surety Bond was later amended on 23 June 1981 to increase the
amount of coverage from P6.4 million to P6.967 million and to change the bank in
whose favor the petitioners guarantee was issued, from Rafidain Bank to Al Ahli
Bank of Kuwait.[14]
On 11 June 1981, SOB and the joint venture VPECI and Ajyal executed the
service contract[15] for the construction of the Institute of Physical
Therapy Medical Rehabilitation Center, Phase II, in Baghdad, Iraq, wherein the joint
venture contractor undertook to complete the Project within a period of 547 days or
18 months. Under the Contract, the Joint Venture would supply manpower and
materials, and SOB would refund to the former 25% of the project cost in Iraqi Dinar
and the 75% in US dollars at the exchange rate of 1 Dinar to 3.37777 US Dollars.[16]
The construction, which was supposed to start on 2 June 1981, commenced only
on the last week of August 1981. Because of this delay and the slow progress of the
construction work due to some setbacks and difficulties, the Project was not
completed on 15 November 1982 as scheduled. But in October 1982, upon
foreseeing the impossibility of meeting the deadline and upon the request of Al Ahli
Bank, the joint venture contractor worked for the renewal or extension of the
Performance Bond and Advance Payment Guarantee. Petitioners Letters of
Guarantee Nos. 81-194-F (Performance Bond) and 81-195-F (Advance Payment
Bond) with expiry date of 25 November 1982 were then renewed or extended to 9
February 1983 and 9 March 1983, respectively.[17] The surety bond was also
2
extended for another period of one year, from 12 May 1982 to 12 May 1983.[18] The
Performance Bond was further extended twelve times with validity of up to 8
December 1986,[19] while the Advance Payment Guarantee was extended three
times more up to 24 May 1984 when the latter was cancelled after full refund or
reimbursement by the joint venture contractor.[20] The surety bond was likewise
extended to 8 May 1987.[21]
As of March 1986, the status of the Project was 51% accomplished, meaning the
structures were already finished. The remaining 47% consisted in electro-mechanical
works and the 2%, sanitary works, which both required importation of equipment and
materials.[22]
On 26 October 1986, Al Ahli Bank of Kuwait sent a telex call to the petitioner
demanding full payment of its performance bond counter-guarantee.
Upon receiving a copy of that telex message on 27 October 1986, respondent
VPECI requested Iraq Trade and Economic Development Minister Mohammad Fadhi
Hussein to recall the telex call on the performance guarantee for being a drastic
action in contravention of its mutual agreement with the latter that (1) the imposition
of penalty would be held in abeyance until the completion of the project; and (2) the
time extension would be open, depending on the developments on the negotiations
for a foreign loan to finance the completion of the project. [23] It also wrote SOB
protesting the call for lack of factual or legal basis, since the failure to complete the
Project was due to (1) the Iraqi governments lack of foreign exchange with which to
pay its (VPECIs) accomplishments and (2) SOBs noncompliance for the past several
years with the provision in the contract that 75% of the billings would be paid in US
dollars.[24]Subsequently, or on 19 November 1986, respondent VPECI advised the
petitioner not to pay yet Al Ahli Bank because efforts were being exerted for the
amicable settlement of the Project.[25]
On 14 April 1987, the petitioner received another telex message from Al Ahli
Bank stating that it had already paid to Rafidain Bank the sum of US$876,564 under
its letter of guarantee, and demanding reimbursement by the petitioner of what it
paid to the latter bank plus interest thereon and related expenses.[26]
Both petitioner Philguarantee and respondent VPECI sought the assistance of
some government agencies of the Philippines. On 10 August 1987, VPECI
requested the Central Bank to hold in abeyance the payment by the petitioner to
allow the diplomatic machinery to take its course, for otherwise, the Philippine
government , through the Philguarantee and the Central Bank, would become
instruments of the Iraqi Government in consummating a clear act of injustice and
inequity committed against a Filipino contractor.[27]
On 27 August 1987, the Central Bank authorized the remittance for its account of
the amount of US$876,564 (equivalent to ID271, 808/610) to Al Ahli Bank
representing full payment of the performance counter-guarantee for VPECIs project
in Iraq. [28]
On 6 November 1987, Philguarantee informed VPECI that it would remit
US$876,564 to Al Ahli Bank, and reiterated the joint and solidary obligation of the
respondents to reimburse the petitioner for the advances made on its counter-
guarantee.[29]
3
The petitioner thus paid the amount of US$876,564 to Al Ahli Bank
of Kuwait on 21 January 1988.[30] Then, on 6 May 1988, the petitioner paid to Al Ahli
Bank of Kuwait US$59,129.83 representing interest and penalty charges demanded
by the latter bank.[31]
On 19 June 1991, the petitioner sent to the respondents separate letters
demanding full payment of the amount of P47,872,373.98 plus accruing interest,
penalty charges, and 10% attorneys fees pursuant to their joint and solidary
obligations under the deed of undertaking and surety bond.[32] When the respondents
failed to pay, the petitioner filed on 9 July 1991 a civil case for collection of a sum of
money against the respondents before the RTC of Makati City.
After due trial, the trial court ruled against Philguarantee and held that the latter
had no valid cause of action against the respondents. It opined that at the time the
call was made on the guarantee which was executed for a specific period, the
guarantee had already lapsed or expired. There was no valid renewal or extension of
the guarantee for failure of the petitioner to secure respondents express consent
thereto. The trial court also found that the joint venture contractor incurred no delay
in the execution of the Project. Considering the Project owners violations of the
contract which rendered impossible the joint venture contractors performance of its
undertaking, no valid call on the guarantee could be made. Furthermore, the trial
court held that no valid notice was first made by the Project owner SOB to the joint
venture contractor before the call on the guarantee. Accordingly, it dismissed the
complaint, as well as the counterclaims and cross-claim, and ordered the petitioner
to pay attorneys fees of P100,000 to respondents VPECI and Eusebio Spouses
and P100,000 to 3-Plex and the Santos Spouses, plus costs. [33]
In its 14 June 1999 Decision,[34] the Court of Appeals affirmed the trial courts
decision, ratiocinating as follows:
First, appellant cannot deny the fact that it was fully aware of the status of project
implementation as well as the problems besetting the contractors, between 1982 to
1985, having sent some of its people to Baghdad during that period. The successive
renewals/extensions of the guarantees in fact, was prompted by delays, not solely
attributable to the contractors, and such extension understandably allowed by the
SOB (project owner) which had not anyway complied with its contractual
commitment to tender 75% of payment in US Dollars, and which still retained
overdue amounts collectible by VPECI.
