Professional Documents
Culture Documents
Scheduling Aace International: Overlapping Networks Techniques
Scheduling Aace International: Overlapping Networks Techniques
time between a request for action and when the action takes
place, and time for the approval process after a report has
Overlapping Networks Techniques been submitted and the action is taken following approval.
The use of overlapping network techniques is common in The alternate approach to this problem would be to include
PDM applications. Overlapping network techniques allow an activity in the network called “concrete cure,” “review
activities to be grouped together, which reduces the number request,” or “review and approval,” and assign the added
of activities in a network and can reduce the overall time of activity a duration of “N” days.
performance.
A start-to-start + lag (SS+N) relationship links the start of the
The overlapping scheduling technique allows for the develop- preceding activity with the start of the following or succeed-
ment of a schedule, which more closely represents how a plan- ing activity. It indicates that the successor activity cannot
ner visualizes actual field conditions. For example, rather than begin until the preceding activity has been started and the
wait for an activity to complete before starting the succeeding specified work periods (lag) or overlap time after the start of
activity, it can be said that a successor activity can start a num- the preceding activity has elapsed. For example, in Figure
ber of days after the start of its predecessor, or that it can finish
a number of days after the finish of its predecessor.
13.6