1.0 General Report Information
1.0 General Report Information
1.0 General Report Information
1.1 Introduction
This monthly report has been prepared with the objective of outlining the
progress of works for the construction and completion of the proposed
Kampung Bungin extension, Spaoh, Betong Division, Sarawak for the
contract period from 5th July 2018 to 25th July 2019.
Jabatan Tanah Dan Servei Sarawak intents to extend the existing Kampung
Bungin at Spaoh, Betong Division, Sarawak. The project site (Kampung
Bungin) can be accessed by road from Betong Town.
The total length of the access road is approximately 1.75km. The carriageway
for the access road shall be 7.0m and 5.5m wide for two ways traffic with 3m
and 1.5m wide earth shoulders on both sides. The carriageway shall be of
stone surfacing. 0.9m wide earth drains to be constructed on both side of the
roads. An approximate length of 97m of HDPE culverts are also to be
constructed. The total length of the water supply pipeline is approximately
1.77 km, consisting of HDPE and DI pipes.
h) Environment Management.
i) Provision and Maintenance of S.O Facilities
j) Any Works Incidental to and Necessary for Completion of The
Specified Works.
2
THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,
SPAOH, BETONG DIVISION, SARAWAK
Project Director
Ir. Tan Kee Beng
Resident Engineer
(Part Time)
Nur Hisyam
013-8396465
Clerk of Work
(Full Time)
Jolly Ong Soon Keng
016-5895155
3
THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,
SPAOH, BETONG DIVISION, SARAWAK
4
THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,
SPAOH, BETONG DIVISION, SARAWAK
5
THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,
SPAOH, BETONG DIVISION, SARAWAK
6
THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,
SPAOH, BETONG DIVISION, SARAWAK
7
THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,
SPAOH, BETONG DIVISION, SARAWAK
8
THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,
SPAOH, BETONG DIVISION, SARAWAK
ROAD 6
ROAD 7
ROAD 8
1.4 SUPPLY AND LAY 150MM THICK ROAD SUBBASE 0
ROAD 1
ROAD 5
ROAD 4
ROAD 2
ROAD 3
ROAD 6
ROAD 7
ROAD 8
2.0 DRAINAGE AND DRAINAGE STRUCTURES 0
2.1 DRAINS
EARTH DRAIN
PILING WORKS
75MM DIA BAKAU PILE FOR CULVERT WING WALL
2.2 CULVERTS
CULVERT NO. 9 SINGLE 2.1M DIA HDPE PIPE CULVERT
CULVERT NO. 8 SINGLE 1.2M DIA HDPE PIPE CULVERT
CULVERT NO. 7 SINGLE 1.2M DIA HDPE PIPE CULVERT
CULVERT NO. 3 SINGLE 0.9M DIA HDPE PIPE CULVERT
CULVERT NO. 6 SINGLE 1.2M DIA HDPE PIPE CULVERT
CULVERT NO. 5 SINGLE 1.2M DIA HDPE PIPE CULVERT
CULVERT NO. 4 SINGLE 0.9M DIA HDPE PIPE CULVERT
CULVERT NO. 2 SINGLE 0.9M DIA HDPE PIPE CULVERT
CULVERT NO. 1 SINGLE 0.9M DIA HDPE PIPE CULVERT
3.0 WATER RETICULATION 0
WATER SUPPLY
9
THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,
SPAOH, BETONG DIVISION, SARAWAK
5.0 CONCLUSION
The contract period lapsed is 5.32%. The achieved financial progress is 2.38%
against the scheduled financial progress of 2.59% (0.21% delay). As for the
physical progress, the actual work done is 0.11% against the scheduled
physical progress of 0.34% (0.23% delay). The main cause of delay is due to
delay arrival of the excavators to site on 25th July 2018 when it is scheduled to
arrive on 16th July 2018.
10
THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,
SPAOH, BETONG DIVISION, SARAWAK
11
THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,
SPAOH, BETONG DIVISION, SARAWAK
12
THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,
SPAOH, BETONG DIVISION, SARAWAK
13
THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,
SPAOH, BETONG DIVISION, SARAWAK
14
THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,
SPAOH, BETONG DIVISION, SARAWAK
15
THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,
SPAOH, BETONG DIVISION, SARAWAK
16
THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,
SPAOH, BETONG DIVISION, SARAWAK
17
THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,
SPAOH, BETONG DIVISION, SARAWAK
18
THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,
SPAOH, BETONG DIVISION, SARAWAK
Legendary:
Sunday
Public Holiday
19
THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,
SPAOH, BETONG DIVISION, SARAWAK
20
THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,
SPAOH, BETONG DIVISION, SARAWAK
Legendary:
Sunday
Public Holiday
21
THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,
SPAOH, BETONG DIVISION, SARAWAK
Appendix G - Photographs
22
THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,
SPAOH, BETONG DIVISION, SARAWAK
23
THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,
SPAOH, BETONG DIVISION, SARAWAK
24
THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,
SPAOH, BETONG DIVISION, SARAWAK
25
THE CONSTRUCTION AND COMPLETION OF KAMPUNG BUNGIN EXTENSION,
SPAOH, BETONG DIVISION, SARAWAK
27