Second, appellant was very much aware of the violations committed by the SOB of
its contractual undertakings with VPECI, principally, the payment of foreign currency
(US$) for 75% of the total contract price, as well as of the complications and injustice
that will result from its payment of the full amount of the performance guarantee, as
evident in PHILGUARANTEEs letter dated 13 May 1987 .
Third, appellant was fully aware that SOB was in fact still obligated to the Joint
Venture and there was still an amount collectible from and still being retained by the
project owner, which amount can be set-off with the sum covered by the
performance guarantee.
4
Fourth, well-apprised of the above conditions obtaining at the Project site and
cognizant of the war situation at the time in Iraq, appellant, though earlier has made
representations with the SOB regarding a possible amicable termination of the
Project as suggested by VPECI, made a complete turn-around and insisted on acting
in favor of the unjustified call by the foreign banks.[35]
The petitioner then came to this Court via Rule 45 of the Rules of Court claiming
that the Court of Appeals erred in affirming the trial courts ruling that
I
II
III
The main issue in this case is whether the petitioner is entitled to reimbursement
of what it paid under Letter of Guarantee No. 81-194-F it issued to Al Ahli Bank
of Kuwait based on the deed of undertaking and surety bond from the respondents.
The petitioner asserts that since the guarantee it issued was absolute,
unconditional, and irrevocable the nature and extent of its liability are analogous to
those of suretyship. Its liability accrued upon the failure of the respondents to finish
the construction of the Institute of Physical Therapy Buildings in Baghdad.
By guaranty a person, called the guarantor, binds himself to the creditor to fulfill
the obligation of the principal debtor in case the latter should fail to do so. If a person
binds himself solidarily with the principal debtor, the contract is called suretyship. [37]
Strictly speaking, guaranty and surety are nearly related, and many of the
principles are common to both. In both contracts, there is a promise to answer for the
debt or default of another. However, in this jurisdiction, they may be distinguished
thus:
1. A surety is usually bound with his principal by the same instrument
executed at the same time and on the same consideration. On the other
hand, the contract of guaranty is the guarantor's own separate
undertaking often supported by a consideration separate from that
supporting the contract of the principal; the original contract of his
principal is not his contract.
5
2. A surety assumes liability as a regular party to the undertaking; while the
liability of a guarantor is conditional depending on the failure of the
primary debtor to pay the obligation.
3. The obligation of a surety is primary, while that of a guarantor is
secondary.
4. A surety is an original promissor and debtor from the beginning, while a
guarantor is charged on his own undertaking.
5. A surety is, ordinarily, held to know every default of his principal; whereas
a guarantor is not bound to take notice of the non-performance of his
principal.
6. Usually, a surety will not be discharged either by the mere indulgence of
the creditor to the principal or by want of notice of the default of the
principal, no matter how much he may be injured thereby. A guarantor is
often discharged by the mere indulgence of the creditor to the principal,
and is usually not liable unless notified of the default of the principal. [38]
In determining petitioners status, it is necessary to read Letter of Guarantee No.
81-194-F, which provides in part as follows:
In the event of default by V.P. EUSEBIO, we shall pay you 100% of the
obligation unpaid but in no case shall such amount exceed Iraq Dinars (ID)
271,808/610 plus interest and other incidental expenses. (Emphasis supplied) [39]
6
conditional guaranty. But as earlier ruled the fact that petitioners guaranty is
unconditional does not make it a surety. Besides, surety is never presumed. A party
should not be considered a surety where the contract itself stipulates that he is
acting only as a guarantor. It is only when the guarantor binds himself solidarily with
the principal debtor that the contract becomes one of suretyship.[42]
Having determined petitioners liability as guarantor, the next question we have to
grapple with is whether the respondent contractor has defaulted in its obligations
that would justify resort to the guaranty. This is a mixed question of fact and law that
is better addressed by the lower courts, since this Court is not a trier of facts.
It is a fundamental and settled rule that the findings of fact of the trial court and
the Court of Appeals are binding or conclusive upon this Court unless they are not
supported by the evidence or unless strong and cogent reasons dictate
otherwise.[43] The factual findings of the Court of Appeals are normally not
reviewable by us under Rule 45 of the Rules of Court except when they are at
variance with those of the trial court. [44] The trial court and the Court of Appeals were
in unison that the respondent contractor cannot be considered to have defaulted in
its obligations because the cause of the delay was not primarily attributable to it.
A corollary issue is what law should be applied in determining whether the
respondent contractor has defaulted in the performance of its obligations under the
service contract. The question of whether there is a breach of an agreement, which
includes default or mora,[45] pertains to the essential or intrinsic validity of a
contract. [46]
No conflicts rule on essential validity of contracts is expressly provided for in our
laws. The rule followed by most legal systems, however, is that the intrinsic validity
of a contract must be governed by the lex contractus or proper law of the contract.
