Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

SCHEDULING AACE INTERNATIONAL

time between a request for action and when the action takes
place, and time for the approval process after a report has
Overlapping Networks Techniques been submitted and the action is taken following approval.
The use of overlapping network techniques is common in The alternate approach to this problem would be to include
PDM applications. Overlapping network techniques allow an activity in the network called “concrete cure,” “review
activities to be grouped together, which reduces the number request,” or “review and approval,” and assign the added
of activities in a network and can reduce the overall time of activity a duration of “N” days.
performance.
A start-to-start + lag (SS+N) relationship links the start of the
The overlapping scheduling technique allows for the develop- preceding activity with the start of the following or succeed-
ment of a schedule, which more closely represents how a plan- ing activity. It indicates that the successor activity cannot
ner visualizes actual field conditions. For example, rather than begin until the preceding activity has been started and the
wait for an activity to complete before starting the succeeding specified work periods (lag) or overlap time after the start of
activity, it can be said that a successor activity can start a num- the preceding activity has elapsed. For example, in Figure
ber of days after the start of its predecessor, or that it can finish
a number of days after the finish of its predecessor.

Overlapping consists of two parts: a relationship and a lag


value or constraint. Four types of overlapping relationships
exist:

1. finish-to-start + lag (FS + N) Where “N” is lag,


2. finish-to-finish + lag (FF + N),
3. start-to-start + lag (SS +N), and
4. start-to-finish + lag (SF + N).
Figure 13.7—Start-to-Start + Lag Relationship.
In each case, a number of days (work periods) “N” are indi-
cated that define the overlapped time frame, or the lead-time, 13.7, Activity 20 cannot start until “N” work periods after the
between the activities in question. Lags can be either positive start of activity 10.
or negative, but are assumed to be zero if not specified.
Typical applications include the relationship between the
A finish-to-start + lag (FS + N) links the finish of the preceding pulling wire and cable and wire terminations, or starting the
activity with the start of the succeeding activity and indicates report preparation before all the research information has been
that the successor activity cannot begin until the preceding completed. These relationships assume that if the work can
activity is complete. A lag “N” can be placed on the relationship begin before the preceding activities are complete, an SS + N
to indicate that the succeeding activity cannot begin until a relationship between them can be utilized. The schedule com-
given time after the preceding activity has finished. A finish-to- putations will indicate that the start of the succeeding activities
start relationship with a lag value of zero is considered the can begin “N” days after the preceding activity has started.
default if no other value is specified. For example, in Figure The alternate approach to this problem would be to include
additional activities in the network to show the start and fin-
ish of both the predecessor and successor activities.

A finish-to-finish + lag (FF + N) relationship links the finish


of the preceding activity with the finish of the following or
succeeding activity and indicates that the latter activity can-
not be completed until the preceding activity has been com-
pleted and the specified work periods (lag) or overlap time
has elapsed. For example, in Figure 13.8, Activity 20 cannot
finish until “N” work periods after Activity 10 is finished.
Figure 13.6—Finish to Start + Lag Relationship
Typical finish-to-finish applications include the relationship
between the finish of wire terminations and the finish of test
13.6, Activity 20 cannot start until “N” work periods after equipment, or between finish of research information and
Activity 10 is complete. finishing the report preparation. These relationships assume
Typical applications include cure time between the place- that if the successor work can finish “N” work periods after
ment of concrete and the stripping of formwork, queuing the finish of the preceding activities, an FF + N relationship

13.6

You might also like