This is the law voluntarily agreed upon by the parties (the lex loci voluntatis) or the
law intended by them either expressly or implicitly (the lex loci intentionis). The law
selected may be implied from such factors as substantial connection with the
transaction, or the nationality or domicile of the parties. [47] Philippine courts would do
well to adopt the first and most basic rule in most legal systems, namely, to allow the
parties to select the law applicable to their contract, subject to the limitation that it is
not against the law, morals, or public policy of the forum and that the chosen law
must bear a substantive relationship to the transaction. [48]
It must be noted that the service contract between SOB and VPECI contains no
express choice of the law that would govern it. In the United States and Europe, the
two rules that now seem to have emerged as kings of the hill are (1) the parties may
choose the governing law; and (2) in the absence of such a choice, the applicable
law is that of the State that has the most significant relationship to the transaction
and the parties.[49] Another authority proposed that all matters relating to the time,
place, and manner of performance and valid excuses for non-performance are
determined by the law of the place of performance or lex loci solutionis, which is
useful because it is undoubtedly always connected to the contract in a significant
way.[50]
In this case, the laws of Iraq bear substantial connection to the transaction, since
one of the parties is the Iraqi Government and the place of performance is
in Iraq. Hence, the issue of whether respondent VPECI defaulted in its obligations
may be determined by the laws of Iraq. However, since that foreign law was not
7
properly pleaded or proved, the presumption of identity or similarity, otherwise known
as the processual presumption, comes into play. Where foreign law is not pleaded
or, even if pleaded, is not proved, the presumption is that foreign law is the same as
ours.[51]
Our law, specifically Article 1169, last paragraph, of the Civil Code, provides: In
reciprocal obligations, neither party incurs in delay if the other party does not comply
or is not ready to comply in a proper manner with what is incumbent upon him.
Default or mora on the part of the debtor is the delay in the fulfillment of the
prestation by reason of a cause imputable to the former. [52] It is the non-fulfillment of
an obligation with respect to time.[53]
It is undisputed that only 51.7% of the total work had been accomplished. The
48.3% unfinished portion consisted in the purchase and installation of electro-
mechanical equipment and materials, which were available from foreign suppliers,
thus requiring US Dollars for their importation. The monthly billings and payments
made by SOB[54] reveal that the agreement between the parties was a periodic
payment by the Project owner to the contractor depending on the percentage of
accomplishment within the period. [55] The payments were, in turn, to be used by the
contractor to finance the subsequent phase of the work. [56] However, as explained
by VPECI in its letter to the Department of Foreign Affairs (DFA), the payment by
SOB purely in Dinars adversely affected the completion of the project; thus:
4. Despite protests from the plaintiff, SOB continued paying the accomplishment
billings of the Contractor purely in Iraqi Dinars and which payment came only after
some delays.
5.2 That Plaintiff is a foreign contractor in Iraq and as such, would need foreign
currency (US$), to finance the purchase of various equipment, materials, supplies,
tools and to pay for the cost of project management, supervision and skilled labor not
available in Iraq and therefore have to be imported and or obtained from the
Philippines and other sources outside Iraq.
5.3 That the Ministry of Labor and Employment of the Philippines requires the
remittance into the Philippines of 70% of the salaries of Filipino workers working
abroad in US Dollars;
5.5 That the Iraqi Dinar is not a freely convertible currency such that the same
cannot be used to purchase equipment, materials, supplies, etc. outside of Iraq;
5.6 That most of the materials specified by SOB in the CONTRACT are not available
in Iraq and therefore have to be imported;
5.7 That the government of Iraq prohibits the bringing of local currency (Iraqui
Dinars) out of Iraq and hence, imported materials, equipment, etc., cannot be
purchased or obtained using Iraqui Dinars as medium of acquisition.
8
8. Following the approved construction program of the CONTRACT, upon
completion of the civil works portion of the installation of equipment for the building,
should immediately follow, however, the CONTRACT specified that these equipment
which are to be installed and to form part of the PROJECT have to be procured
outside Iraq since these are not being locally manufactured. Copy f the relevant
portion of the Technical Specification is hereto attached as Annex C and made an
integral part hereof;
10. Due to the lack of Foreign currency in Iraq for this purpose, and if only to assist
the Iraqi government in completing the PROJECT, the Contractor without any
obligation on its part to do so but with the knowledge and consent of SOB and the
Ministry of Housing & Construction of Iraq, offered to arrange on behalf of SOB, a
foreign currency loan, through the facilities of Circle International S.A., the
Contractors Sub-contractor and SACE MEDIO CREDITO which will act as the
guarantor for this foreign currency loan.
Arrangements were first made with Banco di Roma. Negotiation started in June
1985. SOB is informed of the developments of this negotiation, attached is a copy of
the draft of the loan Agreement between SOB as the Borrower and Agent. The
Several Banks, as Lender, and counter-guaranteed by Istituto Centrale Per II Credito
A Medio Termine (Mediocredito) Sezione Speciale Per LAssicurazione Del Credito
AllExportazione (Sace). Negotiations went on and continued until it suddenly
collapsed due to the reported default by Iraq in the payment of its obligations with
Italian government, copy of the news clipping dated June 18, 1986 is hereto attached
as Annex D to form an integral part hereof;
As found by both the Court of Appeals and the trial court, the delay or the non-
completion of the Project was caused by factors not imputable to the respondent
contractor. It was rather due mainly to the persistent violations by SOB of the terms
and conditions of the contract, particularly its failure to pay 75% of the accomplished
work in US Dollars. Indeed, where one of the parties to a contract does not perform
in a proper manner the prestation which he is bound to perform under the contract,
he is not entitled to demand the performance of the other party.A party does not
incur in delay if the other party fails to perform the obligation incumbent upon him.
The petitioner, however, maintains that the payments by SOB of the monthly
billings in purely Iraqi Dinars did not render impossible the performance of the
Project by VPECI. Such posture is quite contrary to its previous representations. In
his 26 March 1987 letter to the Office of the Middle Eastern and African Affairs
(OMEAA), DFA, Manila, petitioners Executive Vice-President Jesus M. Taedo stated
that while VPECI had taken every possible measure to complete the Project, the war
situation in Iraq, particularly the lack of foreign exchange, was proving to be a great
obstacle; thus:
9
VPECI has taken every possible measure for the completion of the project but the
war situation in Iraq particularly the lack of foreign exchange is proving to be a great
obstacle. Our performance counterguarantee was called last 26 October 1986 when
the negotiations for a foreign currency loan with the Italian government through
Banco de Roma bogged down following news report that Iraq has defaulted in its
obligation with major European banks. Unless the situation in Iraq is improved as to
allay the banks apprehension, there is no assurance that the project will ever be
completed. [58]
In order that the debtor may be in default it is necessary that the following
requisites be present: (1) that the obligation be demandable and already liquidated;
(2) that the debtor delays performance; and (3) that the creditor requires the
performance because it must appear that the tolerance or benevolence of the
creditor must have ended. [59]
As stated earlier, SOB cannot yet demand complete performance from VPECI
because it has not yet itself performed its obligation in a proper manner, particularly
the payment of the 75% of the cost of the Project in US Dollars. The VPECI cannot
yet be said to have incurred in delay. Even assuming that there was delay and that
the delay was attributable to VPECI, still the effects of that delay ceased upon the
renunciation by the creditor, SOB, which could be implied when the latter granted
several extensions of time to the former. [60] Besides, no demand has yet been made
by SOB against the respondent contractor. Demand is generally necessary even if a
period has been fixed in the obligation. And default generally begins from the
moment the creditor demands judicially or extra-judicially the performance of the
obligation. Without such demand, the effects of default will not arise.[61]
Moreover, the petitioner as a guarantor is entitled to the benefit of excussion,
that is, it cannot be compelled to pay the creditor SOB unless the property of the
debtor VPECI has been exhausted and all legal remedies against the said debtor
have been resorted to by the creditor.[62] It could also set up compensation as
regards what the creditor SOB may owe the principal debtor VPECI. [63] In this case,
however, the petitioner has clearly waived these rights and remedies by making the
payment of an obligation that was yet to be shown to be rightfully due the creditor
and demandable of the principal debtor.
As found by the Court of Appeals, the petitioner fully knew that the joint venture
contractor had collectibles from SOB which could be set off with the amount covered
by the performance guarantee. In February 1987, the OMEAA transmitted to the
petitioner a copy of a telex dated 10 February 1987 of the Philippine Ambassador in
Baghdad, Iraq, informing it of the note verbale sent by the Iraqi Ministry of Foreign
Affairs stating that the past due obligations of the joint venture contractor from the
petitioner would be deducted from the dues of the two contractors.[64]
Also, in the project situationer attached to the letter to the OMEAA dated 26
March 1987, the petitioner raised as among the arguments to be presented in
support of the cancellation of the counter-guarantee the fact that the amount of
ID281,414/066 retained by SOB from the Project was more than enough to cover the
counter-guarantee of ID271,808/610; thus:
10
The Iraqi Government does not have the foreign exchange to fulfill
its contractual obligations of paying 75% of progress billings in US
dollars.
VPECI also maintains that the delay in the completion of the project was mainly due
to SOBs violation of contract terms and as such, call on the guarantee has no basis.
But surprisingly, though fully cognizant of SOBs violations of the service contract
and VPECIs outstanding receivables from SOB, as well as the situation obtaining in
the Project site compounded by the Iran-Iraq war, the petitioner opted to pay the
second layer guarantor not only the full amount of the performance bond counter-
guarantee but also interests and penalty charges.
This brings us to the next question: May the petitioner as a guarantor secure
reimbursement from the respondents for what it has paid under Letter of Guarantee
No. 81-194-F?
As a rule, a guarantor who pays for a debtor should be indemnified by the
latter[67] and would be legally subrogated to the rights which the creditor has against
the debtor.[68] However, a person who makes payment without the knowledge or
against the will of the debtor has the right to recover only insofar as the payment has
been beneficial to the debtor.[69] If the obligation was subject to defenses on the part
of the debtor, the same defenses which could have been set up against the creditor
can be set up against the paying guarantor.[70]
From the findings of the Court of Appeals and the trial court, it is clear that the
payment made by the petitioner guarantor did not in any way benefit the principal
debtor, given the project status and the conditions obtaining at the Project site at that
time. Moreover, the respondent contractor was found to have valid defenses against
SOB, which are fully supported by evidence and which have been meritoriously set
up against the paying guarantor, the petitioner in this case. And even if the deed of
undertaking and the surety bond secured petitioners guaranty, the petitioner is
11
precluded from enforcing the same by reason of the petitioners undue payment on
the guaranty. Rights under the deed of undertaking and the surety bond do not arise
because these contracts depend on the validity of the enforcement of the guaranty.
The petitioner guarantor should have waited for the natural course of
guaranty: the debtor VPECI should have, in the first place, defaulted in its obligation
and that the creditor SOB should have first made a demand from the principal
debtor. It is only when the debtor does not or cannot pay, in whole or in part, that the
guarantor should pay.[71] When the petitioner guarantor in this case paid against the
will of the debtor VPECI, the debtor VPECI may set up against it defenses available
against the creditor SOB at the time of payment. This is the hard lesson that the
petitioner must learn.
As the government arm in pursuing its objective of providing the necessary
support and assistance in order to enable [Filipino exporters and contractors to
operate viably under the prevailing economic and business conditions,[72] the
petitioner should have exercised prudence and caution under the circumstances. As
aptly put by the Court of Appeals, it would be the height of inequity to allow the
petitioner to pass on its losses to the Filipino contractor VPECI which had sternly
warned against paying the Al Ahli Bank and constantly apprised it of the
developments in the Project implementation.
WHEREFORE, the petition for review on certiorari is hereby DENIED for lack of
merit, and the decision of the Court of appeals in CA-G.R. CV No. 39302
is AFFIRMED.
No pronouncement as to costs.
SO ORDERED.
12
Republic of the Philippines
SUPREME COURT
Manila
SECOND DIVISION
DECISION
13
On March 5, 1997, PGSMC and KOGIES executed a Contract[1] whereby
KOGIES would set up an LPG Cylinder Manufacturing Plant in
Carmona, Cavite. The contract was executed in the Philippines. On April 7, 1997, the
parties executed, in Korea, an Amendment for Contract No. KLP-970301
dated March 5, 1997[2] amending the terms of payment. The contract and its
amendment stipulated that KOGIES will ship the machinery and facilities necessary
for manufacturing LPG cylinders for which PGSMC would pay USD
1,224,000. KOGIES would install and initiate the operation of the plant for which
PGSMC bound itself to pay USD 306,000 upon the plants production of the 11-kg.
LPG cylinder samples. Thus, the total contract price amounted to USD 1,530,000.
On October 14, 1997, PGSMC entered into a Contract of Lease [3] with Worth
Properties, Inc. (Worth) for use of Worths 5,079-square meter property with a 4,032-
square meter warehouse building to house the LPG manufacturing plant. The
monthly rental was PhP 322,560 commencing on January 1, 1998 with a 10%
annual increment clause.Subsequently, the machineries, equipment, and facilities for
the manufacture of LPG cylinders were shipped, delivered, and installed in the
Carmona plant. PGSMC paid KOGIES USD 1,224,000.
For the remaining balance of USD306,000 for the installation and initial
operation of the plant, PGSMC issued two postdated checks: (1) BPI Check No.
0316412 dated January 30, 1998 for PhP 4,500,000; and (2) BPI Check No.
0316413 dated March 30, 1998 for PhP 4,500,000.[5]
When KOGIES deposited the checks, these were dishonored for the
reason PAYMENT STOPPED. Thus, on May 8, 1998, KOGIES sent a demand
letter[6] to PGSMC threatening criminal action for violation of Batas Pambansa
Blg. 22 in case of nonpayment. On the same date, the wife of PGSMCs President
faxed a letter dated May 7, 1998 to KOGIES President who was then staying at
a Makati City hotel. She complained that not only did KOGIES deliver a different
brand of hydraulic press from that agreed upon but it had not delivered several
equipment parts already paid for.
14
On May 14, 1998, PGSMC replied that the two checks it issued KOGIES were
fully funded but the payments were stopped for reasons previously made known to
KOGIES.[7]
On June 1, 1998, PGSMC informed KOGIES that PGSMC was canceling their
Contract dated March 5, 1997 on the ground that KOGIES had altered the quantity
and lowered the quality of the machineries and equipment it delivered to PGSMC,
and that PGSMC would dismantle and transfer the machineries, equipment, and
facilities installed in the Carmona plant. Five days later, PGSMC filed before the
Office of the Public Prosecutor an Affidavit-Complaint for Estafa docketed as I.S. No.
98-03813 against Mr. Dae Hyun Kang, President of KOGIES.
On June 15, 1998, KOGIES wrote PGSMC informing the latter that PGSMC
could not unilaterally rescind their contract nor dismantle and transfer the
machineries and equipment on mere imagined violations by KOGIES. It also insisted
that their disputes should be settled by arbitration as agreed upon in Article 15, the
arbitration clause of their contract.
On June 23, 1998, PGSMC again wrote KOGIES reiterating the contents of
its June 1, 1998 letter threatening that the machineries, equipment, and facilities
installed in the plant would be dismantled and transferred on July 4, 1998. Thus,
on July 1, 1998, KOGIES instituted an Application for Arbitration before the Korean
Commercial Arbitration Board (KCAB) in Seoul, Korea pursuant to Art. 15 of the
Contract as amended.
15
arbitration. KOGIES also asked that PGSMC be restrained from dismantling and
transferring the machinery and equipment installed in the plant which the latter
threatened to do on July 4, 1998.
On July 9, 1998, PGSMC filed an opposition to the TRO arguing that KOGIES
was not entitled to the TRO since Art. 15, the arbitration clause, was null and void for
being against public policy as it ousts the local courts of jurisdiction over the instant
controversy.
After the parties submitted their Memoranda, on July 23, 1998, the RTC
issued an Order denying the application for a writ of preliminary injunction, reasoning
that PGSMC had paid KOGIES USD 1,224,000, the value of the machineries and
equipment as shown in the contract such that KOGIES no longer had proprietary
rights over them.And finally, the RTC held that Art. 15 of the Contract as amended
was invalid as it tended to oust the trial court or any other court jurisdiction over any
dispute that may arise between the parties. KOGIES prayer for an injunctive writ was
denied.[10] The dispositive portion of the Order stated:
16
On July 29, 1998, KOGIES filed its Reply to Answer and Answer to
Counterclaim.[11] KOGIES denied it had altered the quantity and lowered the quality
of the machinery, equipment, and facilities it delivered to the plant. It claimed that it
had performed all the undertakings under the contract and had already produced
certified samples of LPG cylinders. It averred that whatever was unfinished was
PGSMCs fault since it failed to procure raw materials due to lack of funds. KOGIES,
relying on Chung Fu Industries (Phils.), Inc. v. Court of Appeals,[12] insisted that the
arbitration clause was without question valid.
On September 21, 1998, the trial court issued an Order (1) granting PGSMCs
motion for inspection; (2) denying KOGIES motion for reconsideration of the July 23,
1998 RTC Order; and (3) denying KOGIES motion to dismiss PGSMCs compulsory
counterclaims as these counterclaims fell within the requisites of compulsory
counterclaims.
17
On October 2, 1998, KOGIES filed an Urgent Motion for Reconsideration [17] of
the September 21, 1998 RTC Order granting inspection of the plant and denying
dismissal of PGSMCs compulsory counterclaims.
Ten days after, on October 12, 1998, without waiting for the resolution of its
October 2, 1998 urgent motion for reconsideration, KOGIES filed before the Court of
Appeals (CA) a petition for certiorari[18] docketed as CA-G.R. SP No. 49249, seeking
annulment of the July 23, 1998 and September 21, 1998 RTC Orders and praying for
the issuance of writs of prohibition, mandamus, and preliminary injunction to enjoin
the RTC and PGSMC from inspecting, dismantling, and transferring the machineries
and equipment in the Carmona plant, and to direct the RTC to enforce the specific
agreement on arbitration to resolve the dispute.
In the meantime, on October 19, 1998, the RTC denied KOGIES urgent
motion for reconsideration and directed the Branch Sheriff to proceed with the
inspection of the machineries and equipment in the plant on October 28, 1998.[19]
On November 11, 1998, the Branch Sheriff filed his Sheriffs Report[21] finding
that the enumerated machineries and equipment were not fully and properly
installed.
On May 30, 2000, the CA rendered the assailed Decision [22] affirming the RTC
Orders and dismissing the petition for certiorari filed by KOGIES. The CA found that
the RTC did not gravely abuse its discretion in issuing the assailed July 23,
1998 and September 21, 1998 Orders. Moreover, the CA reasoned that KOGIES
contention that the total contract price for USD 1,530,000 was for the whole plant
and had not been fully paid was contrary to the finding of the RTC that PGSMC fully
18
paid the price of USD 1,224,000, which was for all the machineries and
equipment. According to the CA, this determination by the RTC was a factual finding
beyond the ambit of a petition for certiorari.
On the issue of the validity of the arbitration clause, the CA agreed with the
lower court that an arbitration clause which provided for a final determination of the
legal rights of the parties to the contract by arbitration was against public policy.
Furthermore, the CA held that the petition for certiorari had been filed
prematurely since KOGIES did not wait for the resolution of its urgent motion for
reconsideration of the September 21, 1998 RTC Order which was the plain, speedy,
and adequate remedy available. According to the CA, the RTC must be given the
opportunity to correct any alleged error it has committed, and that since the assailed
orders were interlocutory, these cannot be the subject of a petition for certiorari.
Hence, we have this Petition for Review on Certiorari under Rule 45.
The Issues
Petitioner posits that the appellate court committed the following errors:
a. PRONOUNCING THE QUESTION OF OWNERSHIP OVER THE
MACHINERY AND FACILITIES AS A QUESTION OF FACT BEYOND
THE AMBIT OF A PETITION FOR CERTIORARI INTENDED ONLY
FOR CORRECTION OF ERRORS OF JURISDICTION OR GRAVE
ABUSE OF DISCRETION AMOUNTING TO LACK OF (SIC) EXCESS
OF JURISDICTION, AND CONCLUDING THAT THE TRIAL COURTS
FINDING ON THE SAME QUESTION WAS IMPROPERLY RAISED IN
THE PETITION BELOW;
19
NECESSITATING PAYMENT OF DOCKET FEES AND
CERTIFICATION OF NON-FORUM SHOPPING;
Before we delve into the substantive issues, we shall first tackle the
procedural issues.
KOGIES strongly argues that when PGSMC filed the counterclaims, it should
have paid docket fees and filed a certificate of non-forum shopping, and that its
failure to do so was a fatal defect.
20
On July 17, 1998, at the time PGSMC filed its Answer incorporating its
counterclaims against KOGIES, it was not liable to pay filing fees for said
counterclaims being compulsory in nature. We stress, however, that effective August
16, 2004 under Sec. 7, Rule 141, as amended by A.M. No. 04-2-04-SC, docket fees
are now required to be paid in compulsory counterclaim or cross-claims.
Also, appeals from interlocutory orders would open the floodgates to endless
occasions for dilatory motions. Thus, where the interlocutory order was issued
without or in excess of jurisdiction or with grave abuse of discretion, the remedy is
certiorari.[29]
21
The alleged grave abuse of discretion of the respondent court equivalent to
lack of jurisdiction in the issuance of the two assailed orders coupled with the fact
that there is no plain, speedy, and adequate remedy in the ordinary course of law
amply provides the basis for allowing the resort to a petition for certiorari under Rule
65.
Neither do we think that KOGIES was guilty of forum shopping in filing the
petition for certiorari. Note that KOGIES motion for reconsideration of the July 23,
1998 RTC Order which denied the issuance of the injunctive writ had already been
denied. Thus, KOGIES only remedy was to assail the RTCs interlocutory order via a
petition for certiorari under Rule 65.
The September 21, 1998 RTC Order directing the branch sheriff to inspect the
plant, equipment, and facilities when he is not competent and knowledgeable on said
matters is evidently flawed and devoid of any legal support. Moreover, there is an
urgent necessity to resolve the issue on the dismantling of the facilities and any
further delay would prejudice the interests of KOGIES. Indeed, there is real and
imminent threat of irreparable destruction or substantial damage to KOGIES
equipment and machineries. We find the resort to certiorari based on the gravely
abusive orders of the trial court sans the ruling on the October 2, 1998 motion for
reconsideration to be proper.
We now go to the core issue of the validity of Art. 15 of the Contract, the
arbitration clause. It provides:
22
Article 15. Arbitration.All disputes, controversies, or differences
which may arise between the parties, out of or in relation to or in
connection with this Contract or for the breach thereof, shall finally be
settled by arbitration in Seoul, Korea in accordance with the
Commercial Arbitration Rules of the Korean Commercial Arbitration
Board. The award rendered by the arbitration(s) shall be final and
binding upon both parties concerned. (Emphasis supplied.)
Petitioner claims the RTC and the CA erred in ruling that the arbitration clause
is null and void.
Petitioner is correct.
Established in this jurisdiction is the rule that the law of the place where the
contract is made governs. Lex loci contractus. The contract in this case was
perfected here in the Philippines. Therefore, our laws ought to govern. Nonetheless,
Art. 2044 of the Civil Code sanctions the validity of mutually agreed arbitral clause or
the finality and binding effect of an arbitral award. Art. 2044 provides, Any
stipulation that the arbitrators award or decision shall be final, is valid, without
prejudice to Articles 2038, 2039 and 2040. (Emphasis supplied.)
The arbitration clause was mutually and voluntarily agreed upon by the
parties. It has not been shown to be contrary to any law, or against morals, good
customs, public order, or public policy. There has been no showing that the parties
have not dealt with each other on equal footing. We find no reason why the
arbitration clause should not be respected and complied with by both
parties. In Gonzales v. Climax Mining Ltd.,[35] we held that submission to arbitration
is a contract and that a clause in a contract providing that all matters in dispute
between the parties shall be referred to arbitration is a contract.[36] Again in Del
Monte Corporation-USA v. Court of Appeals, we likewise ruled that [t]he provision to
submit to arbitration any dispute arising therefrom and the relationship of the parties
is part of that contract and is itself a contract.[37]
23
Arbitration clause not contrary to public policy
The arbitration clause which stipulates that the arbitration must be done
in Seoul, Korea in accordance with the Commercial Arbitration Rules of the KCAB,
and that the arbitral award is final and binding, is not contrary to public policy. This
Court has sanctioned the validity of arbitration clauses in a catena of cases. In the
1957 case of Eastboard Navigation Ltd. v. Juan Ysmael and Co., Inc.,[38] this Court
had occasion to rule that an arbitration clause to resolve differences and breaches of
mutually agreed contractual terms is valid. In BF Corporation v. Court of Appeals, we
held that [i]n this jurisdiction, arbitration has been held valid and constitutional. Even
before the approval on June 19, 1953 of Republic Act No. 876, this Court has
countenanced the settlement of disputes through arbitration. Republic Act No. 876
was adopted to supplement the New Civil Codes provisions on arbitration. [39] And
in LM Power Engineering Corporation v. Capitol Industrial Construction Groups, Inc.,
we declared that:
Having said that the instant arbitration clause is not against public policy, we
come to the question on what governs an arbitration clause specifying that in case of
any dispute arising from the contract, an arbitral panel will be constituted in a foreign
country and the arbitration rules of the foreign country would govern and its award
shall be final and binding.
24
For domestic arbitration proceedings, we have particular agencies to arbitrate
disputes arising from contractual relations. In case a foreign arbitral body is chosen
by the parties, the arbitration rules of our domestic arbitration bodies would not be
applied. As signatory to the Arbitration Rules of the UNCITRAL Model Law on
International Commercial Arbitration[41] of the United Nations Commission on
International Trade Law (UNCITRAL) in the New York Convention on June 21, 1985,
the Philippinescommitted itself to be bound by the Model Law. We have even
incorporated the Model Law in Republic Act No. (RA) 9285, otherwise known as
the Alternative Dispute Resolution Act of 2004 entitled An Act to Institutionalize the
Use of an Alternative Dispute Resolution System in the Philippines and to Establish
the Office for Alternative Dispute Resolution, and for Other Purposes, promulgated
on April 2, 2004. Secs. 19 and 20 of Chapter 4 of the Model Law are the pertinent
provisions:
While RA 9285 was passed only in 2004, it nonetheless applies in the instant
case since it is a procedural law which has a retroactive effect. Likewise, KOGIES
filed its application for arbitration before the KCAB on July 1, 1998 and it is still
pending because no arbitral award has yet been rendered. Thus, RA 9285 is
applicable to the instant case. Well-settled is the rule that procedural laws are
construed to be applicable to actions pending and undetermined at the time of their
passage, and are deemed retroactive in that sense and to that extent. As a general
25
rule, the retroactive application of procedural laws does not violate any personal
rights because no vested right has yet attached nor arisen from them.[42]
Under Sec. 24, the RTC does not have jurisdiction over disputes that are
properly the subject of arbitration pursuant to an arbitration clause, and mandates
the referral to arbitration in such cases, thus:
26
The applicant shall establish that the country in which foreign
arbitration award was made in party to the New York Convention.
xxxx
xxxx
It is now clear that foreign arbitral awards when confirmed by the RTC are
deemed not as a judgment of a foreign court but as a foreign arbitral award, and
when confirmed, are enforced as final and executory decisions of our courts of law.
27
Thus, it can be gleaned that the concept of a final and binding arbitral award
is similar to judgments or awards given by some of our quasi-judicial bodies, like the
National Labor Relations Commission and Mines Adjudication Board, whose final
judgments are stipulated to be final and binding, but not immediately executory in the
sense that they may still be judicially reviewed, upon the instance of any
party. Therefore, the final foreign arbitral awards are similarly situated in that they
need first to be confirmed by the RTC.
Sec. 42 in relation to Sec. 45 of RA 9285 designated and vested the RTC with
specific authority and jurisdiction to set aside, reject, or vacate a foreign arbitral
award on grounds provided under Art. 34(2) of the UNCITRAL Model Law. Secs. 42
and 45 provide:
xxxx
28
Thus, while the RTC does not have jurisdiction over disputes governed by
arbitration mutually agreed upon by the parties, still the foreign arbitral award is
subject to judicial review by the RTC which can set aside, reject, or vacate it. In this
sense, what this Court held in Chung Fu Industries (Phils.), Inc. relied upon by
KOGIES is applicable insofar as the foreign arbitral awards, while final and binding,
do not oust courts of jurisdiction since these arbitral awards are not absolute and
without exceptions as they are still judicially reviewable. Chapter 7 of RA 9285 has
made it clear that all arbitral awards, whether domestic or foreign, are subject to
judicial review on specific grounds provided for.
(4) Grounds for judicial review different in domestic and foreign arbitral
awards
For final domestic arbitral awards, which also need confirmation by the RTC
pursuant to Sec. 23 of RA 876[44] and shall be recognized as final and executory
decisions of the RTC,[45] they may only be assailed before the RTC and vacated on
the grounds provided under Sec. 25 of RA 876.[46]
29
The losing party who appeals from the judgment of the court
confirming an arbitral award shall be required by the appellate court to
post a counterbond executed in favor of the prevailing party equal to
the amount of the award in accordance with the rules to be
promulgated by the Supreme Court.
Finally, it must be noted that there is nothing in the subject Contract which
provides that the parties may dispense with the arbitration clause.
Having ruled that the arbitration clause of the subject contract is valid and
binding on the parties, and not contrary to public policy; consequently, being bound
to the contract of arbitration, a party may not unilaterally rescind or terminate the
contract for whatever cause without first resorting to arbitration.
What this Court held in University of the Philippines v. De Los Angeles[47] and
reiterated in succeeding cases,[48] that the act of treating a contract as rescinded on
account of infractions by the other contracting party is valid albeit provisional as it
can be judicially assailed, is not applicable to the instant case on account of a valid
stipulation on arbitration. Where an arbitration clause in a contract is availing, neither
of the parties can unilaterally treat the contract as rescinded since whatever
infractions or breaches by a party or differences arising from the contract must be
30
brought first and resolved by arbitration, and not through an extrajudicial rescission
or judicial action.
The issues arising from the contract between PGSMC and KOGIES on
whether the equipment and machineries delivered and installed were properly
installed and operational in the plant in Carmona, Cavite; the ownership of
equipment and payment of the contract price; and whether there was substantial
compliance by KOGIES in the production of the samples, given the alleged fact that
PGSMC could not supply the raw materials required to produce the sample LPG
cylinders, are matters proper for arbitration.Indeed, we note that on July 1, 1998,
KOGIES instituted an Application for Arbitration before the KCAB
in Seoul, Korea pursuant to Art. 15 of the Contract as amended. Thus, it is
incumbent upon PGSMC to abide by its commitment to arbitrate.
Corollarily, the trial court gravely abused its discretion in granting PGSMCs
Motion for Inspection of Things on September 21, 1998, as the subject matter of the
motion is under the primary jurisdiction of the mutually agreed arbitral body, the
KCAB in Korea.
In addition, whatever findings and conclusions made by the RTC Branch
Sheriff from the inspection made on October 28, 1998, as ordered by the trial court
on October 19, 1998, is of no worth as said Sheriff is not technically competent to
ascertain the actual status of the equipment and machineries as installed in the
plant.
For these reasons, the September 21, 1998 and October 19, 1998 RTC
Orders pertaining to the grant of the inspection of the equipment and machineries
have to be recalled and nullified.
Petitioner assails the CA ruling that the issue petitioner raised on whether the
total contract price of USD 1,530,000 was for the whole plant and its installation is
beyond the ambit of a Petition for Certiorari.
31
It is settled that questions of fact cannot be raised in an original action for
certiorari.[49] Whether or not there was full payment for the machineries and
equipment and installation is indeed a factual issue prohibited by Rule 65.
However, what appears to constitute a grave abuse of discretion is the order of the
RTC in resolving the issue on the ownership of the plant when it is the arbitral body
(KCAB) and not the RTC which has jurisdiction and authority over the said
issue. The RTCs determination of such factual issue constitutes grave abuse of
discretion and must be reversed and set aside.
Anent the July 23, 1998 Order denying the issuance of the injunctive writ
paving the way for PGSMC to dismantle and transfer the equipment and
machineries, we find it to be in order considering the factual milieu of the instant
case.
Firstly, while the issue of the proper installation of the equipment and
machineries might well be under the primary jurisdiction of the arbitral body to
decide, yet the RTC under Sec. 28 of RA 9285 has jurisdiction to hear and grant
interim measures to protect vested rights of the parties. Sec. 28 pertinently provides:
32
Such relief may be granted:
(f) Either party may apply with the Court for assistance in
implementing or enforcing an interim measure ordered by an arbitral
tribunal.
(g) A party who does not comply with the order shall be liable for
all damages resulting from noncompliance, including all expenses, and
reasonable attorney's fees, paid in obtaining the orders judicial
enforcement. (Emphasis ours.)
Art. 17(2) of the UNCITRAL Model Law on ICA defines an interim measure of
protection as:
(b) Take action that would prevent, or refrain from taking action that is
likely to cause, current or imminent harm or prejudice to the arbitral
process itself;
33
(c) Provide a means of preserving assets out of which a subsequent
award may be satisfied; or
Art. 17 J of UNCITRAL Model Law on ICA also grants courts power and
jurisdiction to issue interim measures:
It is thus beyond cavil that the RTC has authority and jurisdiction to grant
interim measures of protection.
34
machineries either for their protection and preservation or for the better way to make
good use of them which is ineluctably within the management discretion of PGSMC.
Thirdly, and of greater import is the reason that maintaining the equipment
and machineries in Worths property is not to the best interest of PGSMC due to the
prohibitive rent while the LPG plant as set-up is not operational. PGSMC was losing
PhP322,560 as monthly rentals or PhP3.87M for 1998 alone without considering the
10% annual rent increment in maintaining the plant.
Fourthly, and corollarily, while the KCAB can rule on motions or petitions
relating to the preservation or transfer of the equipment and machineries as an
interim measure, yet on hindsight, the July 23, 1998 Order of the RTC allowing the
transfer of the equipment and machineries given the non-recognition by the lower
courts of the arbitral clause, has accorded an interim measure of protection to
PGSMC which would otherwise been irreparably damaged.
Finally, while PGSMC may have been granted the right to dismantle and
transfer the subject equipment and machineries, it does not have the right to convey
or dispose of the same considering the pending arbitral proceedings to settle the
differences of the parties. PGSMC therefore must preserve and maintain the subject
equipment and machineries with the diligence of a good father of a family [51] until
final resolution of the arbitral proceedings and enforcement of the award, if any.
35
(2) The September 21, 1998 and October 19, 1998 RTC Orders in Civil Case
No. 98-117 are REVERSED and SET ASIDE;
(3) The parties are hereby ORDERED to submit themselves to the arbitration
of their dispute and differences arising from the subject Contract before the KCAB;
and
No pronouncement as to costs.
SO ORDERED.
36